Professional Documents
Culture Documents
TECHNICAL PART
1. PROJECT SCHEDULE................................................................................................................1
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
0
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
1. PROJECT SCHEDULE
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
1
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
2
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
3
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
P r o je c t M a n a g e r
C o s t C o n t r o l E n g in e e r S c h e d u le E n g in e e r
P r o je c t S e c r e t a r y Q A / Q C E n g in e e r
D e s ig n M a n a g e r P ro c u re m e n t M a n a g e r C o n s t r u c t io n M a n a g e r H SE M anager
P r o c e s s E n g in e e r F ir e f ig h t in g E n g in e e r P ro c u re m e n t S it e S a f e t y E n g in e e r
E n g in e e r S u p e r in t e n d e n t
P ip in g E n g in e e r E q u ip m e n t E n g in e e r E x p e d it in g C iv il E n g in e e r
E n g in e e r
M a c h in e r y & P u p m I n s t r u m e n t a t io n T r a n s p o r t a t io n W e ld in g
E n g in e e r E n g in e e r E n g in e e r E n g in e e r
E le c t r ic a l E n g in e e r T e l. c o m m u n ic a t io n M a t e r ia l C o n t r o l
E n g in e e r E n g in e e r
S t r u c t u r e E n g in e e r W a t e r s u p p ly &
s e w e r a g e E n g in e e r
A R c h it e c t u r e E n g in e e r P lo t P la n E n g in e e r
H V A C E n g in e e r
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
4
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
5
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
6
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
The procedure for progress measurement for sub-contracts is essentially the same
as for procurement in the pre-award phase.
(4) Construction
The Overall Master Schedule for Construction activities will be updated prior to
mobilization to site using the latest estimate, sub-contractor schedules, material
control chart, drawings and other available engineering data. It is reviewed and
approved by the Project Manager, the Construction Manager and Owner
representative prior to the start of field construction activities.
Following award of the sub-contract, the contractor will be required to prepare a
detailed schedule for their scope of work for review and approval by TCC. This will
include detailed bar charts, S-curves, manpower histograms, progress charts and
daily schedules.
Progress Chart
A progress chart consisting of data tables and a progress graph, segregated by
summary level accounts will be developed as construction proceeds.
TCC will report progress achievement information on the summary progress
report. From this information, planned, forecast and actual progress is
calculated, tabulated on the progress data chart, and plotted on a progress
graph. This information will be available to Owner.
Daily Scheduling
Since the master schedule usually is not in enough detail to provide a daily
work plan, a detailed construction schedule is prepared and updated in the
field, adopting the logic and order of precedence for construction activities from
the master schedule.
The detailed schedule is designed to interface with a variety of commercially
available scheduling programs. By downloading the construction activities from
the master schedule, any level of detail required for efficient project control can
be displayed such as drawing numbers, equipment item numbers, work area
locations, crew information, etc.
This system provides a stand-alone construction schedule, with subsequent
capability for the generation of daily or weekly look-ahead schedules. Since
logic connections are not required, the program allows input of start and finish
dates with comments directly from the Construction Manager’s work plan. The
program’s database structure is listed below.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
7
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Activity ID
Activity Description
Code 1 (used for sorting and selecting)
Code 2 (used for sorting and selecting)
Planned Start Date
Forecast Start Date
Actual Start Date
Planned Finish Date
Forecast Finish Date
Actual Finish Date
Remarks / Comments
A look-ahead schedule is prepared on a periodic basis, usually weekly, always
projecting forward to the next upcoming time period.
Weekly field scheduling review meeting(s) are normally held at job-site. The
meetings can be held more frequently if project requirements dictate. Attendees
usually include representatives from engineering, purchasing and material control,
field supervision, and any subcontractor representatives.
At the meeting the current period’s schedule is discussed and the previous week’s
schedule reviewed. Comments and decisions made at the meeting are
incorporated into the schedule update for the period. The look-ahead schedule is
incorporated as part of the weekly report.
2.1.6 Change Control
Design change control procedure will be used as change control.
2.1.7 Document Control
Document control procedure is utilized for document control.
2.1.8 Project Reporting
Scheduling, Controlling and Reporting procedure will be executed in the project.
2.1.9 Finance and Accounting
The project controls system can provide commitment-based accounting. For
example, as soon as any purchase order is written for the project, the commitment
to spend is recorded tracked back to the relevant line item category in the project
construction plan. The commitment record is updated each week so that the status
of expenditures is always known and they can be tracked and compared
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
8
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
9
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
As
Built Package (AP)
TCC will provide project management and controls to ensure quality, cost and
schedule objectives are achieved. Owner will be responsible for providing design
information and constructability review. Detail Design will be finished by TCC as per
the Overall Master Schedule.
Reporting to the Project Manager, the TCC Engineering Manager will control the
design activities, co-ordinate the transfer of information and monitor progress and
quality of the design work. He will ensure that they are kept fully informed of the
project goals and priorities.
The TCC Engineering Manager will be supported by TCC Discipline Lead
Engineers,. The Discipline Lead Engineers will review the design to ensure that
the design intent is correctly implemented in the detailed design. They will also
ensure that the necessary quality standards are maintained and that the degree of
design detail is sufficient to support a fast and trouble free construction schedule.
In addition, these engineering reviews will address issues such as constructability,
construction safety and overall safety for the operating plant.
2.2.3 TCC Engineering Team Responsibilities
Responsibilities of Engineering Personnel
A multi-discipline task force team will be organized and assembled in TCC
design office. The engineering team including an Engineering Manager,
discipline lead engineers and discipline engineers will be fully involved in the
project.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
10
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
11
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
2.3 Construction
2.3.1 Objectives
The objectives of the Construction Management team will be to:
Establish a “Zero Tolerance” Environmental, Health and Safety program
with a target of zero accidents.
Ensure construction quality consistently meets all applicable standards,
codes and Owner requirements.
Plan, construct, mechanically complete and hand-over the facilities in
accordance with the project schedule.
Ensure constructablity issues are considered and incorporated in the
design phase.
Establish and maintain good relationships with Owner and Local
Government agencies.
2.3.2 Construction Strategy
The Construction Works for the project will be sub-contracted by TCC to
experienced and capable Construction organizations who are “Class One” certified
by Ministry of Construction.
TCC has worked with all of these organizations and is confident of their ability to
execute the construction works with the appropriate level of Construction
Management supervision.
