You are on page 1of 7

METHOD STATEMENT

CONSTRUCTION OF COMMERCIAL AND SPRINKLE TANK


Work Activities

Excavation Work

Pre-start checks:
checks:
The pre-start checks must cover prior to commence the excavation works:-
1 Avail
Availabi
abilit
lity
y of plan
plantt and
and equip
equipmen
mentt to be
be used
used
- 2 nos of PC 200 Excavators
- 2 nos of dumpers truck

2 Gro
Ground Con
Conditio
ition
ns
- The information for client, The excavation area is backfilled and no contaminated.
- No overhaed and undergound services at the excavation area.
- Pile group at excavation area.

Planning and co-ordination


1 Planning
Planning and
and co-ordinat
co-ordination
ion between
between those
those involves
involves in the excavtio
excavtion
n activities
activities is essential
essential to ensure
ensure
the safety of all members.

2. Site plans
plans and drawin
drawing
g is refer, the depth
depth of excavati
excavation
on is less than 6m.The
6m.The dimens
dimension
ion of the excavat
excavation
ion
at the top is planned. This information need to pass to site foreman and machine operator.
Figure 1 shown the planned excavation area.

3. Planning
Planning the
the excavation
excavation work
work before
before work starts
starts to ensure it can be carried
carried out
out safely.
safely. Planning
Planning
involves as below:-
a Exca
Excava
vati
tion
on Meth
Method
od - Ope
Open
n Cut
Cut
b Stati
Staticc and dynami
dynamicc loads
loads near
near the
the exca
excavat
vation
ion area.
area.
c Safe
afe work
work met
metho
hod
d stat
statem
emen
ents
ts
e Proced
Procedure
uress to
to deal
deal with
with emerge
emergenci
ncies.
es.
f Dewatering System
Functional Flowchart

 A c tivit y requir ing the move ment of


s oi l or ground or the ins ertion of
obj ects i nt o the ground

S pec if ic manufac turer i ns truc ti ons or


Do es t he ac tivit y involve Y es operati ona l gu ides of pl ant used (if
any of the following ? appli cable ) is to be fol lowed as we ll as
any s ign age lo c at ed i n the area

 dig gi ng or mov ement of a k now n material


stockpile , or 
 diggi ng of rais ed ga rden be ds w i th a k now n
absence of underground services , or 
 diggi ng or cl eari ng of mat eria l / soi l bu ild up
wit hi n culv erts , drains or simil ar loc at ions wi th
a known absence of underground services .

No

S pec if ic manufac turer i ns truc ti ons or


The dept h of 
Y es operati ona l gu ides of pl ant used (if
the exca vati on , diggi ng
appli cable ), s ignage , etc to be foll owed
or i ns erti on of objec t i s
as wel l as any ge neral requir ements of
<150 mm
this Co rpo rate S tan dard

No

Compl et e an Excavation &


Digging Contr ol Guide  as part
of pre -wo rk planning

Undert ak e an und ergroun d


servi ces inv es ti gati on as per the
Imple ment c ontrol me as ures as
Cont rol Gu ide req ui rements
ident ifi ed wi thin the Co nt rol
Guide

Ident ify collap se and entry


c ontrol s as r el ev ant to t he
excavati on an d ac ti vi ty req ui red

Ident ify ad di tional wo rk s pec ifi c


c ontr ol s rele van t t o the
excavati on an d ac ti vi ty req ui red

Figure 2 : Planning Flowchart for Excavation


3.1 Mechanical Excavation - Open cut
a The area of excavated will be clearly marked on the ground serface using cements or sand

b The machine operators was informed the dimension of the excavation at the top and the final depth
of the excavation.

c The material from the exacavtion will be loaded into the dump truck and tipped away from the
working area so it does not apply a surcharge to the side of the excavation.

d The trained supervisor to assit in the safe operation of the plant and to observe the area being
excavated and to ensure there are no hit or damp to the piling for the foundation.

e The 300mm high earth berm at the top of the slope to avoid surface run off to the excavated area
after heavy rain.

f As the excavation increases in depth the side of slope should be battered and cover with canvas
to prevent collapse.

g Care needs to be taken to avoid over excavation. Frequent levelling is necessary to check the depth
of cut. Workers entering the excavated area to trim of the excavation is often required.

h Safety supervisor and the groundwork supervisor to check the safety of the excavation. The stability
on the surface have to checked when plants adjacent to an excavation area.

Cut Slope cover with plastic sheet 300mm earth berm

Timber Frame Barricade 1

( Horizontal & Vertical ) 1000mm working space

Cut Slope cover with plastic sheet 300mm earth berm

Pile cap excavation should allow approximately 1m ( Surrounding) working space

Timber Frame Barricade

( Horizontal & Vertical )

Figure 3 : Mechanical Excavation - Open Cut ( Benching & Battering )


3.2 Static and dynamic loads near the excavation area.
a The stability on the surface have to checked when plants and machineries adjacent to an excavation area.

b Precaution on the heavy load such as large equipment, heavy materials or large spoil pile can be
too heavy for the sol support, resulting in a cave-in.
The large spoil pile may hide the tension crack that would otherwise signal that a sliding soil failure
occur.

