SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 26.00 26.00 (11.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 1 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
Page 2 of 84
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 2
5 Skill Worker (on site) 2
6 Skill Worker (on Fabrikasi) 7
7 Helper 11
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator -
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 11
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 21 - - 1 1 2 - 11 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 210 - - 10 10 20 - 110 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 12.00
2 Drizzie 13.00 s/d AAR
3 Heavy Rain
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 3 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 17.00 17.00 (2.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 4 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
Page 5 of 84
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 1
4 Foreman 1
5 Skill Worker (on site) 2
6 Skill Worker (on Fabrikasi) 7
7 Helper 4
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 12.00
2 Drizzie
3 Heavy Rain 13.00 s/d AAR
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 6 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 31.00 31.00 (16.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 7 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 6
6 Skill Worker (on Fabrikasi) 7
7 Helper 13
Page 8 of 84
TOTAL HEAD COUNT 31 1 1 2 1 13 13 - - 0.00 - - - - - -
TOTAL MANHOURS 310 10 10 20 10 130 130 - - 0.00 - - - - - -
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator -
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 15 - - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 150 - - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 16.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*type CO-201, CO-202 --> Install Rebar (diatas), Dewatering, *type CO-205 --> Install Waterstop (6,30 m), Joint Survey & inspek Slab;
TBM Pouring Concrete (LC); *type CO-206 --> Pouring Concrete, *type OM-207 --> Joint Survey dan inspek Slab;
Dewatering *type OM-212 --> Dewatering, Perkuat Bekisting, Pouring Concrete
Sutrisno
Project Control Superintendent General Superintendent
Page 9 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 30.00 30.00 (15.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 10 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 7
6 Skill Worker (on Fabrikasi) 7
7 Helper 11
Page 11 of 84
TOTAL HEAD COUNT 30 1 1 2 1 14 11 - - 0.00 - - - - - -
TOTAL MANHOURS 300 10 10 20 10 140 110 - - 0.00 - - - - - -
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator -
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 14 - - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 140 - - 10 10 10 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 14.30
2 Drizzie
3 Heavy Rain 15.00 - 15.30
PHOTOGRAPH
*type OM-212 --> Dewatering , Install Rebar (100%), *type CO-201, CO-202 --> Perapihan, Dewatering; *type CO-205 --> Dewatering, Loading Install Rebar, Install Bekisting
Install Waterstop (8m) *type OM-211 --> Dewatering , Install Rebar (100%); (100%); *type CO-206 --> Joint Survey dan Inspek Slab
Sutrisno
Project Control Superintendent General Superintendent
Page 12 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 31.00 31.00 (16.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 13 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 8
6 Skill Worker (on Fabrikasi) 7
7 Helper 11
Page 14 of 84
TOTAL HEAD COUNT 31 1 1 2 1 15 11 - - 0.00 - - - - - -
TOTAL MANHOURS 310 10 10 20 10 150 110 - - 0.00 - - - - - -
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 15 1 - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 150 10 - 10 10 10 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*type OM-212 --> Dewatering, *type CO-206 --> Install Formwork & Install Waterstop (5m); *type *type CO-201 --> Perapihan, Dewatering, Joint Survey LC, DCP Test (Passed),
Install Rebar (60%); *type CO-202 CO-205 --> Dewatering; *type OM-206 --> Perkuatan Bekisting; Install Rebar (50%); *type CO-202 --> Excavation , Dewatering
--> DCP Test (Passed) *type OM-211 --> Install Rebar (50%)
Sutrisno
Project Control Superintendent General Superintendent
Page 15 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 27.00 27.00 (12.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 16 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 11
Page 17 of 84
TOTAL HEAD COUNT 27 1 1 2 1 11 11 - - 0.00 - - - - - -
TOTAL MANHOURS 270 10 10 20 10 110 110 - - 0.00 - - - - - -
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*type OM-209 --> Demob Bekisting, Install Rebar (Slab) --> 100%; *type CO-202 --> Dewatering, Excavation; *type CO-206, CO-207 --> Install Rebar (Wall & Slab) -->
*type OM-211 --> Dewatering, Demob Bekisting, Install Rebar (Slab) *type CO-201, OM-206 --> Dewatering; *type OM-212 100%; *type CO-204, 205 --> Demob Rebar & Bekising
--> 100%, Install Rebar (Wall) --> 1 sisi (25%) --> Dewatering, Install Rebar (Slab) --> 100%
Sutrisno
Project Control Superintendent General Superintendent
Page 18 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 27.00 27.00 (12.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 19 of 84
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 2
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 10
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
Page 20 of 84
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 14.00
2 Drizzie
3 Heavy Rain 15.00 s/d AAR
PHOTOGRAPH
*type CO-201 --> Excavation; *type CO-205 --> Install Rebar (90%); *type CO-206 -->
TBM *type OM-209 --> Install Rebar (50%); Dewatering, Install Rebar (90%); *type CO-207 (OM-211) -->
