Structural, Architectural Works Index Total Amount US$: Construction of Water Tank in Chebaa Priced Bill of Quanitites
Structural, Architectural Works Index Total Amount US$: Construction of Water Tank in Chebaa Priced Bill of Quanitites
Index
Division 2 Siteworks -
Division 5 Metals -
Division 9 Finishes -
Division 15 Mechanical -
Summary -
10% VAT -
SECTION NO. 1
GENERAL REQUIREMENTS
Amount
Item Description
US$
GENERAL NOTES
the word "tenderer" or "contractor" mentioned below have the same meaning.
A
The tenderer should price the below items and sub items individually. The tenderer
is not allowed to price any item covering more than 1 item. If any item not priced in
D the BOQ, then this item deemed included in the total summary of the project.
During the tender phase, the contractor should have deemed visited the site and
make their self aware of all site conditions of the project such as but not limited to
site access, roads, temporary facilities, temporary works, utilities etc.… During the
site visit shall take all the necessary steps to ensure the right implementation of the
project without any harm of the surrounding or of the existing buildings & utilities.
having said that, the Employer will not accept any claim or variation on the cost
E related to the above at any circumstances after submission of the offer. Any
potential contractor did not do a site visit, they deemed accepted the above and will
not be entitled to any claim whatsoever related to the above or not being able to do
a site visit.
The bidder shall price each item shown in the BOQ individually and in US dollars
only. Any bidder that has priced an item on percentage base will be disqualified.
F Moreover, any item left unpriced will be deemed to be included on other items
mentioned in the BOQ.
Priced Bill of Quanitites
Construction of Water Tank in Chebaa
Amount
Item Description
US$
Quantities included in the Break of Lump Sum shall not be re-measured after
execution. The Contract is a lump sum contract. The Contractor shall during
tender phase, verify and check the quantities for any discrepancies or mistakes. In
case of discrepancies, the Contractor shall during the tender phase raise this issue to
G the employer by sending to him a table showing the location of discrepancies for
Employer’s verification. The Employer will assess and answer the contractor’s
query with the amended quantities if there is any.
All combined documents that form this contract shall be mutually complimentary,
explanatory, cumulative, additive and not alternative and what is required by one
document shall be required by all. In case of conflict, the Engineer shall determine
H which document governs and the contractor shall comply with engineer decision
without any claim for extra cost if this conflict is not related to design.
During tender process, the tenderer should study carefully all the document
included in the tender and if he wishes to send any query, the tenderer should
submit them to the procurement unit, who will reply to any raised query in due
time. if the tenderer consider that there is any discrepancy or any missing item, the
I tenderer should address this issue during the tender phase to the procurement unit,
who will take the necessary action.
Insurances
The tenderer should provide all insurances as stipulated in the condition of contract.
A The tenderer shall include herein all cost related for those insurances.
The contractor shall price herein any fees related to bank guarantee or advance
B bank guarantee if applicable
To Collection US$ 0
Priced Bill of Quanitites
Construction of Water Tank in Chebaa
Amount
Item Description
US$
The contractor shall provide all Employer/Engineer staff with the required
equipment & safety equipment to perform their work, inspections or any task on
A site. The contractor shall provide as well as much as needed labors to perform or
help the staff of the Employer/Engineer with their tasks without any extra cost.
The tenderer has the responsibility to coordinate at all time with effectiveness and
required time as per the agreed or approved time frame with any contractor
assigned by the Employer or any subcontractor assigned by the contractor. Any
delay or claim resulting from not fulfilling the above task or any claim between
subcontractors, the contractor will be full responsible and he has the obligation to
A solve this claim. the duration of such coordination shall be effective during the
contract period.
As per the contract, The Contractor as part of their duties, they shall coordinate, pay
fees regarding connections of utilities, connections to infrastructure, access roads,
A fencing, and shall report all these matters to the Engineer & Employer
The contractor should always coordinate & inform the municipalities and any
concerned authorities for any temporary blockage of roads or any road found
necessary to execute the works. The contractor is responsible to set meeting &
B follow up any issue related to this project with the local & national authorities. Any
amount resulted from the above is to be borne by the contractor.
The contractor shall provide at any time access to labors of the Authorities to enter
C and do their job. The contractor shall provide all related site facility, safety
equipment and necessary coordination to perform their works on site
Priced Bill of Quanitites
Construction of Water Tank in Chebaa
Amount
Item Description
US$
Contractor to provide when needed any electricity power source to assure proper
D execution of the works under this contract.
