ID Task Task Name Duration Start Finish Predecessors Notes May 2021

Mode 19 22 25 28 01 04 07 10 13 16 19 22 25 28
1 Schedule of Commissioning 25,5 days Tue 27/04/21 Sat 22/05/21 22/05
2 Readiness of System 17 days Wed 05/05/21 Fri 21/05/21 21/05
3 Readiness of air system 1 day Wed 12/05/21 Thu 13/05/21 47SS-3 days Thermax
4 Readiness of chemical boil out 1 day Wed 12/05/21 Thu 13/05/21 47SS-3 days Thermax
5 Readiness of instrument 1 day Thu 06/05/21 Thu 06/05/21 27SS-1 day Thermax
6 Readiness of Power incoming 1 day Thu 06/05/21 Thu 06/05/21 27SS-1 day WRK- close...
7 Readiness of Power from Panel to field equipment 1 day Thu 06/05/21 Thu 06/05/21 27SS-1 day WRK
8 Readiness of control wiring (Local Control, etc) 1 day Thu 06/05/21 Thu 06/05/21 27SS-1 day WRK
9 Readiness of fuel system (conveyor, crusher, vibrating screen, etc) 1 day Wed 12/05/21 Thu 13/05/21 47SS-3 days WRK
10 Readiness of demin water 1 day Wed 12/05/21 Thu 13/05/21 47SS-3 days WRK
11 Readiness of coal 1 day Wed 12/05/21 Thu 13/05/21 47SS-3 days WRK
12 Readiness of grounding system (grounding pit, etc) 1 day Thu 06/05/21 Thu 06/05/21 27SS-1 day WRK
13 Readiness of Boiler house 1 day Wed 12/05/21 Thu 13/05/21 47SS-3 days WRK
14 Readiness of hydrant system 1 day Wed 12/05/21 Thu 13/05/21 47SS-3 days WRK
15 Readiness of bed material feeding(hopper,sand silica, chemical dosing, etc) 1 day Wed 12/05/21 Thu 13/05/21 47SS-3 days WRK
16 Readiness of lighting system on boiler house 1 day Sat 08/05/21 Sat 08/05/21 29SS-1 day WRK
17 Readiness of Panel Room (Lighning, AC, etc) 1 day Thu 06/05/21 Thu 06/05/21 27SS-1 day WRK
18 Readiness of service water (for cooling sample cooler) 1 day Wed 12/05/21 Thu 13/05/21 47SS-3 days WRK
19 Readiness of blowdown pit 1 day Wed 12/05/21 Thu 13/05/21 47SS-3 days WRK
20 Operator for Training on Site 17 days Wed 05/05/21 Fri 21/05/21 WRK
21 Mechanical, E&I Completion 6,5 days Wed 05/05/21 Tue 11/05/21 11/05
22 P&ID Checking 0,5 days Wed 05/05/21 Wed 05/05/21 Thermax
23 Check Instrument List 0,5 days Wed 05/05/21 Wed 05/05/21 22 Thermax
24 Pump Installation 0,5 days Thu 06/05/21 Thu 06/05/21 23 Thermax
25 Deaerator Installation 0,5 days Thu 06/05/21 Thu 06/05/21 23 Thermax
26 Lubrication & greasing 1 day Thu 06/05/21 Thu 06/05/21 23 Thermax
27 Panel Installation MCC + PLC (Continuity,termination) 1 day Fri 07/05/21 Fri 07/05/21 26 RFI with WRK 1 may
28 Panel Energize 1 day Sat 08/05/21 Sat 08/05/21 27 Ramadhan days (13-17 mei)
29 Damper Check (free movement check) 1 day Sun 09/05/21 Sun 09/05/21 28 Thermax
30 Earthing Check 0,5 days Mon 10/05/21 Mon 10/05/21 29 Thermax
31 Transmitter Installation (range check + orifice check) (level+pressure+flow) 0,5 days Mon 10/05/21 Mon 10/05/21 30 Thermax

32 Temperature sensor & switch check 0,5 days Tue 11/05/21 Tue 11/05/21 31 Thermax
33 Pre-Commissioning 19,5 days Tue 27/04/21 Sun 16/05/21 16/05
34 Slow firing/RDO 4 days Tue 27/04/21 Fri 30/04/21 Thermax
35 HMI checking (Installation) 1 day Tue 11/05/21 Wed 12/05/21 32 Thermax
36 MCC Panel setting (OLR + S/D timer + VFD) 0,5 days Wed 12/05/21 Wed 12/05/21 35 Thermax
37 Motor solo-run (Fan + Pump) check rotation 1 day Thu 13/05/21 Thu 13/05/21 36 Thermax
38 Damper, Control Valve & Actuator function test (airline flushing) 0,5 days Fri 14/05/21 Fri 14/05/21 37 Thermax
39 Valves & Damper Function Check 0,5 days Fri 14/05/21 Fri 14/05/21 37 Thermax
40 Valves & Damper Loop Check 0,5 days Fri 14/05/21 Fri 14/05/21 37 Thermax

Task Project Summary Manual Task Start-only Deadline

Project: commissioning schedu Split Inactive Task Duration-only Finish-only Progress


Date: Fri 23/04/21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Predecessors Notes May 2021
Mode 19 22 25 28 01 04 07 10 13 16 19 22 25 28
41 All instrument Loop Test 2 days Fri 14/05/21 Sun 16/05/21 40 Thermax
42 Instrument Range Check 1 day Fri 14/05/21 Sat 15/05/21 40 Thermax
43 Megger Test 1 day Fri 14/05/21 Sat 15/05/21 40 Thermax
44 Interlock & alarm checking 1 day Fri 14/05/21 Sat 15/05/21 40 Thermax
45 Commissioning 7 days Sat 15/05/21 Sat 22/05/21 22/05
46 Bubling Test 0,5 days Sat 15/05/21 Sat 15/05/21 44 Thermax
47 Chemical boil-out 3 days Sat 15/05/21 Tue 18/05/21 44 Thermax+WRK
48 Control system check (furnace draft, drum level, deaerator level, PRS) 0,5 days Tue 18/05/21 Tue 18/05/21 47 Thermax
49 Sub system check Pollution control) 0,5 days Tue 18/05/21 Tue 18/05/21 47 Thermax
50 Start-Up /Steam Out 0,5 days Tue 18/05/21 Tue 18/05/21 47 Thermax
51 PID Tuning 2 days Tue 18/05/21 Thu 20/05/21 47 Thermax
52 Continuous operation + monitoring (check pressure, capacity, efficiency*) 0,5 days Thu 20/05/21 Thu 20/05/21 51 Thermax
53 Setting Safety Valve with disnaker 0,5 days Fri 21/05/21 Fri 21/05/21 52 Thermax
54 Hand Over 1 day Fri 21/05/21 Sat 22/05/21 53 Thermax+WRK

Task Project Summary Manual Task Start-only Deadline

Project: commissioning schedu Split Inactive Task Duration-only Finish-only Progress


Date: Fri 23/04/21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone