Professional Documents
Culture Documents
Excavation Work
Pre-start checks:
checks:
The pre-start checks must cover prior to commence the excavation works:-
1 Avail
Availabi
abilit
lity
y of plan
plantt and
and equip
equipmen
mentt to be
be used
used
- 2 nos of PC 200 Excavators
- 2 nos of dumpers truck
2 Gro
Ground Con
Conditio
ition
ns
- The information for client, The excavation area is backfilled and no contaminated.
- No overhaed and undergound services at the excavation area.
- Pile group at excavation area.
2. Site plans
plans and drawin
drawing
g is refer, the depth
depth of excavati
excavation
on is less than 6m.The
6m.The dimens
dimension
ion of the excavat
excavation
ion
at the top is planned. This information need to pass to site foreman and machine operator.
Figure 1 shown the planned excavation area.
3. Planning
Planning the
the excavation
excavation work
work before
before work starts
starts to ensure it can be carried
carried out
out safely.
safely. Planning
Planning
involves as below:-
a Exca
Excava
vati
tion
on Meth
Method
od - Ope
Open
n Cut
Cut
b Stati
Staticc and dynami
dynamicc loads
loads near
near the
the exca
excavat
vation
ion area.
area.
c Safe
afe work
work met
metho
hod
d stat
statem
emen
ents
ts
e Proced
Procedure
uress to
to deal
deal with
with emerge
emergenci
ncies.
es.
f Dewatering System
Functional Flowchart
No
No
b The machine operators was informed the dimension of the excavation at the top and the final depth
of the excavation.
c The material from the exacavtion will be loaded into the dump truck and tipped away from the
working area so it does not apply a surcharge to the side of the excavation.
d The trained supervisor to assit in the safe operation of the plant and to observe the area being
excavated and to ensure there are no hit or damp to the piling for the foundation.
e The 300mm high earth berm at the top of the slope to avoid surface run off to the excavated area
after heavy rain.
f As the excavation increases in depth the side of slope should be battered and cover with canvas
to prevent collapse.
g Care needs to be taken to avoid over excavation. Frequent levelling is necessary to check the depth
of cut. Workers entering the excavated area to trim of the excavation is often required.
h Safety supervisor and the groundwork supervisor to check the safety of the excavation. The stability
on the surface have to checked when plants adjacent to an excavation area.
b Precaution on the heavy load such as large equipment, heavy materials or large spoil pile can be
too heavy for the sol support, resulting in a cave-in.
The large spoil pile may hide the tension crack that would otherwise signal that a sliding soil failure
occur.
b All workers should attended a special Site Induction/ Tool Box Talk and knowledge of work safe practice
before access to the work area.
c Access/ egress for the workers entering an excavated area usually be a ladder or scaffolding stairway
The scaffolding stairway constructed and extend 1 meter above top of the excavation.
d All excavations will be a rigid barricade ( Timber frame ) and putting signage to protect the workers
from the hazard during the work hours and off hours.
e The slope have to inspected daily, it is important to watch for unsafe situations especially after
heavy rain.
3.4 Procedures to deal with emergencies.
SAFETY OFFICER
NAVIN TROY - H/P 016-735 4407 LOGISTIC CORDINATOR
MR.LOW CHIEW KONG
H/P : 012-432 8385
ACCIDENT CLASSIFICATION
a During construction, the water may accumulate from a number of sources such as high ground
water table seeping into the excavation area and surface run off after heavy rain.
b The well point or sump is constructed and the submersible pump is located to the pump sump
and well piont pipes are connected by piping or hose to the adjacent drainage.
Tanks Construction
1 The Commercial & Sprinkle Tanks is contruct according to C & S Construction Drawing No :
BP 1226/17/WT/1-2 and BP 1226/17/WT/2.
2 The R.C. Works Method Statement is refer to our Letter Ref : NAB/SCTEX/KC/S6/L05 dated on
15 March 2013.
3 The R.C. Works Method Statement is refer to our Letter Ref : NAB/SCTEX/KC/S6/L05 dated on
2 The waterstop is located and fixed at centre of the all round of the tanks wall while the concrete
is being placed. The waterstop will prevent loss of the water from within the tnak and will prevent
ingress of the groundwater whenthe tank is drained down.
3 Concrete must be fully compacted or vibrated around the waterstops to ensure that no voids or
porous areas remain.
4 300mm high of Concrete Wall Kicker must be construct in order the waterstops are securely
held in their correct position.
300mm
5 After the construction of the tanks was completed, apply 3 coats of the Shell Flintkote 3 Bituminous
Waterproofing System to passive surface of tanks wall.
6 The Waterproofing System Method Statement is refer to our Letter Ref : NAB/SCTEX/KC/S6/L23 dated on
19 April 2013.
7 Cover with the plastic sheets immediately when the waterproofing system completed. This is to
protect damaged to the waterproofing system.
8 Cementitious Waterproofing system is apply to internal wall prior to construct of the top concrete slab.
Protection of internal waterproofing by cover a layer of plastic sheet.
9 Water Ponding Test was carry on to ensure is watertight. If any leaking after apply waterproofing
then remedial work is necessary such as P.U Grouting.
Backfilling Works
1 After the construction of the pilecap was completed, backfilling to fill the gap of working space by
using River Sand.
2 Backfill the excavation after placement of the permanent structure such as Reinforced Concrete
Tank and the 3 days cube results reach the required strength.
3 Backfill area free from stone large enough to interface with compactionand construction debris such
as wood and other extraneous materials.
4 The backfill material was haul from the stock pile area by using dumper trucks.
5 Compact each layer ( 600mm per layer ) to meet the density requirements by the 1 ton roller compactor.
6 Avoid wedging sction of backfill against structures, the precaution must be taken such as place
backfilling uniformly around the structures.