*type OM-211 --> Dewatering; Install Rebar (70%); *type OM-206 --> Install Formwork
Sutrisno
Project Control Superintendent General Superintendent
Page 21 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 23.00 23.00 (8.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 22 of 84
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 7
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 17 1 1 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
Page 23 of 84
broken (b)
TOTAL HOUR 170 10 10 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 12.00
2 Drizzie 13.00 s/d 14.30
3 Heavy Rain 15.00 s/d AAR
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 24 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 24.00 24.00 (9.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 25 of 84
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 8
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
Page 26 of 84
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*Pondasi Waterfall 1,2 --> Install Formwork Pedestal (2 nos), *type OM-206 --> Dewatering, Marking, Bongkar bekisting sisi luar,
Install anchor (continue); *type CO-205 dan CO-206 --> Dewatering Perkuatan bekisting sisi dalam; *type OM-207 --> Dewatering, Marking
Sutrisno
Project Control Superintendent General Superintendent
Page 27 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 24.00 24.00 (9.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 28 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 8
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
Page 29 of 84
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*Pondasi Waterfall 1,2 --> Dewatering, Pablikasi Formwork Pedestal, *type OM-207 --> Dewatering;
Pouring Concrete pondasi *type OM-206 --> Dewatering, Install Formwork;
Sutrisno
Project Control Superintendent General Superintendent
Page 30 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 24.00 24.00 (9.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 1.25 - 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 31 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 8
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
Page 32 of 84
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 12.00
2 Drizzie
3 Heavy Rain 13.00 sd 14.40
PHOTOGRAPH
*type OM-209 --> Excavation / Perbaikan Souring, Dewatering; *type *Pondasi Waterfall 1,2 --> Ciping Joint Wall, Joint Survey Top Pondasi,
TBM OM-207 --> Dewatering; *type OM-206 --> Excavation / Perbaikan Install Rebar, Pablikasi dan perkuatan Formwork
Souring
Sutrisno
Project Control Superintendent General Superintendent
Page 33 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 24.00 24.00 (9.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 1.25 - 1.25 1.25 -
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 34 of 84
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 8
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 15 1 - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
Page 35 of 84
standby (s)
broken (b)
TOTAL HOUR 150 10 - 10 10 10 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*type OM-207 --> Dewatering, Install Rebar (95%); *Pondasi *type OM-209 --> Excavation / Perbaikan Galian,
TBM Waterfall --> Install Rebar (100%), Install Formwork (80%); *Pondasi Manual Daging, Dewatering, DCP Test (passed), Pouring LC
Pipe Support 460 --> Pouring LC (DONE) (DONE)
Sutrisno
Project Control Superintendent General Superintendent
Page 36 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 18.00 18.00 (3.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 37 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 2
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 15 1 - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
Page 38 of 84
broken (b)
TOTAL HOUR 150 10 - 10 10 10 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 39 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 6 Total JSA Register
Hot Work 0
6
Cold Work 6
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 18.00 18.00 (3.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 40 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 4
6 Skill Worker (on Fabrikasi) 7
7 Helper 2
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
Page 41 of 84
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*Type OM-206 --> Joint Survey dan inspek (Slab & Wall),
*Pondasi Pipe Support 460 --> DCP Test, Joint survey & inspek, *Type OM-207 --> Dewatering, Install Rebar,
Install plastik siteet, Install Rebar *Type CO-205 --> Dewatering
Sutrisno
Project Control Superintendent General Superintendent
Page 42 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 19.00 19.00 (4.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 43.50 - 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 43 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 4
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
Page 44 of 84
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 14.00
2 Drizzie 14.30 s/d AAR
3 Heavy Rain
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 45 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 22.00 22.00 (7.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 43.50 - 43.50 43.50 -
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 46 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 7
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 17 1 1 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
Page 47 of 84
broken (b)
TOTAL HOUR 170 10 10 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*Type OM-209 --> Excavation (Repair Galian), Manual Daging, Dewatering *Type OM-206 --> Install Formwork segmen 1 (sebatas waterstop) (40%)
