16 - 1
Norms for Rate Analysis
Activity Group:-16: Piling for structures
Spec. Resources
Activity
Nos
Clause Description of works Labour materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
16.02 1607
Instaling and driving pre-cast RCC
pile of specified size and quality as
per specification and drawing etc.
1608 all complete. m
a) Pile size 300mm X 300mm m skilled md 0.10 Diesel lit 2.00 20 tonne capacity pile
unskilled md 1.00 driver (with all accessories) hr 0.20
b) Pile size 350mm X 350mm m skilled md 0.10 Diesel lit 2.30 20 tonne capacity pile
unskilled md 1.00 driver (with all accessories) hr 0.23
Remarks:- 1. For other size of the piles, norms shall be derived by extrapolation of pile cross section.
16.03 1612 Boring , providing and Installing
bored cast-in-situ RCC pile of
specfied diameter including
reinforcement and Bentonite as
per specification and drawing etc.
all complete. m
16 - 2
Norms for Rate Analysis
Activity Group:-16: Piling for structures
Spec. Resources
Activity
Nos
Clause Description of works Labour materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
m3 Boring equipment with
b) Dia .600mm skilled md 0.29 concrete 0.31
pump & all accessories.
semi-skilled md 0.91 admixture kg 0.93 hr 0.40
Crane for handling
m (rigger ) reinforcement kg 49.00
reinforcement cage and
unskilled md 4.26 bentonite kg 24.00 tremie pipe
Diesel lit 6.60 hr 0.26
m
3 Boring equipment with
c) Dia .700mm m skilled md 0.35 concrete 0.42
pump & all accessories.
semi-skilled md 1.09 admixture kg 1.26 hr 0.50
Crane for handling
(rigger ) reinforcement kg 66.00
reinforcement cage and
unskilled md 5.11 bentonite kg 27.00 tremie pipe
Diesel lit 8.10 hr 0.31
m
3 Boring equipment with
d) Dia .800mm m skilled md 0.42 concrete 0.55
pump & all accessories.
semi-skilled md 1.31 admixture kg 1.65 hr 0.60
Crane for handling
(rigger ) reinforcement kg 86.00
reinforcement cage and
unskilled md 6.13 bentonite kg 30.00 tremie pipe
Diesel lit 9.70 hr 0.37
Remarks:- 1.For determining the rate of concrete refer the norms for concrete
2.For detemining the rate of reinforcement refer the norms for reinforcement.
3. For other size of the piles, norms shall be derived by extrapolation of pile cross section.
16 - 3
Norms for Rate Analysis
Activity Group:-16: Piling for structures
Spec. Resources
Activity
Nos
Clause Description of works Labour materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
16.03.02 Do as above 16.03.
In hard soil m
a) Dia .500mm skilled md 0.60 concrete m3 0.22 Boring equipment with hr 1.10
semi-skilled md 1.90 admixture kg 0.66 pump & all accessories.
m (rigger ) reinforcement kg 35.00 Crane for handling
unskilled md 8.80 bentonite kg 20.00 reinforcement cage and hr 0.20
Diesel lit 13.00 tremie pipe
Remarks:- 1.For determining the rate of concrete refer the norms for concrete
2.For detemining the rate of reinforcement refer the norms for reinforcement.
3. For other size of the piles, norms shall be derived by extrapolation of pile cross section.
16 - 4
Norms for Rate Analysis
Activity Group:-16: Piling for structures
Spec. Resources
Activity
Nos
Clause Description of works Labour materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
16.04 1613 Providing, driving and installing
driven cast-in situ RCC pile of
specified diameter etc. complete as
per specification and drawing.
b)Dia 400mm m Skilled md 0.50 concrete m3 0.14 20 t.- Capacity Pile driving
Un-skilled md 1.60 reinforcement kg 28.00 equipment with all
accessories.
steel shell kg 9.20 hr 0.60
Casing m 1.00
Diesel lit 6.00
c)Dia 500mm m Skilled md 0.60 concrete m3 0.20 20 t.- Capacity Pile driving
Un-skilled md 2.00 reinforcement kg 40.00 equipment with all
accessories.
steel shell kg 11.50 hr 0.70
Casing m 1.00
Diesel lit 7.00
Remarks:- 1.For determining the rate of concrete refer the norms for concrete
2.For detemining the rate of reinforcement refer the norms for reinforcement.
3. For other size of the piles, norms shall be derived by extrapolation of pile cross section.
16 - 5
Norms for Rate Analysis
Activity Group:-16: Piling for structures
Spec. Resources
Activity
Nos
Clause Description of works Labour materials Equipment Remarks
No. Unit
Type Unit Qty. Type Unit Qty. Type Unit Qty.
16.04.02 Do- do - do as above 16.04.01
With temporary steel shell Do all as above except the rate of temporary casing which is determined by considering 20 times usage, i.e. the rate of permanent
casing shall be divided by 20
16.05 1600 Providing and driving steel piles m
a) Section of pile: ISHB 250 Skilled md 0.20 Diesel lit 1.00 20 t. Capacity piling hr 0.10 Add 5% of materials
equipment with vibro-hammer.
Un-skilled md 1.00 steel kg 58.00 cost for consumables
b)Section of pile: ISHB 300 m Skilled md 0.24 Diesel lit 1.20 20 t. Capacity piling hr 0.12 Add 5% of materials
equipment with vibro-hammer.
Un-skilled md 1.20 steel kg 67.00 cost for consumables
c)Section of pile: ISHB 350 m Skilled md 0.30 Diesel lit 1.40 20 t. Capacity piling hr 0.14 Add 5% of materials
equipment with vibro-hammer.
Un-skilled md 1.50 steel kg 77.00 cost for consumables
16.06 1614 Loading tests on piles including Engineer md 12.00 Pile no 1 Plotter no 1
installation of platform,loading Technician md 24.00 Gunny bag no 1000 Loader hr 1
3
arrangements,etc.and necessary no Skilled md 24.00 sand m 50
measurements & plotting Un-skilled md 48.00 Steel beam Steel beam required
hiring t 5 for making pile
loading plateform.
16 - 6