You are on page 1of 78

Page 1 of 78

For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Experimental study on the progressive collapse mechanism in the braced and tied-

back retaining systems of deep excavations

G. Zhenga,b, Y.W. Leib, X.S. Chenga,b*, X.Y. Lib, R.Z. Wangb

a MOE Key Laboratory of Coast Civil Structure Safety, Tianjin University, Tianjin
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

300072, China
b Department of Civil Engineering, Tianjin University, Tianjin 300072, China

Corresponding author: Dr. Xuesong Cheng

Associate Professor, Department of Civil Engineering, Tianjin University, Tianjin

300072, China

E-mail: cheng_xuesong@163.com

Tel: +86 138 2180 7355

Co-author: Dr. Gang Zheng

Professor, Department of Civil Engineering, Tianjin University, Tianjin 300072, China

E-mail: zhenggang1967@163.com

Tel: +86 186 0268 3655

Co-author: Dr. Yawei Lei PhD student, E-mail: 15122597216@163.com

Co-author: Mr. Xiyuan Li Master, E-mail: lixiyuan_2016shuo@163.com

Co-author: Dr. Ruozhan Wang PhD student, E-mail: wang18733900016@163.com


For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 2 of 78

Abstract

Collapses of braced or tied-back excavations have frequently occurred. However, the

influence of the failure of some retaining structure members on the overall safety

performance of a retaining system has not been studied. Model tests of failures of

retaining piles, struts or anchors were conducted in this study, and the load transfer
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

mechanisms underlying these conditions were analysed. When failures or large

deformations occurred in certain piles, the increasing ratios of the bending moments in

adjacent piles were much larger in the braced retaining system than in the cantilever

system and more easily triggered progressive failure. When the strut elevation was lower

or the excavation depth was greater, the degree of influence and range of pile failures

became larger. When certain struts/anchors failed, their loads transferred to a few adjacent

struts/anchors, possibly leading to further strut/anchor failure. The influence mechanisms

of strut or anchor failure on piles were different from those of pile failure. As the number

of failed struts or anchors increases, the bending moments of the piles in the failure zone

first decrease and then increase to very high values. Therefore, the progressive failure

path extends from struts/anchors to piles and will lead to large-scale collapse.

KEYWORDS: deep excavation; progressive collapse; partial failure; retaining system;

load transfer coefficient


Page 3 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

1. Introduction

In practice, braced piles/walls and tied-back piles/walls are very common retaining

structures used in large-scale deep excavations with complicated surrounding conditions.

In recent years, many excavations using such retaining structures collapsed worldwide,

with most of these collapses being triggered by the partial failure of a retaining structure,
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

i.e., the failure of certain retaining structures within a relatively small and local range of

the excavation. For example, in the Singapore metro collapse accident (Artola 2005; COI.

2005; Corral and Whittle 2010; Davies 2007; Ishihara and Lee 2008; Puzrin et al. 2010;

Whittle and Davies 2006), the failure started at the ninth-level strutting connection.

Yielding of the connection allowed the diaphragm walls to deform, overloading the struts

in the levels above and causing them to buckle. This triggered a 100 m-long collapse of

the excavation. A Hangzhou metro accident (Chen et al. 2013; Li and Li 2010; Tan et al.

2018) began at the fourth-level struts that were not installed in a timely manner, and

finally led to a 70 m-long collapse. Moreover, in addition to the failures of struts and

retaining piles or walls, many collapses of excavations have also been triggered by the

breakage of anchors, such as the accidents in Cologne and Japan (Haack 2009; Itoh et al.

2011).

The failure of an excavation is a three-dimensional (3D) problem involving large

deformations and nonlinear and multifield coupling, because the failure can propagate

along the depth, width and length directions of the excavation. The traditional stability

analysis methods for excavations (overall stability failure, overturning failure, basal

heaving failure, etc. ( Kempfert and Gebreselassie 2006; Ou 2006; Lu and Tan 2019; Luo

et al. 2012)) are mostly based on the relatively simplified 2D instability failure mode of

an excavation profile (Bjerrum and Eide 2008; Chang 2000; Hsieh et al. 2008; Huang et
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 4 of 78

al. 2008; Osman and Bolton 2006; Ukritchon et al. 2003), which cannot reflect the

physical process of progressive failure in terms of time and space after the partial failure

of a retaining structure. In addition, because the retaining systems of deep excavations

are not permanent structures, they are usually designed with relatively low safety factors

and use member-based methods rather than system-based approaches. Therefore, the
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

retaining structures may lack integrity and sufficient redundancy, i.e., the system safety

performance of the retaining structures is not high, which may be a reason why

progressive collapses of excavations occur frequently. Cheng et al. (2016, 2017)

performed an experimental and numerical analysis on the breakage of retaining piles in

an excavation and found that when the maximum load transfer coefficient (the peak

increasing ratio of the maximum bending moment in the pile after failure over the

corresponding value before failure) is greater than the bearing capacity safety factor of

the piles, partial failure will lead to progressive collapse. However, these conclusions

were based on excavations retained by cantilever piles and few studies have examined

the system safety and progressive collapse of excavations retained by anchored or strutted

piles.

Stille and broms (1976) reported a field study of anchor failures at four sites in Sweden

and found that the maximum change in the anchor load expressed as a percentage of the

initial load of the failed anchor was 35% for walls with two or more rows of anchors.

Using numerical analysis, Goh and Wong (2009) found that the failure of one or two

struts due to an accident will not result in detrimental failure of the entire excavation

system if the struts are of adequate strength. Clause 3.7.4 of Technical Reference 26: 2010

(TR26. 2010) states that the design of deep excavations should accommodate for the

possible failure of any individual strut, tie rod, ground anchor, structural member or
Page 5 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

connection at each stage of construction. Itoh et al. (2011) designed a centrifuge test of

excavation collapse caused by the breakage of anchor heads. Zheng and Cheng et al.

(2011, 2014 and 2015) indicated that when the redundancy of retaining structures is not

sufficient, partial failure will easily evolve to progressive collapse. Pong et al. (2012)

indicated that one-strut failure (OSF) analysis using 2D plane strain analysis lead to more
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

conservative designs with heavier strut sections and proposed a simplified method using

the reduced equivalent strut stiffness to simulate OSF in 2D analysis instead of 3D

simulations. Silva et al. (2017) proposed an assessment method and corresponding

evaluation index to analyse the structural safety of anchored concrete panels after anchor

ruptures through the calculation of the bending moments and punching forces in the

panels. Choosrithong and Schweiger (2018) and Goh et al. (2018) indicated that the load

from a failed strut may transfer to adjacent struts and therefore cause one or more struts

to fail if the adjacent struts are not of sufficient bearing capacity. Zhao et al. (2018) used

the finite-element method to reveal the crucial mechanical behaviours of retaining

structures as a result of different types of anchorage failures. Using numerical and

theoretical analysis, the failure mechanism of a high-rise building collapse near a

basement excavation in Shanghai has been investigated (Wang et al. 2019; Tan et al.

2020). The above literature review shows that most partial collapse analyses were

conducted via numerical studies.

The focus of this paper is an experimental study of pile, strut and anchor failures to

investigate how loads from the failed retaining structures are transferred to the adjacent

retaining structures and lead to the collapse of the whole retaining system, i.e., the

progressive collapse mechanism. Three categories of model tests for strut-pile and

anchor-pile excavation were designed, conducted and compared in this paper. The tests
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 6 of 78

include the initial failures of certain retaining piles, struts or anchors. In these tests, the

changes of the earth pressure, pile internal forces, and strut or anchor axial forces caused

by different types of partial failures were monitored and analysed. The influences of

several crucial factors (partial failure type, excavation depth, etc.) on the progressive

collapse mechanism were discussed.


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

2. Model test introduction

To study the influence of partial retaining structure failure on the adjacent intact

retaining structures and the whole retaining system, 7 tests were conducted, including 5

tests (test 1-5) on a braced-pile retaining system and 2 tests (test 6-7) on a tie-back

retaining system. Tests 1-4 and test 5 simulated the failures of certain retaining piles and

struts in a braced-pile retaining system, respectively, and tests 6 and 7 simulated anchor

failure, as shown in Fig. 1.

2.1 Soil information and scaling ratio of the model

The soil used in this model test was dry fine sand, which was excavated in Tangshan

district, Hebei Province, China. The sand was the same as that in Cheng’s study (Cheng

et al. 2017). The main parameters of the sand are listed in Table 1. The critical-state

friction angle (Schofield 1968; Simoni and Houlsby 2012; Yang and Luo 2018) of the

sand sample at the mid-height of the model, as measured by the direct shear test, was 31°.

Altaee and Fellenius (1994) and Gibson (1997) proposed a scaling law for small-scale

testing under the 1-g condition in sand. They noted that the chief condition for agreement

between the model and prototype is that their initial soil states must have equal proximity

to the steady-state line (SSL). The scaling of the constitutive behaviours of the sand and

structures were the same as those in Cheng’s study (Cheng et al. 2017). The scaling
Page 7 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

relations in terms of the geometric scaling ratio n (ratio of prototype/model) are presented

in Table 2, and the geometric scaling ratio n was set to be 16 for all models in this study.

2.2 Information on the 7 model tests

The information for the 7 model tests, including the depth of excavation, the elevation

of the strut or anchor, and the failure model of the retaining structure, are illustrated in
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

detail in Table 3 and Fig. 1.

Tests 1-4 were model tests of excavation collapse caused by the failure of 4 retaining

piles (P20-P23), representing the retaining pile failure type. Test 1 is illustrated in Fig. 1

(b). The difference between tests 1 and 2 was the elevation of the strut. The difference

between tests 1 and 3 was the excavation depth. The influences of the strut elevation and

excavation depth on the load transfer during partial failure were studied in tests 1-3.

Furthermore, test 4 simulated large deformations rather than pile breakages (P20-P23) in

preset locations, as shown in Fig. 2, and the other model conditions were the same as

those of test 3. The difference between the influences of large localized deformation and

pile breakage on the progressive collapse mechanism was studied in this test.

To compare the failure mechanisms of braced excavation and cantilever pile-retained

excavation, test 3 in Cheng’s paper (Cheng et al. 2017) was introduced as the comparative

test and is labelled test 0 in this paper, as shown in Fig. 1 (a). In test 0, the boundary of

the window was considered to be a symmetrical plane. Two initiating failure piles (IFPs

P1 and P2) were used in test 0, which was equivalent to the four IFPs in tests 1-3. Test 0

was the model test of partial collapse caused by failures of certain cantilever retaining

piles, with the total excavation depth H of 750 mm and the corresponding prototype

excavation depth of 12 m.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 8 of 78

In test 5, the initiating failure struts (IFSs) (S5-S10) were disabled one by one,

representing the strut failure type, as illustrated in Fig. 1(c). The sequence of strut failure

was S7, S6, S5, S8, S9 and S10. In tests 6 and 7, the initiating failure anchors (IFAs) (A6-

A14) were disabled sequentially, representing the anchor failure type, as illustrated in Fig.

1(d). The sequence of anchor failure was A10, A9, A11, A8, A12, A7, A13, A6 and A14.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

The difference between tests 6 and 7 was the excavation depth. Additionally, the

differences in load transfer between the strut failure and anchor failure of a retaining

structure could also be analysed.

For tests 1, 5 and 6, the total excavation depth H was 750 mm, and the corresponding

prototype excavation depth was 12 m. The elevation of the strut or anchor was the ground

surface (+0 mm). For test 2, the total excavation depth was also 750 mm, but the elevation

of the strut was 150 mm (0.2H) below the ground surface (GS). In these tests, when the

excavation depth was shallower than 600 mm, each excavation step was 100 mm. For

deeper excavation depths, the excavation step was 50 mm. For each excavation step, the

sand was removed manually by a steel scraper and the depth marks labeled on the piles

were used for the control of excavation depth in each step. After each excavation step,

when the measured pile head displacement became stable, next excavation step started.

