(JIT-Kanban)
Contribution:
Question 1:
Nguyễn Thị Minh Hạnh – IEIEIU18165
Vũ Ngọc Bảo Trân – IEIEIU18100
Question 2:
Nguyễn Ngọc Hân – IEIEIU18152
Trương Kim Khánh – IEIEIU18037
Phan Minh Thư – IEIEIU18126
Question 3:
Lê Thị Yến Vy – IEIEIU18157
Lại Thị Yến Nhi – IEIEIU18065
Trần Quỳnh Châu – IEIEIU18010
A JIT system has the following processes (C is the final assembly and D is the
warehouse). All the processes employ Kanban. The container size is 250 units and
safety coefficient 0.1. There are 8 operating hours per day.
Process C produces in lot size. The setting up time each time changing lot is 15
minutes. Total time for setting up a day should be less than or equal to 1 hour.
Warehouse D withdraws from C a constant quantity of products which is equal to
the lot size of C. The consuming rate is 4000 units/day. A triangular Kanban is
employed to signal process C to start produce when the stock reaches the reorder
point. Lead time of signal Kanban is 1.0 hour.
A B C D
(1hours) (3.5mins) (1.5 hour) (4000 units/day)
1
1) If process C uses maximum number of set up time per day allowable, what is the lot size of
process C? Where should we put the triangular Kanban?
2) Process C withdraws parts from B also with constant quantity, which is its lot size. Process B
withdraws parts from A in constant cycle of 1.0 hours. How many withdrawals Kanban C
should have?
3) A supplier delivers material to process A 4 times per day. The supplier production lead time is
0.6 day. What is the supplier Kanban cycle a-b-c? What is the total number of supplier
Kanban?
Note:
- Continue using this form to complete your works and submit on Blackboard
- Name your file
o If you submit individually: 21Lean_HW7_StudentID_FullName
o If you submit for a group (Group # are as per the number you have registered as guided
in the file “Semester Project Requirement” and be finalized by lecturer):
21Lean_HW7_G#
- Due Date is defined in detail at each “ ASSIGNMENT INFORMATION” from Blackboard
- Maximum score of late submission is two third of “Point Possible”
- If you can’t submit on Blackboard: Email your work to TA, copy it to your Lecturer, attached also
the screenshot of your Blackboard showing error in that transaction
---------
Answers/Works
1. If process C uses maximum number of set up time per day allowable, what is the lot size of
process C? Where should we put the triangular Kanban?
2
Lead time (LT) = 1 hour
units 4000 units/day
Demand ¿ 4000 = =500 units /hour
day 8 hours /day
Triangular Kanban ¿ ¿ ¿
2. Process C withdraws parts from B also with constant quantity, which is its lot size. Process B
withdraws parts from A in constant cycle of 1.0 hours. How many withdrawals Kanban C
should have?
3. A supplier delivers material to process A 4 times per day. The supplier production lead time is
0.6 day. What is the supplier Kanban cycle a-b-c? What is the total number of supplier
Kanban?
1000( ( 3.5/60+1+1 ) × ( 1+0.1 ) )
Withdrawals Kanban C ¿ =9.06=10 Kanbans
250
Lead Time (LT) = 0.6 day
A supplier delivers material to process A 4 times per day => a=1, b=4
We have:
a
c × ≥ leadtime
b
0.6 × 4
c≥ ≥2.4=¿ c =3
1
Supplier Kanban cycle a – b – c: 1 – 4 – 3
¿
4000 ( 14 + 0.6)+ 400 =15.2 kanbans → 16 kanbans
250