Professional Documents
Culture Documents
Revision History
Revision Changes
Holds
Hold No. Location Description
Page 2 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
Contents
REVISION HISTORY 2
CONTENTS 3
ABBREVIATIONS 5
1 INTRODUCTION 6
1.1 PROJECT 6
1.2 PURPOSE 6
2 REFERENCE CODES STANDARDS AND SPECIFICATIONS 6
2.1 GENERAL 6
2.2 ORDER OF PRECEDENCE 7
2.3 ALGERIAN CODES AND STANDARDS 7
2.4 INTERNATIONAL CODES AND STANDARDS 7
2.5 PROJECT DOCUMENTS 8
3 DEFINITIONS 9
4 KEY ACTIVITIES OVERVIEW 9
5 HSE 10
6 CLEANING AND GAUGING 10
6.1 CLEANING 10
6.2 GAUGING 12
6.2.1 GAUGE PLATE REQUIREMENTS 12
6.2.2 DAMAGED GAUGE PLATE 12
7 HYDROSTATIC TESTING 13
7.1 GENERAL 13
7.2 HYDROSTATIC TEST LENGTHS 13
7.3 TEST PRESSURES 13
7.4 HYDROSTATIC TEST WATER 14
7.5 WATER QUALITY 15
7.6 CHEMICAL TREATMENT 15
7.6.1 COCKTAIL TREATMENT 16
7.6.2 INDIVIDUAL CHEMICAL TREATMENT 16
7.7 APPLICATION 16
7.8 TETING MATERIAL AND EQUIPMENT 16
7.9 REQUIREMENTS PRIOR TO TESTING 17
7.10 FILLING 18
7.11 STRENGTH AND LEAK TIGHTNESS TEST DURATION 18
7.12 PRE-TEST SECTIONS 19
8 DEWATERING AND CLEANING 19
8.1 DEWATERING 19
8.2 CLEANING 20
9 CALIPER SURVEY 20
Page 3 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
Page 4 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
Abbreviations
Page 5 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
1 INTRODUCTION
1.1 PROJECT
Groupement ISARÈNE (the “COMPANY”) will develop the Ain Tsila gas field which is
located in the Illizi basin in the eastern part of the Sahara Desert in south-east Algeria,
south of the Grand Erg Oriental. The field was discovered within the Périmètre Isarène
(Blocks 228, 229a) in 2007 and has been appraised to hold approximately 65 billion
cubic metres (2.29 trillion cubic feet) of recoverable hydrocarbon reserves. The field lies
in the Sahara Desert, approximately 1,100km south-east of Algiers, 175km west of In
Amenas, 175km north- west of Illizi and 450km to the south-east of Hassi Messaoud.
Central Processing Facility (CPF) is designed to produce 10.3 MMSCMD sales gas.
A gathering system, comprising wellsites, wellsite systems, flowlines, manifold stations
and trunk pipelines to gather the produced fluids and transport them to the reception
facilities at the CPF. Raw gas will be treated in the CPF. Processing facilities comprising
pipeline reception facilities, slugcatcher(s), feed gas compression, mercury removal,
gas dehydration, gas conditioning (natural gas liquids extraction), export compression,
condensate stripper, LPG fractionation facilities, condensate and LPG export facilities
and associated utilities, storage and buildings (all located at the CPF). Fiscal metering
for sales gas, LPG and condensate, located at the CPF battery limit.
Sales quality gas will be delivered to SONATRACH TRC’s (TRC) sales gas pipeline
system at a tie-in point on a manifold next to the TFT compressor station. Liquefied
petroleum gas (LPG) will be delivered to TRC’s LPG pipeline system at a tie-in point
located at a block valve station west of the TFT compressor station. Stabilised
condensate will be delivered to TRC’s condensate pipeline system at a tie-in point
located at Méderba, approximately 165km north of Ain Tsila.
1.2 PURPOSE
This specification details the requirements for pipeline hydro-testing, that is the
cleaning, gauging, flooding, hydrostatic testing, dewatering, drying and preservation
activities applicable to all Ain Tsila Gathering and Export System pipelines. Hydrotesting
will be done in accordance with applicable Algerian regulations and ASME codes B31.8
and B31.4.
For pre-commissioning of the above ground installations (AGIs), refer to Specification
for Pressure Testing, Flushing & Reinstatement of Piping Systems (A-PIP-SPE-000-
00003).
2.1 GENERAL
The pipeline hydro-testing shall be carried out in accordance with the documents listed
and referenced in this document.
