Professional Documents
Culture Documents
01.3 ENSTP - 2019 General Overview
01.3 ENSTP - 2019 General Overview
UNIVERSITY OF PADUA
DEPARTMENT OF ENVIRONMENT, LAND AND DEPARTMENT OF CIVIL, ARCHITECTURAL AND
TRANSPORTATION INFRASTRUCTURES ENVIRONMENTAL ENGINEERING
Highway construction project
Planning
• Pre-feasibility study
• Feasibility study
Design
• Preliminary design
• Final design
• Executive design
Construction
• Award of contract (bid process, enterprise competition, works
adjudication and delivery)
• Execution of works
• Measurements and accounting
Final acceptance
L1.3 - General overview 2
Highway construction project
Road authorities are normally the owners and operators of road networks.
If capacity- or safety-related problems in the network are identified, a study need to be
carried out (pre-feasibility study) to quantify the problem and identify potential
improvements.
• simple solutions (additional road markings, pavement reconstruction, improve
public transport)
• complex solutions (the construction of a complex urban motorway)
Options that are too costly or too difficult to build are discarded.
Assessment of impacts on side roads and accesses and the need for land purchasing
need to be considered at this stage also.
Once a road proposal has gained planning permission the preparation of the final
design can begin.
A greater level of detailed information are required and the detailed design of bridges
and other structures, the drainage and the road pavement design are made.
In the final location survey the alignment is materialized on the field by direct
chaining.
L1.3 - General overview 9
New construction
The selection of the route location is a hierarchically structured decision process to
find the best alignment that meets traffic desire lines at an economical cost.
Location process:
1. Fix the end termini and define a region (A) that
include all feasible routes between these two
points.
2. Identify broad bands (B and C) using
reconnaissance techniques
3. Refined searches in broad bands to select
corridors (D, E and F)
4. Choose the best corridor by comparison (E) and
generate the route (G) within it by creating one or
more alignments
5. Select by comparison the most suitable
alignment for structural design and construction
purposes.
A Bid Board is established to open the sealed proposals and ranking the bidders based
on guidelines. The client authority take the decision regarding the awarding of the
contract.
L1.3 - General overview 14
Contractual documents
The client award the contract to the successful bidder (the contractor).
The contract or agreement includes:
• the name of the parties, their legal residence and the date of execution of the
agreement
• the description of the work to be done with quantities and prices with reference to
the plans, specifications and proposal (executive project)
• the starting date and the time for completion
• signatures
Plans are approved drawings pertaining to the work covered by the contract.
Specifications are the written instructions that supplement the plans and cover the
quality of materials, workmanship and other technical data.
The contractor may sublet a part of the work contracted for by means of subcontract.
Usually the subcontractor need to be approved by the authorizing agency.
Right-of-way agreements are contracts between the client authority and a property
owner to obtain the land needed for highway construction purpose.
L1.3 - General overview 15
Executive project
The executive project represents the engineering of all the interventions envisaged in
the previous design phases in every detail, representing the technically more defined
phase of the entire design process and consists of the following elements:
• General report
• Specialty reports
• Drawings (including structures, utilities, environmental remediation)
• Calculations for structures and utilities
• Maintenance plan
• Safety and coordination plans
• Bill of quantities and economic evaluation
• Timetable
• Unit prices and related analyses
• Technical Specifications
FROM DESIGN ….
LONGITUDINAL PROFILE
HORIZONTAL ALIGNMENT
TRANSVERSE SECTION
CUT SECTION
… TO CONSTRUCTION
PAVEMENT
L1.3 - General overview 19
Specifications for roadworks
Specifications are the part of the contract that deals with how the road is
to be constructed.
Typical structure (Italian case):
Part 1 – Description of works and contractual aspects
Part 2 – Technical specifications
Part 3 – Measurement and control
Part 4 – Unit prices
Technical specifications
Characterization and
qualification of component materials
Construction and
placement of materials
Technical specifications
➢ PRESCRIPTIVE vs PERFORMANCE-BASED
Technical specifications
➢ PRESCRIPTIVE vs PERFORMANCE-BASED
S2QC/AC = S2m/c
SAMPLING CRITERIA
Determination of a given characteristic referred to a quantity of product (lot) should
be performed on a limited number of samples
REPRESENTATIVE OF THE
ENTIRE LOT
SAMPLING PROGRAM
• Test frequency
• Location of samples
• Size of samples
𝑋ത = 𝑋𝑖 𝜎 2 – 5% = low variability
𝑛 𝐶𝑉 = ⋅ 100
_ 5 – 10% = moderate variability
𝑖=1 𝑋 10 – 20% = high variability
> 20% = very high variability
Variation range X ± 3s
CONTROL CHARTS
Statistical tool for the verification of the correct functioning of a given system (whether it is «in
control» or not).
It can be considered as a sequence of normal distribution curves (vertical axis) as a function of
tested samples (in individual lots)
There is a problem (the system is not under control any more) when:
• 𝑋ത varies, R constant
• 𝑋ത constant, R varies
• 𝑋ത and R vary
ABRUPT CHANGE TREND IRREGULARITY
Ex. Abrupt failure Ex. Progressive wear Ex. Continuous non necessary
adjustments
L1.3 - General overview 31
Quality control of materials and construction
39.7
36.3
The road structure consists of the pavement (part in direct contact with the
vehicles) and the subgrade (capping layer, embankment, trench, bridge, tunnel) that
connects it to the supporting ground.
Subgrade
Pavement
Road prism
Embankment
Natural ground foundation Anti-capillary layer
L1.3 - General overview 35
Structural elements of road infrastructure
The pavement is the set of elements resting on the surface bordering the subgrade
called formation level, which carry out the road surface.