You are on page 1of 21

CEBU BUS RAPID TRANSIT

SBT STATION

FEBRUARY 2021
< ARCHITECTURAL>
PROJECT PROJECT SCALE PROJECT
SHEET NO. DESCRIPTION OF DRAWINGS SCALE REMARKS SHEET NO. DESCRIPTION OF DRAWINGS REMARKS SHEET NO. DESCRIPTION OF DRAWINGS SCALE REMARKS
TITLE TITLE TITLE

ST-SBT-A-000 TITLE PAGE

CEBU BUS
ST-SBT-A-001 DRAWING INDEX - 1 NONE
RAPIT TRANSIT
(SBT STATION)

ST-SBT-A-101 MASTER PLAN & LOCATION MAP 1/500, NTS

ST-SBT-A-102 PARTIAL PLAN A & B 1/200

ST-SBT-A-103 SBT STATION - FLOOR & ROOF PLAN 1/200

ST-SBT-A-104 SBT STATION - FRONT & REAR ELEVATION 1/200

ST-SBT-A-105 SBT STATION - SECTION & REFLECTED CEILING PLAN 1/200

ST-SBT-A-107 SBT STATION - FLOOR & ROOF PLAN 1/200

ST-SBT-A-108 SBT STATION - FRONT & REAR ELEVATION 1/200

ST-SBT-A-109 SBT STATION - SECTION & REFLECTED CEILING PLAN 1/200

ST-SBT-A-201 ENLARGED PLAN-1 1/100

ST-SBT-A-301 TYPE -A FLOOR PLAN 1/100

ST-SBT-A-302 TYPE -A REFLECTED CEILING PLAN & ELEVATION 1/100

ST-SBT-A-303 TYPE -A REFLECTED CEILING PLAN & ROOF PLAN 1/100

ST-SBT-A-304 TYPE -B FLOOR PLAN 1/100

ST-SBT-A-305 TYPE -B REFLECTED CEILING PLAN & ELEVATION 1/100

ST-SBT-A-306 TYPE -B REFLECTED CEILING PLAN & ROOF PLAN 1/100

ST-SBT-A-307 TYPE -A&B SECTION 1/100

ST-SBT-A-308 PARTIAL SECTION 1/100

ST-SBT-A-401 DETAILS 1/5

ST-SBT-A-402 MISCELLANEOUS DETAILS 1/20

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY:

ST-SBT-A-001
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT DRAWING INDEX - 1
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
N
N

1
2
3
4
5
5
4
3
2
1

LOCATION MAP LOCATION MAP


BRT STATION MAP SBT STATION
1 Scale: NTS
1 Scale: 1/2000 MTS

SBT STATION
MASTER PLAN
1 Scale: 1/600 MTS

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: LOCATION MAP


MASTER PLAN
ST-SBT-A-101
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
KEY PLAN

1 2 3 4 5
3,075 3,900 6,900 1,800 3,000 13,000 3,000 1,200 16,000 4,400 35,200 4,400 1,600

8,800 8,800 8,800 8,800

TOTEM BY OTHERS
BY LANDSCAPE 30mm THK GRANITE
LANDSCAPE BY
30mm THK GRANITE FENCE
TURNSTILES FOR
23,583
FINISH LANDSCAPE CURB FINISH
OTHERS FUTURE DEVELOPMENT
LANDCAPE BY OTHERS

5 4 3 2 1
T.O.F -100
23,583 1,600 4,400 35,200 4,400 16,000 1,200

8,800 8,800 8,800 8,800

4,000
4,350
T.O.F

350
FENCE 30mm THK GRANITE
T.O.F -300 FENCE FINISH
30mm THK GRANITE 30mm THK GRANITE 30mm THK GRANITE
FINISH FINISH (NON-SLIP FINISH) FINISH (NON-SLIP FINISH) 30mm THK GRANITE
FINISH FENCE

350
LANDCAPE BY OTHERS

4,350

4,000
TURNSTILES FOR FENCE

PARTIAL PLAN "A"


FUTURE DEVELOPMENT
30mm THK GRANITE
FINISH (NON-SLIP FINISH)

PARTIAL PLAN "B"

