CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 30 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 26.00 26.00 (11.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.84 0.84 - 0.84 -
6) Formwork for Foundation m2 44.45 - 44.45 44.45 -
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.015 0.01 0.004 0.015 -

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.54 0.54 - 0.54 -
6) Formwork for Foundation m2 44.45 - - - 44.45
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.60 0.60 - 0.60 -
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 1 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 21.74 - 21.74 21.74 -
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.00 5.00 - 5.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 6.30 6.30 - 6.30 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

8 Area-5 CO - 201 1) Excavation m3 18.00 18.00 - 18.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

9 Area-5 CO - 202 1) Excavation m3 22.08 22.08 - 22.08 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

10 Area-5 CO - 212 1) Excavation m3 21.60 21.60 - 21.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

Page 2 of 84
MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position

SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 2
5 Skill Worker (on site) 2
6 Skill Worker (on Fabrikasi) 7
7 Helper 11

TOTAL HEAD COUNT 26 1 1 2 2 9 11 - - 0.00 - - - - - -


TOTAL MANHOURS 260 10 10 20 20 90 110 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator -
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 11
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 21 - - 1 1 2 - 11 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 210 - - 10 10 20 - 110 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 12.00
2 Drizzie 13.00 s/d AAR
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 30/11/20 Area Kerja Terlalu Banyak Genangan Air Harus Dibantu Dari Pihak RJJ
1 30/11/20 Alat Pompa Terbatas

PHOTOGRAPH

Install Bekisting /Wall (OM-206, CO-206); install Round Bar (OM-


TBM Dewatering (CO-206, CO-212, CO-201, OM-206) 206), dan Install Rebar precast (2 unit CO);

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 3 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 29 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 17.00 17.00 (2.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.84 0.84 - 0.84 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 44.45 - - - 44.45
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.015 - 0.011 0.011 0.004

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.54 0.54 - 0.54 -
6) Formwork for Foundation m2 44.45 - - - 44.45
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.60 0.60 - 0.60 -
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 4 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.00 5.00 - 5.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 6.30 6.30 - 6.30 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

8 Area-5 CO - 201 1) Excavation m3 18.00 18.00 - 18.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

9 Area-5 CO - 202 1) Excavation m3 22.08 22.08 - 22.08 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

10 Area-5 CO - 212 1) Excavation m3 21.60 0.00 21.60 21.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

Page 5 of 84
MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position

SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 1
4 Foreman 1
5 Skill Worker (on site) 2
6 Skill Worker (on Fabrikasi) 7
7 Helper 4

TOTAL HEAD COUNT 17 1 1 1 1 9 4 - - 0.00 - - - - - -


TOTAL MANHOURS 170 10 10 10 10 90 40 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 12.00
2 Drizzie
3 Heavy Rain 13.00 s/d AAR

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 29/11/20 CO-213 --> excavation di-cancel karena area tertutup material (tangga)

PHOTOGRAPH

*type CO-206 --> Dewatering, Concrete Chipping;


TBM *type OM-206 --> Dewatering, Penguatan Bekisting, *type CO-212 --> Excavation
Install Round Bar (3 pcs)

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 6 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 28 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 31.00 31.00 (16.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.84 0.84 - 0.84 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 44.45 - - - 44.45
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.54 0.54 - 0.54 -
6) Formwork for Foundation m2 44.45 - - - 44.45
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.60 0.60 - 0.60 -
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 7 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.00 5.00 - 5.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 6.30 - 6.30 6.30 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

8 Area-5 CO - 201 1) Excavation m3 18.00 18.00 - 18.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

9 Area-5 CO - 202 1) Excavation m3 22.08 22.08 - 22.08 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 6
6 Skill Worker (on Fabrikasi) 7
7 Helper 13

Page 8 of 84
TOTAL HEAD COUNT 31 1 1 2 1 13 13 - - 0.00 - - - - - -
TOTAL MANHOURS 310 10 10 20 10 130 130 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator -
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 15 - - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 150 - - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 16.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 28/11/20 Tidak ada excavator dan penggalian berhenti Mohon diusahakan supaya dapat workfront galian
2 28/11/20 Pengecoran 1 titik tidak bisa karena terhalang crane

