Professional Documents
Culture Documents
PROCEDURE FOR
FUNCTIONAL TESTING/LOOP CHECKING
CONTENTS
1.0 Purpose
2.0 Scope
3.0 References
4.0 Definitions
5.0 Procedure
5.1 General
5.2 Personnel/Responsibility
5.3 Safety
5.4 Functional Testing/Loop Checking Procedure
5.5 Equipment Calibration
6.0 Documentation
Rev.
Issue Date Issued For DOME Contractor Client
No.
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
1.0 PURPOSE:
2.0 SCOPE:
3.0 REFERENCES:
4.0 DEFINITIONS:
P.E.F.S Process Engineering Flow Scheme
S.D.E System Distribution Electrical
P.E.F.S. Process Engineering Flow Scheme
R.O.V Remote - Operated Valves
M.O.S Maintenance Over ride Switch
C.C.B Control Center Building
I.C.S Integrated Control System
D.C.S Distributed Control System
TC Thermocouple
R.T.D Resistance Temperature Devices
P.L.C Programmable Logic Control
5.0 PROCEDURE:
5.1 General:
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
5.2 PERSONNEL/RESPONSIBILITY:
5.3 SAFETY:
5.3.1 Dome Health, Safety and Environment manual shall be adhered to at all time.
Personnel shall ensure that the work area facilities are adequate with regard
to illumination, weather protection, scaffolding etc. prior to commencing work
activities.
5.4.1.1 Check utility supplies for correct values. Inject signals of 0%, 50% and 100%
of full scale at the transmitter primary, using a hand pump or gas bottle as
appropriate. Observe and record the effects on other elements of the loop.
Disconnect temperature elements in the instrument head and use a test box
to inject signals of 0% and 100% of full scale. Observe and record the
effects on other elements of the loop.
If a controller is included in the loop, switch to manual and vary the controller
output. Observe the effect on the final element. Check that auto to manual
transfer is smooth and observes the final element reaction to input signal
changes. Record the results.
NOTE:
For controller checks reduce integral and derivative terms to minimum setting. Mid
range settings shall be restored after loop checking is complete.
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
NOTE:
Tests shall follow the logic diagram, using a state diagram to represent all the
necessary input and output conditions.
Firstly, disconnect the input elements for example by opening the knife
terminals in SDE cabinets and connect simulation switches and lights
mounted on a simulation panel. Test all inputs, outputs and logic functions.
Secondly, activate primary elements with knife terminals closed and check
the complete system through to final element(s).
5.5.1 Equipment used for measurement and testing shall be calibrated prior to use
and included in applicable departmental calibration and maintenance
programs per procedure for Inspection, testing and measuring equipment.
6.0 DOCUMENTATION:
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
Attachment 1
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
checking.
3 Control room loop check inside the
control room
3.1 For analogue loops, break the loop at SDE
knife terminals and apply a signal simulator
in accordance with the type of signal (i.e. 4-
20 MA, T/C, RTD, etc)
3.2 Vary the signal input between 0% and 100%
of scale and check all functions of the control
room equipment as defined in the design
documents
3.3 Check analogue signal outputs to field in the
appropriate SDE cabinet
NOTE: If the results are not as expected,
check all documents of the loop and retest
after taking corrective action
3.4 For binary loops, check operation of the
loops by simulating contact inputs and
observing logic outputs using simulation
3.5 After testing logic systems, check that all
jumpers have been removed and that all
temporary modifications have been corrected
4 Total loop check - i.e. from transmitter to
ICS/DCS and from ICS/DCS to final loop
element
4.1 With all knife terminals in the loop and at
SDE cabinets closed inject a signal at the
primary element as follows:
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
NOTES:
1) Performance testing of The CTV camera
shall be carried out during the day and at
night.
2) Final camera orientation should be carried
out in conjunction with the operating team.