*Type CO-205, CO-206, Pondasi MPRK-02 --> Demob material to site *Type OM-207 --> Dewatering, Install Rebar (10%)
Sutrisno
Project Control Superintendent General Superintendent
Page 48 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 22.00 22.00 (7.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 49 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 7
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
Page 50 of 84
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*Type OM-207 --> Dewatering, *Type OM-211 --> Pouring LC, *Type CO-205 --> Excavation (Continue), Pemadatan by stemper, DCP test (Passed)
*Type OM-212 --> Dewatering, Pouring LC *Type CO-206 --> Pemasangan plastik siteet, bekisting LC, joint survey top LC, Pouring LC
Sutrisno
Project Control Superintendent General Superintendent
Page 51 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 22.00 22.00 (7.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 52 of 84
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
1 Construction Manager 1 PC
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 7
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
Page 53 of 84
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*Type CO-205 --> Excavation (Continue) *Type OM-211 --> Dewatering, Perapihan, Repair Subgride, DCP Test (Passed)
*Type CO-206 --> Dewatering, Perapihan, Repair Subgride, Pasang plastik *Type OM-212 --> Dewatering, Perapihan
siteet, DCP Test (Passed)
Sutrisno
Project Control Superintendent General Superintendent
Page 54 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 22.00 22.00 (7.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 55 of 84
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 7
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
Others
Others
Others
No Name and Type
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
Page 56 of 84
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 15.30
2 Drizzie
3 Heavy Rain 16.00 s/d 17.00
PHOTOGRAPH
*Type CO-206 --> Excavation 80%, *Type OM-211 --> Dewatering, Excavation, Perapihan,
*Type OM-207 --> Dewatering, *Type OM-212 --> Dewatering
*Type OM-209 --> Excavation (Repair longsor), Dewatering
Sutrisno
Project Control Superintendent General Superintendent
Page 57 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 22.00 22.00 (7.00)
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
Page 58 of 84
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 3
6 Skill Worker (on Fabrikasi) 7
7 Helper 7
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
Page 59 of 84
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 15.30
2 Drizzie
3 Heavy Rain 16.00 s/d 17.00
PHOTOGRAPH
*Type OM-207 --> Dewatering *Type OM-211 --> Excavation (Done), Pasang Plastik Siteet
TBM *Type OM-209 --> Manual Daging / Perapian, *Type OM-212 --> DCP Test (passed),
DCP Test (Gagal)
Sutrisno
Project Control Superintendent General Superintendent
Page 60 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 8.00 8.00 2.00
Direct Manpower Mhr 15.00 13.00 12.00 12.00 3.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator -
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
Page 61 of 84
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 2
5 Skill Worker (on site) 2
6 Skill Worker (on Fabrikasi) -
7 Helper 4
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 17 1 1 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 170 10 10 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
*Type OM-209 --> Excavation, Manual Daging, Dewatering, *Type OM-206 --> Install Rebar dan
TBM Demobilisasi Rebar dan formwork dan *Type OM-207 --> Demobilisasi Rebar dan formwork
*Type OM-202 --> Excavation
Sutrisno
Project Control Superintendent General Superintendent
Page 62 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 8.00 8.00 2.00
Direct Manpower Mhr 15.00 13.00 12.00 12.00 3.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator -
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
Page 63 of 84
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 2
5 Skill Worker (on site) 2
6 Skill Worker (on Fabrikasi) -
7 Helper 4
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 16.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
TBM *Type OM-206 --> Install Rebar *Type OM-209 --> Excavation, Manual Daging, Dewatering
Sutrisno
Project Control Superintendent General Superintendent
Page 64 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 8.00 8.00 2.00
Direct Manpower Mhr 15.00 13.00 12.00 12.00 3.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator -
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
Page 65 of 84
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 2
5 Skill Worker (on site) 2
6 Skill Worker (on Fabrikasi) -
7 Helper 4
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 16.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 66 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 8.00 8.00 2.00
Direct Manpower Mhr 15.00 13.00 13.00 13.00 2.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator -
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
Page 67 of 84
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) -
6 Skill Worker (on Fabrikasi) 4
7 Helper 4
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 68 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 13.00 13.00 2.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
Page 69 of 84
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) -
6 Skill Worker (on Fabrikasi) 4
7 Helper 4
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
TBM Excavation --> OM-207 Type OM-206 --> Install Bekisting LC, Install Plastik Siteet,
DCP Test, Pouring LC Beton FC:12 (1m3), Dewatering
Sutrisno
Project Control Superintendent General Superintendent