The construction works will be let in the following main packages:
Civil Works
Erection and installation Works
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
12
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
13
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
the design office in order to review the design concept including layouts, materials
and methods of construction and installation sequence to ensure construction
issues are fully incorporated in the design.
2.3.5 Mobilization and Temporary Facilities
A Mobilization plan will be established as basis for the Construction Management
team’s mobilization as required,
2.3.6 Materials Management at Site
A Materials Controller will be appointed at site with responsibility for the following
functions:
Receiving equipment/materials and arranging for off-loading.
Arranging open box inspection of all equipment and materials when received.
Inspection of materials and approving storage and handling procedures
The Mechanical Workshop Construction will be progress early to enable this
building to be used for storage of procured equipment and materials.
2.3.7 Sub-Contractor Supervision
The Construction Manager will closely monitor the schedule during performance
and adjust resources as required to meet milestones. Regular meetings and site
walk-through with the Owner’ representatives will be conducted to assure full
understanding of actual progress.
Quality Control
Quality Control requirements at the job-site will be the responsibility of a
functionally independent QA Manager. The QA Manager will establish and
implement construction inspection, testing and acceptance procedures that meet
Owner standards with full consideration of successful project experience. The
Quality Procedures will be implemented on a day to day basis by Construction
Supervisors and the sub-contractors with Audits being carried out by the QA
Manager to confirm compliance.
Health, Safety and Environmental
TCC is totally committed to health, safety and environmental protection on its
construction sites based on a policy of continuous improvement. An HSE Plan will
be prepared as part of the Construction Execution Plan.
TCC will develop and implement a policy to ensure that an orderly work site is
created and maintained:-
Site Security The site will be adequately fenced off.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
14
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
15
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
16
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
3.1 QA Strategy
1) Quality policy
Quality first, making continuous improvements, and taking render of quality
work/product and complete follow-up service to client as the prime responsibility.
2) Quality objectives
Establishing a complete QA system, carefully implementing applicable national and
industrial codes and standards, ensuring complete compliance of construction
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
17
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
quality with applicable national and industrial quality requirements, eliminating major
quality accidents, and achieving the following quality indexes:
-- Rate of equipment, materials and fittings qualified: 100%;
-- 100%;Rate of unit work qualified: 100%;
-- Excellence rate of work: above 92%;
-- Rate of welds qualified at first time via NDE: above 96%.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
18
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Project Manager
QA/QC Engineer
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
19
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
20
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
21
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
22
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
23
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
24
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
25
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
b) Quality records shall adopt sample forms. After the award of the contract, the
document controller shall submit the hand-over documentation preparation program
to the owner for approval.
c) Quality records shall be true, accurate and legible. When inspection by the owner is
requested, complete quality records shall be submitted for review and verification
on synchronization with the progress of the work.
d) Maintenance and delivery of quality records and quality documents shall be carried
out strictly in accordance with the requirements of the owner and the quality
management system. Quality records and documents shall be submitted to the
owner within the specified period and in required format.
3.3.5 Quality control
The Quality Inspection Team is an independent quality inspection group consisting
of discipline inspectors. The Quality Inspection Team has right to reject use of
unacceptable materials on the site and stop or allow no start of the work in case of
any quality issue.
1) Control of inspectors and equipment
a) Inspectors
During bidding for the work, the QA/QC Engineer shall determine the number and
disciplines of inspectors according to the general arrangement of the work. After
signing of the contract, an inspection and test schedule shall be prepared and
submitted to the Project Manager for approval.
b) Inspection and testing equipment
The Quality Inspection Team shall develop an inspection and test equipment
mobilization schedule, allocate inspection and test equipment and tools, verify the
conditions of inspection and test instruments and equipment, and ensure use of
advanced reliable and sufficient inspection and test equipment in specified precision
level for complete inspection items which can meet the construction demand. All
inspection and test instruments must be certified by a qualified inspection agency,
remain in validity period, and bear acceptable tags. After arriving on the site, all
inspection and test equipment shall be registered by the Quality Inspection Team.
2) Quality inspection and test plan
a) Prior to start of the work, the QA/QC engineer shall be responsible for developing a
quality inspection and test plan in accordance with the requirements of the owner or
based on selected discipline. The inspection and test plan shall be in consistent
with the approved construction schedule and QC requirements of the contract,
codes, drawing and related standards and regulations, and include inspection and
test on all construction activities.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
26
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
b) The inspection and test plan shall identify times for quality audits and cover:
-- description of quality control points (including hold points, witness points and
classification of hold pints provided by the Contractor);
-- applicable standards;
-- acceptance criteria;
-- sample quality verification records.
c) QC methods include inspections and tests. Inspection covers visual inspection and
measurement of geometrical dimensions while test includes performance
verification.
d) TCC will carry out quality control based on the approved inspection and test plan.
Any modification to the inspection and test plan shall be carried out in accordance
with the original preparation and review procedure.
3) Quality inspection request procedure and joint inspection procedure
a) Procedure for quality inspection request and joint inspection
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
27
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Identifying quality control points for various disciplines as specified by the Owner
Carrying out self inspection based on quality control points Organizing correction
Discipline supervisor
Unacceptable
Acceptable or not
Acceptable
Filling the description, content and results of joint inspection in the joint inspection report and
signing the report by inspection representatives
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
28
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
29
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
inspected or nonconformity.
d) During construction, work/product inspection and test identification marks shall be
properly protected. No free alternation or damage is allowed. Any identification mark
to be covered shall be transferred to the external surface when required to keep.
5) Control of nonconformity
In order to avoid nonconformity or noncompliance with the requirements of
applicable code and the owner, TCC develops a nonconformity control procedure
for effective control of site construction and for timely identification and handling of
nonconformity detected.
a) Managerial responsibilities:
The Quality Inspection Team shall be responsible for management on
nonconformity, including judgment, identification, record and report of
nonconforming work/product detected. The Construction Department shall be
responsible for organizing segregation and handling of nonconformity. The QA/QC
Engineer shall be responsible for organizing evaluation on nonconformity by related
departments and developing relevant handling measures.
b)Management procedure:
Handling of nonconformity: judgment→ report → segregation → evaluation
→handling/disposition → re-inspection after handling. Detailed control procedure is
shown below:
-- Judgment: Any nonconforming sequence confirmed through inspection shall be
identified by discipline inspector and judged by the Manager of the Quality
Inspection Team .
-- Report: The inspector shall issue a nonconformity report to notify the project
management team and the QA/QC Engineer in written.
-- Segregation: Upon receiving the nonconformity report, the Construction Department
shall carry out segregation of nonconformity.