Contractor shall repair any damage to existing infrastructure that is damaged due to
E the works executed on site.
Contractor shall incorporate daily fees for the delays in the project in the unit rate
F or provide it herein.
The tenderer shall under this contract requirement take all safety measures to
protect all adjacent properties. Moreover, the tenderer responsibility to always
maintain the original or temporary access of those properties free from any debris,
A waste, damages or blockage at any time during this contract.
If the tenderer wishes to enter the adjacent properties for any reason, the tenderer
shall inform the Employer and the land owner before 24 hours. Any
B action/damages/works resulted from this interference will be at the full
responsibility of the tenderer.
If the tenderer wishes during the implementation to use any adjacent properties not
related to the project, then the tenderer shall obtain the written approval of the
owner of the properties. The tenderer will be fully responsible of any action, works,
administered works, negotiation or any other action with the owner. the tenderer
should take into consideration that the Employer staff & the Engineer will must
C have access as well to those properties. the Employer will not be responsible for
any claim raised by the owner on the contractor/tenderer.
The tenderer/contractor shall be fully responsible of any payment resulted from the
agreement between the contractor and the owner of the adjacent properties. The
Employer shall be always informed about the permission approval and the
contractor should indemnify the Employer from any claim whatsoever from the
D owner related to this agreement.
Other Obligations
Priced Bill of Quanitites
Construction of Water Tank in Chebaa
Amount
Item Description
US$
The tenderer shall price separately hereunder if he wishes any item not mentioned
E in this division
To Collection US$
General
The Contractor shall satisfy himself as to the meaning of every item in the
Breakdown of Lump Sum and the rates and prices inserted by him will be deemed
to cover all his obligations under the Contract (Specifications, Drawings,
Conditions of Contract, any Addenda, and other contract documents) and all
matters and things necessary for the proper construction, completion and
maintenance of the works including (but not by way of limitation), for all
temporary work required (including any that may be required by Sub-Contractors,
whether nominated or otherwise).
The Contractor's price shall include for all materials and labor, storage and handling
transportation, samples, testing coordination and for the provision and use of all
plant, whether mechanical or non-mechanical, required for carrying out of the
works, in their proper sequence, for shifting, altering and adapting such temporary
work and plant as may be required the progress of the works, and for removing
plant and temporary works at completion and making good any surfaces disturbed.
The Contractor's price shall embrace the costs of preparing a tender; for the final
account; for overheads and profit; for customs and import duties; for temporary
services and for all other statutory tax and establishment charges and costs of
whatever nature. No claim for additional payment will be allowed for any error or
misunderstanding by the Contractor in these respects.
Priced Bill of Quanitites
Construction of Water Tank in Chebaa
Amount
Item Description
US$
To Collection US$
General
The Contractor shall comply with all the requirements and obligations contained in
the Specifications and in particular the requirements of this Division such as but not
limited to:-
Amount
Item Description
US$
E Cutting and Patching
Inspection procedures
Warranties
Final cleaning
Operation and maintenance Data:-
Operation manuals for systems, subsystems, and equipment
Maintenance manuals for the care and maintenance of products, materials, and
finishes systems and equipment
General Commissioning Requirements
HVAC Commissioning Requirements
To Collection US$
General
The Contractor shall comply with all the requirements and obligations contained in
the Specifications and in particular the requirements of this Division such as but not
limited to:-
Demonstration and Training:-
Demonstration of operation of systems, subsystems, and equipment
Training in operation and maintenance of systems, subsystems, and equipment
a) Tests
b) Mock-ups
c) Shop drawings
d) As-built drawings
e) Construction drawings
f) Testing and commissioning
g) Operating and maintenance manuals
h) Training of Employer's personnel
Other Obligations
The Contractor shall allow herein for all the following items as described in the
General Requirements and the Method of Measurement and not included
elsewhere:-
a) Contractor's administrative arrangements
b) Construction plant
A c) Temporary works
d) Sundry items
Priced Bill of Quanitites
Construction of Water Tank in Chebaa
Amount
Item Description
US$
Other items in the Specifications which the Contractor considers to be of value and
for which he has not included elsewhere and wishes to include in his Tender (list
below):-
…………………………………………………………………………….
…………………………………………………………………………….
…………………………………………………………………………….
To Collection US$
The contractor shall during the contract period take all precaution & safety
measures as per the contract to ensure a safe environment for workers and to do all
the necessary safety support for the works. the contractor shall always have security
signs on the site for better work environment.
the contractor shall strictly abide by the rules and laws set by this contract related to
the welfare & safety of all personal on site. Moreover, the contractor shall
implement any temporary work or facility related to safety or protection of works
without any claim for extra cost.
