Professional Documents
Culture Documents
CHAPTER 10
PART 2
CONCRETE DECK SLAB DATE: 30Apr2020
TABLE OF CONTENTS - CHAPTER 10 SHEET 1 of 2
FILE NO. 10.TOC-1
TABLE OF CONTENTS – CONCRETE DECK SLAB
CHAPTER 10
PART 2
CONCRETE DECK SLAB DATE: 14Feb2020
TABLE OF CONTENTS - CHAPTER 10 SHEET 2 of 2
FILE NO. 10.TOC-2
INTRODUCTION
It is the intent of this chapter to establish the practices and specific requirements of the Structure
and Bridge Division for the design and detailing of concrete deck slabs. It will also provide
design aids and other sources of information along with cross references to other parts of this
manual to assist in the design and preparation of plans.
References to LRFD Design Specifications refer to the current AASHTO LRFD Bridge Design
Specifications, Interims, and VDOT Modifications (current IIM-S&B-80). References to standard
specifications in this chapter refer to the AASHTO Standard Specifications for Highway Bridges,
1996 including the 1997 and 1998 Interims and VDOT Modifications.
The practices and requirements set forth herein are intended to supplement or clarify the
requirements of the AASHTO specifications and to provide additional information to assist the
designer. In the event of conflict(s) between the practices and requirements set forth herein and
those contained in the AASHTO specifications, the more stringent requirements shall govern.
It is expected that the users of this chapter will adhere to the practices and requirements stated
herein.
Several major changes and/or additions to the past office practice (Part 2) are as follows:
1. Bridge Layout reference points are revised to lines thru center of bearings/ piles.
2. Updated cantilever design values for CPSR railing and added cantilever layout content.
3. Removed Continuous Deck Slab Retrofitting Existing Bridge Detail, which is addressed in
Chapter 32.
NOTE:
Due to various restrictions on placing files in this manual onto the Internet, portions of the
drawings shown do not necessarily reflect the correct line weights, line types, fonts, arrowheads,
etc. Wherever discrepancies occur, the written text shall take precedence over any of the drawn
views.
PART 2
CONCRETE DECK SLAB DATE: 31Oct2018
INTRODUCTION - CHAPTER 10 SHEET 1 of 1
FILE NO. 10.00-1
General:
A. Concrete deck slabs on bridges designed in accordance with AASHTO LRFD for HL-93
loading. Design shall be in accordance with LRFD Sections 3, 4, 5, 9, 13, and VDOT
Modifications. The empirical design method shall not be used.
Main reinforcement may be designed by use of the tables on File No. 10.01-4. This table is
based on the requirements of LRFD Design Specifications and a ratio of A’s/As = 0.5. A set of
example calculations is provided for a slab design and cantilever design in File Nos. 10.01-8
thru 10.01-11.
Distribution steel in the bottom of slabs shall be designed in accordance with LRFD Article
9.7.3.2 and office modifications. In the top of deck slabs, the minimum amount of distribution
steel shall be 50% of the amount computed for the slab bottom, but shall not exceed 12”
spacing. An example calculation is provided in File No. 10.01-12. See File No. 10.01-13 for
a summary.
B. The following shall be used for deck slabs supported by stringers, according to the c-c
stringer spacings shown:
1. For skew angles from 0° to 20°, main reinforcement shall be placed parallel to ends of
slab with truss-type slab bars alternating with straight bars top and bottom.
2. For skews over 20°, all main reinforcement shall be placed perpendicular to centerline
of bridge. Main reinforcement in the end sections shall be detailed as straight bars
top and bottom. Section of slab requiring full-length main bars shall be detailed with
truss-type bars alternating with straight bars top and bottom. Consideration should be
given to reinforcing the ends of the slab by placing additional slab bars in the vicinity
of and parallel to end diaphragms.
3. Main reinforcement bars shall be #5, distribution bars shall be #4, and reinforcing bars
in negative moment regions over piers shall typically not be greater than a #6 bar.