-- Evaluation: The QA/QC Engineer shall be responsible for organizing technical
professionals and inspectors to make evaluation and to determine the nature of
nonconformity, handling approach and need for preparation of handling measures.
-- Handling: The job team shall be responsible for allocating proper resources to
handle nonconformity as required by rework or repair notification issued by the
Construction Department and handling measures.
-- Re-inspection: After handling of nonconformity, the job team shall make inspection
request to the Quality Inspection Team for re-inspection by discipline inspector and
drawing of conclusion on re-inspection.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
30
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
-- Others
Upon receiving any nonconformity report from the Contractor, the Quality Inspection
Team shall carry out the above-mentioned procedure. After handling, the Quality
Inspection Team shall fill out the handling comments for submission to the
Contractor.
6) Management on corrective and preventive measures
a) Determination of corrective and preventive measures
The QA/QC Engineer shall organize and analysis on the causes of the following
issues, to make recommendations on developing corrective and preventive
measures, and to designate a department for developing measures:
--external audit result;
-- problems existing in in-process and final inspection and test;
-- nonconformity cause analysis;
--comments and complaints from the Contractor;
--comments from quality supervision department, local government and competent
authority.
b) Development of corrective and preventive measures
Measures developed shall include:
--preparation basis;
--anticipated objectives;
--procedures and methods adopted;
--control sequences and points in the process;
-- resource demands;
--scope of implementation.
c) Implementation of corrective and preventive measures
The relevant unit must implement corrective and preventive measures strictly in
accordance with the following requirements, and supervise and check on
implementation of corrective and preventive measures:
-- Allocating qualified resources. The Quality Inspection Team shall be responsible
for recognition on quality and qualification of designated individuals while the
Construction Department shall be responsible for recognition on equipment
capacity;
-- Assigning responsible individual to learn status of implementation of measures ;
-- Observing strictly process requirement, monitoring on key sequences and control
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
31
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
32
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
b) The inspector shall carry out appearance inspection and check on geometrical
dimensions;
c) The inspector shall make initial check on certificates while the competent material
engineer shall review.
d) A qualified inspection agency shall be used to carry out test on materials as
required.
e) Inspection and test report issued by the inspection agency shall be reviewed.
f) Only materials qualified in the above-mentioned inspection and test can be used.
g) The inspector shall carefully fill out the Material Warehouse-in Receiving Inspection
Record which shall be signed by all individuals involved in the inspection for
confirmation after completion of the inspection;
h) Unqualified materials shall be segregated and identified so as to avoid confusion;
i) Qualified material shall be such identified physically and on its certificate.
4) Material test
a) In case of any omitted index or doubtful index exists in material certificate, test on
such omitted index or doubtful index shall be conducted according to material
specification.
b) Material shall be subject to inspection and test on items required by the Contract or
applicable construction specification.
5) Material identification management
Materials in warehouse shall be identified as required blow to ensure accuracy and
traceability:
a) Materials stored in warehouse shall be attached with tags while materials stored in
laydown shall have signs posted.
b) Any material without clear identification on its body shall be color coded;
c) Transfer of original identification mark deems necessary during cutting of material
which may make the original identification mark incomplete;
3.4.3 Transportation management procedure
1) Loading, unloading, lifting and transportation shall be carried out as required and as
indicated on the package.
2) Proper vehicles, loading/unloading tools, lifting slings and tackles and vehicle
closing materials shall be selected according to the size, length and properties of
material to be handled.
3) Materials like pipe fittings, valves, flanges and electrodes shall be separated,
marked, seized, padded, isolated and boxed up for protection against confusion and
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
33
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
34
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
3.5 Procurement and construction progress control within the scope of work of
TCC
3.5.1 Material control shall be carried out based on the principle of ensuring work quality
and progress, speeding up turnover, cutting down consumption, saving cost and
increasing economic benefit.
3.5.2 In-process material management and control shall be carried out strictly in
accordance with the requirements on material control and of the documented
quality system procedures.
1 ) The Procurement manager shall be responsible for establishing files of
subcontractors related with the work in supply, maintaining licenses and permits for
equipment and materials supplied by subcontractors, and qualifying quality of the
supply. Any subcontractor which fails in qualification shall be timely stopped from
supplying.
2) TCC is responsible for providing the following information to the owner for review:
-- complete report on procurement at the end of each month;
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
35
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
36
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Based on characteristics of the work, quality control on the following key sequence
shall be strengthened in the progress of construction:
3.6.1 Compressor installation
1) Prior to installation of compressor, the Quality Inspection Team shall be responsible
for carrying out foundation acceptance inspection, going through interim handover
procedure and making proper foundation acceptance record.
2) During equipment alignment, size of shims, number of layers of shims and height of
shim sets as well as the levelness and coupling alignment stress after installation
shall meet the requirements of the applicable construction codes and specifications.
Discipline supervisor shall be responsible for check on elevation, orientation and
alignment of equipment.
3) Equipment grouting shall be subject to continuous monitoring by discipline
supervisor. Prior to grouting, check on foundation preparation shall be made. During
grouting, attention shall be paid to air release and compaction. After completion of
grouting, both foundation and body of equipment shall be cleaned and the
procedure for hidden work timely handled.
4) Prior to coupling alignment, check shall be made to prevent imposing of any stress
from piping on the inlet and outlet of equipment. Any remaining stress shall be
relieved through adjustment of piping. Otherwise, no alignment shall be allowed to
proceed. Reversed rim method or optical/laser method shall be adopted for
coupling alignment.
5) Prior to commissioning, various preparations shall be made according to the
commissioning plan and relevant provisions. Inspector shall request for confirmation
by the Owner’s Representative on conditions for commissioning. The site for
commissioning shall be barricaded with warning tapes and banned from entry by
any unauthorized personnel. The discipline inspector shall be responsible for
continuously monitoring on the commissioning process and supervising the
inspection on load, temperature, pressure, vibration and flow. After completion of
commissioning, both the site and equipment shall be cleaned out.
3.6.2 Process piping installation
1) Construction preparation: The QA/QC Engineer shall attend design
briefing/clarification and joint review on construction drawings, and coordinate
interface with other disciplines, especially control on connection of process pipeline
with equipment.
2) Material inspection: The Supply Department shall be responsible for controlling
strictly on quality of pipes, valves and their fittings in accordance with the
established material inspection procedure, verifying grades, lot Nos. and quality
certificates, and carrying out visual inspection, check on geometrical dimensions
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
37
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
38
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
obtained.