Page 6 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
• Algerian Legislation
• Algerian Regulatory Authorities Regulations
• International codes and standards
Page 7 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
API 1102 (Edition – 2007) Steel Pipelines Crossing Railroads and Highways
API 1104 (Edition – 2017) Welding of Pipeline and Related Facilities
API 5L ( 46th Edition) Specification for Line Pipe
API 6D Specification for Pipeline and Piping Valves
ASME VIII, Division 1 Boiler and Pressure Vessel Code
API RP 1110 Recommended Practice for the Pressure Testing of
Steel Pipelines for the Transportation of Gas,
Petroleum Gas, Hazardous Liquids, Highly Volatile
Liquids or Carbon Dioxide
API 1104 Standard for Welding Pipelines and Related Facilities
BS 8010-2.8 Code of Practice for Pipelines – Part 2: Pipelines on
land: design, construction and installation – Section
2.8 Steel for oil & gas
ISO 14313 Petroleum and natural gas industries -- Pipeline
transportation systems -- Pipeline valves
Page 8 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
3 DEFINITIONS
“CONTRACTOR” means the party, which carries out all or part of the
design, engineering, installation and commissioning,
procurement and construction applicable to this
specification
Page 9 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
5 HSE
CONTRACTOR shall include for COMPANY review, as part of their detailed cleaning
and testing plan, adequate measures for safety and environmental control.
These shall include the requirements of the referenced Algerian Regulations and ARH
requirements, CONTRACTOR shall comply with Human Factors Engineering Design
Specification (A-HSE-SPE-000-00001), Specification for Personal Protective
Equipment (C-HSE-SPE-000-00014) and Safety Requirements Specification Overview
(C-HSE-SPE-000-00018).
Additionally, CONTRACTOR shall include detailed requirements and procedures for:
• Exclusion zones: Special precautions, including pre-defined personnel protection
exclusion zones, during pressure testing.
• Night Time Working: Whilst night time working is generally not allowed during
construction, CONTRACTOR may submit a proposal to COMPANY
considering night time supervision of the pipelines during the hydro-testing phase.
6.1 CLEANING
Prior to commencement of a hydrotest, each pipeline section shall be cleaned firstly by
running a robust bi-directional disc pig fitted with a location device. This is to be followed
by further pipeline cleaning using trains of pigs fitted with brushes and magnets. The
detail and design of which shall be submitted to COMPANY for review. Each pig train
shall contain a minimum of 2 Brush pigs followed by a magnetic pig.
Consideration shall be given to the length of the cleaning sections and the effect on the
pig’s performance.
Page 10 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
Block valves shall not be installed before the initial cleaning operations have been
completed in order to avoid damage to valve seats and seals.
CONTRACTOR shall submit a Cleaning Method Statement for review by COMPANY,
incorporating environmental requirements of the Environmental Design Strategy (A-
ENV-PHL-000-00001).
In order to reduce the total water requirements, cleaning pig trains may be propelled by
air, incorporating a suitable slug of water. Where a water slug propelled by compressed
air is used, CONTRACTOR shall ensure that his discharge pipework is designed and
installed to resist the high forces which can be generated when a mixture of air and
water is being used. Venting of air should be accomplished through a knock-out pot and
silencer. Noise levels are not to exceed 90 dBA with provisions of ear defenders are to
be made to all personnel within the vicinity. Noise levels shall conform to the Human
Factors Engineering Design Specification (A-HSE-SPE-000-00001).
CONTRACTOR shall inform, for COMPANY about the volumes and source of water
intended to be used both in front of, and between, the cleaning pigs. All cleaning water
must be disposed of in accordance with the requirements in the Environmental Design
Strategy (A-ENV-PHL-000-00001).
Temporary launchers and receivers shall be fitted to either end of the cleaning section.
These shall incorporate a pressure monitoring and recording device to provide a record
of each cleaning run. Temporary launchers and receivers shall be designed and
operated in accordance with the pollution prevention requirements within the
Environmental Design Strategy (A-ENV-PHL-000-00001) and CONTRACTOR’S
Method Statement shall detail how these requirements will be met.
The first pig to pass through each section shall be run independently to prove each
section prior to the running of cleaning trains. This first pig shall be fitted with a tracking
device which will enable location of the pig should it become lodged within the pipeline.
The acceptance criteria for pipeline cleaning shall be to the satisfaction of Company /
Contractor based on each pig train showing a diminishing trend in recovery of debris
and that the last pig of the cleaning train removes negligible debris and magnetic pigs
receiving minimal debris.