For tests 3, 4 and 7, the total excavation depth was 900 mm (prototype excavation depth:

14.4 m), and the elevation of the strut or anchor was the GS (+0 mm). When the

excavation depth was shallower than 800 mm, each excavation step was 100 mm. For

deeper excavation depths, the excavation step was 50 mm.

2.3 Soil tank and devices

The inner dimensions of the soil tank were 2.50 m × 2.46 m × 1.40 m (length × width

× height). A schematic model setup and photographic model example are shown in Fig.
Page 9 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

3 and Fig. 4, respectively. To observe the movements of the soil and retaining structure,

a tempered glass window was installed on one lateral side of the soil tank. A Teflon (PTFE)

film was attached to the internal wall surfaces of the tank (except the window) to reduce

any friction between the soil and the sidewalls. As shown in Fig. 3(a), sand-pouring

equipment was installed above the soil tank.


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

2.4 Model retaining piles

As shown in Fig. 4, 39 total contiguous piles were placed along the length of the soil

tank (2.46 m) to serve as the retaining structure, including 4 failure-initiating piles (IFPs),

9 monitoring IPs (MPs) and 26 normal IPs. In addition, the average pile spacing was 63

mm. Each model pile was composed of a rectangular polyvinyl chloride (PVC) tube with

a cross section of 60 mm × 40 mm × 3 mm (length × width × wall thickness). The length

of each model pile was 1.20 m. The long side of the pile cross section was perpendicular

to the cross section of excavation. Through the loading test of the simply supported model

pile, the flexural stiffness EI (where E is elastic modulus and I is moment of inertia) of

the model pile was measured to be 560 N·m2.

Because the retaining pile is mainly a bending member, the geometric scaling ratio n

was determined based on the equivalent flexural stiffness EI principle. In this study, the

prototype pile was set to be the C30 cast-in-place pile with a diameter of 0.8 m and a

length of 19.2 m (Cheng et al. 2017), which is commonly used in practice. The flexural

stiffness EI of the prototype pile was 603 MN·m2, which is approximately 165 times of

the flexural stiffness of the model pile. Therefore, based on the scaling relations in Table

2, the geometric scaling ratio n was set to be 16 for all models in this study. In addtion,

the compressive stiffness EA of the model pile and prototype pile were 2.2 MN and 9011

MN, respectively.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 10 of 78

As shown in Fig. 3(b) and Fig. 4, the retaining piles are numbered from 1 to 39,

increasing with distance to the observation window. P4, P7, P10, P12, P14, P16, P18, P19

and P26 are MPs, and P20 to P23 are IFPs. Dial indicators were set on top of the MPs to

monitor the horizontal displacement of the MP heads, and earth-pressure cells were

arranged to monitor the soil pressure acting on the MPs at depths of 40 cm and 60 cm
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

below the GS. In addition, similar to the MP in Cheng’s experiments (Cheng et al. 2017),

the distribution of the pile body strain along the pile length could be measured to calculate

the bending moment of the pile body.

To simulate the partial failure of the retaining pile structure, certain piles remained

intact during the excavation stage but were broken automatically at a preset location when

they received a control signal. Such a pile is called an IFP in this paper, and the working

mechanism is shown in Fig. 5. An IFP has two parts (upper and lower) that are separated

by a preset inclined rupture plane (60 cm above the bottom of the pile). The results of the

numerical simulation and tests showed that the position of the maximum bending moment

was close to this preset inclined rupture plane for most of the tests performed in this paper.

2.5 Model struts and waler beam

The initiating-failure struts (IFSs) and monitoring struts (MSs) were modelled using

hollow circle PVC tubes with cross sections of 40 mm × 3.2 mm (external diameter ×

thickness). A total of 13 struts was set along the length of the excavation; that is, the

supporting range of each strut was 3 piles, as shown in Fig. 4. A screw rod with a round

head was set at both ends of the strut, and this design has two advantages. While the strut

length could be adjusted using the screw to create close contact between the struts and

the waler beam, because of the round head of the screw rod, the two ends of the strut were

in contact at a point, which ensured that the support was subjected to the axial force. The
Page 11 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

waler beam adopted the same PVC tube as the retaining pile, with a width of 40 mm, a

height of 60 mm and a length of 2.40 m.

Among the 13 struts, 8 MSs had strain gauges installed on their outer surfaces to obtain

the axial force of the MS. According to the axial tensile calibration test, the compressive

stiffness EA of the model struts was 926 kN; the strain at the strain gauge was 1.08 under
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

the action of a unit axial force (1 N). Based on the scaling relations in Table 2, the

compressive stiffness EA of the corresponding prototype was 3793 MN, which was close

to the compressive stiffness EA of the steel pipe with a diameter of 609 mm and a wall

thickness of 8 mm.

To simulate the partial failure of the struts, some struts were designed to be IFSs that

could be broken manually. The working mechanism is shown in Fig. 6. During the

excavation stage, limit blocks were used to avoid the ends of struts sliding on the waler

surface. For the partial failure stage in which the struts needed to be broken, the upper

limit blocks were removed first. Then, the IFS was pulled manually by a steel strand to

make it fail.

2.6 Model anchors

The model initiating failure anchors (IFAs) and monitoring anchors (MAs) were 2.0-

mm-diameter steel strands installed at 15° from the horizontal direction. The ends of the

steel strands were connected to the load cells, as shown in Fig. 3(c). In total, 19 anchors

were set along the length of the excavation, i.e., the anchoring range of each anchor was

2 piles, as shown in Fig. 1(d). According to the loading test in the tension testing of the

anchors, the tensile stiffness EA of the model anchors was 262 kN; the strain value of the

strain gauge was 3.82 when the anchor was subjected to a unit axial tension load (1 N).

Based on the scaling relations in Table 2, the tensile stiffness EA of the prototype anchor
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 12 of 78

was 1073 MN. Before the excavation, all anchors were prestressed precisely by turning

the screws, as shown in Fig. 6 (c). After the excavation, to simulate anchor failure, the

steel strand of the designated IFA was cut manually with cutting pliers, as shown in Fig.

6 (d).
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

3. Model test results in a normal-excavation stage

The model test process can be divided into two stages: a normal-excavation stage and

a partial-failure stage. This section will introduce the results of the normal-excavation

stage. To easily understand the model test results and associate them with practical

engineering implications, the results discussed in the following sections are all converted

to the prototype scale based on the scaling relationships in Table 2.

3.1 Moment and deflection curves of the pile

Fig. 7 shows the induced bending moments and deflection along the pile at various

excavation depths in two typical tests, test 1 (braced pile) and test 6 (tied-back pile). The

pile deflection profile can be obtained by integrating the bending moment distribution

twice using the measured pile head displacement and rotation as the input boundary

conditions (Leung et al. 2000; Tan et al. 2015). The bending moment along the pile

increased with the excavation depth, and the location of the maximum bending moment

was observed to be approximately 9.6 m below the GS level. By considering this factor,

it was reasonable to choose this depth for the preset rupture plane of the IFP.

When the excavation depth was 12.0 m, the bending moments in piles of different

retaining systems differed. For the braced retaining piles in tests 1, 3 and 5, the maximum

bending moments were 710.41 kN·m, 625.21 kN·m and 591.13 kN·m (the tension at the

excavation side was positive), resulting in an average of 642.25 kN·m, when the
Page 13 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

excavation depth was 12.0 m. For the tied-back retaining structure, the maximum bending

moments in tests 6 and 7 were 389.3 kN·m and 444.9 kN·m, respectively. For the

cantilever pile in test 0, the maximum bending moment (Cheng et al. 2017) was 1652.82

kN·m, which was much larger than those of the braced and tied-back piles. In addition,

when the excavation depth was 14.4 m, the maximum bending moments of the piles in
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

tests 3 (braced piles) and 7 (tied-back piles) were 988.94 kN·m and 682.9 kN·m,

respectively. For the same excavation depth, the maximum bending moment in a braced

pile was larger than that in a tied-back pile, mainly because the strut could provide a

stronger lateral stiffness compared to the anchor (EA values of the strut and anchor were

3793 MN and 1073 MN, respectively).

3.2 Average axial force curves of the struts or anchors

In this paper, the increase of the axial forces of the struts was induced only by the

excavation depth. When the excavation depth was 12.0 m, the average axial compressive

forces of the struts were 169.98 kN, 218.32 kN, 153.19 kN, 145.82 kN, and 163.97 kN

for tests 1-5, respectively, while the average axial tensile forces of the anchors were 44.03

kN and 45.18 kN for tests 6-7. The average axial compressive forces of the struts in test

2 were approximately 28% greater than those in other tests, indicating that a reduction of

the elevation of the strut can improve the supporting effect and provide greater lateral

stiffness to the retaining pile. Additionally, the average axial compressive forces of the

struts were clearly greater than the average axial tensile forces of the anchors, which also

indicated that struts have a higher lateral stiffness than that of anchors.

4. General model test results in the partial-failure stage

4.1 Scenarios after collapse in pile failure tests


For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 14 of 78

When the excavation finished, the partial failure of the retaining structure was triggered

by controllable equipment. As shown in Fig. 8, after the IFPs failed, the soil behind the

IPs adjacent to the IFPs and inside the boundary of the crater became loose and gradually

slid into the excavation in test 1, forming a changing stress arching behind these piles

during collapse. After collapse, the bending moments of these piles (P14-19) increased,
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

and the axial forces of some struts (S7-S8) decreased. As the sand moved into the

excavation, a crater appeared outside the excavation, and the sand formed a slope inside

the excavation, as shown in Fig. 9. For tests 0-3, the sizes of the craters outside the

excavations, which represented the range of the unloading effect, are summarized in

Table 4. At the same excavation depth (tests 0-2), the crater sizes in different tests were

similar, and when the excavation depth increased (test 3), the size of the crater also

increased.

4.2 Changes in the pile head displacements induced by partial failure in each test

Fig. 10 shows the increase in the pile head displacement induced by the partial failure

of the retaining structure in different tests. For cases with pile failure, the pile heads were

slightly displaced toward the outside excavation in tests 0-3 when the 4 IFPs (P20-23)

were kicked out completely because the soil behind the IFPs flowed into the excavation,

which reduced the total horizontal earth pressure acting on the piles and thus reduced the

axial forces of certain piles near the local failure zone, as shown in Fig. 8. Generally, the

pile head displacements were consistent with the axial force reduction phenomenon. In

engineering practice, when the retaining piles (walls) move outside the excavation, the

joints between the horizontal struts and the retaining piles will be damaged, which will

cause the struts to fall and exacerbate the progressive failure.


Page 15 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

For the large deformations of the 4 IFPs (P20-23) in test 4, the IFPs moved 24 cm

inside the excavation along the preset rupture plane, and the stress arching in the

horizontal and vertical planes (as shown in Fig. 2) induced by the soil deformation slightly

increased the pile head displacements.

For the piles that failed during cantilever excavation in test 0, the pile heads clearly
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

moved toward the inside of the excavation (Cheng et al. 2017). For cases with strut or

anchor failure, the pile head also moved inside the excavation in tests 5-7, and the

increases in the pile head displacements were clearly greater than those in the other tests

(such as test 0) because the struts or anchors undertook a large amount of horizontal load

and limited the pile head displacements. Once the horizontal retaining structures failed,

the pile head displacements increased obviously.

5. Analysis and comparison of the load transfer mechanisms in the retaining pile

failure cases

To study the influence of partial retaining pile failure on the adjacent retaining

structures and the whole retaining system, four tests (tests 1-4) are introduced in this

section. The load transfer mechanisms, including the variations in the earth pressure, the

axial forces of the struts and the internal forces of adjacent IPs caused by the failure of

IFPs, were analysed in detail based on test 1. The influence of the struts, strut elevation,

excavation depth and the initial localized large deformation of piles on the load transfer

mechanism were studied by comparing tests 0 and 2-4 with test 1.

