You are on page 1of 9

Complete information is a key to success

Value Engineering
for Steel Construction
By David T. Ricker, P.E.
Figure 1: Mill Extras
(as reported by Nucor Yamato Steel)

S uccessful projects require a


team effort, with the owner, designer,
The following sections are available at the same cost for A36, A572 Gr. 50,
A992, and CSA 40.21 Gr. 350W:
fabricator and erector working W24x68-103, W24x55-62, W21x62-93, W21x44-57, W18x50-71, W18x35-
together to create the finished struc- 46, W16x67-77, W16x36-57, W16x26-31, W14x61-82, W14x43-53,
ture. Each of the key team members W14x30-38, W14x22-26, W12x53-58, W12x40-50, W12x16-22, W10x49-
have specific roles, and with these 77, W10x33-45, W10x22-30, W8x31-67, W8x24-28, W8x18-21, W6x15-
roles come responsibilities to the 25.
other team members. For other shapes, A572 Gr. 50, A992 and CSA 40.21 Gr. 350W require sur-
For example, one of the fabrica- charges as follow:
tor’s and erector’s key roles is to cor- sections to 150 lbs./ft. inclusive ..........................................$1.25/CWT
rectly interpret and comply with the all sections over 150 lbs./ft. to 300 lbs./ft. inclusive ............$2.00/CWT
designer’s instructions. In order to all section over 300 lbs./ft. ..................................................$2.25/CWT
accomplish this goal, however, (note: CWT = 100 lbs)
he/she requires loads, dimensions Minimum item quantity requirements
and member sizes to be summarized A588 or equivalent
as outlined below: Mill 1 ......................................................................................Inquire
Mill 2 ......................................................................................20 tons
• Beam end reactions for gravity, ABS-AH36 ................................................................................20 tons
axial and torsion loads, as well as Length Requirements
moments, should be shown. stock lengths 30’-80’ inclusive ......................................................none
Likewise, the designer should indi- under 30’-25’ ......................................................................$1.00/CWT
cate if live load reductions have or non-standard lengths >30’ - <80’ ........................................$0.25/CWT
Over 80’ ..............................................................................$0.25/CWT
can be taken. And, in LRFD, the Standard lengths (30’, 35’, 40’, 45’, 50’, 55’, 60’, 65’ 70’ & 80’) are available in
designer should indicate whether or bundle quantities only.
not the reactions are factored.
• Column loads—not only axial but
should be discussed at the pre-con- • If painting or galvanizing is
also shear loads at splices and at the
struction conference.) required, the fabricator/erector
base, plus any moments at beam
needs to know the specific require-
ends, brackets and splices—can be • The fabricator and erector need to ments, such as surface preparation,
shown on the column schedule. know which beams, if any, are sub- which members are to be painted,
ject to vibration loads such as from
• The designer should indicate diago- the type of paint, etc. This informa-
machine rooms and elevator beams.
nal axial loads and whether they are tion should be expressed using stan-
in tension, compression or both. The • Reactions for special load condi- dard SSPC notation.
fabricator also needs to know if tions—such as cantilevered members, • Special attention should be given to
allowable stresses can be increased two- and three-span beams, beams details where steelwork structurally
(ASD). If the designer has a prefer- with both uniform and concentrated interacts with the work of other
ence for bracing work point location loads and beams with non-uniform trades, such as web openings, support
it should be shown. snow-drift loads—should be shown. for fascia panels, support for metal
• The fabricator and erector need to • Specific column stiffener and dou- deck, etc.
know all special floor and roof loads bler plate requirements should be
and point loads for special equip- shown—including sizes and locations.
ment or service requirements such as
beams supporting construction
equipment storage areas or jump
However, designers should consider
the oftentimes more economical
option of increasing the column size
O ne of the most perplexing sit-
uations for fabricators/erectors is
cranes during erection. (Such items to eliminate the need for stiffening. when designers don’t share the infor-

