Platform Estimation Day FSE May June

No. Description Est Days PSP target


El. GA Detail Hand Ladder Promise 10 11 12 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6
PLATFORM & LADDER DESIGN
RDMP V Small Vessel Project
1 C-052-56 Ligth Hydrocarbon Sump Drum II +99150 1 3 1 1 5 6-Jun-2021 6-Jun-2021 D1 D1 D1 D1 D1 C S
2 C-052-54 Sour Hydrocarbon Sump Drum +98800 1 3 1 1 5 6-Jun-2021 6-Jun-2021 D3 D3 D3 D3 D3 C S
3 C-052-57 Heavy Hydrocarbon Sump Drum II +99150 1 3 1 1 5 6-Jun-2021 6-Jun-2021 D2 D2 D2 D2 D2 C S
4 C-052-52 Heavy Hydrocarbon Sump Drum I +98800 1 3 1 1 5 1-Jun-2021 1-Jun-2021 C C C C C C S
5 C-052-46 Amine Sump Drum +98800 1 3 1 1 4 28-May-2021 28-May2021 D1 D1 D1 D1 C S
6 C-052-44 Ligth Hydrocarbon Sump Drum II +98800 1 3 1 1 5 28-May-2021 31-May-21 C C C C C S

Preparation & Collect Data


7 C-052-27 LPG Amine Settler +109200 1 5 1 1 10 7-Jun-2021 6/7/2021 S

Distributed To Team
8 C-052-10-DA~C Oxidation Tank +111890 1 5 1 2 11 7-Jun-2021 6/7/2021 S
9 C-052-36A/B Feed MP Steam Heater Condensate Pots +106100 1 3 1 1 6 25-May-2021 25-May-21 D1 D1 D1 D1 D1 D1 C S

GET Contract
10 C-052-10-D4 PTU Efluent Tank +104250 1 1 1 1 4 7-Jun-2021 6/7/2021 S
11 C-052-48 Fuel Gas K.O Drum +107550 1 2 1 1
4 1-Jun-2021 6/1/2021 D3 D3 D3 D3 C S
+104950 1 3 1 1
12 C-052-41 Blowdown Collector +110800 1 2 1 1
+108250 1 3 1 1
12 25-May-2021 29-May-21 D4 D4 D4 D4 D4 D4 D4 D4 D4 D4 D4 D4 C S
+105700 1 4 1 1
+104700 1 2 1 1
13 C-052-42 MP Condensate Collector +109050 1 3 1 1
8 25-May-2021 27-May-21 D3 D3 D3 D3 D3 D3 D3 D3 C S
+105650 1 4 1 1
14 C-052-43 LP Condensate Collector +113100 1 2 1 1
+110550 1 4 1 1
28-May-2021 30-May-21 D2 D2 D2 D2 D2 D2 D2 D2 D2 D2 D2 C S
+106700 1 4 1 1 12
+105950 1 2 1 1
15 C-052-47-AB Stripper IP Condensate Pots +106300 1 3 1 1 6 1-Jun-2021 6/1/2021 S

FIRGA SENA ENGINERING


Note :
1. D1~4 Drafter
2. C = Checker
Ivan R. Nurhamsah