Professional Documents
Culture Documents
ENVIRONMENTAL ENGINEERING – II
LECTURE # 02
DATED: 2ND MARCH, 2020
ENVIRONMENTAL IMPACT
ASSESSMENT
Introduction
• A systematic identification and evaluation of the potential impacts of
proposed projects, plans, programs, or legislative action relative to
physical-chemical, biological, cultural and socioeconomic components
of environment.
OR
• The process of predicting, identifying, evaluating and mitigating the
biological, social and other relevant effects of developmental proposals
prior to major decision being taken and commitment made.
OR
• An important procedure for ensuring that the likely effects of new
developmental activities on the environment are fully understood and
taken into account before the development is allowed to go ahead.
Introduction
• Compare alternatives to a proposed project (including the possibility of not developing the site),
management, techniques and mitigation measures.
• Clear EIS mentioning importance of impacts and their specific characteristics to experts as well as to
non expert in the field.
• (i) Design problem (ii) Construction problem; and (iii) Operational problem
• The screening process is usually addressed in EIA guidelines that described which
type of project needs to proceed in EIA or not. If the screening process suggests that
there is no need of detailed assessment then preliminarily assessments are essential.
If screening and/or preliminarily assessment suggest an impact assessment then the
next step is scoping.
Screening Screening
• Identify environmental issues of concern
• Determine whether EIA is needed
• Establish need for project
Environmental
impact
In other cases, it is essential that members of the local community involvement be along
with other key representatives. The scoping process indicates the detailed information
that will be required and it can be used to review alternatives for project design. Scoping
process identify the following as early as possible
• The purpose of scoping is;
• To consider a balance and appropriate options for a proposed action;
• New field work may necessary (e.g. ecological survey) if relevant data is
not already available
ALTERNTIVES
• An EIA process is conducted for a project and its alternatives (e.g. different locations,
scales, designs). Alternatives are the “raw material” of EIA process. The different
alternatives can be clearly assessed to help the decision makers to select the best available
option. They are;
• Option (iii) is not a practicable option, when donor agencies are interested to invest in an
area. For decision makers they have to select from the two remaining options. It is a
difficult decision, because of non-availability of baseline information in a country like
Pakistan.
• The decision makers should try their best to utilize the available data
for selection of site. It is a common practice that alternatives are
ignored and the only option is to select the site, which is under
consideration. If the alternative site or operation has minimum impact
on environment, then decision makers should use the second option to
change the site for the proposed activities.
Impact Prediction and Assessment
• Minimizing impacts by limiting the degree or magnitude of the action and its implementation.
• Rectifying the impact by repairing, rehabitating, or restoring the affected
environment.
The decisions on proposals subject to EIA, whether they are Yes / No decisions
or involve choice between alternatives are frequently made incrementally.
At early stages of EIA process, it will be clear that some impacts are unacceptable
causing to redesign or withdrawal. Similarly, at review process new information will
be collected from public and experts for further actions.
Monitoring committee is authorized to inspect the site periodically to ensure that the
• Construction phase Monitoring: It can be carried out during the construction and
oriented either to the emissions and discharges of the installation or to the status of the
environmental variable.
• After-use Monitoring: it can be carried out when the installation is left or has finished
its operative period and oriented to residual emissions, e.g. long term evaluation of the
environmental conditions.
EIA Auditing and Evaluation
• Environmental auditing is an assessment process to check that the pollution level or an impact
of project is within the limits prescribed by the authorized agency at the time of decision-
making process. Environmental audit will usually be carried out by authorized agency and will
report it to EPA-Pak. There is a need of regular environmental audit procedure to check the
proponent is following the instructions of project approval or not. Similarly, the existing
industries are polluting water, land and air. An independent commission to check pollution
level is essential to prevent the degradation of environment. For this purpose, industries have
to be obliged to keep a proper and regular record of pollutants. The Commission members can
randomly, check industries records and monitor the procedure personally for minimizing of
pollutants. Also, different samples can be selected and compare its level of pollution with the
one that has been taken from industries record. Inspection and audit of industrial units is the
best way to achieve the goals of pollution control strategy.