2) The discipline supervisor shall organize weld identification, and make proper record
of welding work. During site welding, the discipline supervisor shall carry out
continuous monitor on welding quality. Daily weld inspection and report system is
adopted. The discipline inspector shall monitor on edge preparation and assembly
gap, carry out appearance inspection on welds based on requirements of quality
control points, attach inspection identification marks (code of inspector) on the
qualified welds, notify the NDE team the specified percentage of welds subject to
NDE, and enter the inspection results into the computer for use in construction
statistics.
3) The identification marks of pipe welds shall be parallel to the axis of the pipe with
content and format as shown below:
Pipe diameter ≥φ89 φ57≤Pipe diameter<φ89
Pipeline No.
4) In case of welding on rainy days or days with wind speed, temperature or relative
humidity exceeding the specified limit, effective measures shall be taken for
protection as specified in the statement of methodology. Otherwise, no welding shall
be allowed. Discipline engineer shall study welding quality issues, find root causes,
and carry out quality improvement.
5) The Quality Inspection Team shall be responsible for establishing dossiers for
welders for timely and accurate record of performance of welders, periodical
summary and study on causes for deviations and adoption of corrective measures.
Any welder with the current monthly rate of welds qualified at first time lower than
90% shall be temporarily removed from job, provided with training and allowed to
return his job after qualified.
6) After completion of the work, the Quality Inspection Team shall be responsible for
submitting all original NDE reports and X-ray films to the Owner for review.
3.6.4 NDE control
1) Computer-aided management is adopted by TCC on pipeline welds and NDE. The
work procedure for inspection is shown below:
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
39
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Piping welding
Job team
Job team
Extend percentage
Counting welds by welders and notifying NDE
of welds subject to
personnel NDE NDE results
Quality Inspection Team
Quality Inspection Team
NDE
Inspection agency
Unacceptable
Inspection agency
Acceptable
Inspection agency
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
40
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
41
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
4.1 Introduction
4.1.1 Scope
The Project HSE Plan: Site Management [this document] defines how TCC will
discharge its responsibilities with respect to a body of HSE requirements. These
include the Corporate procedures of the participating TCC Companies, the
requirements of the Owner.
This HSE Plan: Site Management [this document] applies to all site activities
associated with the implementation phase of the project, which includes the
following:
Site surveying
Site preparation
Construction
Commissioning
4.1.2 Safety Performance Goals
The targets of this project are as followings:
Fatality=0
Fire/Explosion=0
Property Damage (the costs of accident > 6 thousands USD )=0
Total Recordable Incident Cases < 0.4 (per 200 K man-hours)
4.1.3 HSE Organization
The HSE team is shown in the following Figure:
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
42
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
HSE Engineer
Worker
4.3.1 Commitment
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
43
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
44
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Optimise the use of continuous improvement practices as the basis for Zero
Accident Performance initiatives;
Prove to customers that TCC is dedicated to safety excellence; and
Select subcontractors that are committed to "Zero Accidents Performance".
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
45
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
46
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
They shall assist in, and coordinate the development, presentation and result
measurement of HSE awareness training modules for all site personnel and
participate in monitoring HSE activities including audits, sampling and inspections.
They shall liaise closely with Subcontractors, internal and external safety staff, and
other personnel who may influence the overall safety management performance.
Safety Supervisors shall also assist the HSE Manager in conducting impartial
investigations into any incident whether or not it results in injury, damage, ill health
or environmental impact.
They shall conduct weekly meetings with Subcontractors Safety Supervisors and a
Safety Supervisor will also be nominated as Secretary of the monthly HSE
Committee.
4.5.5 Subcontractors
All Subcontractors on the project shall be capable of demonstrating the existence of
formal HSE management system within their companies. The minimum
demonstrable requirement shall be:
Details in respect of historical HSE performance
A structured safety policy document
A HSE Plan specific to their operations
Safe working procedures
Subcontractor management and supervisors shall:
Ensure compliance with the HSE programme
Take responsibility for the HSE programme under their control
Conduct daily inspections and remedy unsafe acts and conditions
Participate in the site audit programme
Train and monitor workers for safe work practices
Conduct daily Toolbox meetings
Attend monthly safety committee, weekly Safety Supervisor meeting, and
other meeting as deemed necessary by Contractor or Owner
All Subcontractors shall maintain a minimum ratio of HSE representatives to
employees of 1:100.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
47
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
In addition, the HSE team is responsible for initiating or providing assistance to other
members of the project team in the following areas:
Formulation and determination of suitability of HSE rules and procedures;
Participation in planned audits and inspections together with line management;
Unscheduled performance monitoring efforts; and
Administration of HSE training that may be required beyond the foreseen
project-specific training.
The structure of the HSE organization, for the implementation phase, will change to
address evolving requirements as the project moves forward through detailed design
and on into construction. Recognizing this, the implementation phase should be
viewed in two stages:
Detailed design and
Mobilization/construction
In developing a plan for these distinctly different stages of activity, TCC will take
particular care to ensure that the HSE organization is consistent with regards to the
leadership and technical support needed to carry critical processes forward without
interruption and sustain progress toward achieving strategic HSE objectives.
In both stages of the implementation phase, TCC will place emphasis on retention of
key HSE staff that will transition forward into onsite positions, carrying job
knowledge and ownership of planning decisions forward into execution.
4.6 Standards and Specifications
The following laws, regulations, codes, standards and specifications will be applied
in order of priority in this Project:
HSE related local community and municipal Regulations and Codes
Owner’s HSE
Owner Standards, Specifications, Plans, procedure and work practices
HSE laws and Regulations of the local regulation
TCC’s HSE, Plans and programs, procedures and work practices
Subcontractor’s and Vendor’s method statements
4.7 Communications
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
48
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
4.7.2 Meetings
A number of formal meetings and discussion forum will be used to deliver HSE
information. These will be detailed in the TCC HSE Communications procedure.
They include:
Daily pre-start team meetings
Weekly tailgate meetings lasting 15-20 minutes in duration will be conducted by
the supervisor
Weekly supervisor meetings shall be conducted and the contractor’s
supervisors shall attend
Special meetings to deal with any exceptional events, circumstances.