Any obstruction found during the cleaning process shall be cleared by Contractor.
All take-offs and dead legs are to be manually cleaned and after main pipeline cleaning,
they are to be visually inspected for cleanliness.
Inspection and acceptance methodology shall be included in the Method Statement and
include the inspection requirements of the Procedure for Processing Technical Dossiers
and the Rules for Carrying Out Regulatory Inspections and Testing (A-PMT-PRO-000-
00005).
The use of compressed air to drive pigs shall be at a pressure below 7 barg with a
maximum pressure differential of 7barg applied in the event that the pig becomes stuck.
Relevant and appropriate HSE measures shall be in place to ensure safety of the
personnel.
Page 11 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
6.2 GAUGING
Prior to hydrostatic testing, all sections of the pipeline shall be checked for ovality,
buckles, dents and similar irregularities with a gauging plate.
Gauging should be carried out once the backfill is complete. An additional “end to end”
gauging run should be undertaken once the block valves are installed.
A pig tracking system shall be provided. Launch procedures shall be carefully defined
in writing and implemented to avoid damage to the plate during the launch procedure.
CONTRACTOR shall notify COMPANY of his intention to perform the gauging pig runs
in adequate time for COMPANY to witness the loading and removal of the gauging pig.
The plate shall be inspected in accordance with the Procedure for Processing Technical
Dossiers and the Rules for Carrying Out Regulatory Inspections and Testing (A-PMT-
PRO-000-00005). A photographic record shall be made of the gauging plate following
its removal from the pipeline segment, clearly showing areas of damage and including
a means of referencing the photo to the line segment in which the plate was run.
All gauge plates shall be indelibly marked to identify the relevant section and run
number. Upon completion of the gauging operations all gauge plates shall be delivered
to COMPANY for acceptance and record purposes.
Filling of a section of pipeline for hydrostatic test shall not commence until COMPANY
has accepted gauging plates for that particular section.
Page 12 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
7 HYDROSTATIC TESTING
7.1 GENERAL
The hydraulic testing operation shall be carried out by a Specialist Test Engineer
approved by COMPANY They shall have sufficient qualified assistants so that one shall
be available on site at all time during each hydrostatic testing operation. The Specialist
Test Engineer shall be mobilised well in advance of the planned start date for testing
and no later than the date of commencement of mainline welding.
The Specialist Test Engineer shall draw up a procedure of all operations for the tests,
clearly stating the responsibilities of his subordinates during all phases of his work.
The procedure shall be submitted to COMPANY for review not less than 28 days prior
to commencement of testing and shall be approved in writing before any testing
commences. The procedure shall include details of the following:
1. Hydrotest Schedule
2. Safety precautions
3. The design including the Hydrostatic test and supply of test ends
4. The location of the test cabin, pumps, and any other equipment
5. Specification and preparation of test water for initial use and for re-use, including
sampling, laboratory testing facilities, chemical treatment, settling tanks and
filtration system.
6. Filling and pressurising, including the sources of water, storage ponds, test
connections and vent points.
7. Hydrostatic test procedure, including details of test sections.
8. Depressurising and emptying, if appropriate, including details of drainage
connections and method of disposal of water.
9. Detailed programme giving proposed dates of tests.
10. List of nominated personnel supervising tests, with dates and times of duty.
Above ground station pipework shall be tested in accordance with Specification for
Pressure Testing, Flushing & Reinstatement of Piping Systems. Any underground
station pipework shall be tested in a similar manner to the main pipeline.
All measurements and calculations, except nominal pipe sizes, shall be in S.I units.
Page 13 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
Zone
1/1a/2/3
Zone 1/1a Zone 2/3
PMS / Zone Zone 2/3 Maximum
Minimum Minimum
MAOP 1/1a Test Test Combined
Pipeline Test Test
(minimum) Pressure Pressure Test
Pressures Pressures
barg barg barg Pressure
barg barg
barg Note
1
PMS / PMS /
Flowlines 89 132.8 104.7 132.8
0.67 0.85
PMS / PMS /
Trunklines 89 132.8 104.7 132.8
0.67 0.85
Condensate PMS x PMS x
65 78 71.5 78
Export 1.2 1.1
PMS x PMS x
LPG Export 97.25 145.9 121.6 145.9
1.5 1.25
PMS / PMS /
Gas Export 91.5 136.9 107.6 NA
0.67 0.85
Note 1: Contractor is to test all pipeline material to the same combined maximum test
pressure or Zone-wise test pressure depending on the test section requirement.
