DAFTAR HARGA SATUAN UPAH DAN BAHAN

PROYEK : PEMBANGUNAN RAKHA RESIDENCE


PEKERJAAN : RUMAH TYPE 36
LOKASI USB : ULAK LEBAR LAHAT
T.A : 2011

NO URAIAN HARGA (Rp) SATUAN


I. UPAH
1 Tukang 60,000.00 Orang/Hari
2 Mandor 55,000.00 Orang/Hari
3 Pekerja 50,000.00 Orang/Hari

II. BAHAN
1 Amplas Kain 3,000.00 lb
2 Bak Air 160,000.00 bh
3 Batu bata besar 450.00 bh
4 Batu kali 170,000.00 m3
5 Batu koral 170,000.00 m3
5a Batu Split 250,000.00 m3
6 Baut U dia. 1/2" + plat 40.4 410,000.00 bh
7 Baut penguat dia. 1/2" 1,000.00 bh
8 Baut dia. 16" 1,500.00 bh
9 Baut dia. 12" 1,000.00 bh
10 Besi beton 5,000.00 kg
11 Besi L. 30.30.3 20,000.00 m'
12 Besi L. 25.25.5 17,500.00 m'
13 Besi L. 40.40.4 17,500.00 m'
14 Besi L. 70.70.7 27,500.00 m'
15 Besi L. 50.50.5 16,500.00 m'
16 Besi pipa dia. 2,5" 100,000.00 kg
17 Box Panel Induk MCB 3 Phase 40 A 55,000.00 set
18 Box Panel MCB 2 Phase 6 A 50,000.00 set
19 Cat dasar 7,300.00 kg
20 Cat meni 8,000.00 kg
21 Cat tembok merek Dulux 64,000.00 kg
22 Cat warna merek Platon 40,000.00 kg
22a Cat tembok merek Q-lux 10,000.00 kg
23 Cat besi 45,000.00 kg
24 Chellak 42,500.00 kg
25 Closet jongkok biasa 100,000.00 bh
25a Closet jongkok + Jet Washer 400,000.00 Set
26 Engsel kupu-kupu 4" + Upah 10,000.00 bh
27 Engsel kupu-kupu 3" + Upah 9,000.00 bh
28 Eternit 12,000.00 m2
NO URAIAN HARGA (Rp) SATUAN
29 Floor Drain + Upah 30,000.00 bh
NO URAIAN HARGA (Rp) SATUAN
30 Genteng 3,000.00 bh
31 Genteng bubungan 5,500.00 bh
32a Gypsum 9 mm 20,000.00 m2
32 Grendel 5" 11,500.00 bh
33 Grendel 2" 9,200.00 bh
33a Grendel 3cm 9,000.00 bh
33b Grendel 10cm 10,300.00 bh
34 Handle jendela 3,500.00 bh
35 Instalasi titik lampu 40,000.00 set
36 Instalasi stop kontak 45,000.00 set
37 Instalasi pipa dan fitting 3/4" dan 1" 32,000.00 m'
38 Kabel NYM 3x21/2 4,100.00 m'
39 Kabel NYY 4x10 16,000.00 m'
40 Kaca nako 8 daun tbl.5 mm polos 20,000.00 m2
41 Kaca Es Buram 5 mm 45,000.00 m2
42 Kaca polos 5 mm 55,000.00 m2
43 Kait angin jendela 2,000.00 bh
44 Kawat ikat 15,000.00 kg
45 Kawat duri 2,000.00 m'
46 Kawat las elektroda 22,000.00 kg
47 Kayu kls II 2,000,000.00 m3
48 Kayu kls III 1,700,000.00 m3
49 Kayu kls IV 1,300,000.00 m3
50 Keramik putih uk. 30x30 cm 3,500.00 bh
51 Keramik uk. 20x20 cm 1,850.00 bh
51a Keramik Uk 40x40cm 10,000.00 bh
51b Keramik Uk. 20x25 cm 2,000.00 bh
52 Kran Air 25,000.00 bh
53 Kuas cat 15,000.00 bh
54 Kubah Mushola 750,000.00 bh
55 Kunci tanam 2 slaag + Upah 145,000.00 bh
56 Kunci tanam 1 slaag + Upah 82,500.00 bh
57 Lampu TL. 2x20 watt 75,000.00 bh
58 Lampu Pijar 40 watt 1,750.00 bh
59 Lampu Baret 40 watt 35,000.00 bh
60 List plafond 3,000.00 m'
61 List kayu 2,000.00 m'
62 Minyak cat 48,300.00 btl
63 Oker 4,000.00 kg
64 Paku biasa 20,000.00 kg
65 Paku Plywood 20,000.00 kg
66 Paku seng 15,000.00 kg
67 Pasir pasangan 100,000.00 m3
68 Pasir urug 70,000.00 m3
69 Pipa PVC 2" 6,500.00 m'
NO URAIAN HARGA (Rp) SATUAN
70 Pipa PVC 1/2" 4,000.00 m'
NO URAIAN HARGA (Rp) SATUAN
71 Pipa PVC 1,5" 5,500.00 m'
72 Pipa PVC 3/4" 4,700.00 m'
73 Pipa PVC 3" 7,000.00 m'
74 Lem Pipa 5,000.00 bh
75 Pipa PVC 4" 9,000.00 m'
76 Plamir kayu 7,500.00 kg
77 Plamir tembok 8,600.00 kg
78 Plint keramik 30x10 1,500.00 bh
79 Plywood 10 mm 32,000.00 m2
80 Plywood 18 mm 125,000.00 kp
80a Plywood 4 mm 16,000.00 m2
81 Porselen 20x20 cm 1,200.00 bh
82 Roster uk. 20 x 20 cm 2,500.00 bh
83 Saklar Tunggal 12,500.00 set
84 Saklar Seri 15,000.00 set
84a Stop Kontak 15,000.00 set
85 Semen 50 kg 60,000.00 zak
86 Semen putih 80,000.00 zak
87 Seng BJLS. 20 32,500.00 hl
88 Seng Plat BJLS. 20 8,000.00 m'
89 Spritus 3,500.00 ltr
89 Shower Set + Upah 300,000.00 buah
90 Tanah Urug 55,000.00 m3
91 Teer 2,000.00 kg
92 Cerucuk Gelam 10,000.00 btg
92a Tedmond Plastik + Upah 1,250,000.00 bh
93 Vanity Basin + Kran dan Upah 200,000.00 Set
94 Wastafel + Kaca Cermin 350,000.00 Set
DAFTAR ANALISA

