You are on page 1of 10

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/255729015

Power System Contingency Analysis: A Study of Nigeria’s 330KV Transmission


Grid

Conference Paper · July 2013

CITATIONS READS

9 10,584

2 authors:

Chibuzo Joseph Nnonyelu Theophilus Chukwudolue Madueme


University of Nigeria University of Nigeria
13 PUBLICATIONS   27 CITATIONS    69 PUBLICATIONS   181 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Renewable Energy Technology View project

Power generation and demand in Nigeria. View project

All content following this page was uploaded by Chibuzo Joseph Nnonyelu on 02 June 2014.

The user has requested enhancement of the downloaded file.


Power System Contingency Analysis: A Study of Nigeria’s 330KV
Transmission Grid
Nnonyelu, Chibuzo Joseph Prof. Theophilus C. Madueme
Department of Electrical Engineering Department of Electrical Engineering
University of Nigeria, Nsukka University of Nigeria, Nsukka
chibuzo.nnonyelu@unn.edu.ng
Abstracts
As new sources of power are added to the Nigeria’s power system, an over-riding factor in the
operation of the power system is the desire to maintain security and expectable reliability level
in all sectors –generation, transmission, and distribution. System security can be assessed using
contingency analysis. In this paper, contingency analysis and reliability evaluation of Nigeria
power system will be performed using the load flow method. The result of this analysis will be
used to determine the security level of the Nigeria power system and suggestions will also be
made on the level of protection to be applied on the Nigeria power system with aim of
improving system security.
Keywords: Contingency Analysis, Contingency, Power System Security, Overload Index

1. INTRODUCTION
Power system protection is an important factor of consideration in all sectors of a power system
during both planning and operation stages. This is because any loss of component leads to
transient instability of the system and can be checked immediately by the help of protective
devices put in place. As we propose and source new sources of power in order to meet up the
Nigeria energy demand, it is important to access the security level of the existing grid in order
to devise a more defensive approach of operation.

Currently, the Transmission Company of Nigeria (TCM), projected to have the capacity to
deliver about 12,500 MW in 2013, has the capacity of delivering 4800 MW of electricity.
Nigeria has a generating capacity of 5,228 MW but with peak production of 4500 MW against
a peak demand forecast of 10,200MW. This shows that if the generation sector is to run at full
production, the transmission grid will not have the capacity to handle the produced power
reliably [7]. This goes a long way to tell that the 330 KV transmission system is not running
effectively as expected. Therefore to maintain and ensure a secure operation of this delicate
system, the need for contingency analysis cannot be over emphasized.

Contingencies are defined as potentially harmful disturbances that occur during the steady state
operation of a power system [1] Contingencies can lead to some abnormalities such as over
voltage at some buses, over loading on the lines, which if are unchecked, can lead to total
system collapse.
Power system engineers use contingency analysis to predict the effect of any component
failure. Periodically, maintenance operation are carried out on generating units or transmission
lines. During this, a unit is taken offline for servicing. The effect of this forced outage on other
parts of the system can be observed using contingency analysis.

1
As demand for power increases, more generating units are installed in Nigeria with no
corresponding increase in transmission capacity. This makes the transmission lines run at their
maximum power capacity which is very dangerous as there is too much power in the system at
any moment. This power will be shifted to any available portion of the transmission system in
case of any contingency thereby overloading the available portion. This effect can be analysed
by the calculation of Line Outage Distribution Factor (LODF). Also, the overloading index of
the remaining lines will can be obtained equally.

2. POWER SYSTEM SECURITY


One of the most important factors in the operation of any power system is the desire to maintain
system availability and reliability. This ensures a secure operation of the system and improved
economic operation. Power system security is the ability of the system to withstand one or
more component outages with the minimal disruption of service or its quality. System security
involves practices designed to keep the system operating in emergency state when components
fail and to restore it to its preventive state. For instance, a generating unit may break down or
have to be taken off-line for maintenance purposes. This leads to frequency and voltage
instability as the available generating unit experiences more loads than usual, hence frequency
drops and bus voltages lowers. If this is not foreseen and defensively prevented by use of
protective devices such as relays for load shading, it can lead to the collapse of the concerned
system. Therefore the control objective in the emergency state is to relieve system stress by
appropriate actions while economic consideration becomes of secondary.

