SABA ENGNEERING PLC COMPANY

TRAFFIC VOLUME STUDY

TRAFFIC VOLUME STUDY


TRAFFIC COUNT

FEBRUARY 8, 2021
SABA ENGNEERING PLC COMPANY
PREP BY: ABDIRIZAK HUSSEIN EIDLEH
SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

DATA COLLECTION

Location: Location of the traffic volume study was selected to be from Boon to Borama. Vehicles from
Boon to Borama, and from Borama to Boon were counted. We stood by the side of the road and
different vehicles were counted by different persons. We selected one enumerator among us who was
in charge of time. He commanded us when to jump from current time step we were working to next
time step.

Date: Data for traffic volume study was collected on 04 Feb 2021 up to 06 Feb 2021.

Time: Time of data collection for traffic volume study was 6:00 AM to 6:00 PM.

Weather Condition: Sunny Day.

Observation: Classified Vehicle Counts.

Method: Direct Manual Method.

Equipment: Tally Counter, Road measuring wheel stock, Vest.

Number of Enumerators: Nine

Table 1.1: Summary of Data for 1st day “6:00 AM UP TO 6:00 PM”

DATA COLLECTION
DAY ONE
TIME 6:00 AM UP TO 6:00 PM " DAY"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 36 65.45454545
4 SMALL BUS 10 18.18181818
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 3 5.454545455
7 MEDIUM TRUCK 2 3.636363636
8 HEAVY TRUCK 4 7.272727273
9 TRUCK TRAILER 0 0
TOTAL # 55

Preb By: Abdirizak Hussein Eidle 1


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

DAY
70

60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 1.1: Volume of different vehicle type at different time

Table 1.2 : Summary of Data for 1st day “6:00 PM UP TO 6:00 AM”

DATA COLLECTION
DAY ONE
TIME 6:00 PM UP TO 6:00 AM " night"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 20 50
4 SMALL BUS 7 17.5
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 8 20
7 MEDIUM TRUCK 1 2.5
8 HEAVY TRUCK 4 10
9 TRUCK TRAILER 0 0
TOTAL # 40

Preb By: Abdirizak Hussein Eidle 2


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

NIGHT
60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 1.2: Volume of different vehicle type at different time

Table 1.3: Summary of Data for 1st day “6:00 AM UP TO 6:00 PM”

DATA COLLECTION
DAY TWO
TIME 6:00 AM UP TO 6:00 PM " DAY"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 37 66.07142857
4 SMALL BUS 8 14.28571429
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 3 5.357142857
7 MEDIUM TRUCK 2 3.571428571
8 HEAVY TRUCK 6 10.71428571
9 TRUCK TRAILER 0 0
TOTAL # 56

Preb By: Abdirizak Hussein Eidle 3


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

DAY
70

60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig1.3 : Volume of different vehicle type at different time

Table 1.4: Summary of Data for 1st day “6:00 PM UP TO 6:00 AM”

DATA COLLECTION
DAY TWO
TIME 6:00 PM UP TO 6:00 AM " NIGHT"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 23 60.52631579
4 SMALL BUS 7 18.42105263
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 1 2.631578947
7 MEDIUM TRUCK 2 5.263157895
8 HEAVY TRUCK 5 13.15789474
9 TRUCK TRAILER 0 0
TOTAL # 38

Preb By: Abdirizak Hussein Eidle 4


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

NIGHT
70

60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 1.4: Volume of different vehicle type at different time

Table 1.5: Summary of Data for 1st day “6:00 AM UP TO 6:00 PM”

DATA COLLECTION
DAY THREE
TIME 6:00 AM UP TO 6:00 PM " DAY"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 26 38.80597015
4 SMALL BUS 28 41.79104478
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 5 7.462686567
7 MEDIUM TRUCK 1 1.492537313
8 HEAVY TRUCK 7 10.44776119
9 TRUCK TRAILER 0 0
TOTAL # 67

Preb By: Abdirizak Hussein Eidle 5


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

DAY
45
40
35
30
25
20
15
10
5
0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 1.5: Volume of different vehicle type at different time

Table 1.6: Summary of Data for 1st day “6:00 PM UP TO 6:00 AM”

DATA COLLECTION
DAY THREE
TIME 6:00 PM UP TO 6:00 AM " DAY"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 23 60.52631579
4 SMALL BUS 6 15.78947368
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 4 10.52631579
7 MEDIUM TRUCK 0 0
8 HEAVY TRUCK 5 13.15789474
9 TRUCK TRAILER 0 0
TOTAL # 38

Preb By: Abdirizak Hussein Eidle 6


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

NIGHT
70

60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 1.6: Volume of different vehicle type at different time

Table 1.7: Summary of Data for 4tH day “6:00 AM UP TO 6:00 PM”

DATA COLLECTION
DAY FOUR
TIME 6:00 AM UP TO 6:00 PM " DAY"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 32 57.14285714
4 SMALL BUS 16 28.57142857
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 2 3.571428571
7 MEDIUM TRUCK 3 5.357142857
8 HEAVY TRUCK 2 3.571428571
9 TRUCK TRAILER 1 1.785714286
TOTAL # 56

Preb By: Abdirizak Hussein Eidle 7


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

MORNING
60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 1.7: Volume of different vehicle type at different time

Table 1.8: Summary of Data for 4st day “6:00 PM UP TO 6:00 AM”

DATA COLLECTION
DAY FOUR
TIME 6:00 PM UP TO 6:00 AM " NIGHT"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 2 4.255319149
3 UTILITEIS 21 44.68085106
4 SMALL BUS 16 34.04255319
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 4 8.510638298
7 MEDIUM TRUCK 2 4.255319149
8 HEAVY TRUCK 2 4.255319149
9 TRUCK TRAILER 0 0
TOTAL # 47