5.1 Analysis of the load transfer mechanisms underlying test 1

5.1.1 Changes in earth pressures at depths of 6.4 m and 9.6 m

Fig. 11 shows the curves of the earth pressures acting on the piles at depths of 6.4 m

and 9.6 m after the failure of the 4 IFPs (P20-P23) in test 1. As shown in Fig. 11(a), the
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 16 of 78

increasing ratios of the earth pressure at different locations followed different loading and

unloading modes at the failure moment of the piles. The earth pressure acting on the

closest pile, i.e., P19, first increased and then decreased as the sand slid into the

excavation. The reason for the earth pressure increase was the loading of the horizontal

soil arch (Cheng et al. 2017) due to the stress redistribution of the soil pressure behind
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

the piles at the moment the piles failed, and the decrease was due to the loss of soil behind

P19 (the height of the sand loss was approximately 5.6 m). Although the sand behind P19

and P18 was missing at certain heights, the increasing ratios of the earth pressure

stabilized to approximately 2.09 and 1.96 after the collapse, respectively. Therefore, the

results proved that the loading effect of the soil arch was greater than the unloading effect

of the sand loss.

Slightly farther from the IFPs, the earth pressure acting on P16 and P14 continued to

increase until the sand was stable. The fluctuation phenomenon in these earth pressure

variation curves was also described in Cheng’s paper (Cheng et al. 2017) and can be

interpreted based on the coupling between the soil arch effect and the unloading effect.

In addition, the earth pressure acting on the distant piles (P10, P7 and P4) did not change

or increased only slightly.

The variation in the earth pressure acting on the piles at a depth of 9.6 m was similar

to that at a depth of 6.4 m, as shown in Fig. 11 (b). Due to the deeper burial depth, the

sand loss had little influence. Therefore, the loading effect of the soil arch played a

dominant role compared with the unloading effect of the sand sliding into the excavation.

Fig. 12 shows the maximum increasing ratio of the earth pressure at a depth of 6.4 m

induced by partial failure in tests 0 and 1. The increasing ratio of the earth pressure acting
Page 17 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

on piles adjacent to the IFPs (P20-P23) in test 1 was greater than that in test 0, but the

influence range of the earth pressure in test 1 was significantly smaller than that in test 0.

This result is because the horizontal struts in test 1 increased the lateral stiffness of the

retaining structure and made the braced retaining system have a much higher lateral

stiffness than the cantilever retaining system. In test 0, the soil arching effect caused by
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

partial collapse forced the IPs to move toward the excavation (Cheng et al. 2017), which

caused the additional soil pressure acting on the IPs to be redistributed and transferred to

the distant IPs. In summary, the unloading effect induced by the pile body displacement

decreased the soil pressure acting on these piles. In contrast, because of the struts, the

displacement of the IPs caused by the soil arching effect in test 1 was much smaller than

that in test 0; thus, the unloading effect induced by pile body displacement was weaker.

Therefore, the final increase in the soil pressure acting on the IPs was much greater than

that acting on the cantilever piles. Furthermore, the pile heads of some IPs adjacent to the

collapse position moved several millimetres toward the outside of the excavation, as

shown in Fig. 7 and Fig. 10, which further resulted in a greater increase in the soil pressure

acting on the IP heads.

In conclusion, the increment of the soil pressure acting on the IPs adjacent to the

collapse position was influenced by three factors: the loading effect of the soil arching

effect, the unloading effects of soil movement and the displacement of the pile. When the

pile at the foot of the soil arch has a lower lateral stiffness, the arching effect will be

significantly weakened. In addition, the IPs adjacent to the failed piles will have larger

displacements, causing the earth pressure to be transferred to more distant piles.

Consequently, the influence zone of the earth pressures in test 0 was larger than that in

test 1. Therefore, the lateral stiffness of the piles was one of the chief factors of the
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 18 of 78

different ranges of the influence of failure between the braced excavation and the

cantilever excavation.

5.1.2 Changes in the strut axial forces

Fig. 13 shows the curves of the changes in the strut axial forces in test 1. When the

IFPs (P20-P23) were broken at the preset positions, the strut axial forces of S7 and S8
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

within the failure zone decreased instantaneously. Because the waler beam could not

provide effective support for the failed piles within the failure area, the earth pressure

previously acting on the IFPs did not transfer to the waler beam. Therefore, the strut axial

forces of S7 and S8 decreased. The strut force of S6 also clearly decreased because the

load acting on the waler beam near the failure area decreased considerably. For the struts

far from the IFPs (S4 and S5), the soil arching effect increased the earth pressure acting

on the piles within the support range of S4 and S5 and thus slightly increased their strut

axial forces at first. Then, due to the unloading effect caused by the sand sliding into the

excavation, the strut forces of S4 and S5 decreased slightly. Additionally, because the

distances between struts S1-S3 and the IFPs were much larger than those between the

other struts, the strut forces increased slightly until reaching stability.

Based on the above analysis, when pile failure occurred in the retaining structure, it

caused the pile head and waler beam to move toward the active zone, as shown in Fig.

10. Therefore, the strut forces near the pile failure decreased considerably. If the

connection between the struts and the retaining structure is weak, then the struts could

drop, which is similar to the phenomenon in which the struts dropped from a waler beam

in the Xianghu station collapse of the Hangzhou metro (Zheng et al. 2011). The integrity

and redundancy of the retaining structure would be influenced, and the degree of the

excavation collapse would increase.


Page 19 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

5.1.3 Changes in the bending moments

The changes in the increasing ratios of the bending moments of pile sections 10.4 m

below the GS, which are close to the maximum bending moments of the piles, are

illustrated in Fig. 14. After partial failure of the IFPs (P20-23), piles P19-10 adjacent to

the collapse position were loaded by the soil arching effect, and the bending moments of
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

these piles increased immediately to the first peak. Then, the bending moments of P19

increased slowly to the maximum, and this process lasted approximately 9 s. Finally, due

to the unloading effect of the sand entering the excavation, a slight unloading

phenomenon was observed at P19 and P18. At piles far from the failure position, such as

P7-P4, the bending moments did not clearly change after partial failure. When the sand

behind the IFPs (P20-P23) moved inside the excavation and gradually stabilized, the

increasing ratio of the pile bending moment approached a certain value.

Under the same initial failure condition, the variations in the pile bending moment

between cantilever excavation and one-strut-retained excavation were almost the same,

as shown in Fig. 12 and Fig. 14. However, the maximum increasing ratio of the pile

closest to the partial collapse zone (P19) was the greatest at 1.20 in test 0, which was

considerably smaller than the corresponding result of 1.36 in test 1. Considering the trends

in the increase of the soil pressure acting on the IPs between the two tests, the strut-

retained excavation had a stronger lateral stiffness in test 1, and the loading effect caused

by partial failure was obvious. While cantilever excavation had a weaker lateral stiffness,

the retaining structure produced a greater displacement response for the same partial

failure condition. Therefore, the unloading effect of the greater displacement certainly

weakened the loading effect of the soil arching effect.


For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 20 of 78

After the bending moment of the piles peaked in test 1, the unloading magnitude was

much smaller than that of the cantilever pile, as shown in Fig. 15, indicating that the

unloading phenomenon of the pile bending moment is very weak. This phenomenon was

also seen in tests 1-5 and represents one of the differences between cantilever excavation

and braced excavation after the failure of piles. Furthermore, this phenomenon can be
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

interpreted by the deformation coordination effect of the waler beam supported by

horizontal struts. The failure of piles clearly leads to the soil arching effect, and the

adjacent piles will be reloaded by the deformation coordination of the waler beam during

the spread of the soil arching effect. Therefore, it is difficult to observe obvious unloading

in the braced retaining piles.

5.1.4 Load transfer coefficients of test 1 (braced pile) and test 0 (cantilever pile)

The peak increasing ratio of the bending moment in an adjacent pile induced by partial

failure was defined as the “load transfer coefficient (bending moment)” (Cheng et al.

2017), which was used to measure the change in the internal force of the piles outside the

partial failure zone. As shown in Fig. 12, the load transfer coefficients of piles P19-P16

in test 1 were higher than those in test 0 within the failure zone; however, they were lower

than those in test 0 far from the failure position because the decrease in the load transfer

coefficient was greater in test 1, i.e., the range of the influence of failure was smaller. The

reasons behind this phenomenon have been discussed in Section 5.1.1, as follows: the

braced retaining system has a much larger lateral stiffness than does the cantilever

retaining system; thus, the additional displacement of the piles induced by the soil arching

effect was smaller, and the additional soil pressure caused by the soil arching effect was

acting on only the piles close to the zone of influence of the failure, leading to a higher

load transfer coefficient (bending moment).


Page 21 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

5.2 Influence of the strut elevation on the load transfer mechanisms (comparison of

tests 2 and 1)

The difference between test 2 and test 1 was the installation elevation of the struts. In

test 2, the struts were 0.2H (H: 12 m) below the GS. When the IFPs (P20-P23) were

broken, the change in the horizontal earth pressure at a depth of 6.4 m and the strut force
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

in test 2 were similar to those in test 1 (and will not be introduced here). Fig. 16 shows

the increase ratios of the bending moments of the pile sections 10.4 m below the GS after

the failure of the IFPs in test 2. Fig. 17 shows the comparison of the load transfer

coefficients (bending moment) in tests 1 and 2.

As shown in Fig. 17, the increasing ratio of the bending moment of P19 in test 2 was

1.46, which was greater than that in test 1 (1.36). The influence range in test 2 was also

larger than that in test 1. This result is because the lateral stiffness of the retaining

structure and the magnitude of the unloading caused by the partial failure were two

important factors that significantly influenced the value of the load transfer coefficient

and the range of the load transfer. In tests 1 and 2, the increments of maximum pile

deflection were 48 mm and 37 mm from excavation depth of 3.2 m (the depth when the

struts were installed in test 2) to 12 m (final excavation depth), respectively, as shown in

Fig. 7(a). Therefore, the lateral stiffness of the retaining piles with struts installed at a

certain depth under pile head in test 2 was greater than that with struts installed at the

level of pile head in test 1. In addition, although the excavation depths in test 1 and test 2

were the same, axial force on the strut in test 2 was greater than that in test 1, as discussed

in Section 3.2. Therefore, the unloading induced by the failure of piles P20-P23 in test 2

was higher than that in test 1, causing a greater load to be transferred to the adjacent piles.

Because of the above two factors, the load transfer coefficient (bending moment) and
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 22 of 78

influence range caused by partial failure in test 2 were significantly greater than those in

test 1.

5.3 Influence of the excavation depth on the load transfer mechanisms (comparison

of tests 3 and 1)

5.3.1 Analysis of the soil pressure and load transfer coefficient (bending moment)
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

The difference between test 3 (14.4 m) and test 1 (12.0 m) was the excavation depth.

After the IFPs (P20-P23) were broken, the change in the earth pressure over time at a

depth of 6.4 m below the GS was approximately the same as that in test 1. However, the

increasing ratios of the soil pressure caused by the partial failure in test 3 were generally

greater than those in test 1, except for that of P19, as shown in Fig. 18. In the strutted pile

retaining system, the horizontal soil load supported by each strut increased with the

excavation depth. Therefore, the strut unloading induced by the failure of piles P20-P23

in test 3 was significantly greater than that in test 1. Consequently, in test 3, the load

transferred to adjacent piles was greater, and the effect of the soil arching was stronger.

Similarly, the load transfer coefficient and influence range caused by partial failure in test

3 were clearly greater than those in test 1. For P19, because the crater caused by the failure

outside the excavation was deeper in test 3, as shown in Table 4, the missing soil behind

P19 reduced the stress arch acting on P19. Therefore, the increasing ratio of the soil

pressure acting on P19 became lower than that in test 1.