Page 70 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 13.00 13.00 2.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
Page 71 of 84
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) -
6 Skill Worker (on Fabrikasi) 4
7 Helper 4
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 12.00
2 Drizzie
3 Heavy Rain 13.00 s/d 16.00
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 72 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 14.00 14.00 1.00
TEMPORARY FACILITIES Ls 1.00 0.33 - - 1.00
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.66 - 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - - - 15.34
2) Backfill (Purchased/Imported Soil) m3 9.39 - - - 9.39
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - - - 0.23
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - - - 0.38
6) Formwork for Foundation m2 24.60 - - - 24.60
7) Insert Steel Pipe Setting Ton 0.18 - - - 0.18
8) PVC Water Stop Hmin=230 mm m 5.84 - - - 5.84
9) Light Duty Manhole Cast Iron Nos 0.30 - - - 0.30
10) Heavy Duty Manhole Cast Iron Nos 0.20 - - - 0.20
11) L-Profile Ton 0.05 - - - 0.05
12) Round Bar Ton 0.01 - - - 0.01
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
Page 73 of 84
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 1
6 Skill Worker (on Fabrikasi) 4
7 Helper 4
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 15 1 - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 150 10 - 10 10 10 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
TBM
Sutrisno
Project Control Superintendent General Superintendent
Page 74 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 14.00 14.00 1.00
TEMPORARY FACILITIES Ls 1.00 0.33 0.33 0.67
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.33 0.33 0.66 0.34
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - Err:522 Err:522 Err:522
2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
Page 75 of 84
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 1
6 Skill Worker (on Fabrikasi) 4
7 Helper 4
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 1
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 15 1 - 1 1 1 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 150 10 - 10 10 10 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 15.30
2 Drizzie
3 Heavy Rain 16.00 s/d AAR
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 76 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 13.00 14.00 14.00 1.00
TEMPORARY FACILITIES Ls 1.00 0.33 0.33 0.67
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.33 - 0.33 0.67
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 Area-6 OM - 209 1) Excavation m3 15.34 - Err:522 Err:522 Err:522
2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 1
6 Skill Worker (on Fabrikasi) 5
7 Helper 3
Page 77 of 84
TOTAL HEAD COUNT 14 1 1 2 1 6 3 - - 0.00 - - - - - -
TOTAL MANHOURS 140 10 10 20 10 60 30 - - 0.00 - - - - - -
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck -
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) 1
5 Alcont Pump 2
6 Scaffolding -
7 Hand Tools 5
8 Bar Cutter (on fabrikasi) 1
9 Bar Bending (on fabrikasi) 1
10 Gerinda Potong (on fabrikasi) 1
11 Cutting Wheel (on fabrikasi) 1
12 Mesin Bor (on fabrikasi) 1
13 Innova 1
14 L300 -
working (w) 16 1 - 1 1 2 - 5 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 160 10 - 10 10 20 - 50 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 16.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 78 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 12.00 13.00 13.00 2.00
TEMPORARY FACILITIES Ls 1.00 0.33 0.33 0.67
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.33 - 0.33 0.67
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 OM - 209 1) Excavation m3 15.34 - Err:522 Err:522 Err:522
2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) 1
6 Skill Worker (on Fabrikasi) 4
7 Helper 3
Page 79 of 84
EQUIPMENT AND TOOLS
Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) -
5 Scaffolding -
6 Hand Tools 4
7 Bar Cutter (on fabrikasi) 1
8 Bar Bending (on fabrikasi) 1
9 Gerinda Potong (on fabrikasi) 1
10 Cutting Wheel (on fabrikasi) 1
11 Mesin Bor (on fabrikasi) 1
12 Innova 1
13 L300 -
working (w) 13 1 1 1 - - - 4 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 130 10 10 10 - - - 40 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 10.30 s/d 17.00
2 Drizzie
3 Heavy Rain 07.00 s/d 10.00
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 80 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 9.00 9.00 9.00 1.00
Direct Manpower Mhr 15.00 12.00 12.00 12.00 3.00
TEMPORARY FACILITIES Ls 1.00 0.33 0.33 0.67
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.33 - 0.33 0.67
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 OM - 209 1) Excavation m3 15.34 - Err:522 Err:522 Err:522
2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) -
6 Skill Worker (on Fabrikasi) 4
7 Helper 3
Page 81 of 84
EQUIPMENT AND TOOLS
Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator 1
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) -
5 Scaffolding -
6 Hand Tools 4
7 Bar Cutter (on fabrikasi) 1
8 Bar Bending (on fabrikasi) 1
9 Gerinda Potong (on fabrikasi) 1
10 Cutting Wheel (on fabrikasi) 1
11 Mesin Bor (on fabrikasi) 1
12 Innova 1
13 L300 -
working (w) 13 1 1 1 - - - 4 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 130 10 10 10 - - - 40 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 15.00
2 Drizzie
3 Heavy Rain 15.30 s/d AAR
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 82 of 84
CONSTRUCTION DAILY REPORT SUBCONTRACTOR
SAFETY STATUS
Total Permit to work 7 Total JSA Register
Hot Work 0
7
Cold Work 7
Note: Site Survey CV. Anugrah Bumi Nusantara
ACTIVITIES
FWBS Step Up to Today Up to Target Remain Plan Cumm.