PHOTOGRAPH

*type CO-201, CO-202 --> Install Rebar (diatas), Dewatering, *type CO-205 --> Install Waterstop (6,30 m), Joint Survey & inspek Slab;
TBM Pouring Concrete (LC); *type CO-206 --> Pouring Concrete, *type OM-207 --> Joint Survey dan inspek Slab;
Dewatering *type OM-212 --> Dewatering, Perkuat Bekisting, Pouring Concrete

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 9 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 27 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 30.00 30.00 (15.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 - 8.00 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 10 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.00 5.00 - 5.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

8 Area-5 CO - 201 1) Excavation m3 18.00 18.00 - 18.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

9 Area-5 CO - 202 1) Excavation m3 22.08 22.80 - 22.80 (0.72)


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 7
6 Skill Worker (on Fabrikasi) 7
7 Helper 11

Page 11 of 84
TOTAL HEAD COUNT 30 1 1 2 1 14 11 - - 0.00 - - - - - -
TOTAL MANHOURS 300 10 10 20 10 140 110 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator -
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 14 - - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 140 - - 10 10 10 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 14.30
2 Drizzie
3 Heavy Rain 15.00 - 15.30

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 27/11/20 Supporting (talang bocor) Segera diadakan
2 27/11/20 Sarana angkut belum ada Segera diadakan
3 27/11/20 Power consumble belum ada Segera diadakan

PHOTOGRAPH

*type OM-212 --> Dewatering , Install Rebar (100%), *type CO-201, CO-202 --> Perapihan, Dewatering; *type CO-205 --> Dewatering, Loading Install Rebar, Install Bekisting
Install Waterstop (8m) *type OM-211 --> Dewatering , Install Rebar (100%); (100%); *type CO-206 --> Joint Survey dan Inspek Slab

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 12 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 26 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 31.00 31.00 (16.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 13 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.00 - 5.00 5.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

8 Area-5 CO - 201 1) Excavation m3 18.00 18.00 - 18.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

9 Area-5 CO - 202 1) Excavation m3 22.08 22.80 - 22.80 (0.72)


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 8
6 Skill Worker (on Fabrikasi) 7
7 Helper 11

Page 14 of 84
TOTAL HEAD COUNT 31 1 1 2 1 15 11 - - 0.00 - - - - - -
TOTAL MANHOURS 310 10 10 20 10 150 110 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 15 1 - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 150 10 - 10 10 10 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 26/11/20 Keterbatasan Alat Pompa utk Dewatering Harus dibantu pihak RJJ
2 26/11/20 Kesulitan workfront untuk galian dikarenakan interface Harus dicarikan galian dari pihak RJJ

PHOTOGRAPH

*type OM-212 --> Dewatering, *type CO-206 --> Install Formwork & Install Waterstop (5m); *type *type CO-201 --> Perapihan, Dewatering, Joint Survey LC, DCP Test (Passed),
Install Rebar (60%); *type CO-202 CO-205 --> Dewatering; *type OM-206 --> Perkuatan Bekisting; Install Rebar (50%); *type CO-202 --> Excavation , Dewatering
--> DCP Test (Passed) *type OM-211 --> Install Rebar (50%)

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 15 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 25 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 27.00 27.00 (12.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 16 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

8 Area-5 CO - 201 1) Excavation m3 18.00 18.00 - 18.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

9 Area-5 CO - 202 1) Excavation m3 22.08 0.00 22.08 22.08 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 11

Page 17 of 84
TOTAL HEAD COUNT 27 1 1 2 1 11 11 - - 0.00 - - - - - -
TOTAL MANHOURS 270 10 10 20 10 110 110 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 25/11/20 Masih terlalu banyak genangan air di OM-209 & masih belum teratasi Mohon dibantu pompa dari pihak RJJ, pompa ABN terbatas
2 25/11/20 Kondisi Plant di CO-206 bengkok Peralatan terbatas, diusahakan palu besar
3 25/11/20 Belum bisa melakukan DCP Test utk area yg sudah kebuka

PHOTOGRAPH

*type OM-209 --> Demob Bekisting, Install Rebar (Slab) --> 100%; *type CO-202 --> Dewatering, Excavation; *type CO-206, CO-207 --> Install Rebar (Wall & Slab) -->
*type OM-211 --> Dewatering, Demob Bekisting, Install Rebar (Slab) *type CO-201, OM-206 --> Dewatering; *type OM-212 100%; *type CO-204, 205 --> Demob Rebar & Bekising
--> 100%, Install Rebar (Wall) --> 1 sisi (25%) --> Dewatering, Install Rebar (Slab) --> 100%