Modern Steel Construction / April 2000


in the range of 50% - 75%. Full
Figure 2 composite design is often inefficient
and uneconomical. The cost of one
shear stud in place equals the cost of
approximately 10 lbs. of steel. Unless
this ratio can be attained, the addi-
tion of more studs will prove uneco-
nomical.
• Take advantage of live-load
reductions if governing codes per-
mit.
• Select optimum bay sizes. An
exhaustive study by John Ruddy,
P.E., of Structural Affiliates
International in Nashville (AISC
Engineering Journal, Vol 20, #3,
Figure 3 1983) indicated that a rectangular
bay with a length-to-width ratio of
approximately 1.25 to 1.50 was the
most efficient. The filler members
should span in the long direction
with the girder beams in the short
direction (see figure 2).
• Tailor the surface preparation
and the painting requirements to
the project conditions—do not over-
do or underdo the coating require-
ments. An extensive examination of a
multitude of aged structures with
steel frames indicates that the pres-
mation developed during the design member with the greatest impact on ence or absence of a shop primer is
process. During the design process, the economic success of the project is immaterial as long as the structural
the structural engineer develops all the designer. The team members all steel is kept dry (LRFD Specification
of the information required to fabri- live or die with the engineer’s design. Commentary Chapter M). These
cate and connect the structural steel The following is a checklist of items same studies indicate that shop
members, including loads, reactions, designers should consider while primer alone affords very little pro-
stiffening, special conditions, etc. But designing a steel project. tection if a structure develops a seri-
when it comes to the design drawing, ous leak. In recent years, the trend
• Capitalize on steel’s strengths. has gone toward not painting. There
the engineer all-to-often merely
• Good weight-to-strength ratio are many side benefits to be gained
shows the member sizes.
• Efficiency of pre-assembly. by the omission of paint—no masking
Skimping on the design drawing • Speed of delivery and erection. around bolt holes, better adhesion
always comes back to haunt the • Strength in three directions. for concrete and/or fire proofing,
designer in the form of questions, • Ease of modification/renovation. easier weldability, ease of inspection,
higher bids, change orders, arbitrat- ease of making field repairs/alter-
• A designer should keep current
ing disputes, a slower ations, etc. If shop painting is neces-
on the cost and availability of the
review/approval process and a drag- sary, bear in mind that a shop coat is
various steel products he/she pre-
ging construction schedule. If it is a by definition a temporary coat—usu-
scribes. A steel fabricator can supply
question of time, then the designer ally serving less than six months in
basic steel prices and mill extras (see
is fooling himself or herself. The duration. As such, there is little justi-
figure 1). A designer also should be
time the fabricator spends deriving fication that the coat be perfect (that
aware of where the money is spent
all of the needed information is is, of uniform thickness with no
on steel construction: approximately
passed back to the owner in the form drips, runs or sags).
30% on material, 30% on shop costs,
of higher fees. And the engineer’s • Show all necessary loads on the
30% on erection, and 10% of other
approval reviewer has to spend addi- design drawing to avoid costly over-
items such as shop drawings, painting
tional time analyzing the questions designing of connections or—worse
and shipping. Labor is more than
and change orders. yet—underdesigning. The designer
60%!
The solution is greater teamwork • Consider using partial composite who provides a complete design will
and a consciousness of the impor- design of floor beams—something find that the subsequent review and
tance of value engineering. The team approval process of shop drawings
will be much quicker and more
ositive.
• Make sure the general contractor bolt values for the pur-
or construction manager indicates pose of obtaining an Figure 4
who is responsible for any “grey extra factor of safety.
areas” such as loose lintels, masonry The trend in recent
anchors, elevator sill angles, elevator years is toward the use
sheave beams, fastenings for precast of “snug-tight” bolts
concrete spandrel beams, etc. Unless and bearing values.
the responsibility is specifically dele- • Allow the use of
gated, it is likely that the cost of tension control
these items will be included in the (twist-off) high-
bids of multiple contractors, which strength bolts. These
means the owner will pay more than bolts are as reliable as
once for the same article. other methods of mea-
• Don’t require the steel sub-con- suring bolt tension and
tractor to perform work normally save labor costs in both Figure 5
done by other trades, such as shop and field.
installing masonry anchors, ceiling • Where possible,
hangers, toilet partition supports, specify fillet welds
window wall supports, etc. rather than groove
Information required to perform this welds. Groove welds
work is often slow to develop, result- are more costly
ing in needless delay to the fabrica- because of the joint
tor. The most efficient steel jobs are preparation required
those on which the fabricator and and the generally
erector are allowed to concentrate on Figure 6
greater volume of weld
the steel frame while unencumbered (see figure 4).
by the intricacies pertinent to other
trades. This reduces coordination • Use single-pass
requirements and allows the steel welds where possible.
framework to be turned over to the This involves keeping
other trades in far less time than fillet welds to a maxi-
would otherwise be possible. mum of 5/16”.
• Consider the use of cantilevered • Favor the horizon-
rafters and purlins to save weight tal and flat welding
on roof design (see figure 3). positions. These welds
are easier and quicker
• Do not design for minimum to make and are gener-
weight alone. The savings in materi- ally of high quality
al cost will often be negated by the (see figure 5).
need for more members, more con-
nections and more costly shop work • Don’t specify more weld than is four-floor columns due to higher
and field erection. necessary. Over-welding creates wind speed and difficulties in guying.
excessive heat, which may contribute • Avoid designing column splices
• Excessively stringent mill, fabri- to warping and shrinkage of the
cation and erection tolerances at mid-story height. These are often
members resulting in costly straight- too high for the erector to reach
beyond state-of-the-art construc- ening expense.
tion practices will reduce the without rigging a float or scaffold. If
number of bidders and raise the • Grant the fabricator the option the splice can be located no higher
cost of the project. ASTM A6 toler- of eliminating some column than 5’ above the tops of the steel
ances and those established by AWS splices. The cost of one column beams, it saves the expense of the
and AISC have served the industry splice equals the cost of approxi- extra rigging and still will be in a
well for many years and should be mately 500 lbs. of A992 steel. The region of the column where bending
adhered to except under extraordi- fabricator should study the situation forces are relatively low (see figure
nary circumstances where some spe- carefully before he decides to omit 6).
cial condition dictates a more strict the column splice as the resulting
column may be too long for safe • Except where dictated by seismic
treatment. considerations, do not design col-
erection. Multi-tier columns should
• Design the proper type of high- be designed to have splices every two umn splices to “develop the full
strength bolt value. The correct or four floors. Three-floor columns bending strength of the governing
application of each type is well-docu- are to be avoided due to erection dif- column size.” Seldom is the splice
mented in the current bolt specifica- ficulties. The higher up in a tall located at the point of maximum
tions. Do not specify “slip-critical” building, the less desirable it is to use bending and seldom do the bending
stresses result in a condition that
Figure 7 Figure 8