5.3.2 Changes in the strut axial forces

Fig. 19 shows the changes in the increasing ratios of the forces of the 8 MSs in test 3,

which were similar to those in test 1. However, compared to test 1 and test 2, the soil

arching effect caused by the unloading in test 3 was greater and had a greater loading

effect on the struts far from the local failure position (e.g., S4 and S3).
Page 23 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Near the IFPs (P20-P23), the strut axial forces of S7 and S8 first decreased, then

increased, and ultimately decreased again. The forces acting on S7 and S8 decreased

immediately after pile failure occurred. At the same time, the soil body behind the IFPs

moved into the excavation, developing the soil arch that acted on the IPs adjacent to the

IFPs. Then, the loading of the soil arch acted on S3-S5 through coordination with the
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

waler beam, causing their axial forces to increase quickly. Subsequently, as the soil

behind the IFPs slid into the excavation, the axial forces of S7 and S8 eventually

decreased. During this process, the deformation coordination of the waler beam, the effect

of the soil arch and the unloading of the local soil mass played important roles in changing

the internal force in each component of the strutted retaining system.

5.4 Influence of large pile deformation on the load transfer mechanisms (comparison

of tests 3 and 4)

5.4.1 Changes in the earth pressure at a depth of 6.4 m

The difference between test 4 and test 3 was the state of the IFPs (P20-P23) after

receiving the signal command for IFP failure. In test 4, the IFPs were broken in the preset

section, and the upper parts of the IFPs moved 24 cm toward the excavation in the

horizontal direction; however, the upper parts of the IFPs were not completely kicked out

and fell into the excavation. Therefore, the soil behind the IFPs did not flow into the

excavation, which is unlike what occurred in tests 0-3. The state of the IFPs in test 4 was

intended to simulate unexpected large deformations in some piles.

The changes in the earth pressure over time at a depth of 6.4 m below the GS are shown

in Fig. 20. The earth pressure acting on P19 first increased, then decreased, and ultimately

increased and stabilized. First, the loading effect of the horizontal soil arching effect led

to the immediate increase of the earth pressure when the large deformation of the IFPs
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 24 of 78

occurred. Then, the soil behind the upper part of the IFPs followed the movement of the

IFPs in the horizontal direction, which decreased the earth pressure due to the soil

unloading effect of the large deformation. Finally, because of the large deformation of

the IFPs, the loading of the vertical soil arching effect led to another increase in the earth

pressure. However, the maximum increasing ratio of the earth pressure acting on the other
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

piles was clearly lower than that in test 3, as shown in Fig. 18, mainly because the soil

arching effect caused by excessively large deformation of the IFPs was weak.

5.4.2 Changes in the strut axial forces

Fig. 21 shows the changes in the increasing ratios of the MS axial forces after the large

deformation of the IFPs occurred in test 4. The horizontal axial forces of S7 and S8

immediately decreased, then increased, and gradually stabilized. The horizontal axial

forces of S6-S3 first fluctuated and then increased to stable values. The axial forces of S7

and S8 first decreased because at the moment of IFP breakage, the earth pressure acting

on the IFPs could not effectively transfer to the waler beam and S7 and S8. Finally, the

axial force of each strut increased significantly compared with that before failure because

a large soil deformation near the preset section (depth of 9.6 m) resulted in soil arching

in both the horizontal and vertical planes in the surrounding soil, as shown in Fig. 2.

The soil arch in the horizontal plane transferred the loading released by the IFPs to the

adjacent IPs and further compressed all struts through deformation coordination with the

waler beam, immediately increasing the horizontal axial force of the struts. The upper

foot of the soil arch in the vertical plane was at the waler beam, causing the earth pressure

acting on the waler beam to increase. Therefore, the large deformation of the IFPs had a

loading effect on all struts, which also led to all piles deforming toward the excavation,
Page 25 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

as shown in Fig. 10. The influence of the large deformation of the IFPs on the struts was

significantly different from that of the completely broken IFPs.

5.4.3 Changes in the bending moments of the retaining piles

As shown in Fig. 22, in test 4, although the upper and lower parts of the IFPs were not

completely separated, the partial damage led to loading due to the soil arching effect,
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

causing the bending moments of adjacent IPs to quickly peak and then stabilize. For such

a response, the retaining piles did not need to be completely broken. A large deformation

of the retaining pile body could lead to a significant soil arching effect behind the pile

wall, resulting in a redistribution of the internal forces of the retaining structure. Therefore,

in engineering practice, large deformations of retaining piles should be considered

because they are an important factor related to the progressive collapse of deep

excavations. The maximum load transfer coefficient (bending moment) caused by the

large deformation of the IFPs (P20-P23) was 1.54, while that induced by the IFPs (P20-

P23) that failed in test 3 was 1.71.

6. Analysis and comparison of the load transfer mechanisms in horizontal bracing

structure failure cases

To study the influence of horizontal bracing structure failure, such as the failure of

struts and anchors, on the adjacent retaining structure, three tests (tests 5-7) are introduced

in this section. Test 5 included the failure of 6 struts that supported 18 piles (the sequence

of strut failure was S7, S6, S5, S8, S9 and S10), and tests 6 and 7 included the failure of

9 anchors that also supported 18 piles (the sequence of anchor failure was A10, A9, A11,

A8, A12, A7, A13, A6 and A14). The influence of the excavation depth on the load

transfer is discussed in terms of tests 6 and 7.

6.1 Load transfer mechanisms under the condition of strut failure


For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 26 of 78

6.1.1 Changes in the earth pressure at a depth of 6.4 m

As shown in Fig. 23, six struts (S5-S10) were broken in test 5. The failure of the six

IFSs also led to the redistribution of the soil pressure behind the piles. The six IFSs (S5-

S10) were located between P14 and P29. Each IFS could not function, reducing the

stiffness of the corresponding position of the retaining structure and leading to an increase
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

in the horizontal displacement of the pile top toward the excavation. Then, the soil arching

effect behind the piles loaded the piles beyond the range of influence of strut failure; thus,

the earth pressure acting on these piles increased. For example, the earth pressure acting

on P10 and P4 continuously increased as each strut broke. With the increase of the number

of failed struts, a pile in the range of the influence of strut failure underwent a greater

displacement in the horizontal direction; thus, the earth pressure acting on the pile

decreased. As shown in Fig. 23, the earth pressure acting on P19 and P16 decreased

slightly as each strut failed after the failure of S5.

6.1.2 Changes in the strut axial forces

For test 5, the changes in the strut axial force caused by the successive failure of the

six struts (S5-S10) are shown in Fig. 24. S7 was broken first, and the load that it supported

was transferred to the adjacent struts due to the load transfer of the waler beam. The axial

forces of S6 and S8 (i.e., the struts nearest to S7) increased clearly. When struts S7 and

S6 were broken, the axial forces of S5 and S8 increased the most. Likewise, when the

remaining struts were successively broken, each strut transferred most of its load to the

two nearest struts, with one on each side. After the failure of strut S10, the axial force of

strut S4 adjacent to the failure zone increased to 1015.8 kN (approximately 1.99 times the

strut axial force when the excavation was finished), while the axial force of strut S3,

which was one strut farther from the failure zone, increased much less than did that of
Page 27 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

adjacent strut S4. Therefore, each strut failure will increase the load on the nearest strut

on either side, which was similar to the findings in the numerical simulations conducted

by some researchers (Choosrithong and Schweiger 2018; Goh et al. 2018). This loading

pattern is referred to as the nearest phenomenon of load transfer caused by strut failure.

When a strut was broken, its load was not transferred to many other intact struts but was
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

concentrated on the adjacent struts, increasing the axial force of some struts and leading

to further failure. Therefore, wide-ranging progressive failure of the struts might occur in

this case.

According to the survey results of the collapse accident of Singapore's Nicoll metro

excavation, a ninth-level strut failed first, which resulted in the load supported by the

eighth-level struts increasing significantly and to the struts sustaining damage. Then, a

domino effect caused the progressive failure of the struts in the excavation profile (COI.

2005; Puzrin et al. 2010; Whittle and Davies 2006). Singapore's Nicoll metro accident

was an example of the nearest phenomenon of load transfer in an excavation profile. In

consideration of this phenomenon, setting interval-strengthened struts may be an effective

measure to avoid the progressive failure of struts.

6.1.3 Changes in the bending moments of the retaining piles

As shown in Fig. 25, in test 5, the failure of strut S7 caused the bending moment of

adjacent pile P18 to decrease slightly. Subsequently, when struts S6 and S5 were broken,

the bending moments of P4 and P10 increased slightly. However, the bending moments

of piles P14-19 adjacent to the strut-failure zone decreased. When S8, S9 and S10

successively failed, the bending moments of the piles adjacent to the strut-failure zone

decreased significantly, and those of the distant piles increased slightly, as shown Fig. 26.

After the failure of S5-S10, the bending moments of piles outside the failure zone, such
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 28 of 78

as P4, P7, P10 and P12, increased, mainly due to the arching effect, as discussed in

Section 6.1.1. However, the bending moments of piles in the failure zone decreased,

especially for the piles at the central area of the failure zone, such as P18. The changes of

the bending moment of the pile in the failure zone can be interpreted as follows.

Fig. 27 shows the changes in the bending moment of P26 within the strut-failure zone
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

as the number of failed struts increased. The bending moment distribution of pile P26 was

a typical single-row strutted pile distribution before strut failure. When the struts far from

P26, namely, struts S7, S6 and S5, were successively damaged, the bending moment of

P26 slightly increased due to the soil arching effect caused by the increase in the pile

displacement within the region of struts S7-S5. When the struts close to P26, namely,

struts S8, S9 and S10, were successively broken, the maximum bending moment of the

upper part of P26 gradually decreased, while the bending moment of the lower part of

P26 gradually increased. However, in general, the absolute value of the maximum

bending moment of a pile body decreased after the failure of the struts, as shown in Fig.

25 and Fig. 27. The resulting situation can be interpreted by the force analysis of an

isolation body of P26, as shown in Fig. 28. When x ≤ 12.0 m (x is the depth below the GS

and anchor head), i.e., when point C is above point B (excavation surface), the bending

moment Mc at point C is Mc = F·x - M1 (M1 is the bending moment at point C generated

by the earth pressure in the active zone). Since the earth pressure in the active zone above

the excavation bottom decreased slightly, as shown in Fig. 29, M1 also decreased slightly.

When the strut failed, the axial strut force decreased to 0 kN. Then, the shear force in the

pile head within the anchor-failure zone, which equals the support force F of the waler

beam acting on the pile head, decreased significantly. Therefore, the influence of F·x on

Mc was greater than that of M1, and the bending moment Mc in the retaining pile above
Page 29 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

the bottom of the excavation decreased. The above analysis is a major mechanism for the

decrease of the maximum bending moment of retaining piles in the anchor-failure zone.

The influences of strut failure and pile failure on adjacent piles were significantly

different.

6.2 Load transfer mechanisms under the conditions of anchor failure and the
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

comparison with strut failure (comparison of tests 6 and 5)

6.2.1 Changes in the earth pressure at a depth of 9.6 m

As shown in Fig. 29, nine anchors (A6-A14) were broken in test 6. Each IFA failure

reduced the stiffness of the corresponding position of the retaining structure, increasing

the horizontal displacement of the pile top toward the excavation and leading to the

redistribution of the soil pressure behind the piles. Generally, the earth pressure acting on

the piles in the anchor-failure zone decreased gradually as each anchor failed, while the

earth pressure acting on the distant piles slightly increased. The location of the increase

in earth pressure was the soil arch foot. This phenomenon is similar to that of the strut

failure case, i.e., test 5.

6.2.2 Changes in the anchor axial forces

For test 6, the changes in the anchor axial forces caused by the successive failure of the

nine anchors (A6-A14) are shown in Fig. 30. After nine anchors were broken, their loads

were distributed to the adjacent anchors due to the load transfer of the waler beam and

the redistribution of the soil stress. The axial force of A15 and A5 (i.e., the anchors nearest

to the anchor-failure zone) increased clearly, as shown in Fig. 31(b). The resulting

situation was similar to that due to strut failure; that is, each anchor failure increased the

load of the nearest anchor on either side, but the load transfer coefficient (axial force) was

clearly smaller than that in the strut failure test. In particular, after 9 anchors were broken,
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 30 of 78

the load transfer coefficients (anchor forces) of A5, A4 and A3 were 1.49, 1.17, and 1.11,

respectively, as shown in Fig. 31(b). However, after 6 struts were broken, the load transfer

coefficients (strut forces) of S4 and S3 were 2.99 and 1.32, as shown in Fig. 31(a). In

addition, the range of influence of anchor failure was larger than that of strut failure, as

shown in Fig. 31. These phenomena can be interpreted by the lateral stiffness of the
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

struts/anchors and the effect of the waler beam. Because struts can provide a stronger

lateral stiffness compared to anchors, the two nearest struts will bear most of the load

released by the failure of a strut, and the distant struts will share a small percentage of the

load transferred due to the failure of the strut. However, anchors provide a weaker lateral

stiffness than do struts. Therefore, the load released by the failure of an anchor will

redistribute to more anchors through the waler beam. The higher the lateral stiffness of

the retaining structure, the larger will be the load transfer coefficient (axial force) and the

smaller will be the transfer range.

