Professional Documents
Culture Documents
Reconciliation In
L3-DARRANG Pending with SITE PS
Progress
RP
Pending with
EDRC
PE Completed COM
Reconciliation UOM Tender Additional BOQ from BOQ from Final Agreed Variation Sign by EDRC Sign by Site Remarks
Status BOQ BOQ GFC Drawing GFC drawing BOQ between (+ indicates
No. Item description (1) (1a) as per EDRC as per site EDRC & Site savings)
(2) (3) (4) ((1+1a) - 4))
1 Excavation Cu.m 14,308
PE
2 Back filling Cu.m 5,998
PE
3 Plinth Filling Cu.m 4,131
PE
4 Disposal Cu.m 8,309
PE
5 Anti Termite Sq.m 2,754
PE
6 PCC (1:4:8) Cu.m 393 227 0
PS
7 Concrete (RCC-M30/ M40) Cu.m 5,925 6,021 0
PS
8 Concrete (RCC-M50) Cu.m - 239 0
PS
9 Mass Concrete (M30) Cu.m 1,500 1,412 0
PS
10 Shuttering PS Sq.m 32,149 26,197 0
6 Structural steel - MT
3 Reinforcement Steel MT 29
5 Structural steel MT
Misc. PE
WTP
BASE SLAB
WALLS PS 91
BEAMS PS 175 18
ROOF SLAB PS 12
PEDESTALS PS 6
3 Shuttering Sqm 7,709 282 6,099 0
Foundation PS 336 106 106
Columns PS 2,810 55 750 750
Floor Beam GF / Plinth beams PS 175 246 246
Floor Slab GF/Grade slab NA 134 0
Floor Beam 1F PS 150 233 233
Floor Beam terrace PS 143 245 245
Floor Slab 1F PS 706 471 471
Floor Slab terrace PS 650 350 350
Staircase PS 100 2 2
Lintels PS 70 70
Sunshades PS 70 70
Mullions & band beams PS 60 60
Elevation features NA
Equipment pedestals NA
Miscellanous PS 170 335 335
LINAC
LINAC foundation PS 115 115
LINAC walls PS 227 1,969 1,969
1,370
LINAC Roof slab PS 200 200
LINAC base slab
WTP
BASE SLAB
WALLS PS 642 642
BEAMS PS 765 205 205
ROOF SLAB
PEDESTALS PS 30 30
03- L3-DARRANG STP & RAMP
1 PCC (1:4:8) Cu.m 0 0 0 0
Below foundation PE
Misc. PE
2 Concrete (RCC) M30 Cu.m 747 841 0
Foundation PS 149 195 195
Columns PS 216 14 180 180
Retainign wall NA 18 0
Floor Beam GF / Plinth beams PS 10 15 15
Floor Slab GF/Grade slab PS 22 9 9
Floor Beam 1F PS 17 48 48
Floor Beam 2F PS 17 36 36
Floor Beam 3F PS 17 36 36
Floor Beam terrace PS 17 21 21
Floor Slab 1F PS 25 27 27
Floor Slab 2F PS 25 20 20
Floor Slab 3F PS 25 20 20
Floor Slab terrace PS 25 39 39
Mullions & band beams NA 2
Elevation features PS 2 77 77
Miscellanous NA 26
STP
BASE SLAB NA
WALLS PS 29 79 79
BEAMS PS 14
134
ROOF SLAB PS 8
STP STAIRCASE PS 4 4
PEDESTALS PS 11 11
3 Shuttering Sqm 5,449 4,799 0
Foundation PS 205 85 85
Columns PS 2,500 74 972 972
Retainign wall NA 90
Floor Beam GF / Plinth beams PS 50 100 100
Floor Slab GF/Grade slab PS 182 66 66
Floor Beam 1F PS 150 272 272
Floor Beam 2F PS 150 204 204
Floor Beam 3F PS 150 204 204
Floor Beam terrace PS 100 175 175
Floor Slab 1F PS 225 218 218
Floor Slab 2F PS 225 164 164
Floor Slab 3F PS 225 164 164
Floor Slab terrace PS 370 310 310
Mullions & band beams NA 18