PROYEK : PEMBANGUNAN RAKHA RESIDENCE


PEKERJAAN : RUMAH TYPE 36
LOKASI USB : ULAK LEBAR LAHAT
T.A : 2011

NO URAIAN HARGA PENGELUARAN BIAYA JUMLAH


PEKERJAAN UPAH UPAH BAHAN
DAN BAHAN (Rp) (Rp) (Rp)
1 3 4 5 6 7

1 10 M2 Pembersihan Area Pekerjaan


0.7500 Pekerja 50,000.00 37,500.00
0.0250 Mandor 55,000.00 1,375.00
38,875.00 - 38,875.00
1 M2 Pembersihan Area Pekerjaan / 10 3,888

2 10 M' Pasang Bowplank


0.1000 M3 Kayu kls IV 1,300,000.00 130,000.00
0.1000 kg Paku biasa 20,000.00 2,000.00
0.1500 Tukang 60,000.00 9,000.00
0.0600 Pekerja 50,000.00 3,000.00
0.0300 Mandor 55,000.00 1,650.00
13,650.00 132,000.00 145,650.00
1 M' Pasangan Bowplank 14,565.00

3 1 M3 Galian Tanah
0.7500 Pekerja 50,000.00 37,500.00
0.0250 Mandor 55,000.00 1,375.00
38,875.00 - 38,875.00