6.2.3 Changes in the bending moments of the retaining piles

As shown in Fig. 32, in test 6, the failure of anchor A10 caused the bending moment

of adjacent piles P18 and P19 to decrease very slightly. Subsequently, when anchors A9

and A11 were broken, the bending moments of P4 and P10 increased. However, the

bending moments of the piles close to the anchor-failure zone (P14-P19) decreased.

Similarly, when A8, A12, A7, A13, A6 and A14 successively failed, the bending

moments of the piles close to the anchor-failure zone decreased significantly, and those

of distant piles increased slightly because of the arching effect.

Fig. 33 shows the variation of the bending moment distribution in the pile body of P19

at the central area of the failure zone, which can also be interpreted by the mechanism of

test 5 in Section 6.2.3. Because P19 was located at the influence zone of anchor failure at
Page 31 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

all times, the strut effect of P19 provided by the anchors and waler beam gradually

decreased significantly, and then the bending moment distribution pattern changed from

the single-row strut type to the cantilever type. As the number of failed anchors increased,

the maximum bending moment, which is in the upper part of P19, gradually decreased,

while the bending moment of the lower part of P19 gradually increased. However, in
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

general, the absolute value of the maximum bending moment of a pile body decreased

after the failure of the struts.

In addition, based on Fig. 27 and Fig. 33, it can be speculated that when the failure

range of the strut or the anchor continues to increase, the bending moments in the lower

part of the piles in the failure range will increase and become the largest bending moments

in the entire pile. Simultaneously, the support force of the waler beam acting on the pile

head will decrease, which indicates that the mechanics that characterize the pile change

from single-strut mode to cantilever mode, and then the absolute value of the largest

bending moment may be larger than that before partial failure. Based on this analysis,

when the failure zone of anchors or struts is small, the load transfer coefficients (axial

forces) of adjacent anchors or struts are significantly larger than 1; however, the load

transfer coefficients (bending moment) of the piles are relatively small. Then, the

progressive failure path still follows the anchors or struts. When the failure zone of the

anchors or struts is large enough, the mechanics that characterize the piles in the failure

zone enter cantilever mode, and the load transfer coefficients (bending moments) of these

piles become very large. Then, the failure of the piles begins, which will lead to large-

scale collapse of the excavation.

6.3 Influence of the excavation depth on the load transfer mechanisms in the anchor

failure tests (comparison of tests 6 and 7)


For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 32 of 78

6.3.1 Changes in the anchor axial force

The difference between test 7 and test 6 was the excavation depth (14.4 m and 12 m,

respectively). After the IFAs (A6-A14) were broken, the changes in the anchor axial force

over time in test 7 were approximately the same as those in test 6, as shown in Fig. 31(b).

The difference in the results between test 6 and test 7 for anchor failure was in the load
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

transfer coefficients (axial forces) of adjacent anchors. For example, the load transfer

coefficients (axial forces) of A5 and A15 were 2.00 and 2.30 in test 7, while those of A5

and A15 in test 6 were 1.49 and 1.51. In the anchor-pile retaining system, the horizontal

soil load supported by each anchor increased with the excavation depth. Therefore, the

unloading effect of anchors induced by the failure of IFAs (A6-A14) in test 7 was

significantly stronger than that in test 6. Consequently, the load effect of the failed

anchors on adjacent anchors in test 7 was also stronger than that in test 6.

6.3.2 Comparison of the load transfer coefficients (bending moments) of tests 6 and 7

In test 7, the change in the pile moment caused by partial failure was similar to that in

test 6. When A6-A16 successively failed, the bending moments of the piles within and

close to the anchor-failure zone decreased significantly, and those of the distant piles

increased slightly, as shown in Fig. 32. The horizontal stiffness of the pile-anchor system

in test 7 was smaller than that in test 6, and the horizontal displacements of the waler

beam caused by the partial failure and its range in test 7 were much larger, as shown in

Fig. 10. Therefore, the range of decrease due to the bending moments in the piles

increased in test 7.

7. Conclusions

In this study, model tests of partial failure in the retaining structures of strut-pile and

anchor-pile excavations were designed and conducted. The load transfer mechanisms
Page 33 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

after different types of partial failures were analysed and compared. Based on the failure

type, the main conclusions of this research can be divided into two parts and are

summarized below.

7.1 Partial failure of the retaining piles

(1) At the same excavation depth, when certain piles failed, the bending moment
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

increasing ratios of adjacent piles in braced-pile excavation were greater than those in

cantilever-pile excavation, because the braced retaining piles had a much larger lateral

stiffness. This indicates that the same number of failed piles would more easily trigger a

progressive failure of retaining piles in braced-pile excavation.

(2) In braced-pile excavation, the partial failure of the piles caused the axial forces of

the struts in the partial failure zone to decrease significantly because the load previously

sustained by the failed piles could not transfer to the waler beam. This change led the pile

head and waler beam in the pile failure zone to deform towards outside of the excavation,

resulting in a significant reduction of the axial compressive force in the horizontal strut

and possibly of the tensile force. If the connections between the struts and the retaining

structure are weak, the struts may drop and reduce the integrity and redundancy of the

entire retaining system and even cause large-scale progressive collapse, similar to case of

the Hangzhou metro accident (Chen et al. 2013). Therefore, the strength of the

connections should be properly ensured.

(3) The magnitude of strut unloading caused by the partial failure of the retaining pile

and the lateral stiffness of the structure were two important factors that significantly

influenced the value of the load transfer coefficient and the range of the load transfer. For

braced-pile retaining systems, the factor of strut unloading is dominant. When the strut

elevation was lower, or the excavation depth was deeper, the magnitude of strut unloading
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 34 of 78

caused by the partial failure of the retaining pile was larger, and the load transfer

coefficients of the adjacent piles and the influence range were also greater. However, for

cantilever excavation, the lateral stiffness of the retaining structure may be the dominating

factor, because the load transfer coefficients decreased and the influence range increased

as the excavation depth increased.


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

(4) When large deformations occurred in certain retaining piles, it also caused a

substantial increase in the bending moments of the adjacent piles, although the maximum

load transfer coefficient was smaller than that in the pile-rupture situation. Therefore,

large deformation of some pile bodies may lead to the progressive failure of the

excavation.

7.2 Partial failure of the struts or anchors

(1) For single-level strut-pile excavation, each strut failure increased the load on the

nearest (1-2) struts at two sides but had a very limited influence on farther struts. This

loading pattern is referred to as the nearest phenomenon of load transfer caused by strut

failure, which can easily cause the progressive failure of struts. In practical engineering,

when certain struts in an excavation are in a dangerous situation, they should be reinforced

quickly, or additional struts should be installed quickly to avoid strut failure.

(2) For single-level anchor-pile excavation, the load transfer coefficient (axial force)

(1.51 in test 6) was much lower than that in the strut-failure case (2.99 in test 5). However,

the influence range of the failed anchors (3-4 anchors) was larger than that of the strut-

failure case (1-2 struts). This was because anchors provide a weaker lateral stiffness than

do struts. In addition, when the excavation was deeper, the load transfer coefficients (axial

force) of the anchors were larger, which is similar to the case for braced excavation.
Page 35 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

(3) The influences of strut and anchor failure on piles were significantly different from

to the influence of pile failure on adjacent piles. When the failure zones of anchors or

struts were not very large, the bending moments of piles in the failure zone decreased.

The potential progressive failure path only follows anchors or struts. As the number of

failed anchors or struts increases, the piles in the failure zone gradually enter cantilever
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

mode, and their bending moments first decrease and then increase to much higher values

than those before failure. Therefore, the load transfer coefficients (bending moments) of

these piles become very large, and the progressive failure path extends to other piles and

will lead to large-scale collapse of the excavation.

Acknowledgments

This work was supported by the National Key Research and Development Program of

China under grant number 2017YFC0805407, the National Natural Science Foundation

of China under grant number 41630641 and the Natural Science Foundation of Tianjin

city under grant number 18JCQNJC07900.

References

Altaee, A., and Fellenius, B. H. 1994. Physical modeling in sand. Canadian geotechnical

journal, 31(3): 420-431. doi:10.1139/t94-049.

Artola. J. 2005. A solution to the braced excavation collapse in Singapore. M.Sc. thesis,

Department of Civil and Environmental Engineering, Stevens Institute of

Technology, Boston, USA.

Bjerrum, L., and Eide, O. 1956. Stability of strutted excavations in clay. Geotechnique,

6(1): 32-47. doi: 10.1680/geot.1956.6.1.32.


For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 36 of 78

Chang, M. 2000. Basal stability analysis of braced cuts in clay. Journal of Geotechnical

& Geoenvironmental Engineering, 126(3): 276-279. doi: 10.1061/(ASCE)1090-

0241.

Chen, R. P., Li, Z. C., Chen, Y. M., Ou, C. Y., Hu, Q., and Rao, M. 2013. Failure

investigation at a collapsed deep excavation in very sensitive organic soft clay.


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

Journal of Performance of Constructed Facilities, 29(3): 04014078. doi:

10.1061/(ASCE)CF.1943-5509.0000557.

Cheng, X. S., Zheng, G., Diao, Y., Huang, T. M., Deng, C. H., Lei, Y. W., and Zhou, H.

Z. 2016. Study of the progressive collapse mechanism of excavations retained by

cantilever contiguous piles. Engineering Failure Analysis, 71: 72–89. doi:

10.1016/j.engfailanal.2016.06.011.

Cheng, X. S., Zheng, G., Diao, Y., Huang, T. M., Deng, C. H., Nie, D. Q., and Lei, Y. W.

2017. Experimental study of the progressive collapse mechanism of excavations

retained by cantilever piles. Canadian Geotechnical Journal, 54(4):574-587. doi:

10.1139/cgj-2016-0284.

Choosrithong, K., and Schweiger, H. F. 2018. Influence of Individual Strut Failure on

Performance of Deep Excavation in Soft Soil. In Proceedings of China-Europe

Conference on Geotechnical Engineering, Vienna, Austria, 16-19 August 2018. pp.

316–319. doi: 10.1007/978-3-319-97112-4_70.

COI. 2005. Report of the Committee of Inquiry into the incident at the MRT circle line

worksite that led to collapse of Nicoll Highway on 20 April 2004. Ministry of

Manpower, Singapore.
Page 37 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Corral, G., and Whittle, A.J. 2010. Re-analysis of deep excavation collapse using a

generalized effective stress soil model. In Proceedings of the Earth Retention

Conference 3, ASCE. pp. 720–731. doi:10.1061/41128(384)72.

Davies, R.V. 2007. Factors in the Nicoll highway collapse. Tunnels & Tunnelling

International, 2: 31–34.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

Gibson, A. D. 1997. Physical scale modeling of geotechnical structures at one-G. Ph.D.

thesis, California Institute of Technology.

Goh, A.T. C., and Wong, K. S. 2009. Three-dimensional analysis of strut failure for

braced excavation in clay. Southeast Asian Geotech, Soc. 40(2), 137–143.

Goh, A. T. C., Fan, Z., Liu, H.L., Zhang, W. G., and Dong, Z. 2018. Numerical Analysis

on Strut Responses Due to One-Strut Failure for Braced Excavation in Clays. In

Proceedings of the 2nd International Symposium on Asia Urban GeoEngineering,

Changsha, China, 24-27 November 2017. pp. 560-573. doi: 10.1007/978-981-10-

6632-0_43.