Elevation features PS 18 962 962
Miscellanous NA 154
STP
BASE SLAB NA
WALLS PS 195 666 666
BEAMS PS 139
637
ROOF SLAB PS 64
STP STAIRCASE PS 18 18
PEDESTALS PS 18 18
05- L3-DARRANG EXTERNAL WORKS
1 PCC (1:4:8) Cu.m 29 29 0
Below pedestals PE 29
Below compound wall PE 29
Below ramps & brick steps PE
2 Concrete (RCC) Cu.m 345 345 0
DG foundation PE 345
Culverts PE
Drains PE
Precast covers PE
RC manholes PE
RMU room PE
HSD tank PE
Rainwater collection pit PE
345
Access ramps PE
External RC kerb PE
Trenches PE
Boundary retaining walls PE
Elevated roads PE
Connecting corridors PE
Security rooms PE
Gate complex PE
3 Shuttering Sqm 1,233 1,233 0
DG foundation PE 1,233
Culverts PE
Drains PE
Precast covers PE
RC manholes PE
RMU room PE
HSD tank PE
Rainwater collection pit PE
1,233
Access ramps PE
External RC kerb PE
Trenches PE
Boundary retaining walls PE
Elevated roads PE
Connecting corridors PE
Security rooms PE
Gate complex PE
4 Structural steel MT 0
DG shed PE
Girders in pump room PE
Misscelaneous PE
Floor Beam 2F O19035-C-HP-06-RC-0030 0.64 0.20 0.19 0.32 1.89 1.54 2.36 7.14
Floor Beam 2F O19035-C-HP-06-RC-0031 0.52 0.41 0.28 0.26 2.32 1.30 2.27 7.35
1
- - - - - - -
Floor Beam 3F O19035-C-HP-06-RC-0033 0.58 0.59 0.13 0.89 1.06 1.66 3.36 8.27
Floor Beam 3F O19035-C-HP-06-RC-0034 0.64 0.28 0.32 0.50 1.48 1.65 2.36 7.23
Floor Beam 3F O19035-C-HP-06-RC-0035 0.62 0.24 0.12 0.29 2.22 1.01 2.69 7.19
Floor Beam 3F O19035-C-HP-06-RC-0036 0.63 0.34 0.07 0.40 2.05 1.25 1.06 5.80
- - - - - - -
Floor Beam terrace - - - - - - -
Floor Slab 1F O19035-C-HP-06-RC-0022 6.76 2.14 1.33 0.73 - - - 10.95
Floor Slab 2F O19035-C-HP-06-RC-0027 6.18 2.45 0.84 0.20 - - - 9.68
Floor Slab 3F O19035-C-HP-06-RC-0032 0.02 4.19 1.58 0.37 0.02 - - 6.18
Floor Slab terrace O19035-C-HP-06-RC-0037 6.52 2.89 1.24 0.23 - - - 10.88
- - - - - - -
Staircase - - - - - - - -
Above Terrace Slab - - - - - - - -
Above Terrace Beams - - - - - - - -
OHT walls & slabs - - - - - - - -
Lintels - - - - - - - -
Sunshades - - - - - - - -
Mullions & band beams - - - - - - - -
Elevation features - - - - - - - -
Equipment pedestals . - - - - - - - -
Miscellanous - - - - - - - -
TOTAL 60.97 29.93 31.96 61.01 87.26 78.41 71.64 421.18
Foundation O19035-C-HP-06-RC-0102 0.06 0.22 1.69 10.42 4.43 19.34 12.82 48.98
O19035-C-HP-06-RC-0103 0.19 0.24 4.36 5.73 19.83 0.91 - 31.25
- - - - - - - -
Raft pedestals - - - - - - - -
Columns 8.24 - 2.50 - 3.26 10.91 15.47 40.39
Floor Beam GF / Plinth beams O19035-C-HP-06-RC-0107 0.68 0.24 0.19 1.99 - - - 3.09
Floor Beam GF / Plinth beams O19035-C-HP-06-RC-0108 0.38 0.16 0.03 0.53 0.04 - - 1.14
Floor Slab GF/Grade slab 2.03 - - - - - - 2.03
Floor Beam 1F O19035-C-HP-06-RC-0110 0.36 0.37 0.55 0.47 1.13 2.84 0.02 5.74
