REQUEST FOR INFORMATION

Request To : Andrew Potts and Indra Wirawan (PT.BTID)


RFI No. : /RFI/CSCEC-TATA-JO/KKBP/II/2021
Request From : Cao Lian She
Contractors :
Date of Issue : Feb 02th, 2021
Package :

Subject : Relocation MH-11 Road 1


Attachments : 1 (One) Sheets
Questions
Question Date : Reply Required by:

Relocation of MH-11 due to the previous position on the existing road


1. Do we still install it in that area ?, because the position of MH-11 is on the existing road
2. We need to relocate MH-11, advance towards DC 9 meters from the old coordinates to avoid
the existing road

Contractor CSCEC – TATA JO Signature : Date :

Response

Response by : Signature : Date :

Designer : Signature : Date :