Haack, A. 2009. Construction of the North-South-Metro Line in Cologne and the accident

on March 3rd, 2009. In Proceedings of the International Symposium on Social

Management Systems. p. 10.

Hsieh, P. G., Ou, C. Y., and Liu, H. T. 2008. Basal heave analysis of excavations with

consideration of anisotropic undrained strength of clay. Canadian Geotechnical

Journal, 45(6), 788-799. doi: 10.1139/T08-006.

Huang, M. S., Song, X. Y., and Qin, H. L. 2008. Basal stability of braced excavations in

K0-consolidated soft clay by upper bound method. Chinese Journal of Geotechnical

Engineering, 30(2), 250-255. doi: 10.1201/9780203879986.ch117.


For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 38 of 78

Ishihara, K., and Lee, W.F. 2008. "Forensic diagnosis for sitespecific ground conditions

in deep excavations of subway constructions. In Geotechnical and geophysical site

characterization. Edited by R.Q. Coutinho and P.W. Mayne. Taylor & Francis

Group, Boca Raton, Fla. pp. 31–59.

Itoh, K., Kikkawa, N., Toyosawa, Y., Suemasa, N., and Katada, T. 2011. Failure
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

Mechanism of Anchored Retaining Wall due to the Anchor Head Itself Being

Broken. In Proceeding of Tc302 Symposium Osaka: International Symposium on

Backwards Problem in Geotechnical Engineering & Monitoring of Geo-

construction.pp.13-18. Available from http://hdl.handle.net/2433/173850.

Kempfert, H. G., and Gebreselassie, B. 2006. Excavations and Foundations in Soft Soils.

Netherlands: Springer.

Leung, C. F., Chow, Y. K., and Shen, R. F. 2000. Behavior of pile subject to excavation-

induced soil movement. Journal of Geotechnical & Geoenvironmental Engineering,

126(11): 947-954. doi:10.1061/(ASCE)1090-0241(2000)126:11(947).

Li, G. X., and Li, X. M. 2010. The shear strength in stability analysis of subway pit in

soft clay. Geotechnical Investigation & Surveying, 38(1): 1–4.

Lu, Y., and Tan, Y. 2019. Overview of Typical Excavation Failures in China, Geo-

Congress 2019, 2019: 315-332.

Luo, Z., Atamturktur, S., Cai, Y., and Hsein juang, C. 2012. Simplified Approach for

Reliability-Based Design against Basal-Heave Failure in Braced Excavations

Considering Spatial Effect. Journal of Geotechnical and Geoenvironmental

Engineering, 138(4): 441-450.

Meymand, P.J. 1998. Shaking table scale model tests of nonlinear soil-pile-superstructure

interaction in soft clay. Ph.D. thesis, University of California, Berkeley, Calif.


Page 39 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Osman, A. S., and Bolton, M. D. 2006. Ground Movement Predictions for Braced

Excavations in Undrained Clay. Journal of Geotechnical & Geoenvironmental

Engineering, 132(4), 465-477. doi: 10.1061/(ASCE)1090-0241(2006)132:4(465).

Ou, C. Y. 2006. Deep Excavation Theory and Practice. Taylor & Francis group, London,

UK.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

Pong, K. F., Foo, S. L., Chinnaswamy, C. G., Ng, C. C. D., and Chow, W. L. 2012. Design

considerations for one-strut failure according to TR26 – a practical approach for

practising engineers. The IES Journal Part A: Civil & Structural Engineering, 5(3),

166-180. doi: 10.1080/19373260.2012.700790.

Puzrin, A. M., Alonso, E. E., and Pinyol, N. M. 2010. Braced Excavation Collapse: Nicoll

Highway, Singapore. In Geomechanics of failures. Edited by A.M. Puzrin, E.E.

Alonso, and M. Nuria. Springer Verlag, the Netherlands. pp. 151–181.

Schofield, A. 1968. Wroth C. Critical State Soil Mechanics[M]. McGraw-Hill, London.

Silva, A. P. D., Festugato, L., and Masuero, J. R. 2017. A new methodology to assess the

structural safety of anchored retaining walls. Thin-Walled Structures, 117: 343-355.

doi: 10.1016/j.tws.2017.04.022.

Simoni A., Houlsby, G. T. 2006. The Direct Shear Strength and Dilatancy of Sand–gravel

Mixtures. Geotechnical & Geological Engineering, 24(3): 523-549.

Stille, H., and Broms, B. B. 1976. Load redistribution caused by anchor failures in sheet

pile walls. In Proceedings of the 6th European Conference on Soil Mechanics and

Foundation Engineering, Vienna, Austria, vol. 1.2, pp. 197–200.

Tan, Y., Jiang, W., Luo, W., Lu, Y., and Xu, C. 2018. Longitudinal Sliding Event during

Excavation of Feng-Qi Station of Hangzhou Metro Line 1: Postfailure


For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 40 of 78

Investigation. Journal of Performance of Constructed Facilities, 32(4): 04018039.

doi: 10.1061/(ASCE)CF.1943-5509.0001181.

Tan, Y., Jiang W. Z., Rui H. S., Lu, Y., and Wang, D. L. 2020. Forensic Geotechnical

Analyses on the 2009 Building-Overturning Accident in Shanghai, China: Beyond

Common Recognitions. Journal of Geotechnical & Geoenvironmental Engineering.


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

2020, 146(7): 05020005. DOI: 10.1061/(ASCE)GT.1943-5606.0002264.

Tan, Y., Wei, B., Zhou, X., and Diao, Y. P. 2015. Lessons learned from construction of

Shanghai metro stations: importance of quick excavation, prompt propping, timely

casting, and segmented construction. Journal of Performance of Constructed

Facilities, 29(4), 04014096.

TR26. 2010. Technical reference for deep excavation. Spring Singapore, Singapore.

Ukritchon, B., Whittle, A. J., and Sloan, S. W. 2003. Undrained Stability of Braced

Excavations in Clay. Journal of Geotechnical & Geoenvironmental Engineering,

129(8): 738-755. doi: 10.1061/(ASCE)1090-0241(2003)129:8(738)

Wang, W. D., Ng, C. W., Hong, Y., Hu, Y., and Li, Q. 2019. Forensic study on the

collapse of a high-rise building in Shanghai: 3D centrifuge and numerical

modelling. Géotechnique, 69(10): 847-862.

Whittle, A. J., and Davies, R. V. 2006. Nicoll Highway Collapse: Evaluation of

Geotechnical Factors Affecting Design of Excavation Support System. In

Proceedings of the International Conference on Deep Excavations, 28-30 June

2006, Singapore.

Yang, J., Luo, and X. D. 2018. The critical state friction angle of granular materials: does

it depend on grading? Acta Geotechnica, 13(3): 535-547.


Page 41 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Zhao, W., Han, J. Y., Chen, Y., Jia, P., Li, S. G., Li, Y., and Zhao, Z. 2018. A numerical

study on the influence of anchorage failure for a deep excavation retained by

anchored pile walls. Advances in Mechanical Engineering, 10(2): 1-17. doi:

10.1177/1687814018756775.

Zheng, G., Cheng, X. S., and Diao, Y. 2011. Concept and design methodology of
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

redundancy in braced excavation. Geotechnical Engineering Journal of the SEAGS

& AGSSEA, 42(3): 13–21.

List of captions

Tables

Table 1 Parameters of the sand used in the model test

Table 2 Scaling relations of 1-g physical modelling in sand (Altaee and Fellenius 1994;

Gibson 1997; Meymand 1998)

Table 3 Parameters of the piles and excavations in the prototype and model

Table 4 Sizes of the craters caused by collapses in different tests

Figures

Fig. 1. Schematic model information, including the pile, strut and anchor arrangements,

instrument locations and excavation depths (plan view from the top): (a) test 0, (b) test

1, (c) test 5, and (d) test 6.

Fig. 2. Large deformation of piles in test 4: (a) vertical soil arch and (b) horizontal soil

arch.

Fig. 3. Schematic model setup (all dimensions are in mm): (a) side elevation for the

braced pile excavation in test 1, (b) side elevation for the tied-back pile excavation in

test 6, and (c) plan view from the top for the braced pile excavation in tests 1, 3 and 5.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 42 of 78

Fig. 4. Example of an excavation model test (test 1) (IFP: initiating failure pile; IP:

intact pile; MS: monitoring strut; IS: intact strut).

Fig. 5. Device and working mechanism of the initiating failure pile (IFP).

Fig. 6. Device and working mechanism of the initiating failure strut (IFS) and initiating

failure strut (IFA): (a) excavation stage, (b) strut failure stage, (c) excavation stage, and
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

(d) anchor failure stage.

Fig. 7. Moment curves and pile deflection for tests 1 and 6: (a) test 1 and (b) test 6.

Fig. 8. Illustration of the movements of the IFPs that acted as a horizontal trapdoor and

some consequences of the collapse.

Fig. 9. Collapse scenarios: (a) illustration of the slope inside the excavation and (b)

illustration of the crater outside the excavation.

Fig. 10. Increases in the pile head displacement induced by partial failure in each test

Fig. 11. Change curves of the earth pressures acting on adjacent piles in test 1: (a)

increasing ratios of the earth pressures at a depth of 6.4 m and (b) increasing ratios of

the earth pressures at a depth of 9.6 m.

Fig. 12. Comparison of the load transfer coefficients (earth pressure and bending

moment) in test 0 and test 1.

Fig. 13. Change in the axial forces of struts caused by the IFPs in test 1.

Fig. 14. Curves of IP bending moments versus time in test 1.

Fig. 15. Moment curves of the first pile adjacent to the IFPs before and after pile failure

in tests 0 and 1: (a) test 0 and (b) test 1.

Fig. 16. Curves of IP bending moments versus time in test 2.

Fig. 17. Comparison of the load transfer coefficients (bending moment) in test 1 and test

2.
Page 43 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Fig. 18. Comparison of the load transfer coefficients (earth pressure and bending

moment) in test 1 and tests 3-4.

Fig. 19. Change in the axial forces of struts caused by the IFPs in test 3.

Fig. 20. Change in the earth pressure at a depth of 6.4 m over time in test 4.

Fig. 21. Changes in the axial forces of struts caused by the large deformation of IFPs in
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

test 4.

Fig. 22. Curves of IP bending moments versus time in test 4.

Fig. 23. Change in the earth pressure at a depth of 6.4 m versus the strut failure order in

test 5.

Fig. 24. Change in the axial forces versus the strut failure order in test 5.

Fig. 25. Change in IP bending moments versus the strut failure order in test 5.

Fig. 26. Comparison of the load transfer coefficients (bending moments) in tests 5-7.

Fig. 27. Profiles of the bending moment of IP P26 for each strut failure in test 5.

Fig. 28. Stress analysis diagram of the support pile isolation body.

Fig. 29. Changes in the earth pressure at a depth of 9.6 m versus the anchor failure order

in test 6.

Fig. 30. Changes in the anchor forces versus the anchor failure order in test 6.

Fig. 31. Comparison of the load transfer coefficients (axial force) in tests 5-7: (a) strut

axial forces in test 5 and (b) anchor axial forces in tests 6-7.

Fig. 32. Changes in IP bending moments versus the anchor failure order in test 6.

