You are on page 1of 13

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/236449498

Protocol for field testing of tall buildings to determine envelope air leakage rate

Conference Paper · July 1999

CITATIONS READS
7 724

3 authors, including:

William Parry Bahnfleth


Pennsylvania State University
146 PUBLICATIONS   2,042 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

UV Disinfection View project

Risk Assessment of Occupant Exposure During Extraordinary Events View project

All content following this page was uploaded by William Parry Bahnfleth on 26 October 2017.

The user has requested enhancement of the downloaded file.


4275 (RP-935)

Protocol for Field Testing of Tall


Buildings to Determine Envelope
Air Leakage Rate

William P. Bahnfleth, Ph.D., P.E. Grenville K. Yuill, Ph.D., P.E. Brian W. Lee
Member ASHRAE Fellow ASHRAE Student Member ASHRAE

ABSTRACT through the envelope can cause serious moisture problems if


air is cooled to its dew point while within an exterior wall.
The objective of this project was to develop a relatively
Stack effect pressure differential across building shafts can
simple, accurate method for testing the overall envelope leak-
generate objectionable noise that is particularly evident at
age rate of tall buildings. Two fan pressurization test tech-
stairwell and elevator doors. In view of the negative conse-
niques, the floor-by-floor blower door method and the air-
quences of envelope leakage, construction methods to limit
handler method, were developed and tested on two buildings.
leakage and testing procedures to verify their efficacy should
Criteria for conducting accurate tests were developed, includ-
be a part of building design and commissioning.
ing limitations on outdoor air temperature and wind speed.
The floor-by-floor blower door method permits isolation and Measurement of the envelope leakage of houses and other
measurement of the leakage flow rate of a single floor, but it small buildings through pressurization and depressurization
is difficult and time-consuming to apply. The air-handler testing is a common procedure (Shaw et al. 1990). The typical
method uses building air distribution fans for pressurization. test method utilizes a temporarily installed fan to pressurize or
It is most easily applied on a system-by-system level rather depressurize the building to a series of desired indoor-outdoor
than floor-by-floor. Fan airflow techniques including orifice pressure differentials. The airflow rate into or out of the build-
plate, pitot traverse, and tracer gas dilution were considered. ing is measured at steady state for each differential. Data from
The tracer gas method was found to be relatively easy to apply these tests are used to establish a correlation between airflow
and highly accurate. Fan airflow rate measurement uncer- and pressure differential. In principle, this approach is also
tainty by tracer gas was estimated to be 5.4% to 8.8% for the applicable to tall buildings. However, stack and wind effects
cases considered, assuming a 5% uncertainty in interzonal and the large flow rates required for standard leakage tests
leakage. make the application of these techniques to tall buildings less
than straightforward.
INTRODUCTION
The objective of ASHRAE Research Project 935 (Bahn-
Building envelope tightness is of importance to owners, fleth et al. 1998) was to develop a method to evaluate the
operators, and tenants of tall buildings for operational, indoor airtightness of the envelope of tall buildings that represents the
environmental quality and financial reasons. Airflows through best compromise between simplicity and accuracy. Two leak-
envelope leakage paths caused by pressure differential due to age test procedures were developed for tall buildings by exten-
stack effect and wind have several undesirable effects. Uncon- sion of established pressurization test procedures. Criteria for
trolled entry of unconditioned outdoor air into occupied accurate application of these methods to tall buildings were
spaces may adversely affect comfort. Movement of air within developed. The procedures were tested in two different build-
a building as a result of envelope leakage may transfer ings and evaluated according to criteria including the value of
contaminated air. Leakage also adds to air-conditioning peak the information acquired, ease of use, and degree of disruption
loads and total energy consumption. The movement of air of building operations.

William P. Bahnfleth is an assistant professor in the Department of Architectural Engineering, Pennsylvania State University, University Park,
Pa. Grenville K. Yuill is director of Architectural Engineering at the University of Nebraska, Omaha, Neb. Brian W. Lee is a health facilities
officer at the U.S. Air Force Health Facilities Division, Atlanta, Ga.

