Professional Documents
Culture Documents
Sankhuwasabha District,Nepal
AUGUST 2019
1. Introduction:
The Project:
The proposed project is located in the Bhotkhola Rural Municipality-2, Sankhuwasabha District,
Province number 1 of Nepal. The project is located near Nepal-China (Tibet) border near
Kimtahnka. At present, there is no direct road access to the project area. The nearest settlement
with road access is at Gola, Sankhuwasabha. Presently, the Department of Road is opening the
road track from Gola to Kimathanka – a town bordering with China – as part of the 390 km
Biratnagar-Khandbari-Kimathanka trilateral trade route. Plans for expanding the road network to
towns/settlements close to the project area are underway. The major economic hubs near the
project sites are Khandbari (located 70.7 km from Gola), Tumlingtar (located 82 km from Gola) and
Dhankuta (located 158 km from Gola). Of these towns, Tumlingtar has an airport with connecting
flight to Kathmandu.Khandbariis the district headquarters.
Leguwa-Tumling road
East-West highway
The roadway from Tumlingtar to Khandabri is black topped and in good condition, while the
seasonal road connecting Khandbari to Arun 3 HEP headworks is nearing completion. Arun 3
headworks– Num – Gola track is open but is not suitable for heavy vehicles in its current form due
to very sharp hairpin bends and narrow width. As of early monsoon, 2019, opening of a motorable
track from Gola to Chyamtang is on completion.
The project site can be accessed through Gola, which can be reached by two ways: using road all
the way from Kathmandu or by plane to Tumlingtar and then by road to Gola. From Gola, the
Project site can be accessed by a foot trail. Alternatively, a helicopter can be chartered from
Kathmandu to the villages in the project area. The time to reach the site via a helicopter is about
50 minutes.
In the inception phase of the study, four main layout options considering different headwork and
waterways and powerhouse were studied. These options are shown in Figure 1.
Option B: Headworks near KhyokmaVillagewith waterways and powerhouse options at right bank
Option C: Headwork between Khyokma and Chumsur village. Waterways and powerhouse options at both
right and left banks
Option D: Headworks at downstream of the Chumsur Village, waterways at right bank, and powerhouse
options at right bank
The alternative options A and B were envisaged as a ROR projects whereas option D was planned
to be a PROR project. Option C was studied as both a ROR and PROR project.
Based on the comparison between the different options, Option C (PROR) was found to be the
most suitable project alternative.
Consequently, the Option C has been selected for detailed project study and is targeted to be
completed by 2019 including Detailed Project Report.
2. Hydrological Study
Arun basin is located in northeast part of Nepal and south part of Tibet on Arun River, within
Saptakoshi Basin of Nepal as shown in figure 2. Arun River originates at a glacier on the Northen
slope of Mount Xixabangma in Tibet and the river is called Pum Qu in Tibet. The catchment area of
the Arun Basin at Uwagaon outlet point is 26,132.79 km2 and at Kimathanka outlet point (project
site) is 24,835.58 km2 . The annual average distribution of rainfall over the catchment area is
found to be 565 mm for China side area sub-basin and 2645mm for Nepal side area sub-basin.
The meteorological stations around the project and the catchment area as identified in the Upper
Arun Hydroelectric Project Report (Morrison-Knudsen Engineers Inc et al., 1991) are shown in
Table 1
Kimathanka Arun HEP | Brief Project Information | August 2019 Page | 3
Table 1 Meteorological stations available for the project study
SNo Station Name Station No Basin Lat. Long. Elevation Data Period
Hydrological Data
The hydrological stations used in the study provides the following data:
Yearly discharge
Extreme discharges
Daily discharges
The details for the stations relevant to the project are shown in Table 2.