Floor Beam 1F O19035-C-HP-06-RC-0111 0.73 0.63 0.17 0.12 1.92 1.21 - 4.79
Floor Beam terrace - - - - - - - -
Floor Slab 1F O19035-C-HP-06-RC-0112 2.72 0.39 1.76 - - - - 4.87
Floor Slab terrace O19035-C-HP-06-RC-0113 2.58 1.30 0.68 0.38 3.01 3.49 - 11.43
ang LINAC
2
Staircase - - - - - - - -
Darrang LINAC Lintels - - - - - - - -
Sunshades - - - - - - - -
2 Mullions & band beams - - - - - - - -
Elevation features - - - - - - - -
Equipment pedestals - - - - - - - -
Miscellanous - - - - - - - -
LINAC - - - - - - - -
LINAC foundation - - - - - - - -
LINAC walls O19035-C-HP-06-RC-0106 0.47 6.14 5.01 30.06 43.10 13.69 - 98.46
LINAC Roof slab - - - - - - - -
LINAC base slab - - - - - - - -
WTP - - - - - - - -
WATER TANK O19035-C-HP-06-RC-0114 0.71 3.92 0.72 6.29 - - - 11.64
BASE SLAB - - - - - - - -
WALLS - - - - - - - -
BEAMS - - - - - - - -
ROOF SLAB - - - - - - - -
PEDESTALS - - - - - - - -
TOTAL 19.13 13.61 17.67 55.99 76.71 52.39 28.31 263.82
Foundation O19035-C-HP-06-RC-0202 0.07 - - 9.71 6.32 1.07 - 17.17
Columns O19035-C-HP-06-RC-0203 13.90 0.60 - - 1.10 6.80 30.20 52.60
O19035-C-HP-06-RC-0204 - - - - - - - -
- - - - - - -
Ramp Floor Slab O19035-C-HP-06-RC-0206 5.52 - - - - - - 5.52
- - - - - - -
Ramp Beam (Sheet 1 of 2) O19035-C-HP-06-RC-0207 0.34 2.28 1.16 0.77 2.80 6.55 - 13.90
- - - - - - -
Ramp Beam (Sheet 2 of 2) O19035-C-HP-06-RC-0208 0.45 2.18 1.53 1.20 2.47 10.49 - 18.33
- - - - - - -
Ramp Terrace Slab &Beams O19035-C-HP-06-RC-0209 2.24 0.38 0.25 0.54 2.49 0.12 - 6.01
- - - - - - - -
- - - - - - -
Staircase - - - - - - - -
Darrang RAMP & STP
Lintels - - - - - - - -
Sunshades - - - - - - - -
3 Mullions & band beams - - - - - - - -
Elevation features - - 1.00 - - - - 1.00
Equipment pedestals - - - - - - - -
Miscellanous - - - - - - - -
STP - - - - - - - -
BASE SLAB O19035-C-HP-06-RC-0202 - - - - - - - -
- - - - - - -
WALLS O19035-C-HP-06-RC-0213 - 5.21 1.73 - - - - 6.95
- - - - - - -
STP Roof Slab & Beams O19035-C-HP-06-RC-0212 0.69 0.15 0.26 0.41 1.33 1.71 - 4.54
- - - - - - -
- - - - - - - -
STP STAIRCASE - - - - - - - -
PEDESTALS - - - - - - - -
- - - - - - - -
- - - - - - - -
TOTAL 23.22 10.79 5.93 12.63 16.50 26.74 30.20 126.02
DG foundation - - - - - - - -
Culverts - - - - - - - -
Drains - - - - - - - -
Precast covers - - - - - - - -
RC manholes - - - - - - - -
Darrang EXTERNAL WORKS
RMU room - - - - - - - -
HSD tank - - - - - - - -
Rainwater collection pit - - - - - - - -
Access ramps - - - - - - - -
4 External RC kerb - - - - - - - -
Trenches - - - - - - - -
Boundary retaining walls - - - - - - - -
Elevated roads - - - - - - - -
Connecting corridors - - - - - - - -
Security rooms - - - - - - - -