You are on page 1of 5

Operational Planning of Inverter Control in a grid

connected Microgrid with hybrid PV and BESS


Javad Behkesh Noshahr, Babak Mohamadi Morteza Kermani Mostafa Kermani
Ardabil Province Electricity Distribution Department of Electrical Engineering Department of Astronautical, Electrical and
Company (APED Co.) IAU University of Neyshaboor, Energy Engineering (DIAEE), Sapienza
Ardabil, Iran Neyshaboor, Iran. University of Rome, Rome, Italy
{jj3307, Babak.mohamadik}@gmail.com morteza.kermani.eng@gmail.com mostafa.kermani@uniroma1.it

Abstract— Today, with the increase in electrical energy costs through a BESS, in case of the shortage, the power is provided
and the necessity to observe environmental issues, the through the network. However, with attention to size of the
development of solar energy can be observed. Currently, some PV system and BESS, the hybrid system will have the
urban and rural residential buildings use on-grid or off-grid minimum energy exchange with the network. One of the basic
Photovoltaic (PV) systems to supply electrical energy. The problems of such systems is the necessity of disconnecting the
development of electrical industry technologies also leads to the PV system and loads, when the distribution network is
capability of using Battery Energy Storage Systems (BESSs) in disconnected. This will cause an interruption in the stable
on-grid hybrid homes. One of the major advantages of the hybrid energy supply of the system [5]. In hybrid systems, the
homes with a BESS system is the capability of hybrid inverter bilateral hybrid inverters are often used. In addition to the
planning for equilibrium control of power exchange between balance of power excess and power shortage, these inverters
generation, consumption, and storage, and preventing the return
should disconnect the interface key between inverters and PV
of surplus energy to the distribution and load shift network.
However, the load and energy management in hybrid homes is so
system and connect the key between inverters and loads when
difficult and depends on many parameters. The demand profile, the distribution network is disconnected [6]. The hybrid
duration of the PV system, and BESS are among the most systems based on distributed generation (DG) units is an
important factors affecting the inverter behavior of hybrid option to implement some real microgrids such as homes or
homes. The main strategy of hybrid homes with BESS is an buildings [7-8]. The DGs integration [9-10], sizing design [11-
uninterruptible power supply with minimum power exchange 12], protection [13-14], security [15], operation modes [16],
from the distribution network. Therefore, the control and and energy management [17] are the main areas in MGs.
equilibrium of power between load, PV system, and BESS In this paper, the purpose was to simulate a model of
require accurate planning, for having a stable system load hybrid building complex with a BESS connected to the
supply, in addition to providing the BESS restrictions. In this distribution network. The consuming demand for residential
paper, using Matlab/Simulink software, a model of on-grid buildings is considered during a time variable seven-day
hybrid buildings with the BESS is simulated. period. The lowest energy consumption of each residential
unit is 1.04kW and the peak energy consumption is 1.9kW, the
Keywords— battery depth of discharge; load shift; PV system; average consumption of each residential unit per day is
on-grid hybrid homes; demand profile. 1.49kW. The energy generation of the installed PV system is
dependent on the amount of sunlight. The nominal power of a
I. INTRODUCTION PV system is 5kW, and are centrally connected to the hybrid
Today, the network Photovoltaic (PV) systems have been inverter. The maximum generation of a PV system during the
established in many small and big towns and villages in small study is 4.2kW. The depth of discharge of the BESS is
capacities from 1 to 5 kilowatts on the roof of residential and considered 60%. The control system for power balance is
commercial houses [1]. The energy exchange in these systems designed in such a way that the energy exchange between AC
is bilateral. A large part of the production of network PV network and hybrid system is minimum. The simulation
systems enters the distribution network because of imbalance results for a seven-day period show that from the total
between consumption and production loads. During the night generation of 725kWh of the PV system, 388kWh is
and certain climatic conditions, in case of lack of PV system consumed to provide energy for residential loads, and the
power generation, the requirement for load is supplied through remaining 337kWh is stored in the BESS. The BESS is also
the distribution network [2]. The BESS in the PV systems is delivered at 370kWh for supply of residential loads. In this
an appropriate solution to solve this problem [3]. The network period, the control system allowed 33kWh energy deficit from
PV systems equipped with a Battery Energy Storage Systems the network. This is approximately 4% of the total system
(BESSs) are appropriate, especially for residential houses and energy. The results also show that during battery charging, the
small commercial premises. In this method, there is a load voltage is not changed significantly.
possibility to supply the residential and commercial units
when the general network is disconnected. In the normal II. BACKUP ENERGY STORAGE SYSTEM BATTERY
conditions of such systems, the power generated by PV system Batteries play a very important role in the household
is used to supply loads and battery charging, and in case of hybrid systems. Different parameters are involved in choosing
excess generation, the surplus is injected into the network [4]. the energy storage batteries, such as life span and type of
During the night, the supply of electrical loads is carried out battery, depth of discharge (DOD%), and number of charging