Chepuwa
- Sankhuwasabha - - 1580 1976-90 15
(Upper ArunDamsite)
Weather Data
The weather data that are necessary for carrying out hydrological balance by the model are daily
precipitation in mm, minimum and maximum air temperature in degree Celsius, relative humidity in
percentage, wind speed in m/s and daily solar radiation in MJ/m 2/day. Dingri, Nielaer and Laziare
the three meteorological stations in the vicinity of Arun River basin at Kimathanka. Dingri station is
located inside Kimathanka catchment boundary. These observed data can be downloaded from
the Third Pole Environment Database (http://en.tpedatabase.cn/portal/index.jsp) website. Climate
Forecast System Reanalysis (CFSR), Global Weather data (https://globalweather.tamu.edu) and
Aphrodite's Water Resources (http://www.chikyu.ac.jp/precip/english/downloads) are two popular
sites from where gridded climate data sets can be obtained for Tibetan region of Arun River basin.
A comparison of annual precipitation data was made between CFSR and Aphrodite weather data
sources with respect to observed meteorological station at Dingri and shown in Table 3
1 Third Pole 383. 429. 400. 288. 307. 264. 345. 209. 328.6 Dingri Station
9 3 6 9 3 7 4 1
2 CFSR 345. 465. 331. 293. 313. 372. 240. 237. 325.0
8 7 7 3 1 2 1 7
3 Aphrodite 422. 439. 498. 354. 365. 361. 373. 325. 392.4
2 5 3 4 0 7 0 3
Establishment of Gauging Station
Moreover, an automatic gauge has also been installed at the same location for the automatic
monitoring of the water level (Figure 6). Data recording is being continued from 17th of May 2018 till
date.
Since there were no meteorological stations nearby the project area, an automatic rain gauge has
been installed near KAHEP project site. The automatic rain gauge was installed at Guthigumba
Village, Bhotkhola VDC, Sankhuwasabha considering stable mobile network around the gauging
station. The coordinate of the location of the Rain gauge is 27°45'39.51"N latitude and
87°25'19.23"E longitude. The data is being recorded from 15th August 2018 till date.
Currently the measurement of discharge of Arunrivr near headwork location is ongoing. The details
of the measured discharges till date is shown in Table 4
The response of the basin has been monitored at Uwagaon station 27.72km downstream of the
headworks site. The basin is very large and most of the contributing areas lie in Tibet. Since there
is distinct abrupt changes in topography and climate between southern and northern flanks of
Himalayan ridges, estimation of daily discharge using distributed hydrological model is sought. The
parameters of such model calibrated at Uwagaon station will thus be used to simulate at
headworks site. The average percentage daily differences between model simulated discharges at
Uwagaon station and headworks site will then be deducted from the long term observed discharge
at Uwagaon station to arrive estimation of daily discharge at the headworks site.
For the purpose of daily flow estimation with the objective discussed in above para, Soil and Water
Assessment Tool (SWAT) developed by USDA has been selected. SWAT (Arnold et al., 1998) is a
semi-distributed, time continuous watershed simulator operating on a daily time step. It is long term
load model, which uses daily average input values. The model is semi-physically based, and
allows simulation of high level of spatial detail by dividing the watershed into a large number of
sub-watersheds.
Physical characteristics, such as slope, reach dimensions, and climatic data are considered for
each sub basin. For climate, SWAT uses the data from the station nearest to the centric of each
sub basin. Calculated flow, sediment yield, and nutrient loading obtained for each sub basins are
then routed through the river system. Channel routing is simulated using the Variable Storage or
Muskingum method.