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 18 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 24 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 27.00 27.00 (12.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18

Page 19 of 84
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

8 Area-5 CO - 201 1) Excavation m3 18.00 0.00 18.00 18.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - - - 0.63
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 2
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 10

TOTAL HEAD COUNT 27 1 1 2 2 11 10 - - 0.00 - - - - - -


TOTAL MANHOURS 270 10 10 20 20 110 100 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -

Page 20 of 84
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 14.00
2 Drizzie
3 Heavy Rain 15.00 s/d AAR

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 24/11/20 Area kerja banyak genangan air Harus dibantu pihak RJJ utk dipinjami pompa besar
2 24/11/20 Work front semua galian sudah terisi MP Segera diusahakan workfront pengalihan MP

PHOTOGRAPH

*type CO-201 --> Excavation; *type CO-205 --> Install Rebar (90%); *type CO-206 -->
TBM *type OM-209 --> Install Rebar (50%); Dewatering, Install Rebar (90%); *type CO-207 (OM-211) -->
*type OM-211 --> Dewatering; Install Rebar (70%); *type OM-206 --> Install Formwork

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 21 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 23 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 23.00 23.00 (8.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18

Page 22 of 84
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 7

TOTAL HEAD COUNT 23 1 1 2 1 11 7 - - 0.00 - - - - - -


TOTAL MANHOURS 230 10 10 20 10 110 70 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 17 1 1 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)

Page 23 of 84
broken (b)
TOTAL HOUR 170 10 10 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 12.00
2 Drizzie 13.00 s/d 14.30
3 Heavy Rain 15.00 s/d AAR

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 23/11/20 Area kerja Terlalu banyak air

PHOTOGRAPH

*type OM-207, OM-209, OM-212, CO-207 --> Dewatering;


TBM *Pondasi Waterfall --> Setting Anchor Bolt, Joint Survey Anchor Bolt *type OM-211, CO-205, CO-206 --> Demob material Bekisting
(OK) dan Rebar

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 24 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 21 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 24.00 24.00 (9.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18

Page 25 of 84
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT QA & QC


Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 8

TOTAL HEAD COUNT 24 1 1 2 1 11 8 - - 0.00 - - - - - -


TOTAL MANHOURS 240 10 10 20 10 110 80 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

Page 26 of 84
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 21/11/20 Galian area kerja tergenang air (Banjir)

PHOTOGRAPH

*Pondasi Waterfall 1,2 --> Install Formwork Pedestal (2 nos), *type OM-206 --> Dewatering, Marking, Bongkar bekisting sisi luar,
Install anchor (continue); *type CO-205 dan CO-206 --> Dewatering Perkuatan bekisting sisi dalam; *type OM-207 --> Dewatering, Marking

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 27 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 20 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 24.00 24.00 (9.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 28 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 8

TOTAL HEAD COUNT 24 1 1 2 1 11 8 - - 0.00 - - - - - -


TOTAL MANHOURS 240 10 10 20 10 110 80 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)

Page 29 of 84
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 16/11/20 Galian area kerja tergenang air (Banjir)

PHOTOGRAPH

*Pondasi Waterfall 1,2 --> Dewatering, Pablikasi Formwork Pedestal, *type OM-207 --> Dewatering;
Pouring Concrete pondasi *type OM-206 --> Dewatering, Install Formwork;

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 30 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 19 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 24.00 24.00 (9.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 31 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 8

TOTAL HEAD COUNT 24 1 1 2 1 11 8 - - 0.00 - - - - - -


TOTAL MANHOURS 240 10 10 20 10 110 80 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)

Page 32 of 84
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 12.00
2 Drizzie
3 Heavy Rain 13.00 sd 14.40

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 16/11/20 Galian area kerja tergenang air (Banjir)

PHOTOGRAPH

*type OM-209 --> Excavation / Perbaikan Souring, Dewatering; *type *Pondasi Waterfall 1,2 --> Ciping Joint Wall, Joint Survey Top Pondasi,
TBM OM-207 --> Dewatering; *type OM-206 --> Excavation / Perbaikan Install Rebar, Pablikasi dan perkuatan Formwork
Souring

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 33 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 18 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 24.00 24.00 (9.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 - 1.25 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18

Page 34 of 84
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 0.63 - 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 8

TOTAL HEAD COUNT 24 1 1 2 1 11 8 - - 0.00 - - - - - -


TOTAL MANHOURS 240 10 10 20 10 110 80 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 15 1 - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)