No SI Activities Unit Total
1 2 3 4 Ytrday Today per day ing Tmrw
1 GPF AREA
1 PREPARATORY WORK
MOBILIZATION AND DEMOBILISI
Indirect Manpower Mhr 10.00 - 9.00 9.00 1.00
Direct Manpower Mhr 15.00 - 12.00 12.00 3.00
TEMPORARY FACILITIES Ls 1.00 - 0.33 0.33 0.67
(Include Temporary office,accomodation,etc)
Temporary Office
HOME OFFICE COST & SALARY Ls 1.00 0.33 - 0.33 0.67
(Indirect manpower at site)
DAILY PACKAGE 2A
Name
2 Area PERMANENT WORK
Manhole
1 OM - 209 1) Excavation m3 15.34 - Err:522 Err:522 Err:522
2) Backfill (Purchased/Imported Soil) m3 9.39 - Err:522 Err:522 Err:522
3) Lean concrete min fc'=12.2 MPa Cement Type I m3 0.23 - Err:522 Err:522 Err:522
4) Concrete Pouring min fc'=24 MPa Cement Type V m3 133.14 - - - 133.14
5) Deformed Bar Ton 0.38 - Err:522 Err:522 Err:522
6) Formwork for Foundation m2 24.60 - Err:522 Err:522 Err:522
7) Insert Steel Pipe Setting Ton 0.18 - Err:522 Err:522 Err:522
8) PVC Water Stop Hmin=230 mm m 5.84 - Err:522 Err:522 Err:522
9) Light Duty Manhole Cast Iron Nos 0.30 - Err:522 Err:522 Err:522
10) Heavy Duty Manhole Cast Iron Nos 0.20 - Err:522 Err:522 Err:522
11) L-Profile Ton 0.05 - Err:522 Err:522 Err:522
12) Round Bar Ton 0.01 - Err:522 Err:522 Err:522
MANPOWER INDIRECT
QA & QC
Admin
Driver
HSE
Eng
CM
No Position
PC
1 Construction Manager 1
2 Engineer 1
3 Project Control 1
4 Admin Project 1
5 QA & QC 1
6 HSE Coordinator 1
7 HSE Supervisor 1
8 HSE Safety Man 1
9 Driver 1
MANPOWER DIRECT
Foreman
Survetor
Worker
Helper
SPV
Skill
No Position
SI
1 Superintendent 1
2 Supervisor 1
3 Surveyor 2
4 Foreman 1
5 Skill Worker (on site) -
6 Skill Worker (on Fabrikasi) 4
7 Helper 3
Page 83 of 84
EQUIPMENT AND TOOLS
Motorized Equipment Tools Motor vehicle
Hand Tools
Scaffolding
Bar Cutter
Excavator
Bending
Gerinda
Genset
Cutting
Survey
Innova
No Name and Type
Others
Others
Others
Wheel
Tools
L300
bar
DT
1 Excavator -
2 Trailer / Dump Truck 1
3 Survey Tools (DT 740) 1
4 Generator Set (on fabrikasi) -
5 Scaffolding -
6 Hand Tools 4
7 Bar Cutter (on fabrikasi) 1
8 Bar Bending (on fabrikasi) 1
9 Gerinda Potong (on fabrikasi) 1
10 Cutting Wheel (on fabrikasi) 1
11 Mesin Bor (on fabrikasi) 1
12 Innova 1
13 L300 -
working (w) 12 - 1 1 - - - 4 1 1 1 1 1 1 - -
idle (i)
standby (s)
broken (b)
TOTAL HOUR 120 - 10 10 - - - 40 10 10 10 10 10 10 - -
WEATHER CONDITION
Name
No Time Sheet PIC
Time Sheet
1 Clear/Cloudy 07.00 s/d 17.00
2 Drizzie
3 Heavy Rain
PHOTOGRAPH
Sutrisno
Project Control Superintendent General Superintendent
Page 84 of 84