Page 14 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
Page 15 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
A record of all chemicals and the volume of each injected into hydrostatic test waters
shall be kept, chemical residuals shall be analysed prior to the water disposal.
As test water is transferred from one test section to another, the quality of water i.e. the
amount of treatment remaining, shall be checked and additional chemicals added as
required to bring it back up to specification, if required. Re-used test water shall be re-
filtered through 50 micron filters, to reduce the amount of debris. These tests and
activities shall be properly documented and immediately reported to COMPANY.
Two different types of treatment are proposed: cocktail treatment and individual
chemical treatment.
7.7 APPLICATION
Oxygen scavenger shall be injected in a location where there is no contact with air and
contact of water with air shall be avoided downstream of the injection point.
The dosage of oxygen scavenger shall be determined on the basis of the amount of
oxygen present in the water. Tests shall be carried out to determine dosage of oxygen
scavenger and time required for the reaction. If only carbon steel is in contact with the
water the concentration of oxygen in the water shall be reduced below 50ppm.
If oxygen scavenger reacts with the biocide, as occurs for most biocides, the oxygen
scavenger shall be injected before the biocide allowing sufficient time to fully react with
oxygen. Sufficient time shall be determined by tests performed by chemicals supplier.
Good practice is to inject the oxygen scavenger upstream of the pump (in this case
reaction rate in enhanced by the turbulent flow) and biocide downstream of the pump.
Additionally, provisions for the disposal of treated water shall be assessed as part of
the justification to ensure disposal feasibility of the treated hydrotest water.
Test headers shall be fabricated and tested in accordance with the procedures
approved for the pipeline. Test ends shall be numbered and a record shall be kept on
each fabrication weld, the number of times each test end is used and the test pressure
attained on each test. Entries in the record shall be signed by the Specialist Test
Engineer. Test ends which do not have a complete record of use from the new condition
shall not be used.
Prior to each re-use the test end shall be cut back to remove all weld metal and the heat
affected zone. To achieve this at least 12 mm of pipe should be removed. Dimensional
and ultrasonic examination of the new weld end preparation shall be carried out.
All temporary connections fitted to enable the hydrostatic test to be performed shall
preferably be of rigid construction and shall be adequate to handle the test pressures
involved. Flexible hose shall be of the armoured type and shall only be used if it is
manufactured to standards applicable to permanent hydraulic installations. Such hose
shall only be used in short lengths as required for the pressurising line to the test end
and for instrumentation, and each end must be anchored to prevent ‘whip’ in the event
of failure. Flexible hose shall not be used inside the test cabin.
The pressurising pump shall be fitted with a full capacity relief valve set at the local test
pressure. A pressure recorder shall record continuously the pressure at the test
manifold.
Page 17 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
regarding the limiting pressure which shall apply to the pipeline section under test.
During the test any variation in the rate of pressure increase with volume shall be
immediately reported to the Specialist Test Engineer who shall decide such action as
necessary.
Pipe and soil temperature shall be measured and recorded at each end of the test
section and at every 5 km throughout the length of the pipeline using thermocouple type
instruments with digital readout. These shall be firmly attached to bare metal and
covered with insulating materials for the pipe temperature measurements and for the
soil temperature measurements they shall be buried at pipe centreline depth and 0.5 m
laterally from the pipe.
The points of measurement at each end of the test section shall be such that there is at
least 100m of pipeline buried to specified depth between that point and the test head.
For short lines a minimum of three locations shall be used to measure pipe and soil
temperatures.
All line valves shall be in the fully open position prior to filling.
7.10 FILLING
All necessary measures shall be taken to remove air from the line during filling. This
includes backpressure control and a steady controlled filling rate. Use of a break tank,
use of at least two pigs with water in front and in-between, and by regular renewal of
pig rubbers. When practicable the sections shall be filled from the lower end.
The second pig shall be fitted with a gauging plate, in order to gauge the complete test
section length (if this is a combination of two or more cleaning and gauging sections).
The plate shall be inspected by COMPANY prior to installation in the line and after
pressure testing.
In order to assist in controlling the line filling, inlet pressure, inlet flow and downstream
pressure shall be measured and recorded.
A stabilisation period of at least 24 hours is required post-fill such that difference
between water temperature and ground temperature is less than 1°C.
Page 18 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
7. After completion of the test, start depressurizing the section up to 60% of the test
pressure at 1 bar/minute and then continue to decrease at 2 bar/minute.