1 2
3,075 3,900 6,900 1,800 3,000 13,000 3,000 1,200 16,000 4,400

8,800

BY LANDSCAPE 30mm THK GRANITE LANDSCAPE BY 30mm THK GRANITE FENCE


TOTEM BY OTHERS LANDSCAPE CURB TURNSTILES FOR
FINISH OTHERS FINISH
FUTURE DEVELOPMENT

T.O.F -100
4,000
4,350

SLOPE SLOPE
(1/12) (1/12)

T.O.F
350

FENCE 30mm THK GRANITE


T.O.F -300 FENCE FINISH
30mm THK GRANITE 30mm THK GRANITE 30mm THK GRANITE
FINISH FINISH (NON-SLIP FINISH) FINISH (NON-SLIP FINISH)

SBT STATION
PARTIAL PLAN "A"
1 Scale: 1/500 MTS

30mm THK GRANITE


FINISH FENCE

SLOPE
(1/12)

TURNSTILES FOR FENCE


FUTURE DEVELOPMENT 30mm THK GRANITE
FINISH (NON-SLIP FINISH)

SBT STATION
PARTIAL PLAN "B"
2 Scale: 1/500 MTS

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: PARTIAL PLAN A


PARTIAL PLAN B
ST-SBT-A-102
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
KEY PLAN

1 2 3 4 5
1,200 16,000 4,400 35,200 4,400

8,800 8,800 8,800 8,800

TURNSTILES FOR
B FUTURE DEVELOPMENT
INFORMATION POLE
COLUMN

INFORMATION POLE
TICKETING BOOTH FOR
FENCE
FUTURE DEVELOPMENT
400

10 lbs ABC FIRE


BENCH 10 lbs ABC FIRE BENCH BENCH BENCH
STEEL COLUMN EXTINGUISHER STEEL COLUMN
EXTINGUISHER
500

A
4,000
4,350

3,100

T.O.F
350

FENCE 30mm THK GRANITE FINISH 30mm THK GRANITE FINISH 30mm THK GRANITE FINISH

BERTHING CURB
30mm THK GRANITE FINISH (DOT TYPE)
BERTHING CURB

7,000

SBT STATION
FLOOR PLAN
1 Scale: 1/200 MTS 20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM)

1 2 3 4 5
1,200 16,000 4,400 35,200 4,400

8,800 8,800 8,800 8,800

TURNSTILES FOR
B FUTURE DEVELOPMENT
TICKETING BOOTH FOR
FENCE
FUTURE DEVELOPMENT
400
500

A
4,000
4,350

3,100
350

FENCE 30mm THK GRANITE FINISH

HONEYCOMB
COMPOSITE ROOF
PANEL

SBT STATION
20,000 20,000
ROOF PLAN (PLATFORM) 2,000 2,000 (PLATFORM)
2 Scale: 1/200 MTS

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: FLOOR PLAN


ROOF PLAN ST-SBT-A-103
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
KEY PLAN

1 2 3 4 5
4,400 35,200 4,400

8,800 8,800 8,800 8,800

HONEYCOMB
STEEL PIPE FRAME
COMPOSITE ROOF
PANEL
500 200

LOWER ROOF
+4,000)

FENCE FENCE
5,000

4,000
300

274mm STAINLESS
STEEL PIPE COLUMN 274mm STAINLESS
(HAIRLINE FINISH) STEEL PIPE COLUMN
(HAIRLINE FINISH)
20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM)

SBT STATION
FRONT ELEVATION
1 Scale: 1/200 MTS

5 4 3 2 1
4,400 35,200 4,400

8,800 8,800 8,800 8,800


HONEYCOMB
STEEL PIPE FRAME
COMPOSITE ROOF
PANEL
500 200

LOWER ROOF
+4,000)

FENCE FENCE
5,000

4,000
300

274mm STAINLESS
STEEL PIPE COLUMN
(HAIRLINE FINISH)

20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM)

SBT STATION
REAR ELEVATION
2 Scale: 1/250 MTS

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: FRONT ELEVATION


REAR ELEVATION
MARK STEVEN C. CONSTRUCTION OF CEBU ST-SBT-A-104
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
KEY PLAN