4. 40’ and 60’ are standard lengths for reinforcing bars. Longitudinal bars should be
detailed using a series of 40’ bars with one bar at the end to make up the remaining
length. For bridge locations where shipping to the site is not an issue, consider using
a series of 60’ bars (instead of 40’) to reduce the number of lap splices.
D. For deck slabs cast in a single pour wider than 60’ to 80’, a longitudinal or construction joint
should be considered. For deck slabs cast in a single pour wider than 80’, a longitudinal joint
shall be provided.
F. The use of lightweight concrete (LWC) in decks of bridges with span lengths 150 feet or
greater shall be investigated for cost effectiveness.
G. Refer to File No. 11.01-3 for requirements pertaining to additional longitudinal steel in the
negative moment regions of continuous steel girders.
Design assumptions:
1. S (Span Length) = center-to-center stringer/girder spacing.
2. Values given in the design table are based on the equivalent strip method. The crack
control criterion has been neglected in the design.
3. Design is applicable for decks supported on at least three stringers and having a width of
not less than 14 feet between centerlines of exterior stringers.
4. For steel beams/girders, a minimum top flange width of 12 inches is assumed.
* Design controlled by maximum spacing requirement per VDOT Modifications to LRFD.
Yield-line analysis will not be required if all four of the following requirements are met:
railing/parapet type (if any on the cantilever) is an approved VDOT crash tested system.
additional loads (i.e., soundwall, utilities, etc.) are not added to the cantilever except for
fencing as shown in BPF-series standards.
For all other cases, the cantilever deck slab shall be designed in accordance with the AASHTO
LRFD A13.4 with the revisions described herein.
For Design Case 1, the deck overhang supporting concrete parapet railings shall be designed to
resist the combined effects of tensile force T and moment Ms, and other applicable forces at the
inside face of the parapet or the gutter line, as specified as follows.
Ms = design moment in the in the deck overhang due to Ft (kip-ft/ft), not greater than 110%
of the average of Mc of the bridge railing/parapet, Mc_ave
Mc = resistance of the parapet about an axis parallel to the longitudinal axis of the bridge
(kip-ft/ft)
For the VDOT approved Kansas Corral rails, the deck overhang may be designed with the
method described above.
For the deck supporting Post-and-Beam railings, the deck overhang shall be designed in
accordance with the AASHTO LRFD A13.4.3.
Designer shall consider additional loads on the cantilever or blister. Examples include fencing,
soundwall attachments, supports for sign structures, etc.
CANTILEVER LAYOUT
The minimum deck overhang shall be 10” beyond the edge of the top flange for steel
beam/girders and 3” beyond the edge of the top flange for prestressed concrete bulb-T beams.
The maximum deck overhang shall be 0.35 x the beam/girder spacing or 4’-0”, whichever is less.
Curved girders are required when straight beams/girders cannot meet the geometric limits for the
bridge deck overhangs.
The designer shall not design deck overhang or bridge railing/parapet geometry that does not
provide a smooth, continuous alignment in meeting the allowable geometric limits provided
above. Abrupt breaks in the alignment of the bridge railing/parapets will not be allowed. To
provide a smooth transition for the bridge railing/parapet, the designer may design the overhang
to extend not more than 2” beyond the back of the bridge railing/parapet.
Flares on the inside or outside of the deck may be provided to accommodate roadway features
such as the addition of a lane or ramp. Deck overhangs must still meet the geometric limits
provided above.
Design Specifications:
AASHTO LRFD Bridge Design Specifications with current Interims and VDOT Modifications.
Data Provided:
Dead Loads:
( w )(S) 2
M =
10
(8.5" )
wdeck = × 0.150 kcf = 0.106 klf
12
ww.s. = 1 foot x 0.015 ksf = 0.015 klf
Live Loads:
Use Design Table A4-1 LRFD Specifications to compute moments based on interpolation.