wold require a full-strength splice. • Avoid designing heavy or awk- Stiffeners are required to prevent
The column has axial compression ward members in remote hard-to- local deformation or to transfer load
stresses. The excess capacity is allot- reach portions of the structure. from one part of a member to anoth-
ted to bending stress that occur as This may eliminate the need for larg- er (see figure 9). If the main mem-
compression in one flange and ten- er, more expensive hoisting equip- bers are capable of taking care of
sion in the other. The compression ment. themselves, then the cost of stiffeners
forces are added to each other at one can be saved.
flange while at the other flange the • Reinforce beam-web penetra-
tension force is subtracted from the tions only where necessary. It may • Avoid odd sections that may not
compression force. Seldom does this be less costly to use a beam with a be readily available or which are
other side of the column ever go into thicker web, to move the opening to seldom rolled since it could result in
tension and never into full allowable a less critical location or to change costly delays. Consult with a fabrica-
tension of the magnitude that would the proportions of the opening to tor concerning the availability of spe-
require a full-strength splice. Thus, something less demanding (see figure cific shapes.
except in high seismic construction 8). To help in designing web open- • In areas subject to snow drift
there is little justification for ever ings, AISC published Design Guide loading, arrange the purlins paral-
requiring a full-strength column #2: Design of Steel and Composite lel to the drift and space the
splice (see figure 6). Beams with Web Openings. AISC purlins closer together as the drift
also offers a software program, load increases so the same gage
• Consider using a heavier column Webopen, to help in designing web roof deck can be used throughout
shaft to eliminate the need for openings. To order AISC publications (see figure 10).
web doubler plates and/or column and software, visit www.aisc.org or
stiffeners opposite the flanges of • Space floor beams so as to avoid
call 800/644-2400 to order publica-
moment-connected beams. One the necessity for shoring during
tions and 312/670-5444 to order
pair of stiffeners installed costs the concrete pour. The cost of
software.
approximately the same as 300 lbs. of shoring is relatively expensive and
A992 steel if the stiffeners are fillet- • Allow the prudent use of over- can easily be offset by varying the
welded. If they are groove welded, sized holes and slots to facilitate span, gage or depth of the floor deck.
the cost skyrockets to the equivalent fit-up and erection. They may elim-
• Avoid the “catch-all” specifica-
of 1000 lbs. of A992 steel. The cost inate or reduce the need for costly
tion that reads something like this:
of one installed doubler plate is reaming of holes or modification of
“Fabricate and erect all steel shown
about the same as 350 lbs. of A992 connection parts in the field.
or implied necessary to complete the
steel (see figure 7). Considering that • For ordinary structures, do not steel framework.” The bids will
for an average two-floor column specify that connection material undoubtedly be padded to cover
there could be as many as four pair be of one type to the exclusion of whatever might be “implied”.
of stiffeners and two or more doubler other types. Allow the fabricator to
• Avoid the “nebulous” specifica-
plates, at least 1900 lbs. of A992 steel use his stock to good advantage.
tion calling for stiffeners, roof
could be sacrificed in order to save However, the fabricator should rec-
frames, reinforcing of beam web pen-
the time and expense of making the ognize that certain structural situa-
etrations, etc., “as required”. The
lighter shaft compliant. (For more tions require specific types of steel.
fabricator and erector are rarely fur-
information, see AISC Design Guide The designer should identify these
nished enough information at the bid
#13: Wide-Flange Column Stiffening special conditions.
stage to determine what is or is not
at Moment Connections. To order • Avoid calling for the indiscrimi- required and therefore will include
AISC publications and software, visit nate use of stiffeners. Allow partial in the bid an allowance for investi-
www.aisc.org or call 800/644-2400.) depth stiffeners where applicable. gating and furnishing the question-