THIS PREPRINT IS FOR DISCUSSION PURPOSES ONLY, FOR INCLUSION IN ASHRAE TRANSACTIONS 1999, V. 105, Pt. 2. Not to be reprinted in whole or in
part without written permission of the American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc., 1791 Tullie Circle, NE, Atlanta, GA 30329.
Opinions, findings, conclusions, or recommendations expressed in this paper are those of the author(s) and do not necessarily reflect the views of ASHRAE. Written
questions and comments regarding this paper should be received at ASHRAE no later than July 7, 1999.
Modeling of Envelope Leakage • Comparison of leakage flow rate at a standard pressure
Air leakage through the envelope of a building is typically differential calculated using Equation 1. A common
modeled as a power law function of pressure differential standard of comparison is the leakage flow rate at a
(ASHRAE 1997): pressure difference of 0.20 in. H 2O (50 Pa). This is
referred to as Q50.
Q = C∆P n (1) • Comparison of effective leakage area calculated from
flow rate at a standard pressure differential. A common
where reference pressure is 0.016 in. H2O (4 Pa), and the asso-
Q = airflow rate (cfm or m3/s), ciated effective leakage area is denoted as ELA4.
∆P = interior-exterior pressure difference (in. H2O or Pa), • Comparison of the average air changes per hour based
C = flow coefficient (ft3/[min⋅(in. H2O)n] or m3/[s⋅Pan]), on the calculated leakage rate at a standard pressure dif-
n = flow exponent (dimensionless). ferential.
The objective of most envelope leakage test methodolo- Leakage Testing Techniques
gies is to obtain the data needed to determine the coefficients
C and n. Evaluation factors for an envelope leakage measurement
Flow resistance depends upon the crack geometry, technique include accuracy, simplicity, cost-effectiveness,
entrance and exit effects, and wall composition. For fixed-size and minimal disruption of activities in occupied buildings. A
cracks, the flow exponent should vary between values of 0.5 variety of measurement techniques are described in the liter-
and 1.0. Fixed-size cracks with greater flow resistance behave ature. These include fan pressurization methods (CGSB 1996;
like capillaries and have flow exponents closer to 1. Large ASTM 1992); use of buoyancy caused by stack effect to create
cracks that offer little resistance to flow behave like orifices pressurization (Hayakawa and Togari 1990); and tracer gas
and have flow exponents closer to 0.5. If cracks open or close techniques (Kronvall 1980). Each method has advantages and
under the influence of pressure differential, values outside this disadvantages relative to the criteria stated above. A brief
range may be obtained. overview of the various approaches follows.
Wind pressure and stack effect cause pressure differen- The methods reviewed utilize natural or controlled pres-
tials across the envelope of a tall building to vary substantially surization and depressurization to create airflow through the
with height and surface orientation. Equation 1 can be applied building envelope. A correlation between flow and pressure
accurately to an entire building only if an appropriate average differential is derived from the results of a series of steady-
pressure difference, ∆PAvg, is used. This pressure difference is state tests over a range of pressure differential values
obtained by partitioning the building surface into zones of (Kronvall 1980). The pressurization method and method of
nearly uniform pressure differential and calculating the effec- measuring the airflow through the envelope are the distin-
tive whole-building pressure differential by area-weighted guishing characteristics of each test technique.
nonlinear averaging: Pressurization techniques described in the literature
include
M 1/n • use of building air distribution fans, with return and
 
 ∑ α i Ai ∆P in exhaust air dampers closed, to pressurize an entire
i = 1  building (Shaw et al. 1973);
∆PAvg =  ------------------------------- (2)
 ATotal  • use of a large external fan with sufficient capacity to
 