4 1 M3 Urugan Pasir Urug


1.2000 M3 Pasir urug 70,000.00 84,000.00
0.1100 Pekerja 50,000.00 5,500.00
0.0100 Mandor 55,000.00 550.00
6,050.00 84,000.00 90,050.00

5 1 m3 Urugan Tanah Kembali


0.2500 Pekerja 50,000.00 12,500.00
0.0100 Mandor 55,000.00 550.00
13,050.00 - 13,050.00
6 1 m3 Perekat ad. 1 : 3
10.5800 Zak Semen 50 kg 60,000.00 634,800.00
1.0800 m3 Pasir pasangan 100,000.00 108,000.00
742,800.00 - 742,800.00

7 1 m3 Screeeding Lantai ad. 1 : 4


0.5425 Zak Semen 50 kg 60,000.00 32,550.00
0.0697 m3 Pasir pasangan 100,000.00 6,965.00
39,515.00 - 39,515.00

8 1 m3 Pasangan Aanstamping Batu Kali


1.10 m3 Batu kali 150,000.00 165,000.00
0.5000 m3 Pasir pasangan 60,000.00 30,000.00
1.2000 Pekerja 25,000.00 30,000.00
0.1200 Mandor 28,000.00 3,360.00
33,360.00 195,000.00 228,360.00
NO URAIAN HARGA PENGELUARAN BIAYA JUMLAH
PEKERJAAN UPAH UPAH BAHAN
DAN BAHAN (Rp) (Rp) (Rp)
1 3 4 5 6 7

9 1 m3 Pasangan Batu Kali Ad. 1 : 4


1.10 m3 Batu kali 150,000.00 165,000.00
3.9800 Zak Semen 50 kg 30,000.00 119,400.00
0.4000 m3 Pasir pasangan 60,000.00 24,000.00
1.2000 Tukang 34,000.00 40,800.00
3.6000 Pekerja 25,000.00 90,000.00
0.1200 Mandor 28,000.00 3,360.00
134,160.00 308,400.00 442,560.00
10 1 m2 Pasangan Batu Bata Ad. 1 : 4
45.00 Bh Batu bata besar 450.00 20,250.00
0.3160 Zak Semen 50 kg 60,000.00 18,960.00
0.0450 m3 Pasir pasangan 100,000.00 4,500.00
0.1500 Tukang 60,000.00 9,000.00
0.4500 Pekerja 50,000.00 22,500.00
0.0225 Mandor 55,000.00 1,237.50
32,737.50 43,710.00 76,447.50

11 1 m2 Pasangan Batu Bata Ad. 1 : 2


45.00 Bh Batu bata besar 450.00 20,250.00
0.6000 Zak Semen 50 kg 60,000.00 36,000.00
0.0400 m3 Pasir pasangan 100,000.00 4,000.00
0.2500 Tukang 60,000.00 15,000.00
0.5000 Pekerja 50,000.00 25,000.00
0.0225 Mandor 55,000.00 1,237.50
41,237.50 60,250.00 101,487.50

12 1 m2 Plesteran Adukan 1 : 4 dan Acian


0.1085 zak Semen 50 kg 60,000.00 6,510.00
0.0139 m3 Pasir pasangan 100,000.00 1,393.00
0.2000 Tukang 60,000.00 12,000.00
0.4000 Pekerja 50,000.00 20,000.00
0.0200 Mandor 55,000.00 1,100.00
33,100.00 7,903.00 41,003.00

13 1 m2 Plesteran Adukan 1 : 2
0.1785 zak Semen 50 kg 60,000.00 10,710.00
0.0114 m3 Pasir pasangan 100,000.00 1,140.00
0.2300 Tukang 60,000.00 13,800.00
0.4000 Pekerja 50,000.00 20,000.00
0.0200 Mandor 55,000.00 1,100.00
34,900.00 11,850.00 46,750.00

14 1 m2 Plesteran Adukan 1 : 3
0.1600 zak Semen 50 kg 60,000.00 9,600.00
0.0128 m3 Pasir pasangan 100,000.00 1,280.00
0.2200 Tukang 60,000.00 13,200.00
0.4000 Pekerja 50,000.00 20,000.00
0.0200 Mandor 55,000.00 1,100.00
34,300.00 10,880.00 45,180.00