Modern Steel Construction / April 2000


depths.
Figure 9
• Do not call for non-parallel chords
for “K” series joists.
• Do not specify severe top chord
slope for long-span joists and joist
girders.
• Do not call for clip angles, brackets
or any such superficial attachements
to be fastened to the joists by the
manufacturer, as this would disrupt
his normal handling and shipping
system.
• Do not specify non-standard cam-
ber (see Steel Joist Institute
Figure 10 Specifications for more information—
phone 843/626-1995; fax 843/626-
5565; web: steeljoist.org.)
• Do not specify a special joist paint,
surface preparation or method of
paint application.
• Do not specify a special paint color
other than the manufacturer’s stan-
dard (this is usually grey or reddish
brown).
• Do not prescribe a special paint
thickness.
able items whether they’re needed or • Do not specify special chord or web
not. sizes.
• Avoid overly restrictive specifi- • Do not call for a special web pro-
cations. The more restrictions listed Designing for Steel file.
in the steel specifications, the greater • Do not specify special steel materi-
the chance that no one will be able Joist Economy al. The SJI Specification permits a
to meet them all. This will eliminate broad range of acceptable material.
some competition and result in
higher bids.
• Design for duplication of beam
sizes where possible since this
T he engineer-of-record is not
expected to design steel joists or
• Do not stipulate hot-rolled or cold-
rolled material to the exclusion of
the other. The SJI Specification per-
other proprietary products such as mits both types.
results in economies of scale. For
window walls, large atrium skylights • Do not prohibit or limit the number
example, in a mezzanine the edge
or modular storage towers. However, of joist chord splices, restrict the
beams often carry less load and could
they must clearly state the project’s splice locations or require the splice
be made smaller but for the sake of
requirements regarding loads and to be made using a particular weld-
duplication make them the same.
performance to enable the joist man- ing procedure. The SJI prescribes
• Likewise, design for duplication ufacturer to produce a compliant splicing procedures that have passed
of connections. For example, if most product. the test of time with flying colors.
of the filler beams on a job can be
The key to economical steel joist • Do not call for holes in highly
connected using a four-bolt shear
design is “standardization.” Open stressed portions of joist chords.
plate but a few require only a three-
bolt shear plate, make them all four- web steel joists were originally con- • Do not call for joist top chord
bolt. This miniscule “giveaway” is ceived as single-span members carry- extensions to be too long or too
more than made up by the efficien- ing uniform loads and as such they heavily loaded. Follow manufactur-
cies of duplication—both for the shop are at their best. Joists are a standard er’s recommendations.
and field. Connection material rarely product with relatively few variables. • Do not call for concentrated loads
exceeds 5% of the job total weight. Departure from the standard will on joists that are beyond their capac-
Trying to save a tiny percentage of generally increase the cost of the ity to resist. The SJI has established
5% is not cost effective if it leads to joist. The following is a list of “do- maximum limits.
special handling, marking, sorting nots”: • Do not specify bottom-bearing joists
and other special treatment of the if underslung ends will suffice.
members in question. • Do not specify non-standard joist
Figure 11 • Do not call for cross-bridging where
the SJI Specifications permit the use
of horizontal bridging.
• Do not specify that the welds used
by the joist manufacturer be made
using a special weld process or elec-
trode.
• Do not indicate “ceiling extensions”
if the ceiling is “hung” below the
joists.
• Do not require that modest concen-
trated loads be delivered at a panel
point. A joist top chord is designed to
support a 400 lb. concentrated load
anywhere between panel points in
Figure 12: Approximate* Min. Joist Lengths addition to the normal uniform load.
There are other ways to realize
H & K Series Open Web Joists LH Series Longspans cost savings in joist construction.
Depth (in.) Min. Length* (ft.) Depth (in.) Min. Length* (ft.) Sometimes it is less expensive to use
a heavier joist if it reduces the bridg-
8 4-0 18 6-4
ing requirements (see figure 11).
10 4-6 20 7-0
Bridging installation is very labor
12 5-7 24 8-4
intensive. For example, a 12K1 joist
14 5-11 28 9-8
17’ long requires two lines of bridg-
16 6-10 32 11-0
ing whereas a 12K3 joist of the same
18 7-6 36 12-4
length requires only one line of
20 7-10 40 13-8
bridging. This is a 50% reduction in
22 8-2 44 15-0
bridging and installation and the cost
24 8-6 48 16-4
of the heavier joist is only about $3
26 8-10 52 17-8
more.
28 9-2 56 19-0
30 9-6 60 20-4 When a span is so short as to
*varies by manufacturer make it impractical or impossible to
use an open web joist, a joist substi-
tute can be used such as angles,
Figure 13 channels, small wide-flanges, HSS or
combinations thereof. Figure 12
shows approximate limitations for
minimum lengths of short joists.
These may vary among manufactur-
ers. Figure 13 shows some of the
shapes that can be utilized in place of
short joists.
Today, some manufacturers are
willing to customize their product,
often to an amazing degree.
However, for ordinary joist construc-
tion there are practical and economi-
cal limitations on the amount of cus-
tomization that can be performed on
Figure 14 a joist. If the designer sees the steel
joist becoming too complex, chances
are he or she should consider using a
wide-flange alternative.