2.1 CONTINGENCY ANALYSIS


Contingency analysis is the study of the outage of elements such as transmission lines,
transformers and generators, and investigation of the resulting effects on line power flows and
bus voltages of the remaining system. It represents an important tool to study the effect of
elements outages in power system security during operation and planning. Contingencies
referring to disturbances such as transmission element outages or generator outages may cause
sudden and large changes in both the configuration and the state of the system. Contingencies
may result in severe violations of the operating constraints. Consequently, planning for
contingencies forms an important aspect of secure operation [2].

There are various methods of contingency analysis which include the following:
a. AC Load flow method
b. DC Load flow method
c. Z-Matrix method
d. Performance Index method

Of all the above listed methods, methods based on AC power flow calculations are considered
to be deterministic methods which are accurate compared to DC power flow methods. In
deterministic methods line outages are simulated by actual removal of lines instead of
modelling. AC power flow methods are accurate but they are computationally expensive and
excessively demanding of computational time. Because contingency analysis is the only tool

2
for detecting possible overloading conditions requiring the study by the power system planner
computational speed and ease of detection are paramount considerations. [1]
Results of contingency analysis are usually ranked based on some indices calculated during the
analysis. The choice of performance index to calculate depends on the engineer. In a
deregulated power system, a discernibly purely profit driven, economic operation is of utmost
importance hence Available Transfer Capability (ATC) is normally calculated to ascertain the
available transfer capability of the system in case of any contingency. Other Indices include
Voltage Stability Index (VSI), Active Power Loading Performance Index (APLPI), Line
Outage Distribution Factor (LODF), Line loadability, etc.
Generally, once the current working state of a system is known, contingency analysis can be
broken down into the following steps:
a. Contingency definition
b. Contingency selection
c. Contingency evaluation
Contingency definition involves preparing a list of probable contingencies. This typically
includes line outages and generator outages.
Contingency selection process consists of selecting the set of most probable contingencies;
they need to be evaluated in terms of potential risk to the system. Usually, fast power flow
solution techniques such as DC power flow are used to quickly evaluate the risks associated
with each contingency. But in this work, the Newton-Raphson load flow method will be used
to ensure higher accuracy.
Finally, the selected contingencies are ranked in order of their security, till no violation of
operating limits is observed.
The algorithm for a typical contingency analysis is shown in Figure 1.

Figure 1: Algorithm of a typical contingency analysis

3
2.2 LINE LOADABILITY
Line Loadability can be defined as Transmission-line voltages decrease when heavily loaded
and increase when lightly loaded. When voltages on EHV lines are maintained within ±5% of
rated voltage, corresponding to about 10% voltage regulation, unusual operating problems are
not encountered. Ten percent voltage regulation for lower voltage lines including transformer-
voltage drops is also considered good operating practice.

In addition to voltage regulation, line loadability is an important issue. Three major line-loading
limits are:

a. the thermal limit,


b. the voltage-drop limit, and
c. the steady-state stability limit.

The maximum temperature of a conductor determines its thermal limit. Conductor temperature
affects the conductor sag between towers and the loss of conductor tensile strength due to
annealing. If the temperature is too high, prescribed conductor-to-ground clearances may not
be met, or the elastic limit of the conductor may be exceeded such that it cannot shrink to its
original length when cooled.

Conductor temperature depends on the current magnitude and its time duration, as well as on
ambient temperature, wind velocity, and conductor surface conditions.

The loadability of short transmission lines (less than 80 km in length) is usually determined by
the conductor thermal limit or by ratings of line terminal equipment such as circuit breakers.
For longer line lengths (up to 300 km), line loadability is often determined by the voltage-drop
limit. Although more severe voltage drops may be tolerated in some cases, a heavily loaded
line with VR/VS ≥ 0.95 is usually considered safe operating practice. For line lengths over 300
km, steady-state stability becomes a limiting factor [4].

3. METHODOLOGY
In this paper, the AC load flow method of contingency analysis was adopted. The Newton-
Raphson load flow algorithm, an algorithm under the AC load flow method, was used to solve
the power flow problems during the analysis using MATLAB. This is because the NRLF
method has more accuracy than other AC Load flow methods and converges faster. Newton-
Raphon’s Load flow method is discussed more in [3, 4].