All buried pipeline shall be subjected to a 24-hour minimum duration combined strength
and leak test.
If a leak is suspected the pressure shall be reduced to less than 80% of test pressure
before carrying out a visual examination. No work shall be carried out to repair leaks
until the pressure has been reduced to a safe pressure i.e. static head plus 1bar.
During the test, deadweight tester readings shall be recorded every 30 minutes and
pipe, soil and air temperature recorded every 1.5 hours.
The test will be deemed to complete only with approval from COMPANY, otherwise, it
will have to be extended.
Pre-tested short sections shall be tied into the parent pipeline and shall receive final
pressure test in line with the requirements of the documents listed above. Short
sections of station approach (if unavoidable) that cannot meet criteria set above and
that have to be tied-in to the parent pipeline by means of ‘golden welds’ those sections
shall receive strength test at a pressure in accordance with Zone testing requirements
listed in Table – 1.
To avoid damage caused by debris to the valve internal block, valves will not be
installed during the hydrotest including cleaning, filling, pressurizing depressurizing and
de-watering activities. The block valves assemblies will be pre-spooled and tested
separately. The pressure tested valve assemblies will be tied in by golden welds as per
ASME B31.4 (437.1.4(5)(b)) and ASME B31.8(841.31 and A847.b).
8.1 DEWATERING
Following satisfactory completion of the strength and tightness tests the test section
shall be depressurised to a pressure level approved by COMPANY. Under no
circumstances shall full test pressure be retained to transfer water from one section to
another.
When CONTRACTOR needs to bulk dewater a test section in order to transfer water or
to make a tie-in the pipeline, should be left in the bulk dewatered state for a period
Page 19 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
longer than two weeks, further dewatering of this section shall be required until all free
water is removed.
After bulk dewatering has been completed, the CONTRACTOR shall perform pig runs
propelled by oil free air dehydrated to a relative humidity lower than 80% at the pipeline
temperature and operational pressure. Air for propelling pigs shall be made oil free and
dry by means of oil filter units and air-drying or desiccant units downstream
compressors. The capacity and pressure rating of the air compressor, oil filter and air
drying system shall be sufficient.
Only one pig (or pig train) shall be sent through the line at any one time. The pig runs
shall preferably be executed in a downhill direction and in one continuous operation.
The pig velocity shall be kept constant and within the range of 0.5 to 1 m/sec. internal
pipeline pressure shall be kept at least 1 bar above the ambient pressure point along
the pipeline by backpressure control at the discharge end.
CONTRACTOR shall perform dewatering runs until all free water is removed from the
pipeline in front of the pig train.
8.2 CLEANING
For each pipeline section, foam swabbing pigs (density between 30 and 50 kg/rn3) shall
be run for drying in combination with power brush hard foam pig runs to the satisfaction
of COMPANY. Foam pig speed shall not exceed 1.2 m/s.
Final cleaning shall be carried out by cupped brush pigs with bypass plugs open to
create a swirling motion and to blow the loose dust ahead of the pig.
Pigs shall be propelled with oil-free compressed air dehydrated to a relative humidity
lower than 80% at the pipeline temperature and operational pressure.
The line is considered clean when the amount of solids displaced from the line by a new
brush pig is not greater than 10 grams per 10 km section of 16” diameter or less pipeline,
or 18 grams per 10km section of 34” diameter pipeline, as quantified and/or in mutual
agreement with COMPANY.
9 CALIPER SURVEY
Page 20 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
Prior to any calliper survey CONTRACTOR shall run a train of pigs including a final
gauging plate and Magnetic pigs to prove the internal bore and cleanliness of the
pipeline section.
Within 24 hours of calliper runs CONTRACTOR shall present a report to COMPANY
identifying indications.
Contractor shall repeat the run after any investigation, repair or failed run. In case of
any suspected anomaly in pigging report, necessary dig verification shall be carried out
to investigate the cause and repeat the Calliper run.
9.3.1 OVALITY
Definition: Ovality shall be measured as:
Ovality % = 2 (Maximum Outside Diameter (Dmax) – (Minimum Outside Diameter
(Dmin)) x 100
(Maximum Outside Diameter (Dmax) + (Minimum Outside Diameter (Dmin))
Ovality Acceptance Criteria: Ovalities > 5% shall be removed or repaired.