3000
Uwagaon_Simulate
2500 d
Kimathanka_Simula
2000 ted
Discharge(m3/s)
1500
1000
500
0
98 98 98 98 98 98 98 98 99 99 99 99 99 99 99 00 00 00 00 00 00 00 01 01 01 01 01 01 01
/19 /19 /19 /19 /19 /19 /19 /19 /19 /19 /19 /19 /19 /19 /19 /20 /20 /20 /20 /20 /20 /20 /20 /20 /20 /20 /20 /20 /20
3 3 5 5 6 5 5 6 5 7 8 8 7 8 8 7 9 9 9 9 9 9 9 1 1 1 1 1 1
1/ 2/2 4/1 6/ 7/2 9/1 11/ 2/2 2/1 4/ 5/2 7/1 9/ 0/2 2/1 2/ 3/2 5/1 7/ 8/2 0/1 12/ 1/2 3/2 5/1 7/ 8/2 0/1 12/
1 1 1 1 1
Date
Summary of average monthly discharge at headworks site has been estimated and presented in
Table 5
Month/da Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
y
Average 60.0 56.2 54.2 48.0 78.2 237.1 523.8 562.5 404.1 184.8 98.1 70.0
8 2 8 1 0 7 0 2 3 2 0 6
The adopted flow duration curve at KAHEP dam site is shown in Figure 10
0.6
0.5
0.4
0.3
0.2
0.1
0.0
0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0%
Probability of Exceedence
For the estimation of Probable maximum flood, SWAT model is applied and run for the period from
Aug 15, 1999 to Sept 15, 1999. For this run 3 day estimated weighted PMP over the sub-basin are
equally divided as rainfall during August 26, 27 and 28 1999 since on 27 August 1999 historically
highest instantaneous discharge had been observed at Uwagaon station and other weather data
and parameters remain unaltered. The daily output hydrographs at Headworks site (fig. 6.1) and
tailrace site (fig. 6.2) have peaks at2,843 m3/sec and 3,798 m 3/sec m3/sec respectively. Since the
observed maximum instantaneous peak at Turkeghat station is 2.34 times the observed daily
discharge on the same date, PMF is estimated to be 6,652 m 3/s and 8,887 m3/s for Headworks and
tailrace sites respectively.
3000
2500
Estimated Discharge(m3/sec)
2000
1500
1000
500
0
ug ug ug ug ug ug ug ug ug ep ep ep ep ep ep ep
-A - A -A - A -A - A -A - A -A 2-
S
4-
S
6-
S
8-
S -S -S -S
15 17 19 21 23 25 27 29 31 10 12 14
Date
Date
The Arun River has been gauged at Uwagaon (600.1) and Turkeghat (station 604.5). Since the
Instantaneous peak discharges at Turkeghat station are available for more years than with
Uwagaon station peak flow estimation is calculated using Turkeghat station data. Table 6
represents these observed instantaneous annual maximum and minimum discharges at Turkeghat
station. The frequency analysis for these observed events are carried out. The return period of
corresponding observed annual maximum discharges are then calculated for the observed period.
For the same annual series of observed maximum discharges Gumbel’s, Log-normal and Log-
Pearson’s distributions are fitted.
At present, supra-glacial and moraine-dammed lakes are far more common in Nepal than glacier-
dammed lakes as their development is favored by the overall atmospheric warming and glacier
wastage. In Nepal ice-dammed lakes are either only present in very small numbers if at all, or their
existence has escaped notice. Among the river basins in the Himalayas, the Arun river basins is
the most concentrated areas of glacial lakes. The location details of potentially dangerous glacial
lakes in Arun basin are shown in Figure 13
The possible maximum discharges of GLOF estimated by models are 20745 and 16095 m3/s for
G4 glacial lake. Since that lake is 125 km upstream of the headworks site, the peak discharge will
get attenuated more than half when arrived at the headworks site. Therefore, the maximum
possible discharge during GLOF event will be less than that during PMF.
3. Sediment Study
In general, the sediment concentration is low in the upper part of the catchment of the Nepalese
rivers (except for catchment with Tibetan Tethys formation) due to the availability of higher
The sample collection works is being done by point sampling method. Samples are retrieved from
the bank of the river at locations with turbulent flow where the sediments are assumed to be well
mixed and fairly evenly distributed over the depth and width of the flow. Regular sediment
sampling is being carried out at gauging site from three locations (Left, Center and Right).