(The table has been reproduced on File No. 10.01-14)
Positive Moment:
Negative Moment:
Distance from C
L girder to design section = flange width/4 = 12/4 = 3 inches
∴ Negative moment = 6.99 k-ft/ft
Mn = As fs (d – a/2)
a = (As fs) / (0.85 fc’ b)
As = 0.62 in2/ft.
b = 12 inches
d = t – cover of top bar = 8.5 – 2.5 – (0.625/2) = 5.6875 inches
(0.62 × 60 )
a = = 0.91 in.
0.85 × 4 × 12
T = AsxFy εst
εc = 0.003
c = a/β1
c/d = 1.07/5.6875 = 0.188 < 0.6 ∴ OK, strain compatibility check not required, but provided
below as an example.
εst = εc (d-c)/c
∴ #5 @ 6” spacing is OK.
Mn = As fs (d – a/2)
a = (As fs) / (0.85 fc’ b)
As = 0.62 in2/ft.
b = 12 inches
d = t – wearing surface - cover of bottom bar = 8.5 – 0.5 – 1.25 – (0.625/2) = 6.4375 inches
(0.62 × 60 )
a = = 0.91 in.
0.85 × 4 × 12
c = a/β1
c/d = 1.07/6.4375 = 0.166 < 0.6 ∴ OK, Strain compatibility check not required.
∴ #5 @ 6” spacing is OK.
After the spacing is determined for negative and positive flexure, the smaller spacing shall be
used for the transverse reinforcement.
For effective length, use S = 10’-0”. Neglect the small deduction in span for the thickness of the
web in steel beams. For prestressed beams, subtract the thickness of the web to determine the
effective length.
Steel for long. reinforcement = 0.67 x 0.62 = 0.415 in2/ft for bottom layer
= 0.5 x 0.415 = 0.208 in2/ft for top layer (controls over #4’s at 12”)
The following PART SECTION shows the steel density required in this example. See sample
sheets in Chapter 9 for typical PART SECTION that shall be shown in the contract plans.
Data taken from LRFD Design Specifications, Section 4, Appendix A4, Table A4-1
“Maximum Live Load Moments Per Unit Width, k-ft/ft”.
NOTE: Values in table include multiple presence factors and dynamic load allowance.
This section of the chapter establishes the general practices and requirements regarding the
detailing of concrete deck slabs.
The items in blocks are for the designer’s information only and are not to be placed on the plans.
See Introduction File No. 10.00-1.
All bolsters (haunches) for concrete deck slabs on concrete or steel stringers in excess of 4” in
height shall be reinforced.
All bolsters greater than 7” may require additional reinforcement and larger size(s) of bars.
Recommend spacing the U-stirrup bars for larger bolsters with the same spacing as the
transverse reinforcement.
1. DECK SLAB CONCRETE PLACEMENT SCHEDULE shall be placed on plans for all
continuous steel beam or girder spans with concrete decks.
2. Locate construction joints in the positive moment ranges near points of contraflexure and
show dimensions to indicate joints.
1. DECK SLAB CONCRETE PLACEMENT SCHEDULE shall be placed on plans for all
continuous prestressed beam spans with concrete decks.
2. Locate construction joints for closure pours as shown and show dimensions.
The following two notes shall be added to the table of elevations in the plan assembly:
Slab elevations are on top of finished roadway at faces of curbs (and median);
those shown on ____________ centerline are at point of finished grade
denoted on Transverse Section.
Points along faces of curbs (and median) are aligned (radially)(________) with
points on centerline unless otherwise shown. Straight line interpolation for
intermediate elevations on top of finished roadway may be made, in any
direction, between any two adjacent points.
At a minimum, elevations shall be shown at tenth points for spans > 100 feet and
quarter points for spans < 100 feet. Points shall be from C/L bearing to C/L bearing.
Additionally, provide elevations at end of slab.
0 .2
For vertical curvature, the limiting interval is .