Page 21 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
9.3.2 DENTS
Definition: Dents shall be measured as:
Dent size % =
(Nominal Outside Diameter (D) – Minimum Outside Diameter (Dmin)) x100
Nominal Outside Diameter (D)
Page 22 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
10 DRYING
10.1 GENERAL
CONTRACTOR shall submit a detailed drying procedure and method statement for
approval by COMPANY at least 3 months in advance of intended drying. This shall
account for the following requirements:
• CONTRACTOR shall dry the pipeline to ensure a stable dew point of less than or
equal to -20C at 1.5 barg exists throughout the pipelines.
• Drying shall be achieved using one or a combination of super dry air, dry nitrogen
or vacuum drying, as outlined below. CONTRACTOR shall carry out a soak test to
prove pipeline dryness to the agreed final dew point after a period of 24hrs.
• The maximum duration between the completion of a successful hydrotest and the
completion of the drying operation of any test section shall be 3 months.
• CONTRACTOR shall define details of all drying plant and instrumentation to be
used in performance of its drying activity and provide full supporting calculations
and details of the duration of this activity and the acceptance criteria. This shall
include details on proposed monitoring and logging of all data from instrumentation
and drying plant.
• Dew point meters shall have an accuracy of +/- 2°C and shall have a valid calibration
certificate. The dew point meters shall be checked for calibration at 6 monthly
intervals prior to commissioning.
As an option, the CONTRACTOR shall submit a detailed Method Statement of gas-in
for Gathering system pipelines with hydrotest water retained under pressure as the fluid
from wells has water.
Page 23 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
The pipeline shall initially be pigged with foam swabbing pigs using dry air as the
propellant. The pigging speed shall be between 1.0-1.5 m/s. Pigging shall continue until
the dew point of the drying propellant at the receiving end remains below the required
dew point for at least 2 swabbing pig runs.
Dry air shall be blown through the pipeline at up to 3 m/s until the specified dew point
at atmospheric pressure at the pipe outlet end is maintained while at least one full line
content is displaced and held for an additional period of 12 hours.
11 PRESERVATION
Upon completion of drying of a pipeline or pipeline section CONTRACTOR shall use
nitrogen or super dry air to provide a stable dew point less than or equal to -20°C at a
residual pressure of 1.5 – 2.0 barg for pipeline preservation until connection with the
adjacent section or until handover.
After final completion of nitrogen/dry air filling of the pipeline and pipeline
appurtenances, the pipeline shall be secured by locking closed isolation valves in order
to prevent air ingress and contamination of the pipeline with water vapour.
Preservation shall be tested by CONTRACTOR on a monthly basis until handover.
CONTRACTOR shall supply and maintain temporary monitoring equipment to allow for
this. CONTRACTOR shall maintain a log of the preservation monitoring which shall be
made available to COMPANY.
Page 24 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
Appropriate warning signs indicating the hazards of pressurised nitrogen or air shall be
installed at above ground locations whilst the pipeline is pressurised.
Contractor shall maintain complete and comprehensive records of all hydrostatic tests.
Records shall be accurately dated and shall be clearly identified with respect to the
specific test sections to which they apply.
Test records shall include but not limited to:
• Test instrument calibration certificates
• A chronological record of events which occured during the test period including
comments on all leaks and failures and their disposition
• Logs showing deadweight pressure and ambient temperature readings with date
and time for each reading. Each log sheet shall be signed by ARH, Operator and
Contractor's designated representative
• Test section profile showing elevations and instrument and test point locations
• Calculations to support a valid test for applicable buried assemblies
• Test acceptance certificate signed by Operator and ARH
• Temperature and pressure recorder charts
The following shall be listed on the face of each chart:
• The identity of the test section / facility
• The actual time, date and initials of the personnel starting the test
• The actual time, date and initials of the personnel removing the chart
• Explanations of pressure or temperature discontinuities that appear on any chart.
• The following additional information shall be listed on the back of each chart:
• Project name and job number
• Test section number
• Maximum operating pressure
• Location of test section
• Name and signature of personnel responsible for the test.
• Maintaining repair log if any and submit to Company
The following information shall be listed on accompanying forms for each test section:
• Location and elevation of test site
• Test medium
• Date of test, test duration and the minimum test pressure realised
Page 25 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
13 WITNESS POINTS
Table 1 lists out the witness points of ARH and Operator during the entire process of
hydrostatic testing and dewatering of the ancillary facilities.
On Field Calibrations Y Y -
Page 26 of 27
Specification for Pipeline Hydro-Testing
Document No: A-PLE-SPE-200-30011
Revision 1
Page 27 of 27