1. PURPOSE,
The purpose of this Safe Work Instruction is to provide a safe system of work for all personnel
required to carry out this task. This instruction describes what must be done and how it is to be
carried out safely.
2. SCOPE,
This Safe Work Instruction shall relate to all Chichester Water Management personnel who are
required to Change deposition lines or Spigots on the OPF1 and OPF2 Tailings system at Flinders
strip 12 and 19 Tailings Storage Facilities.
3. DEFINITIONS,
“Shall”, “Must” and “Will” are mandatory.
“Should” is recommended but not mandatory.
4. AREA,
Flinders Tailing Storage Facilities.
This document is UNCONTROLLED in hard copy unless stamped and specified and managed in controlled document register
Rev Description of Rev/Comments: Prepared by Reviewed By Approved By Review Date Issue Date Page
1 Issued for Use Brad Nelson Michael Chin Chris Mill 16/02/2020 21/11/2014 1 of 9
CC-00018-WI-OP0017
Department Document Number
Chichester Water Management CC-00018-WI-OP0017
Section Title
SAFE WORK INSTRUCTION Changing Tailing Deposition Lines
6. REQUIREMENTS,
LIFE SAVING CHOICES
The twelve choices define the standards that shall be met in our workplace to ensure safe systems
of work, and to guide you in making the correct decisions. The choices you make, every single
day, are fundamental to creating a safe operation. The non-negotiable choices are.
This document is UNCONTROLLED in hard copy unless stamped and specified and managed in controlled document register
Rev Description of Rev/Comments: Prepared by Reviewed By Approved By Review Date Issue Date Page
1 Issued for Use Brad Nelson Michael Chin Chris Mill 16/02/2020 21/11/2014 2 of 9
CC-00018-WI-OP0017
Department Document Number
Chichester Water Management CC-00018-WI-OP0017
Section Title
SAFE WORK INSTRUCTION Changing Tailing Deposition Lines
7. DESCRIPTION OF WORK,
The Flinders Below Water Table TSF has 2 main Deposition lines. OPF1 is capable of depositing into
Flinders strip 19 and Flinders strip 12 whilst OPF 2, has 4x spigot off take that deposit into Flinders strip
19.
The OPF 2 line has 4 evenly spaced spigots to allows 1 main deposition line for even deposition or
“beaching” of the tailings around the TSF. Monitoring of the beaching is important and if done correctly
will push the supernatant pond towards the decant position.
This document is UNCONTROLLED in hard copy unless stamped and specified and managed in controlled document register
Rev Description of Rev/Comments: Prepared by Reviewed By Approved By Review Date Issue Date Page
1 Issued for Use Brad Nelson Michael Chin Chris Mill 16/02/2020 21/11/2014 3 of 9
CC-00018-WI-OP0017
Department Document Number
Chichester Water Management CC-00018-WI-OP0017
Section Title
SAFE WORK INSTRUCTION Changing Tailing Deposition Lines
Job Steps
No.
Hazards Controls Image or Diagram
7.1 Create a clear plan for the Task. Insert Image/s here
• There must always be a
• Insufficient minimum of 2 individuals
Personnel to or Team members to
Conduct Task. complete the task.
• Each person should have
a handheld two-way Tetra
radio for positive
communications during
the task. Contact OPF
• Poor control rooms to advise of
Communication. a deposition line or spigot
change. Confirm flow and
density of tailings.
• Before work can begin,
the team members
carrying out the task
• Incorrect Planning. should take the time to
discuss the task and
create a clear plan,
complete a take 5 or Take
control as a minimum risk
assessment.
• Confirm with on shift
supervisor that the
proposed new spigot
location has been flushed
• Miss correctly prior to
Communication. changing spigots.
This document is UNCONTROLLED in hard copy unless stamped and specified and managed in controlled document register
Rev Description of Rev/Comments: Prepared by Reviewed By Approved By Review Date Issue Date Page
1 Issued for Use Brad Nelson Michael Chin Chris Mill 16/02/2020 21/11/2014 4 of 9
CC-00018-WI-OP0017
Department Document Number
Chichester Water Management CC-00018-WI-OP0017
Section Title
SAFE WORK INSTRUCTION Changing Tailing Deposition Lines
Job Steps
No.
Hazards Controls Image or Diagram
7.2 Inspect Tailing infrastructure
prior to changing spigots.
• Damage to • Before any system
Infrastructure changes are carried
out, operators are to
inspect the tailings
line and spigots for
any damages or faults
within the system.
• An inspection of the
• Stored energy air actuated gate
release. valves is to be carried
out at the NEW
location and the
exiting location. If
any faults are found
works are to STOP,
and team is to notify
the supervisor.
• Incorrect • Confirm with on shift
depositing location supervisor NEW
location for
deposition.
This document is UNCONTROLLED in hard copy unless stamped and specified and managed in controlled document register
Rev Description of Rev/Comments: Prepared by Reviewed By Approved By Review Date Issue Date Page
1 Issued for Use Brad Nelson Michael Chin Chris Mill 16/02/2020 21/11/2014 5 of 9
CC-00018-WI-OP0017
Department Document Number
Chichester Water Management CC-00018-WI-OP0017
Section Title
SAFE WORK INSTRUCTION Changing Tailing Deposition Lines
Job Steps
No.
Hazards Controls Image or Diagram
7.3 Set up and change to new Retaining pin in gate on air actuated valve
Deposition point.
This document is UNCONTROLLED in hard copy unless stamped and specified and managed in controlled document register
Rev Description of Rev/Comments: Prepared by Reviewed By Approved By Review Date Issue Date Page
1 Issued for Use Brad Nelson Michael Chin Chris Mill 16/02/2020 21/11/2014 6 of 9
CC-00018-WI-OP0017
Department Document Number
Chichester Water Management CC-00018-WI-OP0017
Section Title
SAFE WORK INSTRUCTION Changing Tailing Deposition Lines
Job Steps
No.
Hazards Controls Image or Diagram
This document is UNCONTROLLED in hard copy unless stamped and specified and managed in controlled document register
Rev Description of Rev/Comments: Prepared by Reviewed By Approved By Review Date Issue Date Page
1 Issued for Use Brad Nelson Michael Chin Chris Mill 16/02/2020 21/11/2014 7 of 9
CC-00018-WI-OP0017
Department Document Number
Chichester Water Management CC-00018-WI-OP0017
Section Title
SAFE WORK INSTRUCTION Changing Tailing Deposition Lines
I have received, read, understood, and shall comply with this Safe Work Instruction for
changing deposition lines and spigot at OPF1 and OPF2.
Signature: Crew/Pit:
Company: Department:
This document is UNCONTROLLED in hard copy unless stamped and specified and managed in controlled document register
Rev Description of Rev/Comments: Prepared by Reviewed By Approved By Review Date Issue Date Page
1 Issued for Use Brad Nelson Michael Chin Chris Mill 16/02/2020 21/11/2014 8 of 9
CC-00018-WI-OP0017
Department Document Number
Chichester Water Management CC-00018-WI-OP0017
Section Title
SAFE WORK INSTRUCTION Changing Tailing Deposition Lines
This document is UNCONTROLLED in hard copy unless stamped and specified and managed in controlled document register
Rev Description of Rev/Comments: Prepared by Reviewed By Approved By Review Date Issue Date Page
1 Issued for Use Brad Nelson Michael Chin Chris Mill 16/02/2020 21/11/2014 9 of 9
CC-00018-WI-OP0017