Modern Steel Construction / April 2000


Designing for Metal Figure 15
Deck Economy

F ormed metal deck floors and


roofs play a significant role in steel
building construction. There are
enough variables in deck design to
make it important for designers to
put the right combination together to
maximize value.
Some of these variables include:
• Type (roof deck, centering,
deformed floor cell, cell deck).
• Profile (narrow, intermediate, offered by some manufacturers but rib was not considered because the
wide rib). should only be used in special cases. allowable span would have been so
• Depth. For a given span and gauge, wide-rib short that it would have required
• Gauge. deck is stronger than intermediate- many more supporting members.
• Finish. rib deck, which, in turn, is stronger
• 3”-deep deck was considered and
• Side laps. than narrow-rib deck. As a rule, all
would have allowed the span to
• End laps. things being equal thick deck costs
increase to 10’ and the deck light-
• Span and deflection. more than thin deck, and 3” deck
ened to 22 ga; however, the support-
• Fastening systems. costs more than 1-1/2” deck. Also,
ing members increased in size and
• Acoustic or non-acoustic. G90 galvanized deck generally costs
the spacing did not adapt well to the
more than G60, which costs more
chosen bay of 35’.
Roof Deck than painted roof deck. Some deck
manufacturers offer other finishes, • 20 ga deck is among the most com-
Roof deck is generally available in such as electro-galvanized, phospho- mon used, with most manufacturers
1-1/2” and 3” depths. Deeper deck is rized and galvanized/painted, which carrying a stock of 20 ga and 22 ga
available from a few manufacturers. may be cost effective. Manufacturers coils, which results in good availabili-
Deck is available in thicknesses from should be consulted regarding pric- ty and quick delivery.
16 ga through 22 ga and with paint- ing and availability. Because of the
ed, G60 galvanized or G90 galva- volatility of the deck industry, it is • Painted deck was selected because
nized finishes. Roof deck is available not recommended that a specific the interior of the building is dry,
in acoustic and non-acoustic styles, manufacturer be specified; rather, it well-ventilated and not subject to
with or without cells. Three rib pro- is recommended that the manufac- corrosive atmosphere, condensation,
files are available—narrow, interme- turer be a member in good standing humidity or any other condition that
diate and wide. Side laps are either with the Steel Deck Institute (ph: would have required a more expen-
nestable or interlocking (see figure 847-462-1930; fax: 847-462-1940; sive coating.
14). Deck ends are usually over- web: sdi.org). • The designer needed some
lapped for a minimum of 2”. Die set diaphragm strength from his deck
(swaged) ends were offered at one The following example of value
engineering illustrates how several system so he selected a deck with
time as an aid to deck nesting but nestable side laps rather than inter-
modern deck profiles are such that deck variables can be selected in
order to provide a suitable product at locking side laps. Interlocking side
this is no longer necessary. In fact, laps are normally fastened with a
there are distinct disadvantages a good price:
button-punching devices but this
regarding the erectability of deck • For the metal deck of a large ware- method is unreliable in transmitting
panels that have die set ends. The house, the designer has made several diaphragm shear forces. Nestable side
span is important because it has a efficiency and cost studies and deter- laps can be welded, screwed or pop
direct effect on several other deck mined that a wide-rib, 20 ga, 1-1/2”- riveted. In 20 and 22 ga deck, there
properties, namely the profile, gauge, deep deck on a 7’ three-span condi- is a danger of blowthroughs when