1 2 3 4 5
4,400 35,200 4,400

8,800 8,800 8,800 8,800

100mm STAINLESS 100mm STAINLESS 100mm STAINLESS


STEEL GUTTER HONEYCOMB STEEL GUTTER STEEL GUTTER
COMPOSITE ROOF
500 200 PANEL

LOWER ROOF
+4,000)
5,000

4,000
300

20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM)

SBT STATION
SECTION
1 Scale: 1/200 MTS

1 2 3 4 5
4,400 35,200 4,400

8,800 8,800 8,800 8,800

B
400
500

A
4,000
4,350

3,100
350

25x25mm ALUMINUM LOUVER 25x25mm ALUMINUM LOUVER

32W LED LIGHTING PANEL (300X600MM 6SET) 32W LED LIGHTING PANEL (300X600MM 6SET) 32W LED LIGHTING PANEL (300X600MM 6SET)

20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM)

SBT STATION
REFLECTED CEILING PLAN
2 Scale: 1/200 MTS

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: SECTION


REFLECTED CEILING
PLAN
MARK STEVEN C. CONSTRUCTION OF CEBU ST-SBT-A-105
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
KEY PLAN

5 4 3 2 1
4,400 35,200 4,400 16,000 1,200

8,800 8,800 8,800 8,800

BERTHING CURB

30mm THK GRANITE FINISH 30mm THK GRANITE FINISH 30mm THK GRANITE FINISH FENCE

T.O.F 30mm THK GRANITE FINISH (DOT TYPE)

BENCH 10 lbs ABC FIRE BENCH BENCH 10 lbs ABC FIRE BENCH
EXTINGUISHER STEEL COLUMN EXTINGUISHER TICKETING BOOTH FOR
FENCE
FUTURE DEVELOPMENT
INFORMATION PANEL INFORMATION POLE
STEEL COLUMN
TURNSTILES FOR
FUTURE DEVELOPMENT
FUTURE DEVELOPMENT COLUMN
SBT STATION
20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM) FLOOR PLAN
1 Scale: 1/200 MTS

5 4 3 2 1
4,400 35,200 4,400 16,000 1,200

8,800 8,800 8,800 8,800

HONEYCOMB
COMPOSITE ROOF
PANEL

BERTHING CURB

30mm THK GRANITE FINISH FENCE

TICKETING BOOTH FOR


FENCE
FUTURE DEVELOPMENT
TURNSTILES FOR
FUTURE DEVELOPMENT

SBT STATION
20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM) ROOF PLAN
2 Scale: 1/200 MTS

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: FLOOR PLAN


ROOF PLAN
MARK STEVEN C. CONSTRUCTION OF CEBU ST-SBT-A-107
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
KEY PLAN

1 2 3 4 5
4,400 35,200 4,400

8,800 8,800 8,800 8,800

HONEYCOMB
STEEL PIPE FRAME
COMPOSITE ROOF
PANEL
500 200

LOWER ROOF
+4,000)

FENCE FENCE
5,000

4,000
300

274mm STAINLESS
STEEL PIPE COLUMN 274mm STAINLESS
(HAIRLINE FINISH) STEEL PIPE COLUMN
(HAIRLINE FINISH)
20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM)

SBT STATION
FRONT ELEVATION
1 Scale: 1/200 MTS

5 4 3 2 1
4,400 35,200 4,400

8,800 8,800 8,800 8,800


HONEYCOMB
STEEL PIPE FRAME
COMPOSITE ROOF
PANEL
500 200

LOWER ROOF
+4,000)

FENCE FENCE
5,000

4,000
300

274mm STAINLESS
STEEL PIPE COLUMN
(HAIRLINE FINISH)

20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM)

SBT STATION
REAR ELEVATION
2 Scale: 1/250 MTS

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: FRONT ELEVATION


REAR ELEVATION
MARK STEVEN C. CONSTRUCTION OF CEBU ST-SBT-A-108
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
KEY PLAN

1 2 3 4 5
4,400 35,200 4,400

8,800 8,800 8,800 8,800

100mm STAINLESS 100mm STAINLESS 100mm STAINLESS


STEEL GUTTER HONEYCOMB STEEL GUTTER STEEL GUTTER
COMPOSITE ROOF
500 200 PANEL

LOWER ROOF
+4,000)
5,000

4,000
300

20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM)