M
EXAMPLE
Given:
g1 = -2.65 %
g2 = -1.56 %
LC = 400 feet
R = 5000 feet
e = 2.00 %
0 .2 0.2
l = = = 38.35 feet
M 0.00002725
R 5000
l = 0 .2 = 0.2 = 100 feet
e 0.02
A typical project will normally have a single deck plan sheet. Space permitting, other details
pertaining to the deck may be shown on this sheet. In all cases, the deck plan sheet shall contain
all of the items shown in this section. Information placed in blocks on the sample deck plan
sheets is for designer’s information only and is not to be placed on the deck plan sheet.
For major projects or long structures, the deck plan sheet may have to be extended to additional
sheets to adequately show the complete structure.
While previously, it was recommended that for repetitive spans only one deck plan needed to be
drawn for a typical unit. This practice is no longer recommended. All spans should be drawn to
simplify possible field revisions.
Deck plan sheet shall provide the following information: plan of the deck slab showing
dimensions and reinforcement, end bolster details if needed, pouring sequence, deck slab
elevations, and corner details if needed. If not shown on the deck plan sheet, these details may
be shown on additional sheets.
PART 2
CONCRETE DECK SLAB DATE: 17Dec2008
GENERAL INFORMATION SHEET 1 of 5
FILE NO. 10.05-1
FHWA FEDERAL AID STATE
SHEET
STATE
REGION ROUTE ROUTE NO.
PROJECT PROJECT
15
17
Notes:
-8"
296-SC0502 top - 295 spa. @ 5" = 122'-11" (typ. each overhang) 2•" typ.
o
1'
For spacing of SL0401 and SL0402 bars, see sheet 7.
3"
17 typ.
Detail B
8 For parapet details, see sheet 13.
13 Face of curb
-8"
-0"
on)
30-SL0401 top and
14'
Line thru center of bearings
52-SL0401 bottom
ng see
6
13'
17
Transverse Secti
Abutment A
Sta. 16+96.67 C RL0602
L Rte. 601
Sta. 15+77.33
-4"
18
For spaci
10
29'
-8"
-0"
RS0401
1'
2'
End of slab
-0"
4
Abutment A
-8"
(
10
13'
Line thru center of
14'
5 bearings Abutment B 1'-10ƒ" Face of curb
4"
Face of curb
SC0502
Detail B
3"
-8"
SB0501
52-SL0402 bottom
End of slab
1'
lap w/ SL0401
Detail A Abutment B
SC0501
149-SC0501 top and bottom - 148 spa. @ 10" = 123'-4" 4" typ.
332.05 332.07 332.36 332.72 333.07 333.41 333.75 334.41 334.73 335.05 End of slab
334.08
SC0501
Abutment A
b282-00_012.
4"
C
L Rte. 601 SB0501
2'-1‚"
332.27 332.29 332.58 332.92 333.26 333.59 333.91 334.24 334.55 334.86 335.17 Face of curb
-0"
-8"
2'
335.48 335.50
1'
RS0401
Face of curb
335.02 335.07
10 equal spaces
DETAIL B
Shown at Abutment A
14
COMMONWEALTH OF VIRGINIA
DEPARTMENT OF TRANSPORTATION
o
15
SKEW ANGLE GREATER THAN 20
MULTI-SPAN BRIDGE SHOWN OTHER TYPES OF BRIDGES SIMILIAR Notes:
For spacing of RL06 series and RS0401 bars, see sheet 14.
27-SC0503 top and bottom
26 spa. @ 7•" = 16'-3"
5-SC0504 top and bott. 26-SC0505 top and bott.
