PT PETROKIMIA BUTADIENE INDONESIA

In west Java, Indonesia

PBI 100,000 MTA


BUTADIENE EXTRACTION PLANT

SYSTEM COMPLETION DISSIER


FOR
INFRASTRUCTURE (PILE)

SD-MC-01-01
SYSTEM COMPLETION DOSSIER
INFRASTRUCTURE (PILE)
( SD-MC-01-01 )

INDEX

No Description Page

I Turnover Acceptance Report


1. System Turn Over Notice (STON)
2. System Completion Certificate (SCC)

II Turnover Documents
1. System Description
2. List of Pile Drawing
3. Summary of Field Inspection Report
4. Punch List
System No.

SD-MC-01-01
System Turn Over Notice

System Description: INFRASTRUCTURE (PILE) Date: 07 May, 2012

This certificate acknowledges that the above package as define, has been erected/assembled in full accordance
with design and vendor drawings and has been inspected, tested, completed and pre-commissioned except as
shown in the attach exception list. All outstanding work is defined in the attached punch list or noted below. This
package will be under control of commissioning group upon acceptance.

Summary of remaining items to be completed as follows:

We hereby agree that the above system as define, fully complies with the requirement of CONSTRUCTION
COMPLETION. This certificate documents the transfer of care, custody and control of the system to the
OWNER.
The system is now safe and ready for commissioning activities to begin.
Construction Client Operation
Representative Representative Representative

Date : Date : Date :


SYSTEM DESCRIPTION

Project Name : PBI 100,000 MTA BUTADIENE EXTRACTION PLANT

Dossier Number : SD-MC-01-01

System Number : 01 - 01

System Description : INFRASTRUCTURE (PILE)

Sub System : None


LIST OF PILE DRAWING

No. Description DWG No.

1. Pile Location Plan


Pile Location Plan (ISBL) (1) D51004-8064AA
Pile Location Plan (ISBL) (2) D51004-8064AB
Pile Location Plan (OSBL) (1) (Area 210) D51004-8764AC
Pile Location Plan (OSBL) (2) (Area 210) D51004-8764AD
Pile Location Plan (OSBL) (3) (Area 250) D51004-8764AE
Pile Location Plan (OSBL) (4) (Area 220) D51004-8864AF
Pile Location Plan (OSBL) (5) (Area 220/230) D51004-8864AG
Pile Location Plan (OSBL) (6) (Area 230/250) D51004-8764AH
SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

I. Turnover Acceptance Report

I.1 System Turn Over Notice (STON)

I.2 System Completion Certificate (SCC)


SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

I.1

System Turn Over Notice (STON)


SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

I.2

System Completion Certificate (SCC)


SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

II. Turnover Documents

II.1 System Description

II.2 List of Pile Drawing

II.3 Summary of Field Inspection Report

II.4 Punch List


SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

II.1

System Description
SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

II.2

List of Pile Drawing


SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

II.3

Summary of Field Inspection Report


SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

II.4

Punch List
SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

III. Quality Verifying Documents

III.1 Pile Location Drawing

III.2 Mill Test Certificate of Pile

III.3 Pile Load Test Report

III.4 Pile Driving Record


SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

III.1

Pile Location Drawing


SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

III.2

Mill Test Certificate of Pile


SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

III.3

Pile Load Test Report


SYSTEM COMPLETION DOSSIER
PILING WORKS
( SD-MC-01-01 )

III.4

Pile Driving Record


PT PETROKIMIA BUTADIENE INDONESIA Project No. : 51-004-01
PBI 100,000 MTA STON No. :
BUTADIENE EXTRACTION PLANT STON Date :

SYSTEM TURN OVER NOTICE (STON)

System No. :
System Definition :

Associated Sub-System

Associated Drawings

Reference Commissioning Procedure

Outstanding Work Scope

Comments

We hereby agree that the above system as defined that fully complies with the requirements of
Construction Completion. The system is now safe and ready for commissioning to begin even the
outstanding work is still on progress that will not affected the commissioning works.

Colume of Concerned Party


Commissioning Representative Operation Representative Owner Representative
Flow Chart of System Mechanical Completion
Rev.1_23 Apr, 2012

Contractor (Toyo-K) PMC / OWNER (FW / PBI) Remarks

1 1.1 90% of Work

System Turn Over Notice 1.2 Target Completion Date


(STON)
with Punch List ▶ 2 2.1 (If any) Additional
deficiencies to be added.
Punch List Review
3 ◀ 3.1 Except Punch "C" & "D"
"A" - Before Hydrostatic Test
Punch Clear
"B" - Before Mechanical Comp.
(Punch Item "A" & "B")
▶ 4 "C" - Before RFSU

Confirmation "D" - Before Provisional Accep.


&
5 ◀ Signature on Punch List 5.1 For Review

System Completion Dossier


(SCD)
▶ 6 6.1 Within 14 calendar days

System Completion after receipt of SMCP


Certificate
7 ◀ (SCC) 7.1 Punch Clear (Item "C")

SCD Official Issue &


Completion of
Pre-commissioning


8 8.1 Issue for Review

Notice of
Ready for Start-up
(RFSU) ▶ 9 9.1 Within 7 calendar days
after receipt of RFSU
RFSU Certificate
10 ◀ 10.1 Punch Clear (Item "D")

Commssioning &
Performance Test
▶ 11 11.1 Within 7 calendar days
after performance test
Provisional Acceptance
Certificate