Fig. 33. Profiles of the bending moment of IP P19 versus anchor failure in tests 6-7.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 44 of 78

Table 1 Parameters of the sand used in the model test


Specific Mean Coefficient of Maximum Minimum
Friction angle
gravity grain size nonuniformity void ratio void ratio
φ (°)
Gs D50 (mm) Cu emax emin
2.67 0.23 2.25 0.85 0.43 31

Table 2 Scaling relations of 1-g physical modelling in sand (Altaee and Fellenius 1994;
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

Gibson 1997; Meymand 1998)


Prototype to
Prototype to Prototype to model
Quantity to be scaled model ratio (for
model ratio ratio (for N=n)
n=16)
Linear dimension n n 16
Area n2 n2 256
Volume n3 n3 4096
Acceleration 1 1 1
Stress N n 16
Strain 1 1 1
Displacement n n 16
Force Nn2 n3 4096
Moment Nn3 n4 65536
em=ep+ em = ep - 0.0389
Void ratio em=ep+λln(1/n)
λln(1/N) × ln(1/16)
Compressive/tensile
Nn2 n3 4096
stiffness of strut/anchor
Flexural stiffness of pile Nn4 n5 1048576
Time n1/2 n1/2 4

Table 3 Parameters of the piles and excavations in the prototype and model
Excavation Prototype Elevation of
Retaining
Test no. depth H excavation strut or Failure mode
structure
(mm) depth (m) anchor BGS
Test 0
2 IFPs (P20-P21)
(Cheng et Cantilever pile 750 12
(Symmetry)
al. 2017)
Test 1 Braced pile 750 12 0H 4 IFPs (P20-P23)
Test 2 Braced pile 750 12 0.2H 4 IFPs (P20-P23)
Test 3 Braced pile 900 14.4 0H 4 IFPs (P20-P23)
4 IFPs (P20-P23)
Test 4 Braced pile 900 14.4 0H
(Large deformation)
Test 5 Braced pile 750 12 0H 6 IFSs (S5-S10)
Test 6 Tied-back pile 750 12 0H 9 IFAs (A6-A14)
Test 7 Tied-back pile 900 14.4 0H 9 IFAs (A6-A14)
Note: IFPs-initiating failure piles; P-pile; IFSs-initiating failure struts; S-strut; IFAs-initiating failure
anchors; A-anchor; BGS-below ground surface.
Page 45 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Table 4 Sizes of the craters caused by collapses in different tests


Depth of
Length of Width of crater Pile to which the
Test No. crater
crater (cm) (cm) crater extended
(cm)
Test 0* 57.0 61.0 37.0 10
Test 1 135.6 66.0 35.0 22
Test 2 140.0 59.0 37.0 23
Test 3 156.0 71.5 45.0 25
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

*Half model.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 46 of 78

(a)
0 Pile No.: P1 P39
P1-P2: IFPs

-750
1200
Symmetrical plane
39 piles: 2 IFPs + 37 IPs
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

(b) Pile No.: P1 P39 P20-P23: IFPs


0

-750
1200

Strut No.: S1 S13 39 piles: 4 IFPs + 35 IPs; 13 struts

(c) Pile No.: P1 P39 39 piles; 13 struts: 6 IFSs + 7 ISs


0

-750
1200

Strut No.: S1 S13 S5-S10: IFSs

(d) Pile No.: P1 P38 38 piles; 19 anchors: 9 IFAs + 10 IAs


0

15°, @130
-750

Anchor No.:
1560 A1 A19 A6-A14: IFAs

Initiating-failure pile: IFP Instrumentation of MP:


Intact pile: IP
Monitoring pile: MP
Dial Intact pile
Initiating-failure strut: IFS
indicator
Monitoring strut: MS
Intact strut: IS
Earth Strain gauge
Initiating-failure anchor: IFA pressure cell
Monitoring anchor: MA
Fig. 1. Schematic model information, including the pile, strut and anchor arrangements,

instrument locations and excavation depths (plan view from the top): (a) test 0; (b) test

1; (c) test 5, and (d) test 6.


Page 47 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

(a) Waler (b)


Ground surface beam Large
Strut
deformation
of pile
Large Inside
deformation excavation
of pile
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

A A
Preset
rupture Outside
plane Main stress excavation
direction of
Main stress soil arch
direction of Excavation
soil arch bottom Planform of preset rupture plane A-A

Fig. 2. Large deformation of piles in test 4: (a) vertical soil arch and (b) horizontal soil
arch.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 48 of 78

(a) Wheel Monitoring pile


Sandbox Movement direction Rails for sandbox
of the sandbox

Dial indicator 750

Strut

600
Strain

750
Height of model: 1400
gauges
Preset

1200
rupture
plane
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

Excavation
Sand Earth bottom
pressure
cell
750
Masonry tank

Length of model: 2500

Monitoring pile
(b) Screw Dial indicator
Anchor head
GS +0(mm)

Load
cell
Strain
gauge
Anchor

750
(Steel, ø2@130)
Pulley
Earth Excavation
Pressure bottom
Sand cell
1510
-1200
Masonry 650
-1400 tank

Length of model: 2200

(c)
1710

Outside
63

Excavation
Monitoring pile for IP: MP
P20 - P23: IFPs

Initiating-failure pile: IFP


Intact pile: IP
Width of model: 2460

Instrumentation of MP:
Dial Intact
indicator pile

Earth Strain
pressure cell gauges
S13
P39

Screw Strain gauge Screw


Strut No. : S1
Pile No.: P1

Strain gauge

Masonry tank

Tempered glass window


Length of model: 2500

Fig. 3. Schematic model setup (all dimensions are in mm): (a) side elevation for the
braced pile excavation in test 1, (b) side elevation for the tied-back pile excavation in
test 6, and (c) plan view from the top for the braced pile excavation in tests 1, 3 and 5.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 49 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 50 of 78

Ground surface Waler beam Ground surface Waler beam

Strut Strut
Upper part Upper part
of pile

60 cm
of pile
Steel rod kicked out

Linear
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

bearing
120 cm

Preset Partial
rupture collapse
plane signal
Excavation Steel rod is pulled
bottom into the lower part
Lower Steel wire rope of pile
part of
pile Air cylinder Piston rod push out

Air Air
compressor compressor
Air pipe
Solenoid valve: Switch OFF Solenoid valve: Switch ON

Fig. 5. Device and working mechanism of the initiating failure pile (IFP).
Page 51 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Crank Crank
(a) Pulley (b) Pulley
Waler beam Waler beam
Strut Steel
GS +0(mm) GS +0(mm) strand
Beam Beam

Limit Strain Screw Limit


block gauge block
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

Pile Pile
-750 -750

Excavation Excavation
bottom bottom

(c) (d)
Screw Screw

Cutting
piler
Steel
strand 15° Pulley 15°
Anchor Anchor
Load
cell Pulley Load
cell
Sand Sand

Fig. 6. Device and working mechanism of the initiating failure strut (IFS) and initiating
failure anchor (IFA): (a) excavation stage, (b) strut failure stage, (c) excavation stage,
and (d) anchor failure stage.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 52 of 78

(a) Bending moment (kN·m) Deflection (mm)


0 0
-400 0 400 800 1200 -30 0 30 60 90
-1.6 -1.6
GS Strut
-3.2 -3.2
-4.8 - + -4.8
-6.4 -6.4

Burial depth (m)


Burial depth (m)

-8 -8
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

Pile
-9.6 -9.6
-12.0 m -12 .0 m
-11.2 -11.2
-12.8 Excavation bottom -12.8
-3.2 m in test 2
-14.4 -14.4
-1.6 m -3.2 m -12 .0 m in test 2
-16 -4.8 m -6.4 m -16 -1.6 m -3.2 m
-4.8 m -6.4 m
-17.6 -8.0 m -9.6 m -17.6
-8.0 m -9.6 m
-19.2 -10.4 m -12.0 m -19.2 -10.4 m -12.0 m
(b) Bending moment (kN·m) Deflection (mm)
0 0
-300 0 300 600 -20 0 20 40 60
-1.6 -1.6
GS
-3.2 -3.2
Anchor -4.8
-4.8 - +
-6.4 -6.4
Burial depth (m)
Burial depth (m)

-8 -8
Pile
-9.6 -9.6
-12.0 m -12 .0 m
-11.2 -11.2
-12.8 Excavation -12.8 Excavation bottom
bottom -14.4
-14.4
-1.6 m -3.2 m -1.6 m -3.2 m
-16 -4.8 m -6.4 m -16
-4.8 m -6.4 m
-17.6 -8.0 m -9.6 m -17.6 -8.0 m -9.6 m
-19.2 -10.4 m -12.0 m -19.2 -10.4 m -12.0 m

Fig. 7. Moment curves and pile deflection for tests 1 and 6: (a) test 1 and (b) test 6.
Page 53 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Symmetrical plane
Boundary of crater at ground surface after the collapse
Peak increasing ratio of the max. bending
moment caused by the arching effect
Residual increasing ratio of the max. bending
moment when the collapse finished 1.35 D/2
1.32
1.08 Movements of IFPs:
1.01 P14 P19
GS +0 (mm) P1 P4 P7 Trapdoor
+0 P39
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

1200

-750
S1 S4 S7 S8 S13
0.09 Residual increasing ratio of
0.10
1.12 the max. axial force when
1.01 the collapse finished
1.10 1.01
1.22
Peak increasing ratio of the max. axial
force caused by the arching effect
Test 1 (Partial failure)
Fig. 8. Illustration of the movements of the IFPs that acted as a horizontal trapdoor and
some consequences of the collapse.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

(b)
(a)

Window

Depth of the crater


Steady slope inside excavation

Length of the crater

Width of the crater

illustration of the crater outside the excavation.


IFPs

Fig. 9. Collapse scenarios: (a) illustration of the slope inside the excavation and (b)
Page 54 of 78
Page 55 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

S1 S2 S3 S4 S5 S6 S7 S8 S9 S10
-60 P1
P30

Increases in displacements (mm)


-30 A1 A6 A14
4 IFPs
0 GS Strut

30 Anchor
- +
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

Test 0: 2 IFPs
60 Test 1: 4 IFPs bottom
Test 2: 4 IFPs
90 Test 3: 4 IFPs
Test 4: 4 IFPs
120 (Large deformation)
Test 5: 6 IFSs (S5-10)
150 Test 6: 9 IFAs (A6-14)
Test 7: 9 IFAs (A6-14)
180
0 4 8 12 16 20 24 28 32
Pile No.
Fig. 10. Increases in the pile head displacement induced by partial failure in each test.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 56 of 78

(a) 3.5 Earth pressure cell


P19 P20 P23
P18 6.4 m
3.0 P16

Increase ratio of earth pressure


P14 P1 P4 P10 P14 P18
IFPs
P10 Unloading phenomena
2.5
P4 st
1 pile adjacent to partial failure (P19)
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

2.0
Pile
failure
1.5 time

1.0
st
1 pile adjacent to partial failure in Test 0
0.5
-5 0 5 10 15 20 25 30 35 40
Time (s)
(b) 3.0
P1 P4 P10 P14 P19

9.6 m
Increase ratio of earth pressure

2.5
Earth pressure cell P16 P18 P20 P23

2.0
P19 P18 P16
P14 P10 P4
1.5

1.0
Pile failure time
0.5
0 5 10 15 20 25 30 35 40
Time (s)
Fig. 11. Change curves of the earth pressures acting on adjacent piles in test 1: (a)
increasing ratios of the earth pressures at a depth of 6.4 m and (b) increasing ratios of
the earth pressures at a depth of 9.6 m.
Page 57 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

3.0 1.5
P20 P23
GS Strut
Load transfer coefficient (earth pressure)

Load transfer coefficient (bending moment)


P1 P19
IFPs
1.4
2.5 Test 1: strut elevation 0 H m ( H: excavation depth )
-12.0 m
Increase ratio of earth pressure (-6.4 m)
Increase ratio of bending moment (-10.4m) 1.3
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

2.0 Test 0 : no strut


Earth
Increase ratio of earth pressure
pressure (-6.4 m) 1.2
(-6.4 m)
Increase ratio of bending
Bending
1.5 moment (-10.4 m) moment
(-10.4 m) 1.1
IFPs
P19 P20-P23
1.0 st 1.0
1 pile adjacent to the IFPs

4 6 8 10 12 14 16 18 20 22 24
Pile No.
Fig. 12. Comparison of the load transfer coefficients (earth pressure and bending

moment) in test 0 and test 1.


Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Change in strut force (kN)

-300
-250
-200
-150
-100
-50
0
50
100
150

-5
Pile
failure

0
P1

(P20-23)
S1

5
S2

10
S3

15
S4

S5
S1
S5

Time (s)
S6

20
S8
S7
S1
S5
S6
S2
S6

25
P19
S7

30
IFPs

S7
S3
S8

S4

35
P24

S2

S8
S4

40

Fig. 13. Change in the axial forces of struts caused by the IFPs in test 1.
Page 58 of 78
Page 59 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

1.5 P1 P4 P7 P10 P14 P18 P20 P23


P4
P7 10.4 m

Increase ratio of bending moment


1.4 P10
Bending moment guage P12 P16 P19
IFPs
P12
P14
1.3 P16 Continue loading
P18 Continue unloading
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

1.2 P19

st
1.1 1 pile adjacent to the IFPs in test 0

1.0
Pile failure
P20~P23
0.9
-5 0 5 10 15 20 25 30 35 40
Time (s)
Fig. 14. Curves of IP bending moments versus time in test 1.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 60 of 78

(a) Bending moment (kN·m) (b) Bending moment (kN·m)


0 0
-800 0 800 1600 2400 -500 0 500 1000 1500
-1.6 -1.6
-3.2 Before failure
Before failure -3.2
Peak value
-4.8 Peak value -4.8 Stable value
Stable value
-6.4 -6.4
Burial depth (m)

Burial depth (m)


-8 -8
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

-9.6 -9.6
-12.0 m -12 .0 m
-11.2 -11.2
-12.8 -12.8 Excavation
-14.4 -14.4 bottom

-16 -16
-17.6 -17.6
-19.2 Test 0 -19.2 Test 1

Fig. 15. Moment curves of the first pile adjacent to the IFPs before and after pile failure
in tests 0 and 1: (a) test 0 and (b) test 1.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 61 of 78

Increase ratio of bending moment

1.0
1.2
1.4
1.6
1.8

0
10.4 m
P1

8
st
st
P4

P1

16
P12
P7

Pile failure (P20-P23)


P10

Time (s)
P4

24
P16
Bending moment guage P12
P14

P7

1 pile adjacent to the IFPs in test 1


1 pile adjacent to the IFPs in test 0

32
P18

40
P10
P16 P19 IFPs

P19
P18 P20 P23

Fig. 16. Curves of IP bending moments versus time in test 2.


48
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 62 of 78

Load transfer coefficient (bending moment)


1.6
P20 P23 GS Strut
1.5 P1 P19
IFPs
H: Excavation depth (12.0 m) -12.0 m
1.4
Test 1: Strut elevation 0 H Excavation
1.3
Test 2: Strut elevation -0.2 H bottom

Bending
1.2
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

moment
(-10.4 m)
1.1
IFPs
1.0 P19 P20~P23
st
1 pile adjacent to the IFPs
0.9
0 2 4 6 8 10 12 14 16 18 20 22 24
Pile No.

Fig. 17. Comparison of the load transfer coefficients (bending moment) in test 1 and test
2.
Page 63 of 78
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

3.0 2.0
P20 P23 GS Strut

Load transfer coefficient (bending moment)


Load transfer coefficient (earth pressure)
P1 P19
IFPs 1.8
Increase ratio of earth pressure (-6.4 m)
2.5 Test 1: 4 IFPs -12.0 m
Test 3: 4 IFPs
Test 4: 4 IFPs (large deformation) 1.6
Increase ratio of bending moment (-10.4 m)
2.0 Test 1: 4 IFPs Earth
Test 3: 4 IFPs
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

pressure 1.4
Test 4: 4 IFPs (large deformation) (-6.4 m)
Bending
1.5 moment
(-10.4 m) 1.2
IFPs
P19 P20~P23
1.0 st 1.0
1 pile adjacent to the IFPs
0 2 4 6 8 10 12 14 16 18 20 22 24
Pile No.
Fig. 18. Comparison of the load transfer coefficients (earth pressure and bending
moment) in test 1 and tests 3-4.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Increase ratio of strut force

0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0

0
P1

8
S1
S2

16
S5
S1
S3

Time (s)
24
S4

S6
S2
S5

32
S6

S7
S3
P19
S7

40
IFPs
S8

S8
S4
P24

48

Fig. 19. Change in the axial forces of struts caused by the IFPs in test 3.
Page 64 of 78
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 65 of 78

Increase ratio of earth pressure

0.6
0.8
1.0
1.2
1.4
1.6

-2 -4
6.4 m

P1

0
P4

of IFPs (P20-P23)
Large deformation

2
P7
P10

4
Time (s)
P12
P19
P14

6
P18

8
P10
P18
IFPs

10
P20 P23

P7
P14

12

Fig. 20. Change in the earth pressure at a depth of 6.4 m over time in test 4.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Increase ratio of strut force

0.0
0.3
0.6
0.9
1.2
1.5
1.8
2.1
2.4

0 -1
P1
S1

1
S2

2
S3

S4
S8

3
S4

test 4.
S5

4
Time (s)
S3
S7
S6

5
P19
S7

S2
S6

6
S8

7
P24

of IFPs (P20~P23)
Large deformation

S5

Fig. 21. Changes in the axial forces of struts caused by the large deformation of IFPs in
Page 66 of 78
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 67 of 78

Increase ratio of bending moment

0.8
1.0
1.2
1.4
1.6
1.8

-2
0
10.4 m

P1
P14
P1

2
P4

P4
P7

P16
4
Bending moment guage
P10

P7

Time (s)
P12

6
P18
P14

8
Large deformation of IFPs (P20-P23)
P10
P16 P19

P19
10
IFPs
P18 P20 P23

Fig. 22. Curves of IP bending moments versus time in test 4.


P12

12
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Increase ratio of earth pressure

0.3
0.6
0.9
1.2
1.5
1.8

m
6.4

S7

0
P1
S1

P19
P4

P14
P19
S2

S6
Failure order

40
S3

S5
P10
P18
P10

80
S4

test 5.
S5

P16

S8

Time (s)
P4

120
P16
S6

S9
S7

160
S8

P14 P16 P18 P20 P23

S10
P10
P14

200
S9
S10

P29

P4
P18

240

Fig. 23. Change in the earth pressure at a depth of 6.4 m versus the strut failure order in
Page 68 of 78
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 69 of 78

Change in strut force (kN)

-800
-400
0
400
800
1200
P1

S7

0
S1

S8

S7
S2

S7
S4
S1

S6

40
Failure order
S3

S6

S5
S8
S2
S5
S4

80
S5

S5

S8

Time (s)
S3
S6
S6

120
S7

S9

160
S8

S4

S10
S9

200
S3
S10

S2 S1
P30

240

Fig. 24. Change in the axial forces versus the strut failure order in test 5.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Increase ratio of bending moment

0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.6

m
1.4 10.4

S7

0
Strut
S1

failure
P4
P1 P4

P12
P18

S6
S2

Failure order

40
P7
S3

P7

S5
P19
P16

80
P10
S4

Bending moment guage


S5

P14

P10

S8

Time (s)
P26
P14

120
S6

S9
S7

P18 P20

160
S8

S10

200
S9

P26 P29
S10

240

Fig. 25. Change in IP bending moments versus the strut failure order in test 5.
Page 70 of 78
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 71 of 78

Load transfer coefficient (bending moment)

0.25
0.50
0.75
1.00
1.25
1.50

0
P1
A1

2
S1
S2

4
H: excavation depth
S3

6
H: 14.4 m
H: 12.0 m
H: 12.0 m
S4

A6

Test 5: 6IFSs (S5-S10),

8
Test 7: 9IFAs (A6-A14),
Test 6: 9IFAs (A6-A14),
S5

Pile No.
10
S6

12
S7

14
S8

16
S9

A14

18
S10
P30

20

Fig. 26. Comparison of the load transfer coefficients (bending moments) in tests 5-7.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record.

Burial depth (m)

-19.2
-16.0
-12.8
-9.6
-6.4
-3.2
0.0

-600
-
Outside

-400
+
GS Strut
S9
S8
S5
S6
S7

S10

bottom

-200
Depth 12m

order
Failure

0
200
Bending moment (kN·m)
400
600
bottom
Inside

Excavation
-12.0 m

800

Fig. 27. Profiles of the bending moment of IP P26 for each strut failure in test 5.
Page 72 of 78
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 73 of 78

Anchor

Excavation
Pile
A

B
C

1
A

C
F

Fig. 28. Stress analysis diagram of the support pile isolation body.

xm
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 74 of 78

1.2 A1 A2 A4 A6 A8 A10 A12 A14A15


9.6

Increase ratio of earth pressure


1.1 m
P1 P4 P10 P14 P16 P19
P4 P18 P10
1.0 P14
P16
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

0.9 Anchor failure

P19 P18 P16 P19


0.8 P14 P10 P4
Failure order
0.7 A10 A9 A11 A8 A12 A7 A13 A6 A14

0 40 80 120 160 200 240 280 320 360


Time (s)
Fig. 29. Changes in the earth pressure at a depth of 9.6 m versus the anchor failure order
in test 6.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 75 of 78

Change in anchor axial force (kN)

-400
-300
-200
-100
0
200
300
P1

0
A10
A1 A2

40
A7
A1

A12

A9
100 Anchor failure

Failure order
A4

80
A8
A2

A10 A9 A11
A11
A13
A6

120
A8
A8
A9
A3
A8

160
A14

A12
A12

Time (s)
A4
A10

200
A10

A7
A7
A15

240
A5
A12

A13
A11

280
A6
A16

A13 A6
A6
A14

320
A14
A14
A16

P32

360

Fig. 30. Changes in the anchor forces versus the anchor failure order in test 6.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 76 of 78

(a) S1 S2 S3 S4 S5 S6 S7 S8 S9 S10 S11 S12 S13

Load transfer coefficient (strut axial force)


P1 P39
3.0 Test 5
Strut failure scope
S7 Failure order
2.5 S6 - S7 S7 S6 S5 S8 S9 S10
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

S5 - S7
2.0 S5 - S8
S5 - S9
1.5 S5 - S10

1.0

0.5
0 1 2 3 4 5 6 7 8 9
Strut No.

(b) Failure order


A10 A9 A11 A8 A12 A7 A13 A6 A14

P1 P38
A1 A6 A8 A10 A12 A14 A19
2.00
Load transfer coefficient (anchor axial force)

Anchor failure scope Test 6


1.75 A10
A9 - A11
1.50 A8 - A12
A7 - A13
1.25 A6 - A14
1.00
2.5 Anchor failure scope Test 7
A10
2.0 A9 - A11
A8 - A12
1.5 A7 - A13
A6 - A14
1.0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Anchor No.
Fig. 31. Comparison of the load transfer coefficients (axial force) in tests 5-7: (a) strut
axial forces in test 5 and (b) anchor axial forces in tests 6-7.
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 77 of 78

Increase ratio of bending moment

0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4

0
m
10.4

A10
P4

40
P18
P12
A1 A2

A9
P1 P4

Failure order
Anchor failure

80
A4

A11
P7
P16
P19

120
P10

A8
A6

Bending moment guage

160
P10
P14

P14

Time (s)
A12
A8

200
A7
P19
A10

240
A13
A12

280
A6

320
A14
A14 A15

360

Fig. 32. Changes in IP bending moments versus the anchor failure order in test 6.
For personal use only. This Just-IN manuscript is the accepted manuscript prior to copy editing and page composition. It may differ from the final official version of record. Page 78 of 78

0.0
Failure
order Depth
-3.2 Depth 14.4 m
12.0 m
A10
Burial depth (m) -6.4 A9
A11
Can. Geotech. J. Downloaded from www.nrcresearchpress.com by UPPSALA UNIVERSITET on 06/19/20

A8
-9.6 A12
A7
A13 -12.0 m
-12.8 A6
A14 -14.4 m
Excavation
bottom
-16.0 Excavation
bottom

-19.2
-300 0 300 600 0 300 600 900
Bending moment (kN·m) Bending moment (kN·m)
(a) Test 6 (b) Test 7

Fig. 33 Profiles of the bending moment of IP P19 versus anchor failure in tests 6-7.

You might also like