Professional Documents
Culture Documents
Site Acceptance Test Procedure Last Rev1
Site Acceptance Test Procedure Last Rev1
Putra Wayan
Ronald G Wes
01 IFU 7 Aug 11 Issued for Use Kurnia Adi Prihanto Mega
Moore Richins
Budiartha
Wayan
Putra Ronald G Wes
0B IFA 6 Aug 11 Issued for Approval Adi Prihanto Mega
Kurnia Moore Richins
Budiartha
Wayan
Putra Ronald G Wes
0A IFC 3 Aug 11 Issued for Comment Adi Prihanto Mega
Kurnia Moore Richins
Budiartha
Project Project
Prepared Checked Approved
Rev Status Issue Date Reason for Issue Engineer Manager
Contractor Approvals COPI Approvals
Printed initials in the approval boxes confirm that the document has been signed.
The originals are held within Document Management.
Procedure/Work Instruction/Job Note D-84531-DY-MM1-PRO-ST-01-0002 - Rev. 01
Site Acceptance Test Procedure
ConocoPhillips (Grissik) Ltd. Page 2 of 11
Revision Sheet
ConocoPhillips (Grissik) Ltd.
Contents
Contents ……………………………………………………………………………………………….................. 3
1. Purpose ………………………………………………………………………………………………………... 4
2. Scope …………………………………………………………………………………………………………... 4
3. Responsibilities ……………………………………………………………………………………………… 4
4. Sequence …………………….……………………………………………………………………………….. 4
5. Alarm and Trip Set-Points ………………………………………………………………………………….. 5
6. Procedure ……………………………………………………………………………………………………... 5
7. Readiness for Operation Certificate ……………………………………………………………………. 11
Appendix
Appendix A – P&ID Gas Compressor Package
Appendix B – P&ID Fuel Gas Conditioning Package
Appendix C – PFD Dayung Station-Field Facilities Gas Compression Unit
Appendix D – Compressor Cause and Effect Shutdown Matrix
Appendix E – Compressor and Engine Pre-Start Check List
Appendix F – Compressor Unloaded Run Test Check List
Appendix G – Compressor Loaded Run Test Check List
Appendix H – Site Acceptance Test Checklist
Procedure/Work Instruction/Job Note D-84531-DY-MM1-PRO-ST-01-0002 - Rev. 01
Site Acceptance Test Procedure
ConocoPhillips (Grissik) Ltd. Page 4 of 11
1. Purpose
This document describes the guidance procedure for Site Acceptance Test (SAT) of gas
compressor package units and all associated piping and instrumentation which will be
involved during SAT.
2. Scope
The scope of this procedure covers all aspects for SAT of the gas compressor package unit
including all parameters that shall need to be checked, witnessed, and signed off by all
concerned parties.
3. Responsibilities
The responsibilities for the Site Acceptance Test of gas compressor package reside with a
number of different parties. The following table defines the activities and party responsible.
4. Sequence
The following step generally describes the sequence of works for Site Acceptance Test
(SAT) of compressors unit:
1. Open the starting gas discharge valve and fuel gas discharge valve at the upstream of
fuel gas treatment skid piping.
2. If required, depressurized gas compressor package piping by start-up by pass valve and
blow down valve until the pressure reach 150 psi
3. Perform unloaded run test for all 4 (four) compressor units for about 30 minutes using
compressor start-up by pass until the engine speed reach 1100 rpm. Monitor and log the
compressor parameter as specified in Appendix F from the idle speed 700 rpm to 1100
rpm at 100 rpm interval to ensure they remain within parameters as specified by
compressors manufacturer.
4. On satisfactory of unloaded run test, reduce engine speed to 900 rpm and perform
loaded run test for all 4 (four) compressor units for about 4 (four) hours using station
recycle valve by slowly open ball valve suction line to compressors unit. Keep open all
ball valves suction line until compressor suction pressure reach 950 psi. Once
completed gradually increase the engine speed until the engine speed reach 1150 rpm.
Procedure/Work Instruction/Job Note D-84531-DY-MM1-PRO-ST-01-0002 - Rev. 01
Site Acceptance Test Procedure
ConocoPhillips (Grissik) Ltd. Page 5 of 11
Monitor and log the compressors parameter as specified in Appendix G and ensure that
there are no indication alarms at compressor control panel.
(During initial loaded run test, compressor suction pressure shall be continuously
monitored at each compressor local control panel until compressor suction
pressure reach 950 psi and compressor start-up by pass valve in close position)
5. Perform Site Acceptance Test (SAT) of all 4 (four) compressor units by slowly open 16”
station suction valves. Prior to SAT please ensure that 12” station discharge valve
should be NORMALLY OPEN (see Appendix C)
After all 4 (four) compressors has been successfully tested (no alarms indication in
compressor local control panel / Dayung control room and no one compressor shutdown
due to fail function of compressors unit) for 72 (seventy two) hours, the compressors now
will ready for placed in service (PIS) at inside area of Dayung Gas Gathering Station.
The compressor unit has been completed with some alarm indications, which can be
monitored at local control panel and some of them (common alarms) can be monitored at
Dayung control room, and trip set points to protect the equipment from damage. Please
refer to document “P&ID gas compressor package” in the Appendix A and “Compressor
Cause and Effect Shutdown Matrix”, in the Appendix D for compressor alarm set-points and
shutdown settings.
6. Procedure
This procedure describes the step by step detail for conducting Site Acceptance Test (SAT)
for compressors unit that will be placed in Dayung Gas Gathering Station. This site
procedure has only valid for the following Gas Compressor sets:
6.1. Preparation