The collection of sediment samples is ongoing until now. The concentration analysis of the
sediment samples is also being done continuously which can be seen in the Monthly Progress
Reports of Sedimentation Studies. Up till February a total number of 843 sediment samples have
been collected for sediment concentration analysis. Maximum measured sediment concentration at
Arun river during study period is found to be 6574 ppm. The measured mean monthly
concentration for the headworks site of KAHEP during the current study is shown in Table 7
Month Jun Jul Aug Sep Oct Nov Dec Jan Feb
Avg Sediment
999 2122 2244 617 353 134 92 71 676
Concentration (ppm)
Particle size of sediment is main factors governing erosion potential of sediment. All size range of
sediment particles do not reach turbine and erosion rate is directly proportional to particle size of
sediment. So, during sediment analysis, PSD of sediment is carried to identify critical sediment
size that reaches turbine and erode turbine material. The measured particle size distribution for the
headworks site of KAHEP during the current study is shown in Figure 15
Around 75% of the suspended sediments are finer than 0.2mm size and more than 50% of the
suspended sediments are finer than 0.1mm size.
It was observed that, about 76 percent of the mineral grains in the sediment contain minerals with
hardness greater than 5 in Mohs hardness scale which are Quartz, Feldspar, Tourmaline, Garnet,
and Hornblende. However, in general it was noted that most of the feldspar grains have ‘sub-
angular’ shape which makes them not as abrasive as quartz grains which are ‘angular’ to ‘very-
angular’. Remaining 24 percent of material comprises mica, carbonate minerals, clay lumps, etc.
which possess hardness lower than 5 in Mohs scale.
Project Geology
Regional Setting
The area falls in the Arun Tectonic window that consists rocks of both the Lesser Himalayan Unit
and Higher Himalayan Unit. In general, Quartzite, orthogneiss and augen gneiss are the rock unit
of the Lesser Himalayan while schistose gneiss and banded gneiss are predominant constituents
of the Higher Himalayan rock sequence.
The geological map of the project area is shown in Figure and as shown, the Main Central Thrust,
which forms the boundary between the Higher and Lesser Himalayan Units, is expected to pass
within the project zone.
For long, many researchers have defined the MCT by different criteria, including by lithology that
differs between the hanging wall and the footwall, by metamorphic grade changes from the
hanging wall to thefootwall, by the different Uranium-Lead (U-Pb) detrital zircon ages, by the
different Neodymium isotope compositions, by different strain, etc. Some of these criteria have
also been combined. However, none of these criteria are reliable if they are used by themselves
(Searle et al., 2008). Meanwhile, these all criteria are not satisfied together (Yin,2006). The
dominant problems are:
Lithology and stratigraphy have not been completely investigated and understood;
Metamorphic grades across the MCT shear zone are continuously changing, thus any one
particular isograd is not reliable for determining the location of the MCT;
Strain magnitude cannot be determined as most of the fabrics of the MCT that resulted
from shearing, have disappeared because of strong heating and deformation
Some geologists do not believe that the whole shear surface was active at the same time
because they think that the MCT ductile shear zone is caused by finite strain deformation
Headworks
Headworks area predominantly comprises of well foliated, medium banded, dark grey, coarse
grained banded gneiss (Figure 19). The exposure forms a vertical cliff and slight to moderately
weathered. The pegmatite vein consists of nearly 5 mm thick, 2.5 cm long mica book, 0.5x1.5 cm
long tourmaline and recrystalized quartz (Figure 20). The attitude of foliation plane is N20E/40oSE.
The intake site is proposed in a narrow valley with moderate to steep slope at both banks. The hill
slope is covered with thin slope scree that ranges upto 50 cm and mostly covered by sparse
vegetation. The exposed rocks are banded gneiss and are fresh to slightly weathered with
occasional moderately weathered rock. Highly persistent foliation plane is predominant while joint
planes are low to medium persistent. Some open joints are filled with sand, silt and clay. The rock
mass is strong. Individual thickness of gneiss bands ranges from a few centimeters to 1.5 meters
and 2 to 3 meters in some places. The alluvial deposits found on the river bed are composed of
boulders and gravels of gneiss, schist, amphibolite and a few quartzites. The clasts are generally
sub-rounded to round in shape. The alluvial deposit comprises boulder, cobble and pebble having
more than 75% gneiss, less than 10% schist and 15 % others (based on visual observation). The
debris in the river also consists of large tree trunks. The debris is about 10 m thick. The maximum
size of boulder found has the diameter more than 2.0 m. At the left bank, colluvial fan rests over
the alluvial deposit. The angular clasts in the colluvial fan is composed of gneiss.