16 1 m3 Beton Tumbuk Ad. 1 : 3 : 5


4.2500 Zak Semen 50 kg 60,000.00 255,000.00
0.4000 m3 Pasir pasangan 100,000.00 40,000.00
0.8600 m3 Batu koral 170,000.00 146,200.00
0.8000 Tukang 60,000.00 48,000.00
6.0000 Pekerja 50,000.00 300,000.00
0.3000 Mandor 55,000.00 16,500.00
364,500.00 441,200.00 805,700.00

17 Tulang Besi (Upah/100 kg/m3)


110.000 Kg Besi beton 5,000.00 550,000.00
2.0000 Kg Kawat ikat 15,000.00 30,000.00
3.0000 Tukang 60,000.00 180,000.00
PT. RAKHA SEJAHTERA ABADI
Perumahan Bengkurat Permai Blok A.10
Sari Bungamas Lahat
Telp : 0822 79747878
RENCANA ANGGARAN BIAYA

PROYEK : PEMBANGUNAN RAKHA RESIDENCE


PEKERJAAN : RUMAH TYPE 36
LOKASI PEK. : ULAK LEBAR LAHAT
T.A : 2020
No. Uraian Pekerjan Vol Sat Harga Satuan Total Harga
01 02 03 04 05 07
1. Pekerjaan Persiapan
a Pembersihan Lahan 90.00 M2 3,888 349,875
b Listrik kerja 2.00 bln 125,000 250,000
c Foto-foto proyek ( 3x bukti progres) 1.00 ls 50,000 50,000
d Keamanan 2.00 bln 375,000 750,000
e Bowplank 1.00 ls 2,250,000 2,250,000
Sub Total 3,649,875
2. Pekerjaan Pondasi (Rumah dan Pagar)
a. Galian tanah 3.64 M3 38,875 141,505
b. Lantai kerja pondasi 0.564 M3 90,050 50,788
c Pasangan pondasi batu kali 2.25 M 3
442,560 995,760
d Urugan tanah dan pemadatan 3.64 M3 13,050 47,502
Sub Total 1,235,555
3. Pekerjaan Lantai
Lantai keramik 40 x 40 36.00 M2 150,000 5,400,000
Sub Total 5,400,000
4. Pekerjaan Dinding
a Pasangan dinding bata 36.90 M2 76,448 2,820,913
b Plesteran 36.90 M2 45,180 1,667,142
c Cat tembok bagian depan 9.44 M 2
#N/A #N/A
* ex Q-lux
Sub Total #N/A
5 Pekerjaan Kusen + Pintu dan Jendela
a Kusen + Pintu uk 800x2000 mm 4.00 unit 875,000 3,500,000
* Kayu kelas III
b Pintu WC uk 600x1900 mm 1.00 unit 475,000 475,000
* PVC
c Kusen + Jendela R. Tamu uk 550x1600 mm 2.00 unit 725,000 1,450,000
* Kayu kelas III
d Kusen + Jendela R. Kamar uk 550x1400 mm 3.00 unit 725,000 2,175,000
* Kayu kelas III
e Jendela Kamar Mandi uk 100x200mm 2.00 unit 150,000 300,000
* Roster Tanah
Sub Total 7,900,000
6 Pekerjaan Sanitair
a Closet Jongkok 1.00 bh 250,000 250,000
b Floor Drain 1.00 bh 45,000 45,000
c Vanity Basin + Kran 1.00 bh 275,000 275,000
Sub Total 570,000

PT. RAKHA SEJAHTERA ABADI


Perumahan Bengkurat Permai Blok A.10
PT. RAKHA SEJAHTERA ABADI
Perumahan Bengkurat Permai Blok A.10
Sari Bungamas Lahat
Telp : 0822 79747878