Page 35 of 84
standby (s)
broken (b)
TOTAL HOUR 150 10 - 10 10 10 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 16/11/20 Kekurangan MP (tukang), Belum ada alat angkut Segera diadakan penambahan MP, segera diadakan

PHOTOGRAPH

*type OM-207 --> Dewatering, Install Rebar (95%); *Pondasi *type OM-209 --> Excavation / Perbaikan Galian,
TBM Waterfall --> Install Rebar (100%), Install Formwork (80%); *Pondasi Manual Daging, Dewatering, DCP Test (passed), Pouring LC
Pipe Support 460 --> Pouring LC (DONE) (DONE)

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 36 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 17 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 18.00 18.00 (3.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 37 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.63 - 0.63 0.63 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 2

TOTAL HEAD COUNT 18 1 1 2 1 11 2 - - 0.00 - - - - - -


TOTAL MANHOURS 180 10 10 20 10 110 20 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 15 1 - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)

Page 38 of 84
broken (b)
TOTAL HOUR 150 10 - 10 10 10 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 16/11/20 Kekurangan MP (tukang), Belum ada alat cor Segera diadakan penambahan MP, segera diadakan

PHOTOGRAPH

*type CO-205 & OM-206 --> Dewatering, Pouring Concrete


*Type OM-207 --> Excavation / Galian Manual, Dewatering, Install (Slab & Wall, LC); *Pondasi Waterfall --> Install Rebar,
TBM Rebar; *type OM-209 --> Perbaikan Galian, Dewatering Pablikasi Formwork

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 39 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 16 November 2020

SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 18.00 18.00 (3.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 8.00 - 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 40 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 2

TOTAL HEAD COUNT 18 1 1 2 1 11 2 - - 0.00 - - - - - -


TOTAL MANHOURS 180 10 10 20 10 110 20 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)

Page 41 of 84
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 16/11/20 Kekurangan MP (tukang), Belum ada alat cor Segera diadakan penambahan MP, segera diadakan

PHOTOGRAPH

*Type OM-206 --> Joint Survey dan inspek (Slab & Wall),
*Pondasi Pipe Support 460 --> DCP Test, Joint survey & inspek, *Type OM-207 --> Dewatering, Install Rebar,
Install plastik siteet, Install Rebar *Type CO-205 --> Dewatering

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 42 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 15 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 19.00 19.00 (4.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 8.00 - 8.00 8.00 -
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 43 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 4

TOTAL HEAD COUNT 19 1 1 2 1 10 4 - - 0.00 - - - - - -


TOTAL MANHOURS 190 10 10 20 10 100 40 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)

Page 44 of 84
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 14.00
2 Drizzie 14.30 s/d AAR
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 15/11/20 Kekurangan MP (tukang), Transportasi / alat angkut, Tidak ada genset Segera diadakan penambahan MP, segera diadakan, segera diinspek

PHOTOGRAPH

*Type OM-206 --> Install Waterstop (8m), Install Formwork,


*Pondasi Pipe Support 460 --> Excavation, Perapihan, Install Bekisting LC *Type OM-207 --> Dewatering, Install Rebar

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 45 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 14 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 22.00 22.00 (7.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 - 43.50 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 46 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 12.60 - 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 7

TOTAL HEAD COUNT 22 1 1 2 1 10 7 - - 0.00 - - - - - -


TOTAL MANHOURS 220 10 10 20 10 100 70 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 17 1 1 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)

Page 47 of 84
broken (b)
TOTAL HOUR 170 10 10 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC

PHOTOGRAPH

*Type OM-209 --> Excavation (Repair Galian), Manual Daging, Dewatering *Type OM-206 --> Install Formwork segmen 1 (sebatas waterstop) (40%)
*Type CO-205, CO-206, Pondasi MPRK-02 --> Demob material to site *Type OM-207 --> Dewatering, Install Rebar (10%)

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 48 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 13 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 22.00 22.00 (7.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - 0.97 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - 0.97 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 49 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 11.55 - 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

7 Area-6 CO - 205 1) Excavation m3 12.60 0.00 12.60 12.60 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 7

TOTAL HEAD COUNT 22 1 1 2 1 10 7 - - 0.00 - - - - - -


TOTAL MANHOURS 220 10 10 20 10 100 70 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova

No Name and Type


Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -

Page 50 of 84
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC

PHOTOGRAPH

*Type OM-207 --> Dewatering, *Type OM-211 --> Pouring LC, *Type CO-205 --> Excavation (Continue), Pemadatan by stemper, DCP test (Passed)
*Type OM-212 --> Dewatering, Pouring LC *Type CO-206 --> Pemasangan plastik siteet, bekisting LC, joint survey top LC, Pouring LC

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 51 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 12 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 22.00 22.00 (7.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 27.00 - 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60

Page 52 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

6 Area-6 CO - 206 1) Excavation m3 11.55 0.00 11.55 11.55 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT

QA & QC
Admin

Driver
HSE
Eng
CM

No Position

1 Construction Manager 1 PC
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 7

TOTAL HEAD COUNT 22 1 1 2 1 10 7 - - 0.00 - - - - - -


TOTAL MANHOURS 220 10 10 20 10 100 70 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type
Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

Page 53 of 84
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 11/11/20 Type OM-209 --> galian longsor Pembuatan souring protection, butuh material by RJJ

PHOTOGRAPH

*Type CO-205 --> Excavation (Continue) *Type OM-211 --> Dewatering, Perapihan, Repair Subgride, DCP Test (Passed)
*Type CO-206 --> Dewatering, Perapihan, Repair Subgride, Pasang plastik *Type OM-212 --> Dewatering, Perapihan
siteet, DCP Test (Passed)

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 54 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 11 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 22.00 22.00 (7.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 25.50 - 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

5 Area-6 OM - 211 1) Excavation m3 27.00 0.00 27.00 27.00 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18

Page 55 of 84
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT

QA & QC
Admin

Driver
HSE
Eng
CM
No Position

PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 7

TOTAL HEAD COUNT 22 1 1 2 1 10 7 - - 0.00 - - - - - -


TOTAL MANHOURS 220 10 10 20 10 100 70 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
Others

Others

Others
No Name and Type

Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

Page 56 of 84
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 15.30
2 Drizzie
3 Heavy Rain 16.00 s/d 17.00

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 11/11/20 Type OM-209 --> galian longsor

PHOTOGRAPH

*Type CO-206 --> Excavation 80%, *Type OM-211 --> Dewatering, Excavation, Perapihan,
*Type OM-207 --> Dewatering, *Type OM-212 --> Dewatering
*Type OM-209 --> Excavation (Repair longsor), Dewatering

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 57 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 10 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 22.00 22.00 (7.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 0.52 - 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

4 Area-6 OM - 212 1) Excavation m3 25.50 0.00 25.50 25.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - - - 0.97
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

Page 58 of 84
MANPOWER INDIRECT

QA & QC
Admin

Driver
HSE
Eng
CM
No Position

PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 7

TOTAL HEAD COUNT 22 1 1 2 1 10 7 - - 0.00 - - - - - -


TOTAL MANHOURS 220 10 10 20 10 100 70 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type
Others

Others

Others
Wheel
Tools

L300
bar
DT

1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

Page 59 of 84
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 15.30
2 Drizzie
3 Heavy Rain 16.00 s/d 17.00

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 10/11/20 Telat utk dilakukan pengetesan, telat di inspek dari RJJ

PHOTOGRAPH

*Type OM-207 --> Dewatering *Type OM-211 --> Excavation (Done), Pasang Plastik Siteet
TBM *Type OM-209 --> Manual Daging / Perapian, *Type OM-212 --> DCP Test (passed),
DCP Test (Gagal)

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 60 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 09 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 8.00 8.00 2.00
Direct Manpower Mhr 15.00 13.00 12.00 12.00 3.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.52 - 0.52 0.52 -
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator -
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 8 1 1 1 1 1 2 1 - 0.00 - - - - - -


TOTAL MANHOURS 80 10 10 10 10 10 20 10 - 0.00 - - - - - -

Page 61 of 84
MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position

SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 2
5 Skill Worker (on site) 2
6 Skill Worker (on Fabrikasi) -
7 Helper 4

TOTAL HEAD COUNT 12 1 1 2 2 2 4 - - 0.00 - - - - - -


TOTAL MANHOURS 120 10 10 20 20 20 40 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 17 1 1 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 170 10 10 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC

PHOTOGRAPH

*Type OM-209 --> Excavation, Manual Daging, Dewatering, *Type OM-206 --> Install Rebar dan
TBM Demobilisasi Rebar dan formwork dan *Type OM-207 --> Demobilisasi Rebar dan formwork
*Type OM-202 --> Excavation