A number of formal meetings and discussion forum will be used to deliver HSE
information to subcontractors. These will be detailed in the TCC Sub-
contractor/Vendor Monitoring procedure. They include:
Pre-bid HSE meetings for short listed contractors
Kick off HSE meeting award of a contract
All contractor safety representatives shall attend a daily contractor safety co-
ordination meeting
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
49
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
50
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
51
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
52
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
53
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Work site inspection, hazard identification, and control and recovery processes
Environmental compliance requirements
Employee selection/work assignment and coaching
Emergency response/contingency plans and procedures
The TCC orientation programme will be co-ordinated with similar orientation
initiatives undertaken by the construction contractors to ensure that the orientations
are consistent and complementary. Orientation records will be maintained to confirm
the status of all employees at the job-site.
The orientation programme will be developed during the detailed design phase and
for implementation at the time of mobilization. HSE functional co-coordinators in the
PMC directorate office will be responsible for developing their respective portions of
the overall HSE orientation module.
4.9.4 Certificates
In order to encourage active participation, certificates of attendance will be provided
to participants for successfully completing special training sessions.
4.9.5 Certificates
Visitors will be given appropriate orientation and training, prior to obtaining site
access credentials. This will be described in the TCC HSE Site Orientation and
Training procedure and will include:
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
54
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
4.9.6 Rules
TCC will publish a set of project HSE work rules in booklet with pictograms
appropriate to the literacy level of the work force. This will be described in a TCC
General Safe Work Practices procedure.
Every project employee receives this booklet during HSE orientation. Each
employee will acknowledge receipt of the booklet and the orientation. A test will be
given to verify comprehension. These items will be retained in the HSE files.
4.11 Health
The primary goal is to provide a workplace that is, as far as reasonably practicable,
free from recognized workplace health hazards by:
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
55
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
56
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
57
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
material on site.
TCC will ensure that employees are trained in the recognition, proper handling and
use of hazardous substances. Contractor’s New Employee Orientation will include
introductory training on the topic of hazardous substances. However, Subcontractors
will provide specific hazardous material training for its Project employees whose
work involves the use of any hazardous material under its control. Such training will
be properly documented, filed and made available to Owner.
Subcontractors will properly label all hazardous substances and/or chemicals that
have been transferred from the manufacture’s container into another container.
Inspection will be made and documented by Contractor to ensure that adequate
labeling occurs.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
58
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Contractor will provide a basic first aid with establishment. These facilities are for
use by the entire site personnel.
TCC will promote First Aid Training, and require contractors to have a ratio of trained
employees to work-force population trained in basic first aid and CPR. This is
described in the TCC HSE Site Orientation and Training procedure.
4.13 Safety
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
59
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
4.13.3 Scaffolding
The TCC HSE Scaffolding procedure will include details such as:
Scaffold platforms shall be fully planked and all sides protected by standard
guard-rail system
Capable of supporting 4 times the maximum intended load to be imposed upon
them
All scaffolding shall be tagged and inspected
Erection or modification of a scaffold may only be performed under the direction
of a trained, competent scaffold builder, and designed by an engineer for all
scaffolds over 20 meters in height
Safe access/egress to all working levels of scaffolds shall be provided
Special scaffolds (hanging scaffolds, 2 point suspension scaffolds, etc.) shall be
designed by a competent engineer and erected with all necessary personnel
safety equipment installed, such as rope grabs and lifelines
All personnel accessing scaffolding shall receive scaffold user training
4.13.4 Barricading
The TCC HSE Barricades procedure will include details such as:
Barricades shall be properly erected and in such a manner that they provide
adequate protection from the hazard and do not impede the work of other
subcontractors unless TCC approves such placement
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
60
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
61
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Spoil material shall be placed at least 1 meter (3 feet) away from the excavation
edge
Where trenches or excavations exceed 1.5 meters (4 feet) in depth, protective
systems must be used
Warning signs and barricades shall be installed in a manner that prevents
accidental entry into the trenched or excavated area
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
62
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
such as:
All ladders used on the Project shall be approved by TCC HSE prior to use
The use of metal ladders will be limited and wood or fibre-glass (not metal) is
preferred
All ladders shall have non-slip feet
Wooden ladders shall be treated with preservative
Ladder shall be inspected quarterly and demarcated to identify the inspection
Ladders for egress and/or to conduct low level work of short duration is
acceptable, but ladders may not be used in lieu of scaffolds as a primary means
of conducting work of longer duration, or stairways
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
63
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
as:
Use of the personnel platform is prohibited until all conditions are in compliance
with the TCC permit requirements
Personnel platforms (baskets) shall be designed by a qualified engineer and
manufactured by competent personnel
The crane/derrick used shall have an operational anti two block device and
locking devices on the hook
A positive means of communication shall be provided between the crane
operator and employees in a crane suspended personnel platform
Employees in the platform shall wear full body harnesses attached to a
designated anchor point
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
64
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
cylinder caps in place when provided by the supplier, positive upright securing
of bottles, and maintenance of safe distances from ignition sources
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
65
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
regulations
Seat belts shall be used when provided
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
66
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Subcontractors will provide and ensure that all tools are used in accordance with the
manufacturers’ recommendations, have required guards in place, and are
maintained in good working order.
All job made tools shall be subject to inspection and approved by the TCC HSE
manager prior to use. Generally handmade tools shall be prohibited on the project.
All tools and equipment shall be used and maintained in accordance with
manufacturers’ recommendations. If expectation to this rule are needed (i.e.
spreader beams), they will be brought to PMC attention for review and acceptance
prior to use.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
67
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
4.15 Environment
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
68
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
4.16.2 Inspections
Identification and correction of substandard behavior, conditions or equipment is the
ongoing responsibility of all project personnel. Daily inspections will be conducted by
all supervisors. Supervisors who direct the work activities of employees are
responsible for assessing the work processes within their area for substandard
conditions, practices, and at-risk behavior.
The systematic and scheduled project inspections will be performed in accordance
with the HSE Inspection and Monitoring procedure and the Environmental
Monitoring and Inspection procedure.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
69
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
70
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
procedures, and work practices are in place and are working effectively. All actions
as a result of audits will be followed up and closed out. The findings of the HSE
audits will be communicated to the TCC corporate HSE committee for review and,
where applicable to improve the HSE management system.
Audits and reviews will focus on management effectiveness. The applicable sections
of the HSE management plan and associated plans and procedures will be
assessed to determine compliance by the project and the effectiveness of the overall
programme. Individual leadership, commitment, and service will also be reviewed.
Management of change and process improvements will be continually and
aggressively pursued. The audits will be both internal (self-assessment) and
external, involving qualified off-project personnel.
TCC will use information delivered from its assessment process in Supervisor Safety
Meetings to enhance supervisor safety awareness and improve overall Contractor
safety performance.
This is described in the TCC HSE Assessments procedure.