3.3 Safe work method statements


a All workers should wear the proper Personal Protective Equipment (P.P.E. ) such as safety boots
whilst working, safety helmet, high visibility during night work.

b All workers should attended a special Site Induction/ Tool Box Talk and knowledge of work safe practice
before access to the work area.

c Access/ egress for the workers entering an excavated area usually be a ladder or scaffolding stairway
The scaffolding stairway constructed and extend 1 meter above top of the excavation.

d All excavations will be a rigid barricade ( Timber frame ) and putting signage to protect the workers
from the hazard during the work hours and off hours.

e The slope have to inspected daily, it is important to watch for unsafe situations especially after
heavy rain.
3.4 Procedures to deal with emergencies.

FILL UP & SUBMIT


ACCIDENT OCCURRED
INCIDENT/ACCIDENT
(Witness / Supervisor Incharge To Inform)
NOTIFICATION FORM

KC CONTRACT Person In Charge


MR.C.W LAM - H/P 012-7848832

NAB's SR PROJECT MANAGER OPERATION


MR.WONG SEE POH MR.CH'NG KHENG HOCK
H/P: 012-474 2878 H/P 016-405 4001

SAFETY OFFICER
NAVIN TROY - H/P 016-735 4407 LOGISTIC CORDINATOR
MR.LOW CHIEW KONG
H/P : 012-432 8385

ACCIDENT CLASSIFICATION

MINOR MAJOR FATALITY / SERIOUS


(Lost Time Injury / FIRE UTILITIES
(First Aid) BODILY INJURY
Dangerous AFFECTED
Occurrence)

Hospital Sultanah Aminah Bomba Tmn U


Send Victim Tenaga
Tel : 07 - 223 1666 / 999 Tel : 07- 5203129
To Clinic / Nasional
KLINIK KESIHATAN TMN U Emergency : 994
Hospital TEL: 07-521 6800
Send Victim To
Hospital
Telekom
Send Body / Victim To Malaysia
Send Victim To Clinic
Hospital For Post Mortem (Tel : 100)
 / Hospital (if any)

SET UP INVESTIGATION TEAM COMPRISING OF Syarikat Air


a) Project Director       R Johor 
b) SR.Project Manager       O
     J (Tel : 07-
c) Construction Manager       A 2224222)
d) Consultants      M
e) Safety Officer       R
     O
     N
     I
     M
To Review & Investigate The Accident and Identify The Cause(s) Of The
Accident & Corrective Action(s) To Be Taken

REPORT WILL BE DISTRIBUTED TO


a) Managing Director 
b) Related Government Bodies
c) Project Director / Manager 
d) Head Of Department / Sub Contractor Concerned

Figure 4 : Emergencies Plan


3.5 Dewatering System

a During construction, the water may accumulate from a number of sources such as high ground
water table seeping into the excavation area and surface run off after heavy rain.

b The well point or sump is constructed and the submersible pump is located to the pump sump
and well piont pipes are connected by piping or hose to the adjacent drainage.

Figure 5 : Dewatering System - Pump Sump

Tanks Construction

1 The Commercial & Sprinkle Tanks is contruct according to C & S Construction Drawing No :
BP 1226/17/WT/1-2 and BP 1226/17/WT/2.

2 The R.C. Works Method Statement is refer to our Letter Ref : NAB/SCTEX/KC/S6/L05 dated on
15 March 2013.

3 The R.C. Works Method Statement is refer to our Letter Ref : NAB/SCTEX/KC/S6/L05 dated on

Waterproofing of the Tanks


1 Prevent water leakage on the construction joint, the 200mm wide supercast PVC waterstop is installed.

2 The waterstop is located and fixed at centre of the all round of the tanks wall while the concrete
is being placed. The waterstop will prevent loss of the water from within the tnak and will prevent
ingress of the groundwater whenthe tank is drained down.

Figure 6 : 200mm wide Supercast PVC Waterstop.

3 Concrete must be fully compacted or vibrated around the waterstops to ensure that no voids or
porous areas remain.
4 300mm high of Concrete Wall Kicker must be construct in order the waterstops are securely
held in their correct position.

200mm wide Supercast


Waterstops

300mm

Figure 7 : 300mm high concrete kicker and waterstops

5 After the construction of the tanks was completed, apply 3 coats of the Shell Flintkote 3 Bituminous
Waterproofing System to passive surface of tanks wall.

6 The Waterproofing System Method Statement is refer to our Letter Ref : NAB/SCTEX/KC/S6/L23 dated on
19 April 2013.

7 Cover with the plastic sheets immediately when the waterproofing system completed. This is to
protect damaged to the waterproofing system.

8 Cementitious Waterproofing system is apply to internal wall prior to construct of the top concrete slab.
Protection of internal waterproofing by cover a layer of plastic sheet.

9 Water Ponding Test was carry on to ensure is watertight. If any leaking after apply waterproofing
then remedial work is necessary such as P.U Grouting.

Backfilling Works
1 After the construction of the pilecap was completed, backfilling to fill the gap of working space by
using River Sand.

2 Backfill the excavation after placement of the permanent structure such as Reinforced Concrete
Tank and the 3 days cube results reach the required strength.

3 Backfill area free from stone large enough to interface with compactionand construction debris such
as wood and other extraneous materials.

4 The backfill material was haul from the stock pile area by using dumper trucks.

5 Compact each layer ( 600mm per layer ) to meet the density requirements by the 1 ton roller compactor.

6 Avoid wedging sction of backfill against structures, the precaution must be taken such as place
backfilling uniformly around the structures.

You might also like