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 62 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 08 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 8.00 8.00 2.00
Direct Manpower Mhr 15.00 13.00 12.00 12.00 3.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator -
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 8 1 1 1 1 1 2 1 - 0.00 - - - - - -


TOTAL MANHOURS 80 10 10 10 10 10 20 10 - 0.00 - - - - - -

Page 63 of 84
MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position

SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 2
5 Skill Worker (on site) 2
6 Skill Worker (on Fabrikasi) -
7 Helper 4

TOTAL HEAD COUNT 12 1 1 2 2 2 4 - - 0.00 - - - - - -


TOTAL MANHOURS 120 10 10 20 20 20 40 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 16.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 08/11/20 Type OM-209 --> interface dan Pipa --> Manual Daging

PHOTOGRAPH

TBM *Type OM-206 --> Install Rebar *Type OM-209 --> Excavation, Manual Daging, Dewatering

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 64 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 07 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 8.00 8.00 2.00
Direct Manpower Mhr 15.00 13.00 12.00 12.00 3.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 37.50 - 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 - 1.25 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator -
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 8 1 1 1 1 1 2 1 - 0.00 - - - - - -


TOTAL MANHOURS 80 10 10 10 10 10 20 10 - 0.00 - - - - - -

Page 65 of 84
MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position

SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 2
5 Skill Worker (on site) 2
6 Skill Worker (on Fabrikasi) -
7 Helper 4

TOTAL HEAD COUNT 12 1 1 2 2 2 4 - - 0.00 - - - - - -


TOTAL MANHOURS 120 10 10 20 20 20 40 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 16.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC

PHOTOGRAPH

*Type OM-206 --> Install Rebar;


TBM *Type OM-207 --> Excavation, Manual Daging (1,5x3x1m), Leveling, Dewatering;
*Type OM-209 --> Dewatering

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 66 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 06 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 8.00 8.00 2.00
Direct Manpower Mhr 15.00 13.00 13.00 13.00 2.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 37.50 - 37.50 37.50 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 0.97 - 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator -
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 8 1 1 1 1 1 2 1 - 0.00 - - - - - -


TOTAL MANHOURS 80 10 10 10 10 10 20 10 - 0.00 - - - - - -

Page 67 of 84
MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position

SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) -
6 Skill Worker (on Fabrikasi) 4
7 Helper 4

TOTAL HEAD COUNT 13 1 1 2 1 4 4 - - 0.00 - - - - - -


TOTAL MANHOURS 130 10 10 20 10 40 40 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 06/11/20 Akses naik Turun, Galian Belum Punya Akses Segera diadakan tangga

PHOTOGRAPH

*Type OM-207 --> Excavation, Manual Daging, Leveling, Dewatering;


TBM *Type OM-206 --> Mobilisasi Material Besi dan Begisting to site ;
*Pondasi waterfall MPRK-2 --> Galian 2 titik (2m x 0,80), Joint Survey, DCP test

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 68 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 05 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 13.00 13.00 2.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 15.34 - - - 15.34


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.97 - 0.97 0.97 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

Page 69 of 84
MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position

SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) -
6 Skill Worker (on Fabrikasi) 4
7 Helper 4

TOTAL HEAD COUNT 13 1 1 2 1 4 4 - - 0.00 - - - - - -


TOTAL MANHOURS 130 10 10 20 10 40 40 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC

PHOTOGRAPH

TBM Excavation --> OM-207 Type OM-206 --> Install Bekisting LC, Install Plastik Siteet,
DCP Test, Pouring LC Beton FC:12 (1m3), Dewatering

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 70 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 04 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 13.00 13.00 2.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 15.34 - - - 15.34


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

Page 71 of 84
MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position

SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) -
6 Skill Worker (on Fabrikasi) 4
7 Helper 4

TOTAL HEAD COUNT 13 1 1 2 1 4 4 - - 0.00 - - - - - -


TOTAL MANHOURS 130 10 10 20 10 40 40 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 12.00
2 Drizzie
3 Heavy Rain 13.00 s/d 16.00

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 04/11/20 Droping alcon pukul 10.00 WIB Dipersiapkan alat dan support pekerjaan harus ada

PHOTOGRAPH

TBM Dewatering Manhole Type OM-206 dan OM-207

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 72 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 03 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 14.00 14.00 1.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