  pressurize an entire building as in a blower door test
(Shaw et al. 1990);
where • use of a portable blower door to pressurize a test zone in
Ai = envelope surface i area (ft2 or m2); a building (Hunt 1986; Modera 1995); and
∆Pi = absolute value of interior-exterior pressure • use of stack effect to pressurize or depressurize the
difference, |Pin − Pout|, across envelope surface i (in. whole building (Hayakawa and Togari 1990).
H2O or Pa); The largest uncertainty in envelope leakage testing is
αi = (Pin − Pout)i / |(Pin −Pout)i| (note: this factor accounts associated with leakage flow rate measurement (Kronvall
for the direction of flow through a surface, which is 1980). Total uncertainty depends upon the combination of
assumed to be positive from inside to outside); uncertainties in instrumentation accuracy, the interzonal air
transfer (in methods that test part of a building), and the
M = number of surfaces in tested zone;
M completeness of mixing (when tracer gas methods are used).
ATotal = ∑ Ai . The two most commonly used classes of techniques for
i=1 measuring leakage airflow rate are zone tracer gas concentra-
Envelope leakage comparisons may be made by a number tion methods and fan airflow measurement methods.
of methods, including the following. Zone tracer gas flow measurements are based on the rela-
• Direct comparison of C and n values. tionship between inflow of air to a zone by leakage and the

 
dilution of a known tracer gas source within the zone. The able accuracy in a leakage test. To limit loss of accuracy due
three most widely used zone tracer gas concentration flow to pressure asymmetry, it is essential to take at least one pres-
measurement techniques, as presented by Kronvall (1980), are sure measurement per exposure and to measure at multiple
• decay of tracer gas concentration, in which the leakage vertical locations when measurements are made for zones
rate is derived from the rate at which an initial concen- larger than one floor. Compensation for wind effects is partic-
tration of tracer gas changes with time; ularly problematic because of their transient nature. There-
• constant tracer gas concentration, in which the leakage fore, even spatial refinement of pressure measurements will
rate is inferred from the tracer gas flow rate required to not be sufficient to account for the effects of a high, gusty
maintain a steady concentration in the test zone; and wind. Under such conditions, it may be impossible to conduct
• constant tracer gas emission, in which leakage rate is a quasi-steady-state test.
related to the test zone tracer gas concentration associ- Because of the cost and analytical complexity of obtain-
ated with a fixed rate of release. ing accurate results when stack and wind effects are strong,
Tracer gases should be easily detectable, nontoxic, and it is prudent to limit the temperature range and maximum
not normally present within the building. Two of the most wind speed under which tests are conducted. Existing leak-
common gases used for airflow measurement are N2O and age testing standards provide guidelines for limiting these
SF6. effects. The authors concur with the specification in ASTM
Fan airflow measurement techniques measure the total Standard E 779 (ASTM 1992) that testing be limited to a
airflow through the pressurization fan, which is assumed to be range of outdoor temperature from 41°F to 95°F (5°C to
the same as the envelope leakage rate out of the test zone (or 35°C) to limit the influence of stack effect. However, the
related to it in a known way). This implies that interzonal leak- wind speed limit of 4 mph (2 m/s) established by ASTM
age is zero, a condition probably never achieved in practice. Standard E 779 may be overly conservative. Analysis has
However, if interzonal air transfer can be kept small, accurate been undertaken to determine whether a less restrictive
results can be obtained by this method. Fan airflow measure- criterion is acceptable.
ments may be done by any of several methods, including pitot
Regions of elevated pressure occur on building surfaces
tube traverse, blower door, or tracer gas dilution. The differ-
facing into the wind, and regions of depressed pressure occur
ence between the tracer gas dilution method applied to fan
on surfaces facing away from the wind. If wind speed is suffi-
airflow measurement and the zone tracer gas methods
ciently large, it can cause a negative pressure differential and
described previously is that the tracer is released in the duct-
inflow for some exposures while there is a large negative
work connected to the fan and its concentration is also
differential and increased outflow for other surfaces of a nomi-
measured there.
nally pressurized zone. Further, the distribution of pressure on
LEAKAGE TESTING ISSUES FOR TALL BUILDINGS a planar surface of a given orientation is nonuniform, so a
single pressure measurement per exposure may not be suffi-
Tall building envelope leakage predictions are subject to cient to represent outdoor pressure accurately when there is a
uncertainty that can arise from any of the following sources: high wind.
• wind pressure and stack effect (Modera and Wilson
Typical pressure distributions for tall building surfaces of
1990);
varying orientation have been published by Davenport and
• extreme pressure differential (either low or high) during
Hui (1982). An analysis of the effects of wind pressure has
leakage testing (Sherman and Palmiter 1995); and
been constructed using this data. A building of square plan
• extrapolation to the ELA4 differential of a correlation
shape was evaluated at orientations of 0 degrees and 30
derived from measurements at larger pressure differen-
degrees to the prevailing wind. Horizontal pressure coefficient
tials (Persily and Grot 1985).
Each of these potential problems and guidelines for limit-
ing the measurement uncertainty they create will be
discussed.
'HJUHH)DFH