depth, stress and deflection limits. tion meets his requirements for load welding side laps, so a self-drilling
Narrow-rib deck is so inefficient carrying ability and deflection. screw system was selected. Plain
that it is seldom used today. rather than die set ends were stipu-
• Wide-rib was selected because
Intermediate-rib deck is competitive- lated since there was no reason to
intermediate-rib would have
ly priced with wide-rib deck; 24 ga require die set ends. As the probabili-
required an 18 ga thickness. Narrow-
thickness intermediate-rib deck is ty existed that the deck might have to
Figure 16
H ollow structural sections have
an advantage over wide-flange shapes
in regard to painting and fireproof-
ing, wind resistance and stiffness
about the minor axis. Additionally,
many architects prefer their aesthetic
quality.
Square, rectangular and round
HSS make economical columns.
They are an excellent choice when
stiffness about both axes is required.
They can be used as hollow members
or filled with concrete. There is no
great strength advantage to filling
small HSS with concrete; however,
for larger columns there is a distinct
advantage. For example, the design
strength of an HSS 3x3x1/4x10’ is a
little more than 10% higher when
filled with 3000 psi concrete. But the
design strength of an HSS
be laid in a patch-work manner and • Floor deck with provisions for 8.625x0.322x12’ is about 40% higher
die set ends would have created a ceiling hangers. when filled with 3000 psi concrete
severe hardship for the erectors since than unfilled.
die set deck is normally laid out end- Floor deck is available in 1-1/2”,
to-end all in one direction. 2” and 3” depths and some manufac- HSS have less surface area than
turers have special deeper decks. equivalent wide-flange members,
• Because the deck was supported by with round HSS having the least sur-
Inverted roof deck also can be used
members with relatively thick face area. For example, listed here
as a form for placing wet concrete.
flanges, it was decided that welding are the surface areas per linear foot
Floor deck is available in thicknesses
would be the most efficient manner of three common sizes:
from 16 ga to 28 ga depending on
of fastening (see figure 15). If the
the type selected. It is available in • W8x31 = 3.89 sq. ft.
supporting material had been thin-
uncoated, galvanized, painted and • HSS 8x8x1/4 = 2.60 sq. ft.
ner, screw type or power-driven fas-
certain combinations thereof, again • HSS 8.625x0.233 = 2.26 sq. ft.
teners would have been considered.
depending on the manufacturer and
As it was, the designer wisely permit- This can be a significant cost fac-
the type of deck required. Floor deck
ted all three methods in the specifi- tor if members require an exotic sur-
comes with either nestable or inter-
cation. Since the deck was thicker face coating or fireproofing.
locking side laps.
than 0.028”, weld washer were not
needed or specified. As with roof deck, cost-conscious HSS offer excellent resistance to
designers will only specify those fea- torsional forces and can be used to
Floor Deck tures deemed necessary for proper advantage to support eccentric loads
Similar economical advantages maintenance and performance and such as relieving angles for brick
can be realized in the selection of will reject unnecessary features that veneer, stone, or precast concrete
floor deck. serve no particular fea- panels (see figure 17).
ture but add to the cost
Floor deck for the support of of the project.
poured-in-place concrete is available
in several styles (see figure 16):
• Form deck (centering), which usu- Designing for
ally comes in a modified corrugat-
ed profile varying in nominal Hollow
depths from ½” to 1-1/4”;
• Composite (deformed) floor deck ; Structural Figure 17
• Cellular deck;
• Deck for use with shear studs; Section (HSS)
• Deck that cannot be used with
shear studs; Economy
• Vented or unvented floor deck;
and
Figure 18

