Exam Based Assessment - Practical – 25%

Program Computer and Information Science Division (CIS)

Course CIS4603- Project Management

Academic Honesty Statement


In accordance with HCT policy LP201- Academic Honesty
• Students are required to refrain from all forms of academic dishonesty as defined and explained in
HCT procedures and directions from HCT personnel.
• A student found guilty of having committed acts of academic dishonesty may be subject to one or
more of the disciplinary measures as outlined in Article 33 of the Student and Academic
Regulations.
‫إفادة األمانة األكاديمية‬
‫كاديمية‬B‫مانة األ‬B‫ األ‬LP201 - ‫وف ًقا لسياسة كليات التقنية العليا‬
‫ واإلجراءات الخاصة بكليات التقنية‬B‫ كما هو مبيّن وموضح في السياسات‬،‫• يُطلب من الطلبة االمتناع عن كافة أشكال سوء األمانة األكاديمية‬
.‫ الصادرة من موظفي الكليات‬B‫ والتوجيهات‬،‫العليا‬
33 ‫• في حالة ارتكاب الطالب أي شكل من أشكال سوء األمانة األكاديمية سوف يتعرض الى واحد أو أكثر من التدابير التأديبية على النحو المبين في المادة‬
.‫من األنظمة األكاديمية‬
Signature: _____________________________________________

Student HCT ID: Student Name:

For Examiner’s Use Only:

Question 1 2 3 4 Total

Course CLO CLO2 CLO4 CLO3 CLO3

Marks Allocated 15 30 25 30 100

Marks Obtained
Student Name:
Student No:

Question 1 (CLO2) (15


marks)

Noor is a Project Estimator and she is computing the estimated duration for collecting
requirements using the PERT formula. According to her experience in the worst case,
this activity would take15 days. When there are no problems at all then 8 days are
required. Under normal conditions 10 days, it would take days. Calculate the
estimated duration using the PERT formula and input the following values. (15
Marks Total)

1- Identify Optimistic Duration [OD] (2 marks)

- 8 days

2- Identify Most Likely duration [ML] (2 marks)


- 10 days

3- Identify Pessimistic Duration [PD] (2 marks)


-15 days

4- Identify duration calculated using PERT formula. Round your answer to zero
decimal places [DURATION]. (9 marks)

- PERT weighted average = optimistic time + 4X most likely time +


pessimistic time
6
- 8 + 4*10 + 15 / 6 = 10.5

CIS4608_BL_201920 pg. 2
Student Name:
Student No:

Question2 (CLO3) (30 marks)


Network Diagram
Considering the following project activities:
Activity Duration (days) Predecessor activity
A 2 -
B 3 A
C 2 B
D 2 A
E 2 D
F 2 C,E
G 1 F

a. Draw a network diagram for the project (8 marks)

2 4
4 6
3 D2 5 E2
5 7
ES

CIS4608_BL_201920 pg. 3
Student Name:
Student No:

EF

1 2
2 5 5 7 7 9 9 10
0 A2 2 B3 C2 F2 G1
2 5 5 7 7 9 9 10

LS LF

b. How long does the project need to be completed? (1 mark)

10 days

c. Calculate ES, EF, LS, LF, and float for each activity

(12 marks)

Float A= 0

Float B= 0

Float C= 0

Float D =1

Float E = 1

Float F = 0

Float G = 0

d. What is the critical path for this project? (3 marks)

- ABCFG

e. What will happen if activity G took 4 days instead of 1? (2 marks)

- The project will be late – delay 4 days

f. What will happen if activity E took 5 days instead of 2? (2 marks)

- The project will still be delivered on time, activity E has a float of 1 days

CIS4608_BL_201920 pg. 4
Student Name:
Student No:

g. What can you do to make up for delays, list two techniques that you can use for

schedule compression? (2 marks)

- Crashing and fast tracking

CIS4608_BL_201920 pg. 5
Student Name:
Student No:

Question3 (CLO4) (25


marks)

Farah is the project manager for an application development project. The project budget
is AED 200,000. The project should be finished in 8 months.

By the end of the fourth month, Farah and her team should have completed 60% of the
work. She has completed 65% of the project and spent AED 150,000.

a. Calculate the following: BAC, AC, PV, EV, CV, SV, CPI, SPI, EAC and ETC.
(20 marks, 2 marks each)

BAC = 200 000


AC = 150 000
PV = 4/8 * 200 000 = 100 000
EV = 0.65/1 * 200 000 = 130 000
CV = 130 000 – 150 000 = -20 000
SV = 130 000 – 100 000 = 30 000
CPI = 130 000 / 150 000 = 0,867
SPI = 130 000 / 100 000 = 1.3
EAC = 200 000 / 0.867 = 230 680.5
ETC = 230 680.5 – 150 000 = 80 680.5

b. How is the project doing in terms of cost and budget? (5 marks)


- The project is over budget

CIS4608_BL_201920 pg. 6
Student Name:
Student No:

Question 4 (CLO3) (30 marks)


Consider a simple web design project which is categorized into following three
deliverables:

 Designing of the website which will include selecting a layout, designing


graphics and approving design
 Project content which will include selecting the content writers, writing the
content and inserting the content on web pages.
 Development which will include setting up the website in test environment,
performing test, approving website and setting it up in a live environment.

The project requires one graphic designer, two content writers and one web developer.

The graphic designer charges AED150 per hour and will require 10 hours to complete
the required designs.

The content writers who should be hired to write the web content charge AED100 per
hour, and they need 30 hours of work to complete the job.

Web developer charges AED200 per hour for 40 hours of work required.

The equipment required for the project is 4 laptops at a cost of AED3000 each, and a
printer for AED1000.
Material needed for content writing includes books, and stationary. The books cost
AED 3000 and the stationary cost will be AED 200.

a. Develop a resource WBS for this project (15 marks)

1.0 Project
1.1 Personnel
1.1.1 Graphic Designer
1.1.2 Content writer
1.1.3 Web developer
1.2 Equipment
1.2.1 Laptop
1.2.2 Printer
1.3 Material
1.3.1 Books
1.3.2 Stationary

CIS4608_BL_201920 pg. 7
Student Name:
Student No:

b. Calculate the budget required for the project. (15 marks)

- Personnel = ( 150*10) + 100* 30 + 200*40 = 12 500


- Equipment = 4*3000 + 1000 = 13 000
- Material = 3000 + 200 = 3200
Total = 12 500 + 13 000 + 3200 = 28700

CIS4608_BL_201920 pg. 8
Student Name:
Student No:

Extra Sheet for calculations – as needed

CIS4608_BL_201920 pg. 9
Student Name:
Student No:

CIS4608_BL_201920 pg. 10