7 Pekerjaan Plumbing
a Instalasi air bersih 10.00 m' #N/A #N/A
* Untuk K. Mandi
b Instalasi air kotor u/ closet 4.00 m' #N/A #N/A
c Instalasi air bekas 10.00 m' #N/A #N/A
* Untuk vanity, closet, floordrain
Sub Total #N/A

8 Pekerjaan Electrical
a Lampu 7 ttk 85,000 595,000
b Stop kontak 5 ttk 90,000 450,000
e Box panel 1 ttk 125,000 125,000
g Saklar tunggal 3 bh 40,000 120,000
h Saklar ganda 2 bh 45,000 90,000
Sub Total 1,380,000

9 Pekerjaan Struktur
a Kolom struktur uk 100x100 mm 0.595 M3 2,466,250 1,467,419
* pembesian, bakisting, dan cor
b Sloof uk 150x200 mm 1.140 M3 2,466,250 2,811,525
* pembesian, bakisting, dan cor
c Kolom ring Balok uk 100x100 mm 0.570 M3 2,466,250 1,405,763
* pembesian, bakisting, dan cor
Sub Total 5,684,706

10 Pekerjaan Atap
a Rangka baja ringan + Atap metal polos 60.5 M2 185,000 11,192,500
b Lisplang 32 M' 30,000 960,000
c Plafon gypsum 36 M2 110,000 3,960,000
Sub Total 16,112,500

TOTAL = SUB TOTAL 1+2+3+4+5+6+7+8+9+10 #N/A

PT. RAKHA SEJAHTERA ABADI


Perumahan Bengkurat Permai Blok A.10
Sari Bungamas Lahat
PT. RAKHA SEJAHTERA ABADI
Perumahan Bengkurat Permai Blok A.10
Sari Bungamas Lahat
Telp : 0822 79747878

REKAPITULASI
URAIAN PEKERJAAN Total Bobot
No
(%)
1. Pekerjaan Persiapan 3,649,875
2. Pekerjaan Pondasi (Rumah dan Pagar) 1,235,555
3. Pekerjaan Lantai 5,400,000
4. Pekerjaan Dinding #N/A
5. Pekerjaan Kusen + Pintu dan Jendela 7,900,000
6. Pekerjaan Sanitair 570,000
7. Pekerjaan Plumbing #N/A
8. Pekerjaan Electrical 1,380,000
9. Pekerjaan Struktur 5,684,706
10. Pekerjaan Atap 16,112,500
Jumlah #N/A

Lahat, 3 Januari 2020


PT. RAKHA SEJAHTERA ABADI

Dwinanto, ST
Direktur Utama
Harga CCV Sinar Intan Palembang
Barang Pcs Harga
Semen baturaja 1 Zak 77,500 9/1/2011 harga antar tempat
Pasir 1 m3 105,000
Koral split 1 m3 410,000
Batu Bata 1 bh 700
Besi f 6mm 1 btg 16,000 1 btg 3.66 kg 4371.585
Besi f 8mm 1 btg 45,000 1 btg 6.39 kg 7042.254
Besi f 10mm 1 btg 62,500 1 btg 8.63 kg 7242.178
Besi d 13mm 1 btg 87,500 1 btg 9.77 kg 8955.988
Besi d 16mm 1 btg 162,500
Triplek 3mm 1 kpng 42,000 1kpng 1.2 2.4 2.88
Keramik 30x30mm 1 ktk 35,000 1 ktk 10 bh
Pipa Paralon 3" 1 btg 90 1 btg 4m
Bak mandi Plastik 1 bh 160,000
Pipa Paralon 1/2" 1 btng 15,000 1 btg 4m
Closet Jongkok KIA 1 bh 85,000
Cat Dinding 20 kg 140,000 1 kg 7000
Tedmond Plastik 1000ltr 1 pcs 1,150,000
Kable NYM 3x21/2mm 1 rool 410,000
Saklar Engkel 1 pcs 27,000
Stop Kontak 1 pcs 27,000
Plafon Kepiting 1 pcs 7,000
6903.001