Professional Documents
Culture Documents
Accommodation Building A4 Civil / Structural Mto: Pt. Meindo Elang Indah
Accommodation Building A4 Civil / Structural Mto: Pt. Meindo Elang Indah
ACCOMMODATION BUILDING A4
STATUS CODE : A = Issued for comments/information - B = Issued for approval - C = Approved/issued for design - D = As Built
TABLE OF CONTENT
1. REFERENCE DOCUMENT....................................................................................2
1. REFERENCE DOCUMENT
Total
No Description Unit
Quantity
I. PILING WORK
1 Concrete pile dia.500 L=36000 mm
a. Pile Ø500 L=12000 mm nos 273.00
2 Filing concrete w=800 mm
a. Concrete m³ 14.29
b. Rebar kg 2,871.96
- D19 kg 2,435.16
- Ø8 kg 436.80
3 Cutting pile nos 91.00
II. EARTH WORK
1 Excavation m³ 944.83
2 Soil removal m³ 142.36
3 Backfill m³ 802.46
4 Sandfill m³ 25.34
5 Antitermite m² 543.07
III. CONCRETE WORK
1 Lean concrete m³ 12.67
2 Concrete
a. Pile cap m³ 82.18
b. Tie Beam m³ 22.17
c. Beam at ground floor m³ 44.32
d. Beam at first floor m³ 41.20
e. Beam at second floor m³ 49.46
f. Ring beam m³ 45.56
g. Slab m³ 368.35
h. Column m³ 65.36
i. Stair m³ 15.04
3 Formwork
a. Pile cap m² 175.18
b. Tie Beam m² 270.92
c. Beam at ground floor m² 468.39
d. Beam at first floor m² 441.76
e. Beam at second floor m² 544.71
f. Ring beam m² 512.52
g. Slab m² 2,545.27
h. Column m² 818.14
Total
No Description Unit
Quantity
i. Stair
- Plywood t=12mm sheet 2,021.91
- Timber block m³ 173.31
- Nail kg 1,444.22
4 Rebar
a. Rebar Ø 8 kg 357.84
b. Rebar Ø 10 kg 12,480.54
c. Rebar D13 kg 3,333.74
d. Rebar D19 kg 63,535.55
e. Kawat beton kg 1,594.15
IV. MASONRY WORK
1 Light concrete block t=75mm m² 594.11
2 Light concrete block t=100mm m² 2,327.77
3 Light concrete block t=200mm m² 747.91
4 Plastered brickwall m² 7,339.56
5 Cement rendering m² 7,339.56
V ROOFING WORK
1 Roofing m² 845.00
2 Slab roof waterproofing m² 33.00
3 Steel enamelled flashing t=0.5 mm m¹ 196.00
4 Ridge capping m¹ 50.00
5 Allumunium flashing flat m¹ 131.00
6 Glasswool roof insulation + Mesh m² 850.00
VI STEEL STRUCTURE WORK
1 WF 350 x 175 x 7 x 11. kg 18,000.00
2 WF 150 x 75 x 5 x 7 kg 3,275.00
3 Framing for hanging ceiling at 2nd floor kg 7,110.00