Likewise, at the right bank of the Arun river, near to the proposed site of the dam, at the confluence
between the Arunriver and Chemadengdeng kholsa, there exist a recent landslide. The kholsa is
filled with landslide debris in which boulders and gravels are exclusively of gneiss. Huge tree
trunks and plant remains are also common. The debris consists of huge boulder. Nearly 2 m
diameter boulder is frequent with average size ranging upto 0.5 m diameter. Clay content is
relatively low.
Overall, the quality of rockmass in the headworks area indicates that the site is suitable for the
construction of the proposed dam. However, the orientation of the foliation plane is unfavorable
and indicates that extensive seepage control measures may be necessary. The ongoing core
drilling and Lugeon tests will provide a better indication of the potential seepage issues.
HRT Alignment
The proposed waterway alignment (including the approach tunnel and desander) passes through
banded gneiss (2215 m), augen gneiss (2900 m), schistose gneiss (1735 m) and small portion
through weak or shear zone. Most portion of the tunnel alignment is oblique to the strike of foliation
The initial part of the tunnel alignment (nearly 200 m) from intake is proposed along an azimuth of
205 degrees whereas the remaining downstream portion (1500 m) is oriented at an azimuth of 170
degrees. The two alignments make nearly angle of 140 degrees. The initial tunnel alignment will be
oriented almost parallel to the foliation plane while the second stretch makes nearly 65 degree with
the foliation plane. At some places it is even less. In addition to this, 2500 m long stretch towards
powerhouse has an azimuth of 170 degrees that makes an angle of about 60 degree with the
foliation plane and much less in some section. Beyond this point, towards powerhouse, around
1050 m section uptosugre tank has an azimuth of 175 degree. The section alignment is oblique
with foliation plane making angle much less than 60 degree.
Surge Shaft
The surge shaft lies below the hill ridge of Chyamtang Village, at about 500 m uphill of the
proposed powerhouse area in the right bank of the Arun River. Geologically, the proposed surge
tank area lies on the rocks of the Higher Himalaya and is composed of banded gneiss with
occasional occurrence of schist band. The ridge consists of thick residual to colluvial deposits
consisting boulder, silty-clayey soil. The material is medium dense to loss in nature. exposed rock
along the hill top and downslope have made rock cliff. The rock mass is strong and jointed with
opening ranges up to 7 mm and more in some places that are filled with sand, silt and clay. Joints
with iron staining are also seen in some places. Joints are dry to damp. Seepage from the interface
of rock and soil is also present. The soil thickness in this area is more than 5 m but the thickness
gradually decreases along the edges. The downhill slope, below the rock exposure, is covered by
thick colluvial and is sparsely to medium densely vegetated. The colluvial consists of clay size to
boulder size. The eastern hill slope shows the sign of terrace farmed. The lower section of the
terrace farmed is saturated with water.
Completed drilling suggests that the bedrock is situated at 6 m from the surface with minor
seepage estimated during construction. The present geological investigations support the
proposed surge tank design. Assessment of rockfall hazard for the structure is under study.
Geologically, these project components lie in the rock unit of the Higher Himalayan and
predominantly consist of schistose gneiss. The gneiss reveals well developed schistosity (Figure
25). On the way to Chyamtang from Lingam, fresh to slightly weathered, well foliated, massive,
blocky and medium to coarse grained deformed gneiss is exposed (Figure 26). Moderately to
highly weathered, jointed, coarse grained schistose gneiss is also well exposed in tailrace (Figure
27). The attitude of foliation plane is N40E/45oSE.
Similarly, at the down slope of Lingam and Chyamtang village, massive, moderately jointed,
slightly weathered, coarse grained schistose gneiss is present. A few quartz veins parallel to
chevron fold axial plane is also visible (Figure 9). The attitude of foliation plane is N670E/41 o
SE.Likewise, downhill of the Chyamtang village, at the Khaktok Kholsi, the exposure consists of
Downslope of Chymantang village, further downhill of the end of the cultivated terrace, the
exposure forms series of vertical cliff with spectacular series of water fall (Figure 10). The
exposure consists of fresh to slightly weathered, moderately weathered in some places, medium to
coarse grained, strong schistose gneiss with pytmatic folds along with boudinage. The attitude of
foliation plane in this section is N30E/64oSE.