SBT STATION
SECTION
1 Scale: 1/200 MTS
5 4 3 2 1
4,400 35,200 4,400

8,800 8,800 8,800 8,800

32W LED LIGHTING PANEL (300X600MM 6SET) 32W LED LIGHTING PANEL (300X600MM 6SET) 32W LED LIGHTING PANEL (300X600MM 6SET)

25x25mm ALUMINUM LOUVER 25x25mm ALUMINUM LOUVER


350
3,100
4,350
4,000

A
500
400

20,000 20,000
(PLATFORM) 2,000 2,000 (PLATFORM)

SBT STATION
REFLECTED CEILING PLAN
2 Scale: 1/200 MTS

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: SECTION


REFLECTED CEILING
PLAN
MARK STEVEN C. CONSTRUCTION OF CEBU ST-SBT-A-109
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
3,075 3,900 8,100

TOTEM BY OTHERS 30mm THK GRANITE FINISH 30mm THK GRANITE FINISH
( NON-SLIP FINISH)

CURB STONE CURB STONE FENCE


4,000
4,350

350

BY LANDSCAPE
-300

CURB STONE FENCE

30mm THK GRANITE FINISH

FUENTE STATION

1/50 MTS

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: ENLARGE PLAN


ST-SBT-A-201
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
1 1
10107 10107

5053 5053 5053 5053

4353 700 700 4353 4353 700 700 4353

B B 20mm THK HONEYCOMB


400

COMPOSITE ROOF PANEL


500

500
A A
4000

70

70
96
96
3100

96

96
70
70

6364
350
2366

STAINLESS STEEL
GUTTER (W:100)

4769 4769 4769 4769

TYPE-A FLOOR PLAN TYPE-A ROOF PLAN


1 Scale: 1/100
2 Scale: 1/100

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: TYPE-A PLAN


ST-SBT-A-301
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
5053 5053

4353 700 700 4353

4463 4463

1 20mm THK HONEYCOMB


COMPOSITE ROOF PANEL

499
10107

5053 5053

4353 700 700 4353

4532
4033
274mm STAINLESS

B 25x25mm ALUMINUM
STEEL COLUMN
(HAIRLINE FINISH)
LOUVER @50mm
SPACING
500

A
TYPE-A FRONT ELEVATION

70
96

96
70

2 Scale: 1/100
LED LIGHT BOX
(300X3600)
6314

5053 5053

4353 700 700 4353

4463 4463

20mm THK HONEYCOMB


COMPOSITE ROOF PANEL

499
4769 4769
50mm STAINLESS STEEL
PIPE @ 180mm SPACING

18
0

4532
4033
274mm STAINLESS
STEEL COLUMN
(HAIRLINE FINISH) 75mm STAINLESS STEEL
TYPE-A CEILING PLAN PIPE FRAME
1 Scale: 1/100

TYPE-A REAR ELEVATION


3 Scale: 1/100

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY:


ST-SBT-A-302
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
4440
2220 2220

20mm THK HONEYCOMB


20mm THK HONEYCOMB COMPOSITE ROOF PANEL

1200
COMPOSITE ROOF PANEL

499
1000
1000
6300

4532

4832
4033
1000
5100

2700
1000
1100

300
TYPE-A ROOF PLAN (UPPER) TYPE-A SECTION (UPPER ROOF)
1 Scale: 1/100
2 Scale: 1/100
00

43
12

21 00
50
20mm THK HONEYCOMB
COMPOSITE ROOF PANEL
00

21
10

50
80

499
70

00
10
80

00
58

10

25x25mm ALUMINUM

4532
00

20mm THK HONEYCOMB LOUVER @50mm

4033
10

COMPOSITE ROOF PANEL SPACING


0

274mm STAINLESS

2700
0
10

STEEL COLUMN
(HAIRLINE FINISH)
0
88

300

TYPE-A ROOF PLAN (LOWER) TYPE-A SECTION (LOWER ROOF)


3 Scale: 1/100
4 Scale: 1/100

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY:


ST-SBT-A-303
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
10366 10366

5183 5183 5183 5183

4483 700 700 4483 4483 700 700 4483


600

20mm THK HONEYCOMB


COMPOSITE ROOF PANEL
300

300
A A
4000

74
66

66
74
3100

6171

5871
350

STAINLESS STEEL
GUTTER (W:100)

