You are on page 1of 8

PT.

MEINDO ELANG INDAH

ACCOMMODATION BUILDING A4

CIVIL / STRUCTURAL MTO

B 25/08/2006 JH ISSUED FOR DESIGN TGH BS

A 07/08/2006 JH ISSUED FOR INFORMATION TGH BS


CHECK APPR. SPEC. RESP.

REV DATE BY DESCRIPTION


ENGINEER APROVAL COMPANY APPROVAL

STATUS CODE : A = Issued for comments/information - B = Issued for approval - C = Approved/issued for design - D = As Built

TOTAL OR PARTIAL REPRODUCTION AND/OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN


WITHOUT PRIOR WRITTEN AUTHORIZATION OF THE OWNER

TOTAL E & P INDONESIE


Handil Camp Extension
Accommodation Buildings A4 & A5
REVISION STATUS
HDL- 41- 2 - 101- E B C
ACCOMMODATION BUILDING A4 Page
CIVIL / STRUCTURAL MTO A

TABULATION OF REVISED PAGES


REVISIONS REVISIONS
PAGE PAGE
A B C D E F G H A B C D E F G H
1 X
2 X X
3 X
4 X
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49

HANDIL CAMP EXTENSION DOCUMENT NO. : HDL-41-2-101-E


ACCOMMODATION BUILDINGS A4 & A5 REVISION : B DATE : 25/08/2006
ACCOMMODATION BUILDING A4 Page
CIVIL / STRUCTURAL MTO 1

TABLE OF CONTENT

1. REFERENCE DOCUMENT....................................................................................2

2. MATERIAL TAKE OFF..........................................................................................3

HANDIL CAMP EXTENSION DOCUMENT NO. : HDL-41-2-101-E


ACCOMMODATION BUILDINGS A4 & A5 REVISION : B DATE :25/08/2006
ACCOMMODATION BUILDING A4 Page
CIVIL / STRUCTURAL MTO 2

1. REFERENCE DOCUMENT

    ACCOMMODATION BUILDING A4 - DRAWINGS    


    Drawings Rev. Date
1 HDL-41-2-101-C Piling - Layout and Details B 1-Aug-06
2 HDL-41-2-102-C Foundation - Plan and Sections ( Sheet 1 of 4 ) B 1-Aug-06
3 HDL-41-2-102-C Foundation - Plan and Sections ( Sheet 2 of 4 ) B 1-Aug-06
4 HDL-41-2-102-C Foundation - Plan and Sections ( Sheet 3 of 4 ) B 1-Aug-06
5 HDL-41-2-102-C Foundation - Plan and Sections ( Sheet 4 of 4 ) B 1-Aug-06
6 HDL-41-2-103-C Column - Plan and Details ( Sheet 1 of 2 ) B 1-Aug-06
7 HDL-41-2-103-C Column - Plan and Details ( Sheet 2 of 2 ) B 1-Aug-06
8 HDL-41-2-104-C Ground Slab - Plan, Section and Detail ( Sheet 1 of 2 ) B 1-Aug-06
9 HDL-41-2-104-C Ground Slab - Plan, Section and Detail ( Sheet 2 of 2 ) B 1-Aug-06
10 HDL-41-2-105-C First Floor - Plan, Section and Detail ( Sheet 1 of 2 ) B 1-Aug-06
11 HDL-41-2-105-C First Floor - Plan, Section and Detail ( Sheet 2 of 2 ) B 1-Aug-06
12 HDL-41-2-106-C Second Floor - Plan, Section and Detail ( Sheet 1 of 2 ) B 1-Aug-06
13 HDL-41-2-106-C Second Floor - Plan, Section and Detail ( Sheet 2 of 2 ) B 1-Aug-06
14 HDL-41-2-107-C Ring Beam Plan & Details ( Sheet 1 of 2 ) B 1-Aug-06
15 HDL-41-2-107-C Ring Beam Plan & Details ( Sheet 2 of 2 ) B 1-Aug-06
16 HDL-91-2-101-C Roof - Plan and Details B 1-Aug-06
         

HANDIL CAMP EXTENSION DOCUMENT NO. : HDL-41-2-101-E


ACCOMMODATION BUILDINGS A4 & A5 REVISION : B DATE :25/08/2006
ACCOMMODATION BUILDING A4 Page
CIVIL / STRUCTURAL MTO 3

2. MATERIAL TAKE OFF

Total
No Description Unit
Quantity
I. PILING WORK    
1 Concrete pile dia.500 L=36000 mm    
    a. Pile Ø500 L=12000 mm nos 273.00
2 Filing concrete w=800 mm  
    a. Concrete m³ 14.29
    b. Rebar kg 2,871.96
      - D19 kg 2,435.16
      - Ø8 kg 436.80
3 Cutting pile nos 91.00
         
II. EARTH WORK  
1 Excavation m³ 944.83
2 Soil removal m³ 142.36
3 Backfill m³ 802.46
4 Sandfill m³ 25.34
5 Antitermite m² 543.07
         
III. CONCRETE WORK  
1 Lean concrete m³ 12.67
2 Concrete  
    a. Pile cap m³ 82.18
    b. Tie Beam m³ 22.17
    c. Beam at ground floor m³ 44.32
    d. Beam at first floor m³ 41.20
    e. Beam at second floor m³ 49.46
    f. Ring beam m³ 45.56
    g. Slab m³ 368.35
    h. Column m³ 65.36
    i. Stair m³ 15.04
         
3 Formwork  
    a. Pile cap m² 175.18
    b. Tie Beam m² 270.92
    c. Beam at ground floor m² 468.39
    d. Beam at first floor m² 441.76
    e. Beam at second floor m² 544.71
    f. Ring beam m² 512.52
    g. Slab m² 2,545.27
    h. Column m² 818.14
Total
No Description Unit
Quantity

HANDIL CAMP EXTENSION DOCUMENT NO. : HDL-41-2-101-E


ACCOMMODATION BUILDINGS A4 & A5 REVISION : B DATE :25/08/2006
ACCOMMODATION BUILDING A4 Page
CIVIL / STRUCTURAL MTO 4

    i. Stair  
      - Plywood t=12mm sheet 2,021.91
      - Timber block m³ 173.31
      - Nail kg 1,444.22

4 Rebar    
    a. Rebar Ø 8 kg 357.84
    b. Rebar Ø 10 kg 12,480.54
    c. Rebar D13 kg 3,333.74
    d. Rebar D19 kg 63,535.55
    e. Kawat beton kg 1,594.15
         
IV. MASONRY WORK  
1 Light concrete block t=75mm m² 594.11
2 Light concrete block t=100mm m² 2,327.77
3 Light concrete block t=200mm m² 747.91
4 Plastered brickwall m² 7,339.56
5 Cement rendering m² 7,339.56
         
         
V ROOFING WORK  
1 Roofing m² 845.00
2 Slab roof waterproofing m² 33.00
3 Steel enamelled flashing t=0.5 mm m¹ 196.00
4 Ridge capping m¹ 50.00
5 Allumunium flashing flat m¹ 131.00
6 Glasswool roof insulation + Mesh m² 850.00
         
         
VI STEEL STRUCTURE WORK  
1 WF 350 x 175 x 7 x 11. kg 18,000.00
2 WF 150 x 75 x 5 x 7 kg 3,275.00
3 Framing for hanging ceiling at 2nd floor kg 7,110.00

HANDIL CAMP EXTENSION DOCUMENT NO. : HDL-41-2-101-E


ACCOMMODATION BUILDINGS A4 & A5 REVISION : B DATE :25/08/2006