978-1-7281-7455-6/20/$31.00 ©2020 IEEE

Authorized licensed use limited to: CMU Libraries - library.cmich.edu. Downloaded on August 17,2020 at 06:49:26 UTC from IEEE Xplore. Restrictions apply.
and discharging. The number of charge and discharge in III. CONTROL SYSTEM PROGRAMMING OF HYBRID INVERTER
backup BESS depends on PV system generation and demand Figure (2) shows a hybrid PV system with BESS. This
throughout the day, on the other hand, the battery DOD one of system includes a set of household loads, PV system, energy
the limitations of hybrid systems. The sufficient information storage system (battery) and hybrid inverter.
on the load profile and changes in consumption during 24 Solar System House
hours is essential to calculate the capacity of the batteries [18].
Figure 1 shows an example of the load profile and household
energy consumption over 24 hours.

Meter

Charge Controller
Hybrid Inverter
Meter Transformer

Battery Bank Utility Grid

Fig. 2. PV-BESS hybrid system.

For power exchange monitoring and measuring between


Fig. 1. Load profile sample and household energy over 24 hours. network and microarray, the bilateral measuring tools are
used. The energy consumption is also measured and recorded
by the meter. The distribution network is connected to a
The surface below the curve shows the amount of energy hybrid inverter through a coupling transformer device. The
consumed over 24 hours [19].
output voltage of the inverters is nearly sinusoidal. The PV
24 System generation voltage, and BESS charging and
Total Daily Demand = P
1
Load .dt (1) discharging are DC. A hybrid inverter is an interface between
loads, network, PV system, and BESS [23]. The overall
performance of the hybrid inverter is as follows:
Therefore, in order to determine the battery capacity [20]:
24
A: If the PV system alone can provide loads, therefore:

C Batt =
P
1
Load .dt
(2) PPV (0 < t < 24) PPV ≥ 0 − PLoad _ tot = 0 (5)
LFBatt × DOD% × VBatt
B: In addition to supply of battery, the power of the PV
LFBatt : Internal battery losses coefficient system can also charge the batteries:
DOD% : Battery depth of discharge (%) PPV (0 < t < 24) PPV ≥ 0 − PLoad _ tot − PBatt = 0 (6)
VBatt : Battery voltage (V) C: In addition to supply of load and battery, the PV system
has excess energy, and this power surplus is injected into the
Total Energy (kW.Hr/Day): Total energy consumption per day network:
CBatt : Battery capacity (A_h)
PPV (0 < t < 24) PPV ≥ 0 − PLoad _ tot − PBatt − PInjecttogrid = 0 (7)
The length of time the battery lasts [21]: D: The PV system cannot supply the power, and power
DoD% × C Batt shortage is provided through the battery:
T= (3)
I Batt PPV (0 < t < 24) PPV ≥0 − PLoad _ tot + PBatt SOCmin ≤ SOC ≤ SOCmax =0 (8)
The current that is drawn from the battery is defined as E: The PV and battery systems cannot supply the loads. In
follows [22]: this case, the power shortage is provided through the network.
I Batt = 0.1 × C Batt (4) Therefore:
The average flow rate of PV systems in Iran was not above PPV (0 < t < 24) PPV ≥0 − PLoad _ tot + PBatt SOCmin > SOC + PreciveGrid = 0 (9)
6 hours and depth of charge in the dried batteries in PV
systems is DOD=60%. F: The PV system was out of the generation, which is
provided through the batteries:

