AOM

Assignment 2
Group Members
 Aman
 Amna
 Aleeya
 Ammar
 Abdullah

Problem 1)

Solutions
Method 1

Total Time for processing = 20 + 2*10 = 40

Method 2

Total Time for processing = 1 + 5*10 = 51

If the form has to be fulfilled for a single company then use method 2, if the form is used
to be filled for more than 10 companies use method 1.

Problem 2)

Solutions

Ans a)

1) Max Capacity = 40 x 60 = 2400 minutes

2) Max. Output = 2400/1 = 2400 students per week

3) Max. Output = 2400/1.5 = 1600 students per week

4) Max. Output = 2400/0.8 = 3000 students per week

5) Max. Output = 2400/1 = 2400 students per week

6) Max. Output = 2400/1.2 = 2000 students per week

Ans b) Strip off Bad Habits is the bottle neck with 1600 students per week