Reference:
Project PAINT QUALIFICATION Standard Construction / Maintenance Specifications
Document Code :AMBL-0001234 NACE, SSPC & ASME Standards.
Tittle
Page 1 of 3
5 after sludge removal/ solvent
BP Procedure. Standards. Procedure/ Client Specification.
cleaning, if needed.
Checking of environmental condition Aplus Mega Biz NACE & SSPC Aplus General BP Procedure/
6 on daily bases. Standards. M R
BP Procedure. Client Specification.
Check the quality of surface profile Per-ASTM D-4417 Each component or once per
7 after blasting prior to painting or ISO 8503. SA-2.5 SSPC SP-10 each day/ as specified in the H W
every day Project Painting procedure.
Per the Standard (No visible Before the start of each day
contaminant. shift or change in compress Air
8 Compressed Air Quality. ASTM D 4285. source M M
(compressor) after four hours
interval.
Spot Check, but not less than Maximum quantity and size
9 For Dust. ISO 8502-3 M W
1 per 10m2. . rating 2.
Conduct chloride Test on the Extraction: ISO Average Conductivity Specific location to be
85026 ( Bresle test corresponding to ≤ 20mg/m2 determined by WAS
Blasted
kit ) ( 2µg/cm2 ) Representative.
10 surface Prior to Painting M W
Assessment: ISO
Application to ascertain the 8502-9 ( Conduct
salt level. metric )
Visual to confirm
absence of
contamination,
11 Examination of Coating. pinholes, popping, According to Specification. 100% of all surfaces. M I
sagging Runs or
other defects,
With Elcometer After each coat dry stage, prior
to next Coat application and at
12 D.F.T Quality check. digital D.F.T According to Specification every M W
gauge. final coat dry stage
Holiday Detection three days after Aplus BP NACE RP0188-Sect.3 or Aplus General BP Procedure/
13 the final Coat Application on the Procedure. ASTM D 5162. Client Specification. M W
overall project.
Work progress report will be
every day, and Inspection report
Inspection Report & Daily work Typed, only
will be at
14 progress signatures will be As specified the end of every inspection M R/S
report. hand written. between liquid energy company
NACE Certified QA/QC work.
Page 2 of 3
Signature Date
Approved by : Signature Date
Approved by :
Signature Date
Signature Date
1. W-Witness point. A Stage of Operation that is designated to be witnessed by the Client. If the specified party has been formally notified in accordance with the
Contract Administration
Instruction and no formal response have been returned and the party is not present, the work may continue.
2. H-Hold Point. A designated stopping place during a specific activity at which inspection or examination, and dated signature or initial of the Client -Representative is
required before further work can be performed.
3. R- Review Point. This point is used for review of documents, drawings or records of the work being performed and/or carried out. No formal notification is required.
4. I- Random inspection Point. An inspection where the Aplus Mega Biz Limited Company and Client plans to audit, monitor or witness the activity in process at random
or periodic basis. No formal notification is required.