3.1 Calculating System Line Overload Index (SLOI)


To obtain the overall system overload index, a new performance index was proposed and
calculated based on the Line Loadability discussed in Section 2.2. As stated, for safe operation,
the ratio of the receiving end voltage and the sending end voltage must be greater than 0.95.
This newly proposed index relies on this to calculate the system line overload index. It helps
tell the system designer at a glance, the lines that should be given utmost attention in terms of
protection. SLOI is computed by equation (1):

4
𝑉 𝑘
𝑆𝐿𝑂𝐼 = 1 − [min (𝑉𝑅 )] (1)
𝑆

where
VR, VS are the receiving end and sending end voltages respectively, and
k the number of lines whose VR/VS < 0.95

The Nigerian transmission grid is shown in Figure 2 with the single line diagram shown in
Figure 3.

Figure 2: the Nigerian power system. Blue lines indicate the 330-KV lines
(Source: Nigeria System Operator)

Figure 3: one-line diagram of the Nigeria 330-KV transmission grid

5
The network parameters – generator data, load data, and line & transformer data, of the Nigeria
power system as used in this work were collated from [8, 9, 10] and are shown in tables 1, 2,
and 3 respectively.

Table 1: Generator data


Bus Bus name PG Voltage (pu)
no (MW)
1 Kanji GS 756 1
7 Shiroro 413 1
8 Jebba GS 339 1
20 Sapele 70 1
21 Egbin 967 1
22 Afam 316 1
25 Delta GS 498 1
26 AES 235 1
Table 2: Load data
Bus Bus name Active Reactive Bus Bus name Active Reactive
no Power Power no Power Power
(MW) (MVAr) (MW) (MVAr)
2 Brini-Kebbi 89 55 13 New Haven 182 112
3 Kano 226 140 14 Aiyede 210 130
4 Jos 114 90 15 Ikeja-West 484 300
5 Gombe 130 80 16 Benin 136 84
6 Kaduna 260 161 17 Onitsha 146 77
9 Jebba TS 7.44 3.79 18 Alaoji 248 153
10 Katampe 236 146 19 Akangba 389 241
11 Oshogbo 194 120 23 Aja 200 124
12 Ajaokuta 72 45 24 Aladja 47.997 24.589

Table 3: Lines and Transformer data


from to y/2 from to y/2
bus bus r (pu) x (pu) (pu) bus bus r (pu) x (pu) (pu)
2 1 0.02676 0.06576 1.178 25 24 0.00276 0.00679 0.171
1 9 0.00699 0.01718 0.308 25 16 0.00924 0.0227 0.239
8 9 0.00069 0.0017 0.033 12 16 0.0145 0.03564 0.745
9 11 0.01355 0.0333 0.597 11 16 0.02167 0.05324 0.954
11 15 0.02167 0.05324 0.521 7 9 0.02106 0.05176 0.927
11 14 0.00993 0.02439 0.437 7 10 0.01243 0.03055 0.564
14 15 0.01183 0.02906 0.521 6 7 0.00829 0.02036 0.364
15 19 0.00147 0.00361 0.065 3 6 0.01985 0.04879 0.874
15 21 0.00535 0.01315 0.257 4 6 0.01692 0.04158 0.748
21 23 0.00138 0.00339 0.257 4 5 0.02279 0.056 1.01
15 16 0.02417 0.05939 1.162 16 17 0.01183 0.02906 0.521
16 20 0.00432 0.01061 0.208 13 17 0.00829 0.02036 0.0355
20 24 0.00544 0.01336 0.239 17 18 0.01191 0.02927 0.524
18 22 0.00216 0.0053 0.104

6
3.1 Simulation of Line Outage
Simulation of transmission line outage is carried out by the formulation of the corresponding
admittance matrix [5]. For instance, after outage of a line connecting bus ‘a’ and ‘b’, the
components of the Y bus that will be affected are Yaa, Ybb, Yab, and Yba. For a ‘π-modelled’
transmission line, the admittance values after this outage is obtained by subtracting the
admittance of the line a-b and the shunt susceptance jbab/2 and jbba/2 from Yaa and Ybb.

Line outages was simulated by simply removing the line information from the line data matrix.
This is similar to the line not existing initially as the information no longer exists.

3.2 Simulation of Generator Outage


This simulates mainly outage of one unit (or more) in a power station. Let the total generation
for the station at bus ‘m’ be Pgm, and assume that there exist identical (g) units, then [6]:
′ 𝑃𝑔𝑚
𝑃𝑔𝑚 = 𝑃𝑔𝑚 − 𝑛 ( ) (2)
𝑔

where
P’gm: Active power generated at bus m after the outage
Pgm: Active power generated at bus m before the outage
n: Number of outage generation units in the station
Pgm/g: Active power generated at bus m per generator unit

In this work, generator outages were not simulated as only the effect of line outages were
desired.