4973 4973 4973 4973

TYPE-B FLOOR PLAN TYPE-B ROOF PLAN


1 Scale: 1/100
2 Scale: 1/100

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY: TYPE-B PLAN


ST-SBT-A-304
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
10366
5183 5183

4483 700 700 4483

20mm THK HONEYCOMB


COMPOSITE ROOF
PANEL

489
10366
5183 5183 274mm STAINLESS

4522
STEEL COLUMN

4033
(HAIRLINE FINISH)
4483 700 700 4483

25x25mm ALUMINUM
300

LOUVER @50mm

A SPACING

TYPE-B FRONT ELEVATION


2 Scale: 1/100

LED LIGHT BOX


(300X3600)
6171

5871

10366
5183 5183

4483 700 700 4483

20mm THK HONEYCOMB


COMPOSITE ROOF
PANEL

489
4973 4973
50mm STAINLESS
180 STEEL PIPE @ 180mm
SPACING

4522
4033
274mm STAINLESS
STEEL COLUMN
(HAIRLINE FINISH) 75mm STAINLESS
STEEL PIPE FRAME

TYPE-B CEILING PLAN


1 Scale: 1/100

TYPE-B REAR ELEVATION


3 Scale: 1/100

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY:


ST-SBT-A-305
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
00
12
22 44
14 28

00
22

10
14 4000

47

00
74

10
20mm THK HONEYCOMB

47

00
COMPOSITE ROOF

62

10
PANEL

00
10

489
00
10
47
12

25x25mm ALUMINUM
LOUVER @50mm

4522
SPACING

4822
4033
274mm STAINLESS
STEEL COLUMN
(HAIRLINE FINISH)

300
TYPE-B ROOF PLAN (UPPER) TYPE-B SECTION (UPPER ROOF)
1 Scale: 1/100
2 Scale: 1/100
4410

2205 2205
4000

20mm THK HONEYCOMB


COMPOSITE ROOF
PANEL

489
1200

1000

25x25mm ALUMINUM

4522
LOUVER @50mm

4033

4333
SPACING
1000
5800

274mm STAINLESS
STEEL COLUMN
4600

1000

(HAIRLINE FINISH)

300
600 1000

4000 350 2015

TYPE-B ROOF PLAN (LOWER) TYPE-B SECTION (LOWER ROOF)


3 Scale: 1/100
4 Scale: 1/100

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY:


ST-SBT-A-306
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
5053 5053 5053 5053

4353 700 700 4353 4353 700 700 4353

20mm THK HONEYCOMB


COMPOSITE ROOF PANEL
499

489
CH:3750(VAR)

CH:3750(VAR)

CH:3750(VAR)
25x25mm ALUMINUM 25x25mm ALUMINUM
4532

4522
LOUVER @50mm LOUVER @50mm
4033

4033
SPACING SPACING

TYPE-A CROSS SECTION TYPE-B CROSS SECTION


A 1 Scale: 1/100
2 Scale: 1/100

400500 2650
800 1850

200
500

100

100mmX150mm
940

TRAFFIC INFO. PANEL INFORMATION POLE


4500

(SST'L HAIRLINE HINISH)


4000

(BY ITS)

3350
2360

100mmX150mm
INFORMATION POLE
(SST'L HAIRLINE HINISH)
300

INFORMATION POLE SIDE ELEVATION INFORMATION POLE REAR ELEVATION


3 Scale: 1/100
4 Scale: 1/100

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY:


ST-SBT-A-307
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
A

SST'L GUTTER (W:100)

20mm THK HONEYCOMB


COMPOSITE ROOF PANEL 3mmTHK SST'L SHEET
(HAIRLINE FINISH)

20mm THK HONEYCOMB 25x25mm ALUMINUM


COMPOSITE ROOF PANEL LOUVER @50mm
SPACING

25x25mm ALUMINUM PARTIAL SECTION -2


LOUVER @50mm
SPACING
3 Scale: 1/20

3mmTHK SST'L SHEET

STATION BRT LANE (PLAT FORM)


FENCE
2700

STAINLESS STEEL COLUMN


(HAIRLINE FINISH) 30mmTHK GRANITE FINISH /
30mmTHK GRANITE FINISH DOT TYPE (400X400mm)
(400X400mm)
250 100
150X450 CONCRETE CURB
15 44 12
350X450 BERTING
30mmTHK GRANITE FINISH (400X400mm) 30 CONCRETE CURB