2 Area-6 OM - 207 1) Excavation m3 15.34 - - - 15.34


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

3 Area-6 OM - 206 1) Excavation m3 34.20 34.20 - 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

Page 73 of 84
MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position

SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 1
6 Skill Worker (on Fabrikasi) 4
7 Helper 4

TOTAL HEAD COUNT 14 1 1 2 1 5 4 - - 0.00 - - - - - -


TOTAL MANHOURS 140 10 10 20 10 50 40 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 15 1 - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 150 10 - 10 10 10 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 02/11/20 Tidak ada alcon pompa, area kerja tergenang air Segera pump alcol ABN di inspek

PHOTOGRAPH

TBM

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 74 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 02 November 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 14.00 14.00 1.00
TEMPORARY FACILITIES Ls 1.00 0.33 0.33 0.67
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.33 0.33 0.66 0.34
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - Err:522 Err:522 Err:522
2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522

2 Area-6 OM - 207 1) Excavation m3 15.34 - Err:522 Err:522 Err:522


2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522

3 Area-6 OM - 206 1) Excavation m3 34.20 - 34.20 34.20 -


2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

Page 75 of 84
MANPOWER DIRECT

Foreman
Survetor

Worker

Helper
SPV

Skill
No Position

SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 1
6 Skill Worker (on Fabrikasi) 4
7 Helper 4

TOTAL HEAD COUNT 14 1 1 2 1 5 4 - - 0.00 - - - - - -


TOTAL MANHOURS 140 10 10 20 10 50 40 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 15 1 - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 150 10 - 10 10 10 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 15.30
2 Drizzie
3 Heavy Rain 16.00 s/d AAR

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 02/11/20 Alcon Pump Rusak Segera pump alcol ABN di inspek

PHOTOGRAPH

Fabrikasi Rebar 3 titik (OM-208,


TBM Excavation & Galian manual --> OM-206 (3x3x2,5m) Dewatering --> OM-207 : OM-209, OM-210) di
(3x4x1,5m) Workshop-ABN

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 76 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 31 Oktober 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 14.00 14.00 1.00
TEMPORARY FACILITIES Ls 1.00 0.33 0.33 0.67
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.33 - 0.33 0.67
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - Err:522 Err:522 Err:522
2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522

2 Area-6 OM - 207 1) Excavation m3 15.34 - Err:522 Err:522 Err:522


2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 1
6 Skill Worker (on Fabrikasi) 5
7 Helper 3

Page 77 of 84
TOTAL HEAD COUNT 14 1 1 2 1 6 3 - - 0.00 - - - - - -
TOTAL MANHOURS 140 10 10 20 10 60 30 - - 0.00 - - - - - -

EQUIPMENT AND TOOLS


Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -

working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 16.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 30/10/20 Area Kerja Banyak Air Sediakan Alat Pompa
2 31/10/20 Supporting transport belum ada Segera diadakan transportasi

PHOTOGRAPH

TBM Excavation --> OM-207 (3x3x1,5m) (60-80%) dan OM-209 :


3mx3mx1,8m (continue) dan Dewatering --> OM-209 (3x3x1,8m)

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 78 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 30 Oktober 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 12.00 13.00 13.00 2.00
TEMPORARY FACILITIES Ls 1.00 0.33 0.33 0.67
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.33 - 0.33 0.67
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 OM - 209 1) Excavation m3 15.34 - Err:522 Err:522 Err:522
2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 1
6 Skill Worker (on Fabrikasi) 4
7 Helper 3

TOTAL HEAD COUNT 13 1 1 2 1 5 3 - - 0.00 - - - - - -


TOTAL MANHOURS 130 10 10 20 10 50 30 - - 0.00 - - - - - -

Page 79 of 84
EQUIPMENT AND TOOLS
Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) -
5 Scaffolding -
6 Hand Tools 4
7 Bar Cutter (on fabrikasi) 1
8 Bar Bending (on fabrikasi) 1
9 Gerinda Potong (on fabrikasi) 1
10 Cutting Wheel (on fabrikasi) 1
11 Mesin Bor (on fabrikasi) 1
12 Innova 1
13 L300 -

working (w) 13 1 1 1 - - - 4 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 130 10 10 10 - - - 40 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 10.30 s/d 17.00
2 Drizzie
3 Heavy Rain 07.00 s/d 10.00

CONCERN AND MITIGATION


No Date Concern Mitigation PIC
1 30/10/20 Area Kerja Banyak Air Sediakan Alat Pompa

