KALIMANTAN PRIMA PERSADA


Integrated Mining Services TIME SHEET COAL HAULING
Nama : Tanggal : HM Awal : HM Manual Awal : KM Manual Awal :
NRP : Shift : HM Akhir : HM Manual Akhir : KM Manual Akhir :
Jam Start Unit : Tipe & C/N Unit : Produksi :
Jam Kerja Operator
Jam Stop Unit : Total Ritase : Non Produksi :
RUTE TRANSPORTASI
Area Loading Area Dumping
Trip Alat Loading Time (Waktu) Time (Waktu) Jarak Hauling
Kode Material
Tiba Tes Dumping Start Loading Stop Loading Tiba Start Stop
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
PRODUCTION SHEET
Keterangan Delay & Idle Mulai Selesai Keterangan Delay & Idle Mulai Selesai

D01. P5M, SAFETY TALK D12. ROAD MAINTENANCE (PERBAIKAN


JALAN)
D02. P2H (PRE USE CHECK) D13. SHIFT CHANGE (PINDAH SHIFT)
FUEL AND LUBRICATION (ISI FUEL & D14. DUSTY (DEBU)
D03. LUBE PLUS ANTRI)
D15. CLEANING EQP. (CUCI UNIT)
D04. DAILY CHECK D16. FATIQUE CHECK (CEK FATIQUE)
D05. TYRE CHECK (CEK BAN) D17. FATIQUE
D18. NO OPT (TIDAK ADA OPERATOR)
WAITING OPERATOR (TUNGGU
D19.
D06. QUEUING at ROM (ANTRIAN DI OPERATOR)
STOCKPILE)

I01. RAIN (HUJAN)

D07. QUEUING at PORT (ANTRIAN DI


PELABUHAN)
I02. SLIPPERY (JALAN LICIN)

I03. STRIKE (DEMO)


I04. CUSTOMER PROBLEM
D08. QUEUING at WEIGHT BRIDGE
(ANTRIAN DI TIMBANGAN) KABUT
FORCE ANGIN RIBUT
I05.
D09. REST & MEAL (ISTIRAHAT & MAKAN) MAJEURE POHON TUMBANG
DLL
D10. PRAYING (IBADAH, SHOLAT) ( )
( )
B/D. BREAKDOWN
( )
D11. STOPPAGE (STANDBY BY REQUEST)
( )
KODE MATERIAL CATATAN OPERATOR
OB (OVERBURDEN) CC (COAL CLEAN) HM unit saat pengisian fuel = _________
TS (TANAH MERAH) BT (BATU) Fuel = ________ liter

Dibuat Oleh, Diperiksa Oleh,

(_____________) (_______________)
(Operator) (GL Hauling)