4 spa. @ 7•" = 2'-6" 25 spa. @ 7•" = 15'-7•"
-8"
Detail B
6"
11"
7•"
6"
7 7
3"
1'-8•"
1'
RL series
C
L Pier 1 C
L Pier 2
D
Detail A
-8"
-0"
1'
5
2'
Face of curb "
End of slab RS0401 •
Stage I
es bottom
7
-11"
Abutment A @
both ends)
on)
Line thru center of 1'-7" min. lap typ. 11 Line thru center of 1
20'
2'-0" min 0
bearings Abutment A bearings Abutment B 6
4"
lap typ. o Face of curb S
45
13 typ. 4 4 D E
-8"
ers)
30'
1'-2"
-10"
typ. over pi
(
End of slab
2'-0" min. Abutment B End of slab
-5"
ong skew
-2• " = 62'
Sta. 569+01.92 lap typ. 5
11'
6 18
Sta. 570+18.67
-8"
145-ES0601 @ 7• " al
53-SL0601 top (
52 spa. @ 1'
4"
12
3'-3"
I
Stage I
For spaci
-9"
3'-3"
12
DETAIL A
-8"
C
43'
54-SL04 seri
-4"
Shown at Abutment A
30'
4"
32'
(
SC, SL and ET bars not shown for clarity
SL0401
6"
3"
End of slab
11"
15'-0" 22'-0"
-8"
SL0402 7•"
7•"
3ƒ" typ. 255-SC0510 top - 254 spa. @ 7•" = 158'-9" (typ. each overhang)
"
4"
62-SC0506 top and bottom 62-SC0507 top and bottom •
6'-3" 194-SC0502 top and bottom - 193 spa. @ 7•" = 120'-7•" 3'-2" 7
Face of curb
61 spa. @ 7•" = 38'-1•" 61 spa. @ 7•" = 38'-1•" @
10
1
0
6
0
S
dgn
-0"
E
-8"
9
39'-9" 77'-0" 39'-9" RS0401
999-00_016.
2'
1'
Span a Span b Span c
8 6"
Wingwall
5 spa. @ 6"
SC0506
•" tooled radius SC0508 or
SL04 series
SC0509
2
ES0601 DETAIL B
-4"
ET0501 or
12 SC0508 (Stage I) or 12 SC0509 (Stage II) Scale: •" = 1'-0"
ET0502
3 ET0501 (Stage I) or 3 ET0502 (Stage II) @ 6" SL04 series SC, SL and ET bars not shown for clarity
2 ET0503, typ. between girders
2 ET0504, typ. each overhang 14
ET0503 or
Drip detail ET0504
see sheet 16
COMMONWEALTH OF VIRGINIA
End diaphragm DEPARTMENT OF TRANSPORTATION
4"
STRUCTURE AND BRIDGE DIVISION
2'-10"
•" expanded rubber joint filler - extend the
Back of Bearing stiffener full length of the backwall. Top of backwall
2-ET0504 2-ET0503
backwall and bottom of slab shall be finished parallel
16 SECTION D-D
to the top of slab. DECK SLAB PLAN
Scale: 1" = 1'-0"
SECTION C-C Bearing stiffeners and end diaphragm PART 2
omitted for clarity Date Plan DATE: 14Feb2020
Scale: 1" = 1'-0" No. Description Date Designed: ...........
1 Drawn: ................ SHEET 3 of 5
Scale: ‘" = 1'-0" unless otherwise noted c 2020, Commonwealth of Virginia Revisions Checked: ............
Feb. 2020 999 FILE NO. 10.05-3
FHWA FEDERAL AID STATE
SHEET
STATE
REGION ROUTE ROUTE NO.
PROJECT PROJECT
15
Notes:
17
6
slab 5
B
C of t
Rte. 652 Constr. L d en
En tm
bu
A
3‚
"t
yp of -4
"
. er B 2'
nt t p.
4 ce men ty
5 En u t "
d th
r u -2
Ab of Ab 1'
ut sl Line ngs
me a i
nt b ar
A 4 be
Detail A
Line
D
th
2"
be r
ar u )
ing ce hang 50
over
1'-
s nt .
Ab er each 41
ut of typ.
( 0+
2' me
se bars 12
-4" nt 552-SC05 op transver D ta.
A 02 top - 55 ace between t
1 eq. spaces, pl S
33
53
Detail A
-S
2
"
al
er
-S
i
L P
C
'-2
L0
"
al
l
di
ap
L0
'-0
-6"
di
31'
40
7
14
Ra
"
40
al
13
w/
Detail B
'-4
2
Ra
di
2
C
L Pi
er 1
to
1'
28
-7" m -
'4"
bo
2
Ra
SL
3
typ in. l 31' 603
ap - SL0
p
. #4 6"
04
tt
Sta bars
. 11 32
an
'
-4
"
"
al
7+4
01
om
'-2
6.