PHOTOGRAPH

TBM Excavation --> OM-209 (3x3x1,8m) (60-70%) dan


Galian Manual --> OM-207 (3x3x1,5m)

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 80 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 29 Oktober 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 12.00 12.00 12.00 3.00
TEMPORARY FACILITIES Ls 1.00 0.33 0.33 0.67
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.33 - 0.33 0.67
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 OM - 209 1) Excavation m3 15.34 - Err:522 Err:522 Err:522
2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) -
6 Skill Worker (on Fabrikasi) 4
7 Helper 3

TOTAL HEAD COUNT 12 1 1 2 1 4 3 - - 0.00 - - - - - -


TOTAL MANHOURS 120 10 10 20 10 40 30 - - 0.00 - - - - - -

Page 81 of 84
EQUIPMENT AND TOOLS
Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) -
5 Scaffolding -
6 Hand Tools 4
7 Bar Cutter (on fabrikasi) 1
8 Bar Bending (on fabrikasi) 1
9 Gerinda Potong (on fabrikasi) 1
10 Cutting Wheel (on fabrikasi) 1
11 Mesin Bor (on fabrikasi) 1
12 Innova 1
13 L300 -

working (w) 13 1 1 1 - - - 4 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 130 10 10 10 - - - 40 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 15.00
2 Drizzie
3 Heavy Rain 15.30 s/d AAR

CONCERN AND MITIGATION


No Date Concern Mitigation PIC

PHOTOGRAPH

Excavation --> OM-209 (3x3x1,8m) &


TBM Stakout --> Type (OM-209, 208, 207, Fabrikasi Rebar 3 titik (OM-203,
Install Shelter dan Portable Toilet OM-206, OM-207) di Workshop-ABN
206)

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 82 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR

Subcontractor Name : CV. Anugrah Bumi Nusantara


CONSORTIUM
Work Package Name : Civil Work Package 2A
Date : 28 Oktober 2020

SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara

ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 - 9.00 9.00 1.00
Direct Manpower Mhr 15.00 - 12.00 12.00 3.00
TEMPORARY FACILITIES Ls 1.00 - 0.33 0.33 0.67
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.33 - 0.33 0.67
(Indirect manpower at site)

DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 OM - 209 1) Excavation m3 15.34 - Err:522 Err:522 Err:522
2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522

MANPOWER INDIRECT
QA & QC
Admin

Driver
HSE
Eng
CM

No Position
PC

1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1

TOTAL HEAD COUNT 9 1 1 1 1 1 3 1 - 0.00 - - - - - -


TOTAL MANHOURS 90 10 10 10 10 10 30 10 - 0.00 - - - - - -

MANPOWER DIRECT
Foreman
Survetor

Worker

Helper
SPV

Skill

No Position
SI

1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) -
6 Skill Worker (on Fabrikasi) 4
7 Helper 3

TOTAL HEAD COUNT 12 1 1 2 1 4 3 - - 0.00 - - - - - -


TOTAL MANHOURS 120 10 10 20 10 40 30 - - 0.00 - - - - - -

Page 83 of 84
EQUIPMENT AND TOOLS
Motorized Equipment Tools Motor vehicle

Hand Tools
Scaffolding

Bar Cutter
Excavator

Bending

Gerinda
Genset

Cutting
Survey

Innova
No Name and Type

Others

Others

Others
Wheel
Tools

L300
bar
DT
1 Excavator -
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) -
5 Scaffolding -
6 Hand Tools 4
7 Bar Cutter (on fabrikasi) 1
8 Bar Bending (on fabrikasi) 1
9 Gerinda Potong (on fabrikasi) 1
10 Cutting Wheel (on fabrikasi) 1
11 Mesin Bor (on fabrikasi) 1
12 Innova 1
13 L300 -

working (w) 12 - 1 1 - - - 4 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 120 - 10 10 - - - 40 10 10 10 10 10 10 - -

WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain

CONCERN AND MITIGATION


No Date Concern Mitigation PIC

PHOTOGRAPH

TBM Install Shelter Fabrikasi Rebar 2 titik (OM-201,


OM-202) di Workshop-ABN

Prepared By, Checked By, Approved By,


CV. Anugrah Bumi Nusantara PT. Rekayasa Industri PT. Rekayasa Industri

Sutrisno
Project Control Superintendent General Superintendent

Page 84 of 84