THK 50 MORTAR BED


150 250 CONCRETE SLAB

300

300
450
150
300

350
150

PARTIAL SECTION -1
1 PARTIAL SECTION -3
Scale: 1/20 3 Scale: 1/20

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY:


ST-SBT-A-308
MARK STEVEN C. CONSTRUCTION OF CEBU
KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
JACINTO V. VIADO
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978
25 100
20mm THK HONEYCOMB
STAINLESS STEEL
COMPOSITE ROOF PANEL
GUTTER (W: 100)

3mmTHK STAINLESS
SHEET

60
(HAIRLINE FINISH)

STAINLESS STELL BEAM


(SSB1 / HAIRLINE FINISH)

25x25mm ALUMINUM
LOUVER @50mm
SPACING GUTTER DETAIL
1 Scale: 1/5

SST'L BEAM (SSB2)


ROUND PIPE CLAMP
SST'L BEAM (SSB2) (PLAT BAR)

ROUND PIPE CLAMP


(PLAT BAR) 25x25mm SECONDARY
L-SHAPE HANGER CHANNEL
(PLAT BAR)
25x25mm SECONDARY
CHANNEL
L-SHAPE HANGER
(PLAT BAR)

25x25mm ALUMINUM
25 50 25 50 25 50 25 50 25 50 25 50 25
LOUVER @50mm
SPACING

25x25mm ALUMINUM
LOUVER @50mm
SPACING
CEILING DETAIL -1 CEILING DETAIL -2
2 3 Scale: 1/5
Scale: 1/5

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY:


ST-SBT-A-401
MARK STEVEN C. CONSTRUCTION OF CEBU
JACINTO V. VIADO KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021
TIN: 187-820-978
75X50mm ALUMINUM INJUCTION
200

EDGE 2 - 20 X 40mm SST'L PIPE @ 20mm


CONCRETE KERB 20
SPACING
30mmTHK GRANITE FINISH

20
(STATION)

150

100 50 30
180
CONC SLAB

280

CONCRETE KERB (FOR LANDSCAPE) BENCH PLAN


1 3 Scale: 1/20
Scale: 1/20

2 - 20 X 40mm SST'L PIPE @ 20mm


SPACING

1560 1560

780 780
50 X 50mm TUBULAR
(POWDER-COATED FINISH)
75X50mm ALUMINUM INJUCTION
25 X 50mm TUBULAR
(POWDER-COATED FINISH)
EQ

BENCH ELEVATION-1
4 Scale: 1/20
EQ

2 - 20 X 40mm SST'L PIPE @ 20mm


SPACING
1150
1200

75X50mm ALUMINUM INJUCTION


EQ
EQ
50

FENCE DETAIL BENCH ELEVATION -2


2 Scale: 1/20
5 Scale: 1/20

OWNED BY: CONSULTANT CHECKED BY: SUBMITTED BY: APPROVED BY: PROJECT TITLE: SHEET CONTENTS: DRAWING NO:

PREPARED BY: REVIEWED BY:


ST-SBT-A-402
MARK STEVEN C. CONSTRUCTION OF CEBU
KIM JONG MIN ELMAN JOSE B. MARTINEZ NORVIN V. IMBONG JOHAN G. MARTINEZ PASTOR ANNELI R. LONTOC
JACINTO V. VIADO
KUNHWA EXPERT DIRECTOR, KUNHWA ARCHITECT III - CEBU BRT PIU DEPUTY PROJECT MANAGER PROGRAM MANAGER ASSISTANT SECRETARY UNDERSECRETARY
BUS RAPID TRANSIT PROJECT
PRC NO: 0017723 DATE: 07/24/2023
ARCHITECTURAL AND PLUMBING PLANS FOR SYSTEMS AND STAKEHOLDER
RELATIONS - CEBU BRT PIU
BRT - NPMO FOR ROAD TRANSPORT
AND INFRASTRUCTURE
PHILIPPINE RAILWAY
INSTITUTE AND OIC FOR
PACKAGE 1
BRT PROJECTS
PTR NO: 4598728 DATE: 01/14/2021

TIN: 187-820-978