Wind Pressure and Stack Effect Error 'HJ UHH)DFH

'HJUHH)DFH

'HJ UHH)DFH

Under zero wind and zero temperature difference condi-


tions, an envelope leakage measurement can be correlated
with a single measurement of indoor-outdoor pressure differ-
ential. Stack effect and wind pressure make the distribution of
pressure over the surface of a building nonuniform both hori-
zontally and vertically. As pressure asymmetry increases with Figure 1 Typical pressure coefficients as a function of
increasing wind speed or indoor-outdoor temperature differ- horizontal position on walls with various
ence, it becomes necessary to increase the spatial refinement orientations toward the wind (Davenport and Hui
of surface pressure measurements in order to maintain accept- 1982).

 
TABLE 1
Percent Error in Pressure Measurement Due to Wind Pressure (0 Degrees and 50 Pa)

Number of Pressure Taps

Wind Velocity MPH (m/s) 1 2 3 4 5 6 7 8 9


2 (0.9) 0.11 0.03 0.01 0.01 0.01 0.00 0.00 0.00 0.00
4 (1.8) 0.47 0.12 0.05 0.03 0.02 0.02 0.02 0.01 0.01
6 (2.7) 1.25 0.28 0.13 0.08 0.06 0.04 0.04 0.03 0.03
8 (3.6) 3.02 0.55 0.26 0.16 0.11 0.08 0.07 0.06 0.05
10 (4.5) 13.37 1.58 0.05 1.09 0.42 0.06 0.39 0.17 0.07
12 (5.3) 11.08 5.85 3.79 2.22 0.74 0.74 0.43 0.14 0.09
14 (6.2) 7.57 2.92 1.53 0.88 0.51 0.27 0.10 0.02 0.12
16 (7.1) 7.14 2.72 1.50 0.98 0.70 0.54 0.43 0.36 0.31
18 (8.0) 6.81 2.47 1.32 0.85 0.61 0.46 0.38 0.32 0.28
20 (8.9) 6.64 2.34 1.24 0.79 0.56 0.43 0.35 0.29 0.26