As per this contract, the contractor shall report immediately to the Employer for any
accident or injury happened during the works on site and the contractor shall take
immediately any action to ensure a fast medical help or transportation to the
hospital at his own cost without any claim for extra cost. the contractor shall upon
occurrence of such accidents or injuries, they shall submit all related document &
reports to the Employer detailing the accident and stating the preventive actions to
be taken.
Priced Bill of Quanitites
Construction of Water Tank in Chebaa
Amount
Item Description
US$
If any claim was made by anyone against the contractor related to the above, the
contractor should immediately inform the Employer about such claims and to keep
the Employer with any update related to this subject.
To Collection US$
Management reports
As per the contract, the contractor shall submit as stated daily reports, or any other
report mentioned in the contract. The form of those reports to be agreed on the
kickoff meeting of the project.
Progress report to be submitted with each payment. This progress report must
include:
A
1) Photographic records
B 2) Labor graph for each day till the submission of the payment
3) To provide the salary of each labor for our report
4) The nationality of each labor employed showing the number of workers and for
how long the employment was?
5) The log sheets for the projects
6) The log sheet for the possible variation order & extension of time.
7) The updated time schedule, showing the progress of works, the occurred delay if
A any.
8) Brief description of the project.
To Collection US$
Amount
Item Description
US$
Have no rights to use any part of tender documents for any reason other than the
purpose of this project. All documents are protected by the law
A
Have no right to use any part of the tender documents for any advertising purposes
B
To Collection US$
COLLECTION 0.00
GENERAL REQUIREMENTS
Priced Bill of Quanitites
Construction of Water Tank in Chebaa
Amount
Item Description
US$
Total Carried to General Summary US$ 0
0
Priced Bill of Quanitites
Construction of Water Tank in Chebaa
DIVISION 2 - SITEWORK
Total
Sub- direct OH & Unit Rate Amount
Item Description Qty Unit Material Labor Equipment contractor cost Profit US$ US$
A EXCAVATING (02222)
Excavation Works
B BACKFILLING (02223)
Backfill Works
Visibility signs
Installation of visibility signs following requirements of scope
1) of works and attached drawings 1 LS 0.00
Sub- Total
contrac direct OH & Unit Rate Amount
Item Description Qty Unit Material Labor Equipment tor cost Profit US$ US$
DIVISION 5 - METALS
Total
direct OH & Unit Rate Amount
Item Description Qty Unit Material Labor Equipment Subcontractor cost Profit US$ US$
2) Waterstope 43 lm 0.00
DIVISION 9 - FINISHES
Total
OH & Unit Rate Amount
Item Description direct
Profit US$ US$
cost
Qty Unit Material Labor Equipment Subcontractor
External Paint
DIVISION 15 - MECHANICAL
Total
direct OH & Unit Rate Amount
Item Description Qty Unit Material Labor Equipment Subcontractor cost Profit US$ US$
4) Trench excavation for water supply network (Depth=91 cm, 512.0 lm 0.00
Width=65 cm)
5) Trench excavation to water supply network for backup line 50.0 lm 0.00
feeding the existing water tank (Provision Qty)
7) 212.0 m³ 0.00
Bedding works in layers to trench for water supply network
DIVISION 15 - MECHANICAL
Total
direct OH & Unit Rate Amount
Item Description Qty Unit Material Labor Equipment Subcontractor cost Profit US$ US$
Supply and install vent, drain and gravity pipes including all
fittings, spouts, joints, connections complete, as specified and
as shown on drawings
Connection to existing well with all needed valves and 1 No. 0.00
18) accessories
Connection to existing water tank with all needed valves and 1 No. 0.00
19) accessories
SCHEDULE OF DAYWORKS
Generally
Note:
LABOUR
L Bar-Bender 4 Hour
Priced Bill of Quanitites
Construction of Water Tank in Chebaa
S Carpenter 4 Hour
LABOUR (CONT'D)
C Plasterer 4 Hour
E Pavior 4 Hour
L Painter 4 Hour
Q Plumber 4 Hour
S Electrician 4 Hour
LABOUR (CONT'D)
Sub-Total
PLANT
A Motor 4 Hour
G Vibrator 4 Hour
N Pick-up 4 Hour
W Dumper 4 Hour
PLANT (CONT'D)
Sub-Total
COLLECTION
Total US$