4.17.2 Owner Inspections
Owner will perform periodic HSE assessment of the Project. Contractor will provide
Owner with timely, complete and open access to its safety process, files. Records,
etc., and will participate in this assessment as/if required by Owner.
PRC Government inspections
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
71
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Contractor’s Safety Induction for new employees will include information about
employee responsibility for reporting all injuries, illnesses, property damage and
near miss incidents. Contractor HSE Manager will promptly report all such
occurrences to Owner and will take the lead in the investigation, documentation and
initiation of corrective action. Contractor will keep records of all incident/accident
investigations in a format acceptable to Owner and will provide Owner with a copy
within 24 hours of the occurrence.
The following safety performance indicators data will be recorded and reported in
this Project:
Near-misses
First Aid Case Injuries
Medical Treatment Case Injuries
Restricted Workday Case Injuries
Lost Workday Case Injuries
Partial Disability Case Injuries
Permanent Disability Case Injuries
Fatalities
4.18.2 Registers
The following registers will be retained on site:
Inspection of Excavations
Inspections of Lifting Gear
Inspection of Electrical Powered hand tools
Inspection of Pressure Vessels (e.g. air receivers)
Scaffolding
Inspection of Cranes and Lifting machines
Explosive Powered Tools
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
72
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Watch Tower
HSE Manager
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
73
Subcontractor
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
74
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Accident Detection
In case any accident happens, the HSE manager shall be firstly informed.
HSE manager shall investigate, and try to avoid similar accident happen.
SHE manager shall submit Accident Report (as per TCC’s forms) to PM, Owner,
relative local authorities.
Subcontractor shall submit Accident Report, Injury and Death Accident Report,
Person Accident Record, Automobile Accident Record.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
75
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
TCC’s Supervisor
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
76
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Owner’s
Fire-fighting Organization
Local Owner’s
Fire-fighting Specialist
Inform
Fire Extinguishing
Chart -5 Fire Extinguishing Procedure
TCC and Subcontractors shall inspect all of the fire-fighting equipment monthly, to
ensure them in good condition.
(4) Fire prevention
Safety Engineer (SE) shall try his best to prevent injury and provide First Aid
treatment. SE is responsible for saving by every effort. Check and inspect
Subcontractor’s fire prevention possibility on the other time.
Post fire-fighting team’s telephone number and contact person’s name at the
telephone.
Fire prevention include:
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
77
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Administrator
Hospital
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
78
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
79
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
80
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
81
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
82
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
83
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
84
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
screw adjustment
basement
support plate
grouting depth
50 ~ 70mm
equipment basement
2) Put the motor into position, evenly place temporary adjustment shims near the
supporting plate with elevation 0-2mm lower than basement installation elevation.
Adjust the extension length of the basement jacking screw for relative error less
than 1mm.
4) Install the anchor bolts to the machine unit and place the positioning ring. The
anchor bolts shall be de-greasing treated by wiping the molybdenum disulfide
grease on the screwed part. Clearance of bolts in the reserved holes shall comply
with relative document. anchor bolt positioning ring
anchor bolt
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
85
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
5) Put the gradienter on the manufacturer set datumn level of the combined basement,
accurately adjust with adjustment screw (assisted by mini jack) for longitudinal and
transversal leveling tolerance ≤0.10mm/m , elevation tolerance ≤3mm, and the
positioning tolerance ≤2mm.
5.1.2.7 Machine unit shaft ends distance adjustment and pre-alignment
1) Duly adjust the shaft ends distance and overall machine unit pre-alignment after
unit positioning and primary alignment; take the shaft position and thermal
expansion value into consideration while adjusting the shaft ends distance.
2) Check the lateral clearance of the anchor bolt inside the reserved hole and the
machine unit level for compliance with requirement after the primary alignment.
3) Pre-install the coupler, check the coupler length compatible with shaft ends
distance.
5.1.2.8 Machine unit anchor bolts grouting and curing
1) For the grouting of the reserved through-way anchor bolt hole of the machine unit,
the bottom template is required to tightly contacted with the foundation, the upper
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
86
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
87
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
surface condition of the shaft and bearing with magnifier. Check bearing alloy and
pad junction condition by kerosene dipping method.
5) Fix radial bearing on the shaft, measure the bearing clearance and bearing back
tensile.
6) Install the stop bearing, measure stop clearance, take contrast with origin value.
7) Number the dismantled parts for correct restoration.
8) While restoration, wipe lube oil or greased as per requirement.
5.1.2.12 Oil system flushing
1) Prior to oil flushing, carry out manual cleaning on oil tank, filer of oil tank, oil cooler
and valves on oil line for removing the rust and removing dust by flour ball
adhesion. Carry out pickling and passivation treatment to oil line, then blow it with
compressed air. If the installation cannot be performed at the time, seal the pipe
ends.
2) Dismantle the core of the oil filter for proper storage. Break the oil filling line of the
oil console in proper position and lead it to oil tank by hose for oil console system
self circulation. The position where the temporary hose entering the oil tank shall be
fixed with 120 mesh filter net and proper measures should be taken to prevent
network falling into oil tank.
3) After oil console self circulation, restore the broken line. Connect the inlet and outlet
line of bearings lube oil, sealing oil, and control oil with temporary over-cross line,
for short-circuit oil system circulation, which may prevent foreign matters entering
bearing and control oil line. Place 120 mesh steel filter net in position where oil
return trunk entering oil tank for oil filling 3 phases filtration. While circulation,
repeatedly heating and cooling the oil, beating the piping with wooden hammer,
lead the compressed air into oil circulation line for barbotage to accelerate the
circulation progress.
4) If the above steps are performed acceptable, restore the pipe line (the sealing oil
line remains connection with over-cross line), dismantle the upper bearing block,
place 180 mesh filter net on each inlets, the filter shall be filled with formal filtration
elements, perform the oil circulation as per normal procedure.
5.1.2.13 Compressor train test run
1) The work shall only be performed after the motor sole test run is acceptable.
2) Double check the shaft alignment data, connect the coupler.
3) Carry out the test run as per the requirement of the approved test run plan, make
proper test run record during the operation.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
88
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
89
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
3) While pipeline blowing, all valves connected with cold box shall be closed to prevent
dirt being blown into tower again.
4) While system blowing, the inlet and outlet of the turbine expander and the
circulation liquid oxygen pump shall be broken, remove the filter core on the inlet
pipeline and all the orifice plates for proper storage.
5) The blowing of each pipeline shall be performed repeatedly for no less than 4h.