Preb By: Abdirizak Hussein Eidle 8


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

NIGHT
50
45
40
35
30
25
20
15
10
5
0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 1.8: Volume of different vehicle type at different time

Table 1.9: Summary of Data for 5th day “6:00 AM UP TO 6:00 PM”

DATA COLLECTION
DAY FIVE
TIME 6:00 AM UP TO 6:00 PM "MORNING"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 21 51.2195122
4 SMALL BUS 7 17.07317073
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 12 29.26829268
7 MEDIUM TRUCK 0 0
8 HEAVY TRUCK 1 2.43902439
9 TRUCK TRAILER 0 0
TOTAL # 41

Preb By: Abdirizak Hussein Eidle 9


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

MORNING
70

60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 1.9: Volume of different vehicle type at different time

Table 2.0: Summary of Data for 5th day “6:00 PM UP TO 6:00 AM”

DATA COLLECTION
DAY FIVE
TIME 6:00 PM UP TO 6:00 AM "NIGHT"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 22 51.1627907
4 SMALL BUS 9 20.93023256
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 4 9.302325581
7 MEDIUM TRUCK 3 6.976744186
8 HEAVY TRUCK 5 11.62790698
9 TRUCK TRAILER 0 0
TOTAL # 43

Preb By: Abdirizak Hussein Eidle 10


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

NIGHT
60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 2.0: Volume of different vehicle type at different time

Table 2.1: Summary of Data for 5th day “6:00 AM UP TO 6:00 PM”

DATA COLLECTION
DAY SIX
TIME 6:00 AM UP TO 6:00 PM "MORNING"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 2 4.255319149
3 UTILITEIS 24 51.06382979
4 SMALL BUS 8 17.0212766
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 4 8.510638298
7 MEDIUM TRUCK 2 4.255319149
8 HEAVY TRUCK 7 14.89361702
9 TRUCK TRAILER 0 0
TOTAL # 47

Preb By: Abdirizak Hussein Eidle 11


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

MORNING
70

60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 2.1: Volume of different vehicle type at different time

Table 2.2: Summary of Data for 5th day “6:00 PM UP TO 6:00 AM”

DATA COLLECTION
DAY SIX
TIME 6:00 PM UP TO 6:00 AM " NIGHT"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 23 53.48837209
4 SMALL BUS 7 16.27906977
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 5 11.62790698
7 MEDIUM TRUCK 1 2.325581395
8 HEAVY TRUCK 7 16.27906977
9 TRUCK TRAILER 0 0
TOTAL # 43

Preb By: Abdirizak Hussein Eidle 12


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

NIGHT
70

60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 2.2: Volume of different vehicle type at different time

Table 2.3: Summary of Data for 5th day “6:00 AM UP TO 6:00 PM”

DATA COLLECTION
DAY SEVEN
TIME 6:00 AM UP TO 6:00 PM "MORNING"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 41 56.94444444
4 SMALL BUS 14 19.44444444
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 5 6.944444444
7 MEDIUM TRUCK 3 4.166666667
8 HEAVY TRUCK 9 12.5
9 TRUCK TRAILER 0 0
TOTAL # 72

Preb By: Abdirizak Hussein Eidle 13


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

MORNING
70

60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 2.3: Volume of different vehicle type at different time

Table 2.4: Summary of Data for 5th day “6:00 PM UP TO 6:00 AM”

DATA COLLECTION
DAY SEVEN
TIME 6:00 PM UP TO 6:00 AM "NIGHT"
# OF
NO. VEHICLE TYPE VEHICLE PERCENTAGE
1 MOTOR BIKE 0 0
2 CAR/ TAXI 0 0
3 UTILITEIS 34 65.38461538
4 SMALL BUS 9 17.30769231
5 MEDIUM & LARGE BUS 0 0
6 LIGHT TRUCK 5 9.615384615
7 MEDIUM TRUCK 2 3.846153846
8 HEAVY TRUCK 2 3.846153846
9 TRUCK TRAILER 0 0
TOTAL # 52

Preb By: Abdirizak Hussein Eidle 14


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

NIGHT
70

60

50

40

30

20

10

0
MOTOR CAR/ UTILITEIS SMALL MEDIUM LIGHT MEDIUM HEAVY TRUCK
BIKE TAXI BUS & LARGE TRUCK TRUCK TRUCK TRAILER
BUS

Fig 2.4: Volume of different vehicle type at different time

Preb By: Abdirizak Hussein Eidle 15


SABA ENGINEERING PLC COMPANY
TRAFIIC VOLUME STUDY

SUMMARY REPORT

This table below explains or shows the number of cars pass through Boon district. These cars including
taxi, utilities, small bus, medium bus, light truck, medium truck and etc. According to the table describes
the distribution of cars between day and night.

TRAFFIC COUNT
LOCATION: BOON
NO. DATE MORNING NIGHT TOTAL/day
1 4-Feb-21 55 40 95
2 5-Feb-21 56 38 94
3 6-Feb-21 67 38 105
4 7-Feb-21 56 47 103
5 8-Feb-21 41 43 84
6 9-Feb-21 47 43 90
7 10-Feb-21 72 52 124
TOTAL# OF vehicle
per week 695

TRAFFIC COUNT
140

120

100

80

60

40

20

0
4-Feb-21 5-Feb-21 6-Feb-21 7-Feb-21 8-Feb-21 9-Feb-21 10-Feb-21

Preb By: Abdirizak Hussein Eidle 16