Investigation plan
The major items of the geological and geotechnical study are presented in the following table
Figure 23 Rockmass near potential desander portal area Figure 24 Rock Overhang in Powerhouse Area
(photo facing upstream)
Figure 29Quartzite Bed in Schistose Gneiss, On the way Figure 30Banded Gneiss, On the way towards Chumsur
towards Chumsur Village from Chyamtang Village Village from Chyamtang Village
Core Drilling
The following table provides the general summary of the exploratory drill hole completed and
continued.
Drill Total
Depth to
hole Location Drilled Easting Northing Remarks
bedrock,m
No Depth,m
Surge Tank,
SS1 90 542817.6 3071401 6 completed
Chyamtang
Surge Shaft,
SS2 70 542845.5 3071338 9 completed
Chymtang
completed,
Headworks,R/B
DR1 36 541734.3 3077477 N/A artesian formed
Arun River
and stopped
Headworks,R/B
DR2 45 541740 3077469 1 Completed
Arun River
PH4 Powerhouse site 50 542768 3071165 36 Completed
PH2 Powerhouse site 159 543010.2 3071094.8 Continued
Headworks,L/B Ongoing, paused
DL2 60 541849 3077456 N/A
Arun River due to monsson
TL1 Tailrace Site 65 542832 3071038 35 Completed
Kimathanka Arun Hydroelectric Project utilizes water from Arun River to generate 450 MW of
electricity. The main civil structures of the Project are roller compacted concrete (RCC) dam,
power intakes, upstream (U/S) and downstream (D/S) coffer dams, diversion tunnel, headrace
tunnel, surge shaft, pressure shaft, underground powerhouse, underground transformer cavern
and tailrace tunnel.
All the structures of the project are proposed along the right river bank. All structures are of
underground type except the diversion dam. U/S and D/S coffer dams have been proposed about
400 m and 350 m from dam axis, respectively. The headworks consists of 68 m high (from river
bed) RCC Dam with two overflow spillways with radial gates and three sluice spillways designed to
safely spill the design flood and the PMF. (Core drilling work is being carried out at the dam site to
ascertain the rock foundation.) Two power intakes consist of four openings of width 6.0 m each on
From the power Intake, there are twin approach tunnels of length 885 m and 935 m with finished
diameter of 6 m up to the bifurcation to desanding basin. Four tunnels each of length 140m with
finished diameter of 4m connect the approach tunnels to the desanding basin. There are 4 number
of underground desanding basin chambers each of 200m length, 20 m width and 15m depth. After
the desanding basin, four tunnels of 130m length 4m finished diameter tunnel connect with twin
tunnels each of 267m length and finished diameter of 6m to the headrace tunnel of 4410m with
finished diameter of 8mtill surge shaft. A surge shaft with finished diameter of 16m and 75m height
is proposed at the end of headrace tunnel. After surge shaft, steel penstock tunnel of length 620m
with finished diameter of 6.25mconvey the discharge to the turbines. An underground power
station with 157.0 m length and 18.5 m width cavern with total height of 35 m will accommodate six
Pelton turbines. A 700 m long tailrace tunnel of finished diameter 10 m will discharge water coming
out of the turbines back to the Arun River.
The reservoir volume curve at the dam location is given in Figure 31. The live storage volume with
full supply level at 2035 and minimum drawdown level at 2025 is 3.2 MCM.
2040
2020
Elevation (masl)
2000
1980
1960
1940
1920
0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0
Storage Volume (MCM)
Main Dam
A Roller Compacted Concrete (RCC) gravity dam with crest length of 190 m is proposed. Existing
river bed level at the dam site is 1968 masl.
Deck level of dam is 2038 masl with freeboard of 3 m from full supply level (FSL) 2035 masl.