6) The blowing shall be inspected as per relative regulations and stopped when it is
acceptable.
5.2.6 Pressure test
1) Carry out pressure test after the pipeline system blowing.
2) The system shall be tested with pressured and oil free dry air.
3) Prior to pressure test, all the safety valves, valve position hole of automatic valves
in switching type flow, throttle valves, the turbine expander inlet and outlet, air-
booster inlet and out let, as well as the flange connection where the main heat end
of heat exchanger exiting the cold box pipeline shall be blinded.
4) Pressurize to 20KPa, check welding joint, flanging and other dismountable
connection for obvious leakage, if leakage found, release pressure for reparation or
fastening the dismountable part; after the above process, increase the pressure to
50KPa for detail inspection, if leakage remains, release pressure for reparation, or
otherwise gradually increase pressure to testing level. Check the leakage with
grease free soap water.
5) When the pressure test is acceptable, take out the pressure test blind, install the
new gasket and tighten the bolt and nut.
6) After blind taking out, carry out another pneumatic test at working pressure.
5.2.7 Whole equipment body naked cool test
1) The equipment operator shall be familiar with the process of the packaged air
separation equipment.
2) Prior to test, full heat and cool the fractionation tower; the air compressor, expander,
switching valve, E/I control system and safety protection device shall be made
ready for working.
3) The test shall be performed as per equipment technical document requirement, cool
the main equipment like rectification tower, condensation evaporator to the
temperature as low as possible and hold 1-2h, then cool the whole fractionation
tower, when the outer surface of all the equipment and pipeline appear hoarfrost,
hold the condition 3-4h.
4) After equipment starting up, carefully monitor the variation of each aspect, check
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
90
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
the whole operation process for abnormal status, make relative record (pressure
and temp. etc) every 0.5h. In the cold condition, check each part of equipment for
deformation, judge the leakage upon frost status and mark up the leakage position.
5) After naked cool test and prior to frost melting, re-fasten the connection bolts of all
the flange and valves of the cold box.
6) When the fractionation tower temperature resumes to the normal status, check the
overall system fluency with working pressure, the leakage shall be immediately
rooted out.
7) After the whole body cold test, when welding reparation, sealing surface treatment
and partial renovation is required, the naked cool test shall be re-performed, as
necessary.
5.2.8 Insulation material packing
1) The insulation material shall be packed only after acceptance of whole equipment
body naked cool test, the work shall be performed with fractionation tower and
foundation upper surface kept dry.
2) The insulation material shall be packed in compliance with the following
requirement:
a) The insulation material shall not be mixed with flammable material;
b) The insulation material shall be kept with avoidance of humidity, which shall not be
packed in raining or snowing weather condition;
c) The work shall be done without damage to measuring instrument tube and cable;
d) The packing shall be maintained compacted without hollow;
e) Take safety protection measures.
3) When packing the insulation material, the equipment and pipeline inside the cold
box shall be filled with air of pressure 45 ~ 50kPa (gauge readings), slightly open
the valve of each measuring instrument tube for ventilation, meanwhile energize
each platinum resistance, check the measuring instrument tube and cable for any
malfunction.
4) The insulation material shall be packed to the top of the cold box without any
holiday. Set net at the packing inlet to prevent granule falling into the cold box.
5) After the packing, seal the inlet (by fixing manhole cover).
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
91
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Among these equipment, the 3 sets of storage tanks with item numbers
T622A/B,T722, are of the most heavy ones in horizontal type. The 2 sets of cold
boxes are required installed vertically with unit weight of 84t, which are the most
difficult ones to be lifted and determine the selection of lifting crane. The 2 sets of
Pre-treatment skids with unit weight 42t are in horizontal type.
On basis of our construction experience and the analysis on the project equipment,
the cold boxes and storage tanks are all intended to be lifted by M250 and 272
crawler crane. The lifting of the cold box shall be tailed by LTM1100 auto crane that
can also be used as the main lifting device for Pre-treatment skid and Main Air
Compressor. Other equipment would be lifted by TG500E 50t capacity auto crane.
5.3.2 Lifting process
5.3.2.1 Work organization
Although there are not many large scale equipment to be lifted in this project, the
entrance and exiting of the crawler crane is the most important point of the work.
Therefore, the above mentioned equipment (equipment to be lifted by 272t crane)
are preferred to be delivered to site centrally, for the large scale crane fulfill the
lifting at one time by entering site at one time.
Other equipment are preferred to be delivered to site centrally for convenient lifting
organization
5.3.2.2 Process parameters:
Auxiliary
Main Main crane parameters
crane
Description Weight lifting
Boom Capacity
crane Capacity
length radius
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
92
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Main Auxiliary
Main crane parameters
Description Weight lifting crane
Cold box 84 272t
crane 51.8 13 102.3 100t
Storage Tank 91.4 272t 51.8 13 102.3 ——
Pre-treatment
42 272t 51.8 18 51.7
skid
Main Air
19 100t 27.8 10 27.2
Compressor
5.3.3 Please refer to construction plot plan for lifting plot plan.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
93
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
The major material of the pipeline in the air product company concerns carbon steel,
stainless steel and aluminium and magnesium alloy. The welding shall be performed
upon the nature of various materials for assurance of welding quality in compliance
with design requirement. The welding work of stainless steel and aluminium and
magnesium alloy is the critical point of this project, which deserves control as critical
process.
5.4.2 Welding management
5.4.2.1 PQR management
The PQR and WPS must be available prior to process pipeline welding, the welding
principal engineer is required to prepare the WPS suitable to this site construction
and submit by accompanying PQR to Owner/Contractor for confirmation on basis of
considering the material condition of the project and the company accumulated
mature PQR with combination of project condition.
5.4.2.2 Welder management
1) All welder participating project welding work shall subject to examination. The
construction supervisor is responsible for filling in the Acceptable Welder List and
submit to Owner/Contractor relative department for confirmation.
2) During the course of construction, the quality inspector is responsible for taking
continuous tracing to welder performance, who has right to stop the work of the
welder that is not competent for site construction quality requirement and require
him to return the position after re-exam.
5.4.2.3 Welding material management
The key point of welding material management is to: ensure the welding material
quality; ensure the application of correct type of welding material.