3) The site acceptance test shall be in
accordance with the manufacturer's
recommendations with reference to the
results and procedures of the factory
acceptance test
8 PACKAGE UNITS
NOTE: Conventional instrumentation shall be
loop tested in accordance with the
procedures given in Attachment 1 of this
procedure and with reference to the
manufacturer's recommendations
8.1 ROVs not included in equipment packages
shall be tested as part of the logic control
system
8.2 HEATING VENTILATION AND
AIRCONDITIONING (HVAC)
8.2.1 All instruments shall have been tested prior
to loop testing.
8.2.2 Carry out loop testing in accordance with the
manufacturer's recommendations
8.2.A Start-up Tests:
1) Electric motors
2) Fans
3) Pumps
4) Electric heater
5) Control panel
6) Humidifiers
8.2.B Function tests
1) Trip test
2) Automatic Sequence
3) Air balancing
4) Water balancing
5) Over pressure
6) Sound levels
7) Smoke tests
8) Remote control
9) Fire and gas detection
10) Emergency generator
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
1) Radio
2) Telephone
3) Telex
4) Paging
5) Miscellaneous:
Intercom
Public address
Remote liaison (Control room to fire
station, etc.)
9 SEQUENTIAL CONTROL SYSTEMS
9.A Internal/external room loop check (if the
sequential cabinet is located inside the
control building)
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
NOTE:
The primary and final elements shall be
checked and tested separately prior to
checking of the loop.
9.C Functional Test
NOTES:
1) Functional test procedures shall be in
accordance with the manufacturer's
recommendations.
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
2) Gas detection:
3) Fire detection:
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
NOTES:
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
valve.
2) Connect pressure equipment to vent
connection.
3) With no pressure applied check alarm
state.
4) Apply increasing pressure for high alarm
and observe action.
5) Apply decreasing pressure for low alarm
and observe action.
6) Release pressure and disconnect test
equipment.
7) Close the vent/drain valve.
11.3 Temperature instruments
11.3.A Thermocouples (T1 and T1A)
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
NOTES:
1) Care should be taken with reverse acting
positioners and split range valves check
operations with PETS.
2) Selecting relays are defined by mA signal
and not by valve position.
3) Inverter can be either at the positioner or
ICS/DCS (Engineer decision).
11.4.B Lock-up devices
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
11.5.D
Ite
Action Check Remarks
m
1 Check initial status 1) Low-level alarm On (LCP)
2) Low-pressure alarm On
3) High-level alarm Off
4) High-pressure alarm Off
5) High-temperature alarm
Off
2 All alarms off 1) Low-level alarm off (LC)
1) Place bridge on low- 2) Low-pressure alarm off
level alarm (LCP)
2) Place bridge on low- 3) Common pre-alarm off
pressure alarm (BCS/ADP)
3 Simulation of alarms
3.1 Remove bridge on low 1) Low-level alarm On + Horn
level alarm (LCP). Common pre- + Accept
alarm On (ICS/ADP/DCS)
3.2 Replace bridge on low- 2) Low-level alarm Off
level alarm (LCP). Common pre-
alarm Off (ICS/M3P/DCS
)
3.3 Remove bridge on low 3) Low-pressure alarm On + Horn
pressure alarm (LCP). + Accept
Common pre-alarm On
(ICS/ADP/DCS )
3.4 Replace bridge on low 3) Low-pressure alarm Off
pressure alarm (LCP).
Common pre-alarm Off
(ICS/ADP/DCS )
3.5 Replace bridge on high- 5) High-level alarm On + Horn
level alarm (LCP). + Accept
Common pre-alarm On
(ICS/ADP/DCS)
3.6 Remove bridge on high- 6) High-level alarm Off
level alarm (LCP).
Common pre-alarm Off
(ICS/ADP/DCS)
3.7 Replace bridge on high- 7) High-Pressure alarm On + Horn
Pressure alarm (LCP). + Accept
Common pre-alarm On
(ICS/ADP/DCS)
3.8 Remove bridge on high- 8) High-Pressure alarm Off
This document is a confidential property of Dome Trading & Contracting Company Limited
Master Departmental Manual Code DOMEINSTSOP003
This document is a confidential property of Dome Trading & Contracting Company Limited