distributions were assumed to be worst-case values from Extrapolation Error


Davenport and Hui. Figure 1 shows the assumed pressure
It is common practice to describe the air leakage rate
coefficient values for the 30-degree orientation. Each of the
through a building envelope in terms of ELA4, effective leak-
four surfaces of the building was assumed to have one or more
age area at 4 Pa (0.016 in. H 2O). This allows the comparison
equally spaced exterior pressure measurements. Error in the
of buildings under “atmospheric” conditions. However large
nonlinear area-weighted exterior pressure was calculated as a
uncertainty is associated with extrapolating a power law leak-
function of wind speed.
age model to this very small differential. Uncertainty is small-
Typical results (for the zero degree orientation) are
est in the middle of the range of measured pressure differences
shown in Table 1. For wind speeds less than 9 mph (4 m/s),
(Persily and Grot 1986). Therefore, the authors recommend
the number of pressure taps has little effect on measurement
that tall building leakage be compared on the basis of airflow
uncertainty. In other words, one tap per exposure should be
per unit of envelope area at a pressure differential of 0.20 in.
sufficient provided that wind during a test is below this limit.
H2O (50 Pa), i.e., Q50/Area. This procedure makes use of the
For wind velocity exceeding 9 mph (4 m/s), the error
flow coefficient and exponent determined by regression anal-
increases substantially when there is only one tap per side.
ysis but eliminates error caused by extrapolation, as 0.20 in.
This error can be reduced to low levels at the cost of adding
H2O (50 Pa) is near the center of the range covered by the
additional taps. However, additional concerns arise when the
ASTM E779 procedure.
wind velocity exceeds 9 mph (4 m/s), such as the possibility
of flow reversal on the windward side of the building and
large pressure gradients within the test zone. Therefore, the LEAKAGE TESTING METHODS
authors recommend that the maximum wind velocity for FOR TESTING TALL BUILDINGS
envelope leakage testing be 9 mph (4 m/s). Two methods for testing the envelope leakage of tall
buildings were investigated: the floor-by-floor blower door
Low and High Pressure Differential Error method and the air-handler method. Both are pressurization/
Use of data from tests made at either low or high pres- depressurization methods intended to obtain the data needed
sure differentials can introduce large error into leakage to determine the coefficients of a leakage model of the form
modeling due to the uncertainty associated with measure- described by Equations 1 and 2. The purpose of the floor-by-
ment of small differentials and to departure from the power floor blower door method is to determine the envelope leakage
law relationship (Sherman and Palmiter 1995). To prevent of zones spanning a single floor. Internal leakage paths within
these problems, testing should be performed with interior- the building are sealed and the floors are pressurized by
exterior pressure differentials from 0.05 to 0.30 in. H2O blower door fans. Such a method would provide very detailed
(12.5 to 75 Pa), as prescribed by ASTM Standard E779 information about the leakage of a tall building; however, it
(ASTM 1992). It is also recommended, simply in the interest also poses the greatest challenges in application. The air-
of standardization of practice, that the series of pressure handler method measures the envelope leakage through each
differentials for a tall building test conform to ASTM Stan- air-handler zone. This method utilizes the building supply fans
dard E779, i.e., 0.05, 0.10, 0.15, 0.20, 0.25, 0.30 in. H2O centrally located in the mechanical room to pressurize the air-
(12.5, 25, 37.5, 50, 62.5, 75 Pa). handling zone. Its primary limitation is the minimum size of

