Inspection Report

Date: 18/02/2017
Inspection no: 1
Project No: 16051
Project Title: API Operations Centre
Location: Terminal 3
Contractor: GBM
Inspected by: Pradeep

On-Going Activities
1. Office Modification

Observation Points / Comments


1. Ceiling Works
2. Flooring works
3.
4.
5.

Photos

Photo #1 Photo #2 Photo #3


Description : Ceiling work in Flooring works in progress Flooring works in progress
progress

11.02.2021 Project No: 1


Photo #4

Description : Wall opening


Form: IPR-FOC-AZ1.0

11.02.2021 Project No: 2