"
al
50
di
d
'-0
SL06
di
SL0401
14
03
Ra
C
13
4"
Ra
pl
C
32 SL06
ace be
32-SL0
SL0604 "
Transverse Secti
SL0604 Face of rail 6•
53-SL0401 bottom
For spaci
12
Detail B
typ. ov
Sta. 118+34.
00 603
SL0
Ra
18
604 -
tw een
6•
2"
00
03 and
" 9+54.
11
Sta.
di
1'-
al
4"
er pi
SL06 2'
-5" min. l
ng see
03 ap
to
typ. # 0604
top
6 bars SL
p
ers
12 '-6"
87
on)
al
Sp
Ra
C
str. L
. 652 Con
ong Rte
al
87' 276-SB0501 - 275 spa. @ 1-
'1"= 297-
'11" measured C
.L Measured along Rte. 652 Constr.C
L
- str
6"
e. 652 Con
Spa
n a 9-
' ong Rt
0" al
277 1-
'1" = 29
Rad
-SC0501 top and bottom - 276 spa. @
10
i
-
0'0"
al
al
Radi 12
Span b RL series
Wingwall
Note E:
2"
0"
5"
3 ET0501 @ 6"
1'-
2'-
2 ET0502, typ. between girders DECK SLAB PLAN
2 ET0503, typ. each overhang
ET bars omitted for clarity
RS
04
01
"
dgn
• "
End of slab
10
SC and SB series 1'
-2"
999-00_014.
End of slab
@ 7
•" tooled radius SL04 series
ET05 series
601
See Note E
ES0
-4"
45-
See Note E
ET0501 SL04 series
"
• "
10
1'
- SC
2" 05
@ 7
02 End of slab
End diaphragm
0"
601
Face of rail
45-
RS 4"
04
01 2
2'-10" DETAIL A
2-ET0503 2-ET0502
Back of backwall
Bearing stiffener SECTION D-D Shown at Abutment A
RL series
Scale: •" = 1'-0"
Scale: 1" = 1'-0"
Bearing stiffeners and end SB, SC and SL series
SECTION C-C omitted for clarity 14
diaphragm omitted for clarity
5"
1 Deck plans shall be drawn to a scale of sufficient size to fit the full size sheet and still be
legible when reduced to half-size. It is typical for the final drawing to be shown not to
scale due to the fact that the scale needs to be exaggerated for the end of slab bars.
2 Show additional details if needed. Corner details, end diaphragm. etc. Deck slab
elevations and pouring sequence may be shown on the DECK PLAN sheet or on a
separate sheet. For skewed bridges, adjust dimension of terminal wall extension
beyond end of slab such that the desired length of the terminal wall overhang (see
applicable terminal wall standard) is achieved.
6 Show and label CL / BL of bridge. This designation shall match that shown on the title
sheet. Do not include the word proposed.
7 Show and label CL piers(s)/bent(s). Piers/bents shall be designated from left to right
using consecutive numbers when more than one pier/bent exists, e.g., C L Pier 1/
C
L Bent 1.
8 Label spans from left to right using lower case designators, e.g., Span a, Span b.
9 Dimension span length(s) along the centerline of the baseline . This is the distance
between the face of backwall/end of slab and the CL of pier/bent, CL pier/bent, C
L to CL
pier/bent, and CL pier/bent to face of backwall/end of slab. etc.
12 Dimension the distance between End of slab and Line thru center of bearings/piles at
the intersections to CL / BL of bridge.
14 For instructions on completing the title block, see File Nos. 04.02-1 and -2.
15 For instructions on completing the project block, see File No. 04.01.
16 For instructions on completing this portion of sheet, see File No. 01.01-7.
PART 2
CONCRETE DECK SLAB DATE: 31Oct2019
CHECK LIST – DECK PLANS SHEET 5 of 5
FILE NO. 10.05-5