Authorized licensed use limited to: CMU Libraries - library.cmich.edu. Downloaded on August 17,2020 at 06:49:26 UTC from IEEE Xplore. Restrictions apply.
− PLoad _ tot + PBatt =0 (10) The consuming demand of the residential buildings is
SOCmin ≤ SOC ≤ SOCmax
considered over a time variable seven-day period. The lowest
G: The PV system was out of the generation, and battery energy consumption of each residential unit is 1.04kW, and
cannot provide the loads: peak of energy consumption is 1.9kW, the average
consumption of each residential unit is 1.49kW per day. The
− PLoad _ tot + PBatt SOCmin > SOC + PreciveGrid =0 (11)
overall load profile of buildings is shown in Figure 5. In
Figure (3) shows the chart of power supply of a hybrid Figure 6, the total PV power generation of PV systems over a
system in different conditions. week is shown. In Figure 7, the three-dimensional graph of
power consumption-power generation in the hybrid system is
shown. This figure indicates non-overlapping of power
consumption and power generation.
As shown in Figures (5), (6) and (7), the total demand over
a week is 758kWh, in this period, the power generation of PV
system is 725kWh. However, due to lack of overlapping in the
PV system generation and demand, a major part of the PV
system generation become useless as power inflation.

Fig. 3. Load supply chart in the hybrid system over 24 hours.

As shown in Figure 3, the loads are supplied through the


BESS system between ) 1 < t < 7 ( hours. The loads are
supplied through the PV system and storage battery between
) 7 ≤ t < 9 ( hours. During the hours ) 9 ≤ t < 15 (, the system
loads are only supplied through the PV system generation, and
excess power is discharged to the BESS. Between hours Fig. 5. Load profile and total energy of the hybrid system in a week.
) 15 ≤ t < 17 (, the loads were supplied through the PV system
and BESS. Finally, the loads are supplied through battery and
network at other times.
IV. RESULTS OF SIMULATION
The diagram of the studied on-grid hybrid system is shown
in Figure (4). This system consisted of a 20KV distribution
network, which is connected to three hybrid buildings and
microarrays through a 10KVA transformer device. Each of the
residential buildings has a PV system with nominal power of 5
kW, which is connected to a hybrid inverter intensively.

Fig. 6. Power generation of the PV system in a week.

Fig. 4. System under study.


Fig. 7. Power supply by PV system-battery.

Authorized licensed use limited to: CMU Libraries - library.cmich.edu. Downloaded on August 17,2020 at 06:49:26 UTC from IEEE Xplore. Restrictions apply.
As shown in Figure (7), the generation power of PV system, 388kWh is consumed to provide energy for residential
system is managed using the hybrid inverter control system loads, and the remaining 337kWh is stored in the BESS. The
functioning over a week. A 337kWh of energy inflation of the backup BESS also delivered 370kWh for supply of residential
PV power system has been transmitted to the BESS to be used loads. In this period, the control system allowed the supply of
at other required periods. 33kWh energy deficit from the network. This is approximately
4% of the total system energy, however, the control system
has not allowed the return of power surplus to the network. It
is also shown that the load voltage is not significantly changed
in the charging mode.