 
Air-Handler Method
The air-handler method uses air-handler fans to pressur-
ize a portion of a building that can vary in size from the area
served by a single fan to the entire building. The test objective
is to measure the envelope leakage associated with the test
zone, which is equal to the quantity of outdoor air brought in
by the system air handler to maintain the interior pressure. The
major differences between this method and the floor-by-floor
blower door method are the size of the zone served by the
Figure 2 Floor-by-floor blower door testing method
building air handler and the lack of the need for an independent
schematic.
fan pressurization unit. In the air-handler method, the test zone
the zone that can be tested, but in application it has advantages is defined as the part of the building served by the air handler
in terms of simplicity of implementation. to which the airflow is being measured. The test zone can vary
in size from a single air-handler zone to a whole building,
Floor-by-Floor Blower Door Method depending on the air-handler configuration. Tests can be
conducted with the air-handling unit in 100% outside air mode
The floor-by-floor blower door test procedure uses
or with recirculation.
portable blower doors to pressurize the test floor and adja-
The major advantage of the air-handler method is the
cent floors. Blower doors can be installed either in a door
rapidity of installation of the flow measurement devices, all of
leading to a stairwell shaft or mounted directly to an existing
which are centrally located within the air-handler. The main
opening to the outside, such as an operable window.
disadvantage of this method is that it may not be possible to
Commercial blower doors are available with the flow
determine the location of the leaks in the exterior envelope as
measurement and data-logging capabilities needed to
precisely as is possible with the floor-by-floor blower door
conduct standard tests.
method. However, if a building has more than one air-handler,
A typical test setup is shown in Figure 2. Airflow rates are a degree of localization of leakage can be achieved.
indicated by the symbol “Q” and pressures by the symbol “P.” As noted previously, the outdoor airflow rate entering an
If, as shown, only the test floor is pressurized, there will be air handler can be determined by several methods, including
leakage to the adjacent upper and lower floors and it will be tracer gas dilution, orifice plate, and pitot traverse. The tracer
impossible to separate envelope leakage from interzonal gas method is easily set up in the air handler, but care must be
transfer. Interzonal leakage (QUp and QDown) can be elimi- taken to ensure that the tracer gas is thoroughly mixed with the
nated (for practical purposes) if the floors above and below the airstream at points where concentration measurements are
test floor are pressurized so that pressures PUp, PDown, and PTest made. The orifice plate method requires that a calibrated
are equal. This requires a minimum of two additional blower orifice be installed in the outdoor air path. In general, the
doors, one for each of the adjacent floors. Alternatively, air- orifice plate must be calibrated on site because building and
handling unit fans may be controlled to achieve the same duct geometry may affect its performance. Access to the
result. Under these conditions, the fan flow rate, QFan, and the outdoor air supply duct or grille is also required and will
envelope leakage rate, QOut, should be equal when corrected preclude the use of this technique in many high-rise buildings.
to standard temperature and pressure (i.e., the mass flows they The duct pitot traverse is feasible in most cases; however, the
represent are equal). accuracy of results will depend upon the accessibility of suit-
A potential advantage of the floor-by-floor blower door able locations for measurement.
method is that it can be used to determine the floor-by-floor Fan capacity must be adjusted during testing to produce
distribution of envelope leakage. The ability to pinpoint areas the required series of pressure differences. If the air handler is
of large envelope leakage would be an asset when determin- configured for a 100% outside air test, airflow rate (and, there-
ing which envelope areas should be repaired. A logistical fore, pressure differential) can be controlled by any of several
advantage of this procedure is that the leakage test can be set methods, including adjustment of fan inlet or outlet vane posi-
up on the unoccupied floors of an occupied building. tion, fan speed control, or adjustment of outdoor air damper
The major disadvantage of this method is the setup time position. If these methods are not capable of producing a suffi-
required. Interior leakage paths from the testing floor to all ciently low differential, control of recirculation by modulating
other building components (i.e., elevator and stair shafts and mixed air and outdoor air dampers can be used to obtain lower
ductwork) must be sealed. This can be a very difficult task in outdoor airflow at a higher fan flow rate. The recirculated
a large building, since there can be many vertical shafts airflow will lower the zone pressure differential, but it will
through a single floor. A blower door test can be completed increase the uncertainty in tracer gas dilution flow measure-
by a one- or two-person crew. Sealing of leakage prior to test- ments.
ing can be done by any number but is expedited by larger Air-Handler Method with Tracer Gas Flow Measure-
numbers. ment. For both pitot traverse and orifice plate outdoor airflow

 
Figure 3 Air-handler tracer gas outdoor airflow rate
measurement, recirculating case.
Figure 4 Tracer gas injection/sampling manifold.
rate measurements, there is no difference between the 100%
outside air and recirculating cases. In either instance, the flow The outdoor airflow rate, therefore, is
measurement must be made directly on the outdoor airstream.
S C Ret2 – C Sup
When tracer gas flow measurement is used, the measurement Q OA = -----------  --------------------------------- (6)
C Sup C Ret2 – C Ret1
system configuration for 100% outdoor air is different from
the configuration when there is recirculation. This section Because there is recirculation, the concentrations
describes the procedures required for each case. measured in this procedure will increase over time until a
Recirculating airflow. Outdoor airflow measurement by steady state is achieved. Final measurements for the purpose
tracer gas dilution in an air handler with recirculation is shown of calculating leakage rate should be taken under steady condi-
in Figure 3. Because the relief air damper is closed and sealed, tions.
the supply airflow rate QSup is equal to the sum of the return Uniform mixing of the tracer gas and measurement of the
airflow QRet and the outdoor airflow QOA. In general, it will not correct average concentration are essential to realizing the
be possible to make a single dilution measurement in the potentially high accuracy of this method. An injection/with-
outdoor air intake, so the general case requires injection of the drawal manifold designed to achieve these objectives is shown
tracer source S into the return and measurement of tracer in Figure 4. This device can be used to distribute the tracer
concentration at three locations, two in the return (CRet1 and over the full cross section of the duct and also to sample from
CRet2) and one in the supply (CSup). Measurement of the source multiple locations over the full cross section of the duct. Addi-
strength and three concentrations permits the outdoor airflow tional mixing provided by the fan will increase the possibility
rate to be calculated by simultaneous solution of the following of a well-mixed flow downstream.
three conservation equations:
One hundred percent outdoor air. A typical setup for
Tracer gas balance at injection point:
air-handler pressurization with 100% outdoor air is shown in
S Figure 5. Both the exhaust and return air dampers are closed
Q Ret = -------------------------------------- (3)
( C Ret2 – C Ret1 ) and sealed, so return flow is zero and supply and outdoor
airflows are identical. This simplifies data collection and
Tracer gas balance at mixed air section: reduces measurement uncertainty by eliminating the need for
the two return concentration sensors. Because the concentra-
C Ret2
Q Sup = QRet  ------------- (4) tion of tracer gas in outdoor air is zero, a single concentration
C Sup
measurement downstream of the tracer source is sufficient to
determine flow rate:
Total airflow balance at mixed air section:
Q OA = Q Sup – Q Ret (5)

