08 Scaffolding Erection Dismantling
08 Scaffolding Erection Dismantling
Method
task/operation being Task Carried assessment: Ongoing
Statement Action by
Sajimon KK assessed: out by? 15 January 09
by When?
Site
Ref No: Rev – 02 – RA – 2009 - Depa Cross reference to N.B. Residual risk:
SSOW/method Other on site The risk left
statement: (Highlight SSOW/Method statement control measures after all control
one below) Ref No: may be required measures have
Page No: due to weather been put in
YES NO M/S 001 conditions/other place – see
Risk Persons at risk reasons at time risk matrix at
severity of footer:
E C P Oth
(before task/operation:
Activity/ Significant ers
controls Control measures Work must not
Operation hazard
are in required: start until the
place) risks have
been assessed:
08 Falling of High Yes Yes Yes Prior to the Provide toe board. Project Site Engineer
Materials commencement Manager
Scaffolding of the activity Supervisor
Erection Stop working under Construction
Dismantling scaffolding. Manager Foreman
Steel stacked
materials should be
secured.
Don’t stack
unnecessary materials
on scaffolding.
Frequent cleaning of
platforms.
Out riggers to be
provided to prevent
toppling of mobile
scaffold.
Scaffolding should be
on solid base.
Low
Loads on platform
should be evenly
distributed.
Frequent inspection of
scaffold by
competent person.