SEASHORE GALVANIZING FACTORY

GALVANIZING REPORT
PROJECT TITLE.- EPIC FOR MTBE TANKS AND PIPELINE BETWEEN QAFAC & QP REFINERY
CONTRACT NO. MAIN CODE- GC17102400 PROCEDURE NO.- 4006-00-69-00-0153 RFI NO.- 4006-RFI-6001 REPORT NO.- FERNAS-STR-001
PROJECT NO.- 4006 ITP NO.- 4006-IT-00-69-0029 DRAWING NO.- 4006-21-18-22-0020 DATE- 21/11/2018

S. NO. QTY ITEM BLASTING PICKLING RINSING FLUXING DRYING GALVANIZING COATING COOLING REMARKS

1. Surface 1. Removal of 1. Smoothness


1. Surface 1.Thickness
Inspection cleaniness 1. Check Moisture content 2. Bare spot
cleaniness 2.UOM microns Warpage Adhesion
Parameters 2. Removal of Surface 2. Presence of 3. Dross carry over
3.85 microns
Paint marking Flux coating 4. Lumps

VISUAL ASTM A VISUAL ASTM VISUAL VISUAL VISUAL VISUAL ASTM A ASTM A 123
123 & A 385 A 123 123 TABLE 1
ACCEPTED
1 123 No's TYPE-1(100x600mm) ACCEPTED ACCEPTED ACCEPTED ACCEPTED ACCEPTED 115 Microns N/A PASSED
Sa2.5

ACCEPTED ACCEPTED ACCEPTED ACCEPTED 114 Microns N/A PASSED


2 18 No's TYPE-2(100x600mm) ACCEPTED ACCEPTED
Sa2.5

03 No's TYPE-1(100x800mm) ACCEPTED ACCEPTED 101 Microns N/A PASSED


3 ACCEPTED ACCEPTED ACCEPTED ACCEPTED
Sa2.5

TYPE-1(100x1200mm) ACCEPTED ACCEPTED ACCEPTED ACCEPTED ACCEPTED ACCEPTED 117 Microns N/A
4 01 No PASSED
Sa2.5

INSPECTED BY SGF FERNAS TPI QC QP

NAME

SIGN

DATE

SGF.FO.14 ASTM A 123