REFERENCES
[1] Sun, Q., Wu, J., Zhang, Y. et al. “Comparison of the development of
Smart Grids in China and the United Kingdom,” IEEE Trans. on
Innovative Smart Grid Technologies Europe, pp.1-6, Oct 2010.
[2] Morozumi, S., Kikuchi, S., Chiba, Y., Kishida, J., Uesaka, S., Arashiro,
Y. “Distribution technology development and demonstration projects in
Japan,” IEEE Trans. on Power and Energy Society General Meeting, pp.
1-7, July 2008.
[3] Mohsenian-Rad A. H, “Leon-Garcia A Optimal residential load control
Fig. 8. Charging mode and flowrate capacity of battery. with price prediction in real-time electricity pricing environments,”
IEEE Trans. on Smart Grid, August 2010.
[4] Vilathgamuwa, D.M., Loh, P.C., and Li, Y. “Protection of microgrids
during utility voltage sags,” IEEE Trans. on Industrial Electronics, vol.
5, pp. 1427–1436, Oct 2006.
[5] Pedrasa M., Spooner T., and MacGill I., “Coordinated scheduling of
residential distributed energy resources to optimize smart home energy
services,” IEEE Trans. on Smart Grid, vol.1, pp.134-143, July 2010.
[6] Kerekes T., Teodorescu R., Rodriguez P., Vazquez, G. and Aldabas E.,
“A New High-Efficiency Single-Phase Transformerless PV Inverter
Topology,” IEEE Trans. on Industrial Electronics, vol. 58, pp.184-191,
June 2011.
[7] Alfieri, S., Piccini, S., & Kermani, M. (2019, June). Feasibility study of
Nearly Zero Energy Building in a real Microgrid case study. In 2019
IEEE International Conference on Environment and Electrical
Engineering and 2019 IEEE Industrial and Commercial Power Systems
Europe (EEEIC/I&CPS Europe) (pp. 1-6). IEEE.
[8] Paolillo, A., Carnì, D. L., Kermani, M., Martirano, L., & Aiello, A.
(2019, June). An innovative Home and Building Automation design tool
for Nanogrids Applications. In 2019 IEEE International Conference on
Fig. 9. Three-dimensional graph of load voltage, battery charging Environment and Electrical Engineering and 2019 IEEE Industrial and
mode. Commercial Power Systems Europe (EEEIC/I&CPS Europe) (pp. 1-5).
IEEE.
In Figure (8), it is shown that state of charging (SOC%) is [9] Bagheri, M., Nurmanova, V., Abedinia, O., Naderi, M. S., Ghadimi, N.,
75 > SOC % < 85 . According to Figure (9), the load voltage & Naderi, M. S. (2018, June). Impacts of Renewable Energy Sources by
Battery Forecasting on Smart Power Systems. In 2018 IEEE
has a constant value at state of charging, and the load voltage International Conference on Environment and Electrical Engineering
changes at state of charging is 0.01%, approximately. and 2018 IEEE Industrial and Commercial Power Systems Europe
Table I provides a comparison for the energy exchange (EEEIC/I&CPS Europe) (pp. 1-6). IEEE.
between the different DG units in the MG and the main grid. [10] Bagheri, M., Nurmanova, V., Abedinia, O., Salay Naderi, M., Ghadimi,
As can be see most part of the required power for the load N., & Salay Naderi, M. (2019). Renewable energy sources and battery
forecasting effects in smart power system performance. Energies, 12(3),
demand has been supported by the PV and the BESS systems. 373.
[11] Kalesar, B. M., Rouhollahi, B., Noshahr, J. B., Tadayon, M., &
TABLE I. ENERGY EXCHANGE BETWEEN MICROARRAYS AND Kermani, M. (2018, June). Multi-Objective Fuzzy Model for Optimal
DISTRIBUTION NETWORK Siting and Sizing of DG Units to Reduce Losses Using Genetic
To\From PV Battery Grid Sum Algorithm. In 2018 IEEE International Conference on Environment and
Battery 337 0 33 370 Electrical Engineering and 2018 IEEE Industrial and Commercial Power
Grid 0 -33 0 -33 Systems Europe (EEEIC/I&CPS Europe) (pp. 1-6). IEEE.
Load 388 370 0 758 [12] Forooghi Nematollahi, A., Dadkhah, A., Asgari Gashteroodkhani, O., &
Sum 725 377 33 - Vahidi, B. (2016). Optimal sizing and siting of DGs for loss reduction
using an iterative-analytical method. Journal of Renewable and
Sustainable Energy, 8(5), 055301.
V. CONCLUSION [13] Bayati, N., Aghaee, F., & Sadeghi, S. H. H. (2019). The Adaptive and
In this paper, the programming function of a network Robust Power System Protection Schemes in the Presence of
DGs. International Journal of Renewable Energy Research
hybrid inverter of a PV-BESS was evaluated. The system (IJRER), 9(2), 732-740.
under study was simulated in the Matlab/Simulink software [14] Aghaee, F., Mahdian Dehkordi, N., Bayati, N., & Hajizadeh, A. (2019).
environment. The simulation results for a seven-day period Distributed control methods and impact of communication failure in AC
showed that from total generation of 725kWh of the PV microgrids: A comparative review. Electronics, 8(11), 1265.