4. Results and Discussion


The results of the analysis (the SLOI) is shown in Table 4 ordered by the SLOI from the most
critical to the least critical.

Table 4: SLOI values for line outages


from bus to bus SLOI from bus to bus SLOI
11 14 0.62861 1 9 0.345921
11 15 0.57216 8 9 0.310785
16 20 0.57216 12 16 0.26828
20 24 0.57216 7 9 0.25531
25 16 0.57216 9 11 0.251848
14 15 0.50712 11 14 0.22509
15 16 0.50712 20 24 0.21975
25 24 0.50712 15 21 0.199932
11 16 0.50712 14 15 0.182697
2 1 0.39802 25 24 0.17881
16 20 0.37794 11 15 0.174183
0.35225 15 16 0.14697
11 16
15 19 0.131305
25 16 0.35088
21 23 0.130708

7
The result as shown in Table 4 contains the SLOI values of the different lines for line outages.
It has been organised in the order in descending order.

This shows that the outage of line 11 to 14 (Oshogbo to Aiyede) will have the most critical
effect on the system followed by 11 – 15, 16 – 20, 20 – 24, 25 – 16. These lines have been
shown to pose serious danger on the system stability if they fail, and therefore should be
secured defensively to avoid the level of system instability caused by the outage of any of the
lines.

5. Conclusion
From this study, it is has been shown with values, the importance of operating the transmission
system defensively to avoid system collapse due to overloading. Also, the writer suggests that
the Transmission Company of Nigeria (TCN) should adopts the (Flexible AC Transmission),
FACT devices as they can improve the lines active power capability in any contingency event
as have faster switching than the traditional compensation devices. Also additional lines should
be used to connect Oshogbo to Aiyede through different routes to create more links for power
to be transmitted through to Lagos area in order to reduce the SLOI value of Oshogbo to Aiyede
line.

References
[1] Chary, D. M., “Contingency Analysis in Power Systems, Transfer Capability
Computation and Enhancement Using Facts Devices in Deregulated Power System.”
Ph.D. diss., Jawaharlal Nehru Technological University, 2011

[2] Wood, A. J.; Wallenberg, B. F., “Power Generation, Operation and Control”. 2nd ed.,
New York/USA: John Wiley& Sons, 1996, pp. 410-432.]
[3] Saadat, H., Power System Analysis, New Delhi: McGraw Hill, 2002, pp 189 – 256.

[4] Glover, J. D., Sarma, M. S., Overbye, T. J., Power System Analysis and Design, 5h ed.
Stamford: Cengage Learning, 2012.

[5] Nara, K.,Tanaka,K., Kodama, H., Shoults, R. R., Chen, M. S., Olinda, P. V. and
Bertagnolli, D., “On-Line Contingency Selection for voltage Security Analysis”, ibid, Vol.
PAS – 104, pp. 847-856, April 1985.

[6] Mohamed, S. E. G., Mohamed, A. Y., and Abdelrahim, Y. H., “Power System
Contingency Analysis to detect Network Weaknesses”, Zaytoonah University
International Engineering Conference on Design and Innovation in Infrastructure, Amman,
Jordan, pp. I3-4 Jun., 2012.

[7] “Nigeria's Power Generation hits 5,228 Mega Watt”, Nigeria Compass, May 4, 2013.
[Online]. Available: http://www.compassnewspaper.org/index.php/special-desk/business-
news/12769-nigerias-power-generation-hits-5228-megawatts [Accessed July 15, 2013].

[8] Ogbuefi, U. C., “A Powerflow Analysis of Niegria Power System with Compensation on
Some Buses”,PhD thesis, University of Nigeria, Nsukka, Nigeria, 2013.

8
[9] Nigeria System Operator, “Profile of Transmission”, 2011. [Online]. Available:
http://nigeriasystemoperator.org/spread/profile/ [Accessed: July 15, 2013].

[10] Onohaebi, O. S., “Power Outages in Nigeria Transmission Grid,” Research Journal of
Applied Science, vol. 4, Issue 1, pp 1- 9, 2009.

View publication stats

You might also like