Height of the dam at non-overflow dippiest section from the dam assumed rock foundation is 98 m.
Two overflow spillway radial gates of size 12 m X 10 m have been proposed with maximum
discharge capacity of 1494 m3/s. Crest level of the overflow spillway is at 2025 masl. Two breast
wall spillways of size 10 m X 14 m are also proposed whose bottom level is at 2008 masl. The
cross-section of the dam will have a vertical upstream face and a 0.8H: 1V downstream face. Two
2.5 m X 2.5 m sized mid-level outlets at 1990 masl have been proposed near the intake opening
for passage of the sediment.
Energy dissipater
Flip bucket type energy dissipater has been proposed at end of spillway and is designed to
dissipate energy of upstream water. The design flood is adopted to be 10,000-year return period
flood i.e. about 4570.5 m3/s. A flip bucket is chosen due to high flow and high velocity at the end of
spillway. The total width of flip bucket is provided to be 36 m for overflow spillway and 42 m for
sluice spillway. The lip velocity and throw distance are calculated to be 32 m/s and 110 m
respectively.
To enable river diversion during construction of dam, two rock fill cofferdams with central
impervious cores have been located at approximately 400 m upstream and 350 m downstream of
main dam axis. Upstream coffer dam shall be 30 m high with top elevation 2015 masl and
downstream cofferdam shall be 15 m high with top elevation 1980 masl. Top width of the dam has
been proposed as 6 m. Overtopping of the upstream coffer dam is not permitted during
construction period.
Diversion scheme has been designed to pass flood of 15 years return period which is estimated to
be 1802.7 m3/s representing a peak flood event. Single tunnel has been proposed to divert flow to
downstream of river during construction.
Intake
Side intakes have been proposed to divert required flow to headrace tunnels from reservoir. Side
intake has been provided which are designed to pass the design discharge of 151.6 m3/s. The
intake is proposed to be operated by vertical lift gates. The number and size of trash racks are
provided to be 4 and 7.6m X 8.4m (B X H) respectively whereas number and size of gates are
provided to be 4 and 6m X 6m (B X H).
Twin approach tunnels are proposed to convey water from intake to Desander Basin. Two number
of approach tunnels have been proposed. The tunnels start from intake and end at inlet bifurcation
and have been proposed to be D shaped finished and fully concrete lined. The tunnels are
designed to carry design discharge of 87.4 m 3/s each. The optimum diameter of the tunnels is
estimated to be 6m and the total lengths of the two tunnels according to component layout drawing
is estimated to be 885 m and 935 m. After the twin approach tunnels, each tunnel bifurcates into
140m length D shaped finished diameter of 4m and fully concrete lined till the inlet transition of
Underground Desanding Basin.
Four Underground Desander Basin Chambers are proposed to settle 0.2mm size sediment particle
with at least 90% efficiency. Number and size of desanding basin are 4 and 200 m X 20 m X 15 m
(L X B X H). The flushing channel of 1.5m X 1.5 m size is provided at the center of basins. The
transition of 10o angle is provided at the inlet of the basin. An adit tunnel will be provided to assist
during the construction and operation phase of the project. After the desanding basin, four tunnels
of 130m length 4m finished diameter tunnel connect with twin tunnels each of 267m length and
finished diameter of 6m to the headrace tunnel.
Headrace tunnel
A Headrace Tunnel (HRT) is proposed to convey water from desanding basin to the surge shaft.
The tunnel start from junction point of twin tunnel after desander and ends at surge shaft inlet and
has been proposed to be horseshoe shape finished and fully concrete lined. The tunnels designed
to carry design discharge of 151.6 m3/s. The optimum diameter of the tunnels is estimated to be
8m and the total length of the tunnel according to component layout drawing is estimated to be
4410 m. Design velocity in the tunnel will be 3 m/s. Invert level at the start of the tunnel is
1996.8masl and at the end of the tunnel will be 1981masl.