The dedicated welding material warehouse shall be set on site. The full time store
keeper is responsible for the management of welding material in-warehouse
registration, drying, issuing and reclaiming with detail requirement as follows:
1) Warehouse
a) The warehouse shall be equipped with dehumidifier and thermometer for
maintaining the house temperature 5-35℃ and humidity 60%.
b) All the in-warehouse welding material must be accompanied with principal material
engineer confirmed quality certificate. The in-warehouse welding material shall be
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
94
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
The welding material shall be issued upon the requisition car. The welder who
requisite the electrode shall put the electrode into the quiver at the moment the
electrode is in hand. The welder is only allowed to ask for less than 3kg electrode
each time and consume them within 4h. The outstanding ones beyond 4h shall be
re-dried prior to next using. The storekeeper is required to make duly electrode
issuance record.
5.4.3 Welding of stainless steel material
5.4.3.1 Welding process
1. drawing review, → 2. measures preparation, → 3. tech. brief, → 4. bevel
preparation, → 5. fitting up, → 6. tack welding, → 7. welding, → 8. exterior
inspection, → 9. NDT, → 10. recording, → 11. reparation
5.4.3.2 The major problems to be tackled for stainless steel material welding is the joint
corrosion resistance( intergranular corrosion and stress corrosion) and the hot crack
sensitivity, the major measures are as follows:
1) Select compatible welding material.
2) Apply less linear energy, multi-run and multi-layer, speed up joint cooling.
3) Select reasonable assembling sequence, minimize residual stress.
4) Completely root out the grease and other adhesion on welding wire and bevel.
a) The welding method: material DN≤2″ shall be welded by full argon arc welding;
material DN>2″ shall be welded by argon arc welding backing, filled and covered
with SMAW. Prior to application, grease and other matters on the surface of the
welding wire shall be get rid of. The electrode shall be dried as per regulation.
b) The fitting up shall be performed for assurance of neat inner wall joint with max.
miss-match tolerance less than 0.55mm.
c) The tack welding shall be of over-cross type, TIG. The tack welding shall be ground
off prior to formal welding performance. The tack welding should be of 10-20mm
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
95
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
96
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
8) During the course of welding, the layer oxidation film, the over height overlap and
other deficiency must be duly removed. The roof of double side welding or backing
welding joint must be gouged by mechanical method.
9) When the nozzle is attached with spatter that affect the air flow, the spatter must be
removed or the nozzle must be replaced. The tungsten electrode shall be repaired
or replaced when the tip of it is polluted or in abnormal shape.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
97
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
The oil avoidance pipeline such as oxygen pipeline and its other components must
be subject to degreasing prior to system test.
5.5.1 Requirement to cleaning agent
Determine the type of cleaning agent according to integrated condition of plant
process characteristics, cleaning volume, type of cleaning, pipe diameter, pipe
fitting process, etc. The principle is as follows:
1) For scrubbing method: Carbon tetrachloride or PCE
2) For soaking method: Carbon tetrachloride or PCE
3) For circulation cleaning: Carbon tetrachloride
5.5.2 Construction procedure
In principle, carry out the chemical cleaning upon process system (except for large
diameter pipe that is subject to scrubbing cleaning along with the prefabrication), in
the following procedure:
1. preparation of technology, machinery and chemicals, → 2. pipeline interim hand
over after erection, → 3. dismantling parts to be cleaned, → 4. cleaning
classification, → 5. scrubbing cleaning of large diameter pipe spool or vessel, → 6.
equipment attachment, E/I parts soaking, → 7. mini diameter pipeline circulation
cleaning, → 8. nitrogen purging of the cleaning parts, → 9. cleaning part ultraviolet
inspection , → 10. wrapping cleaning parts by plastic sheet for installation, → 11.
reinstalling the dismantled parts, → 12. system pneumatic test
5.5.3 Cleaning classification and key points
1) The prefabricated pipe spool more than DN100 shall be manually scrubbed.
a) The prefabricated and erected pipe spool shall be dismantled for cleaning. The
equipment shall be scrubbed after installation. The instrument shall be scrubbed
prior to installation.
b) Contain the cleaning chemicals in plastic basin or barrel, scrub the internal surface
of pipeline, equipment and instrument with brush, grease free clothe or silk clothe,
long pipe spool may be scrubbed by come-and-go pulling the rag bound with clean
wire (galvanized wire)
c) The cleaned parts shall be placed in clean area and exposed to natural air drying.
d) The cleaned parts shall be subject to degreasing quality inspection with black light
lamp. The acceptable one shall be sealed on the opening with clean plastic sheet.
After cleaning, all the nozzles of equipment must be sealed with plastic sheet for
installation.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
98
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
99
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
3) When the above mentioned methods are not practical, sample the solvent having
been subjected to parts cleaning for grease analysis, the result that grease content
in the sample is less than 350mg/l is acceptable.
5.5.4.2 Pipeline restoration after cleaning:
1) While pipeline restoration, ensure the on line valve, special part and medium in
same flow direction, the valve operation position shall comply with design
requirement.
2) The pipe supports and hangers, instrument temperature and pressure detecting
elements, fasteners, and sealing elements shall be completely restored in required
system tightness condition without any omit.
5.5.5 Finished product protection
1) No matter what type of cleaning method adopted, performance of pipeline
dismantling or connecting temporary circulation cleaning hose shall not change the
original shape of the pipeline.
2) Temperature and pressure detecting elements, instrument and instrument control
valve on the pipeline must be dismantled and restored by instrument workers.
3) The dismantled parts of the pipeline, no matter to be cleaned or not, shall be in
proper custody for avoidance of damage, loss or contamination.
4) After pipeline cleaning, the pipeline parts shall be duly and cleanly restored; the
parts or openings that are not to be restored on that day must be wrapped or sealed
with clean plastic sheet.
5) Scaffolding used during cleaning course or the dismantling of them shall not knock
on or damage any of the pipeline parts.
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
100
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Origin or Year of
Equipment Type Capacity Quantity
similar manufacture
Civil Equipment
Manitowoc
Crawler 250t America 1994 1
M250
Truck crane LTM1100 100t Germany 1986 1
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
101
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Origin or Year of
Equipment Type Capacity Quantity
similar manufacture
Double-raw car CA10462 1.5t Changchun 1996 1
Prefabricationequipmen
t
Bridge crane L=15 5t 5t Tianjin 1995 1
Erection tools
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
102
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Origin or Year of
Equipment Type Capacity Quantity
similar manufacture
Pneumatic wrench 11/2" 2
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
103
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
104
CHINA TIANCHEN CHEMICAL ENGINEERING CORPORATION
Address: No. 521, Jingjin Road, Tianjin, China
Proposal for Engineering Design and Construction Service of AHG ASU Project in YANBU, KSA
105