Figure 19 as to require the fabricator to per-


form significant portions of the steel
design in order to prepare an accu-
rate cost estimate.
A complete design is the best
assurance that those who must use
that design will accurately interpret
the intent of the designer. There will
be far less chance for ambiguities,
misinterpretations, errors and/or
omissions.
David T. Ricker, P.E., began his
HSS also make efficient bracing career in the American Bridge
members. It is usually easier to hide Division of U.S. Steel and later moved
HSS diagonal bracing systems within to Berlin Steel (Berlin, CT), eventual-
interior walls than it is to conceal ly becoming the company’s chief engi-
wide-flange shapes, angles or chan- neer and then its vice president of
nels. Figure 18 shows various meth- engineering. Now retired, he lives in
ods of connecting HSS and steel pipe. Payson, AZ, and runs Javelina
They also can be combined with Explorations.
other structural shapes to produce
some startling aesthetic effects (see
figure 19).
For more information on design-
ing with HSS, AISC offers a Hollow
Structural Sections Connection
Manual (call 800/644-2400 or visit
www.aisc.org to order).

Uneconomical Design
Practices

A significant portion of a fabri-


cator’s overhead is spent on estimat-
ing. For every job, a fabricator may
prepare 20 or more unsuccessful
bids. Some recent project specifica-
tions have been written in such a way

You might also like