Surge Shaft
Surge protection structure is designed to dampen sudden upsurges and down surges which occur
during operation of power plant. A circular restricted orifice shaft of finished diameter of 16 m and
75 m height is proposed as a surge shaft. The surge shaft is open to sky at the top and at 16 m
towards right of the flow direction. The restricted orifice is circular section with diameter of 3.45m.
The diaphragm connecting the headrace tunnel with surge shaft is also of circular section with
diameter of 3.45m.
Pressure shaft
Pressure shaft consists of three sections i.e. upper horizontal section, vertical shaft and lower
horizontal section. Entire conduit is proposed to be circular in shape, steel lined and 6.25 m in
finished diameter. The total lengths of upper horizontal portion, vertical shaft and lower horizontal
portion are 165 m, 295 m and 160 m. Manifolds are provided at the end of the pressure shaft
Powerhouse Cavern
The main powerhouse cavern is 18.5 m wide, 35 m in height and about 157 m long. There are
mainly three floor levels in the powerhouse cavern situated at different elevations. The machine
floor level is at 1664masl, the generator floor level is at 1660masl and the turbine floor level is at
1655masl.
Transformer Cavern
The transformer hall will be reached through an access tunnel branching off from the main access
tunnel. The size of the main transformer cavern will be 17 m wide, 18.5 m high and 190 m in
length. The floor elevation will be same as that of the main machine floor at the power station.
Tailrace tunnel
The outlets from six turbine units will be connected to tailrace manifold tunnels which will be further
merged to one tailrace tunnel. The length of the tunnel is estimated to be 700 m and length of the
manifolds for the tunnel will be 18 m. The tailrace tunnel will be horseshoe shaped with 10m
finished diameter.
One construction adit tunnel of D shape with finished diameter of 4 m is designed to provide
access and assist the works in headrace tunnel. One adit tunnel is also proposed for the
assistance of work in surge shaft. Whereas, the main access tunnel is proposed above the tailrace
portal for the construction of work in powerhouse cavern. There will be different sized access
tunnels, with inverted D-shape, to different locations at powerhouse complex.
15 Access Road
Length 30 km
The financing terms and schedules are based on construction plan of the company with required
proportion of equity and debt contribution. The project schedule reflects the provision of completion
to satisfy the COD date as per estimated plan. The following parameters form the basis while
concluding the project financial projections:
The costs are prepared in different headings based on details at each heading. The
quantity estimates are prepared based on preliminary drawings and those items which are
not detailed yet are put on lump sum based on experience on conservative side so that it
will suffice during detailed planning.
The Rate Analysis are made from basic rate of construction materials, machines,
equipment, tools and plants with the help of norms referred for the quantity of manpower. A
10% physical contingency is added on each of the surface works items and 15% for
underground works. In addition, that there is a provision of price contingency each items of
heading except preliminary and IDC.
The BoQ is prepared with the quantity and rate prepared from Rate analysis to find the
base cost of the construction in this date.
There will be applicable VAT and Tax as per the rule of GoN. for the applicable items.
Those to be completed by company will not have VAT and tax
In the total cost the insurance and Misc. cost is based on % basis to cover-up the required
reliability on the costing.
The cost obtained from the details analysis is referred as construction capital cost without
financing. There will be further financing cost to be added on the estimate to find the final cost of
the project at the time of commercial operation date (COD).
Capital Cost
Project Evaluation
Kimathanka Arun HEP | Brief Project Information | August 2019 Page | 35
Kimanthanka Arun Hydroelectric Project is found to be attractive project for financing with
installed capacity of the project 495 MW. Project cost is found to be 1684.59 $/kW after
financing considered as 75:25 debt equity financing @ 11% interest rate. The Project Cost
and Financial indicators shows the B/C ratio 1.22, IRR of 13.36 and the project can pay
the loan and interest on 12 year.
Assumptions
1 Installed Capacity 450 MW MW
4 Construction Period (Loan drawdown Period) 5 Years
Conclusion
From the present level of study Kimathanka Arun Hydroelectric Project is technically and financially
feasible. However, the cost- benefit will be finalized after completion of total study.
As the project structures are mostly underground type the environmental impacts are limited. The
Environment Impact Assessment is also being carried out at present.