Authorized licensed use limited to: CMU Libraries - library.cmich.edu. Downloaded on August 17,2020 at 06:49:26 UTC from IEEE Xplore. Restrictions apply.
[15] Teymouri, A., Mehrizi-Sani, A., & Liu, C. C. (2018, October). Cyber [19] Djamila Rekioua, Ernest Matagne, Optimization of Photovoltaic Power
security risk assessment of solar PV units with reactive power capability. Systems Modelization, Simulation and Control, 1st ed. Springer-Verlag
In IECON 2018-44th Annual Conference of the IEEE Industrial London Limited , 2012, ch. 3, pp. 108.
Electronics Society (pp. 2872-2877). IEEE. [20] S. Sumathi, L. Ashok Kumar, Solar PV and Wind Energy Conversion
[16] Javid, G., Abdeslam, D. O., & Benyoucef, D. (2018, June). Maximum Systems An Introduction to Theory, Modeling with
Power Point Tracking of PhotoVoltaic Power System with Adaptive MATLAB/SIMULINK, and the Role of Soft Computing Techniques,
Fuzzy Terminal Sliding Mode Controller. In 2018 IEEE International Springer-Verlag London Limited , 2015, ch. 8, pp. 581.
Conference on Environment and Electrical Engineering and 2018 IEEE [21] Qing-Chang Zhong and Tomas Hornik, Control of Power Inverters in
Industrial and Commercial Power Systems Europe (EEEIC/I&CPS Renewable Energy and Smart Grid Integration, 1st ed. John Wiley &
Europe) (pp. 1-6). IEEE. Sons, Ltd, 2013, ch. 1, pp. 55-56.
[17] Kermani, M., Carnì, D. L., Rotondo, S., Paolillo, A., Manzo, F., & [22] Yannick Riesen, Christophe Ballif, Nicolas Wyrsch, Control algorithm
Martirano, L. (2020). A Nearly Zero-Energy Microgrid Testbed for a residential photovoltaic system with storage, Applied Energy
Laboratory: Centralized Control Strategy Based on SCADA Vol 202, Page: 78-87, 2017
System. Energies, 13(8), 2106. [23] J. Xu, C.C. Mi, B. Cao, et al., The state of charge estimation of lithium-
[18] Anandababu, C., Fernandes, B.G., “A Novel Single-Phase ion batteries based on a proportional-Integral observer, IEEE Tans. Veh.
Transformerless Inverter for Grid-Connected Photovoltaic Systems,” Technol. 63 (May (4)) (2014) 1614–1621.
IEEE Trans. On Industrial Electronics Society, pp. 6962 – 6967, Nov
2013.

Authorized licensed use limited to: CMU Libraries - library.cmich.edu. Downloaded on August 17,2020 at 06:49:26 UTC from IEEE Xplore. Restrictions apply.

You might also like