where
QRet = return airflow rate (ft3/min, m3/s),
QSup = supply airflow rate (ft3/min, m3/s),
QOA = outdoor airflow rate (ft3/min, m3/s),
S = tracer gas supply quantity (ppm⋅ft3/min, ppm⋅m3/s),
CRet1 = tracer gas concentration in return air/building (ppm),
CRet2 = tracer gas concentration in return air after tracer gas
injection (ppm), Figure 5 Air-handler tracer gas outdoor airflow rate
measurement, 100% OA case.
CSup = tracer gas concentration in supply air (ppm).

 
S ground floor). During testing, the entire building was pres-
Q OA = ----------- (7)
C Sup surized; however, leakage was measured only in the upper
air-handling zone, which spans floors 49 through 61. Vari-
The tracer gas is injected upstream of the outdoor air able-air-volume (VAV) supply fans are designed to trans-
dampers, or as close to the outdoor air damper as possible, port a maximum of 500,000 cfm (236 m3/s) to this zone
and the concentration is measured downstream of the fan. from air handlers located on the 64th floor. Approximately
Because the flow rate through the fan should remain nearly 400,000 cfm (189 m3/s) is returned from those floors. To
constant throughout a test, the measured tracer gas concen- achieve the desired pressures required for the air-handler
tration will quickly reach steady state. As noted above, a test procedure, only two supply air handlers, each with a
significant lag exists between the initiation of tracer release capacity of 96,000 cfm (45.3 m3/s), were used.
and the establishment of steady state when there is recircula- Equipment and materials required for these tests included
tion. the following.
TRIAL APPLICATION OF • Blower doors, made of an impermeable fabric attached
LEAKAGE TEST METHODS to an expandable frame able to create a seal against stan-
dard door frames. A fan, used to induce either positive
The proposed leakage test methods were applied in two or negative pressure to the space, is attached to a prefab-
buildings, a 6-story university library located in central Penn- ricated hole in the fabric. The fan is constructed of
sylvania and a 64-story office building located in Pittsburgh, molded plastic and outfitted with a 3/4 hp (0.56 kW) AC
Pennsylvania. motor that has a design flow of 6,400 cfm (3 m3/s). The
fan flow measurements have been factory calibrated to
Site 1—University Library
±3% of the actual flow.
The library is a 130,000 ft2 wing of the main library at a • Digital pressure gauges, used to measure the pres-
university. The building is six stories in height with two inter- sure differential across each face of the building dur-
nal elevator shafts and three perimeter stair shafts. It has a ing the pressurization testing. They indicate pressures
nearly triangular footprint. Two sides of the library are brick from 0.0 to 0.80 in. H2O (0.0 to 199.9 Pa) with an
veneer with fixed windows and the third is a glass curtain wall accuracy of ±1% of reading.
extending from ground level to the top of the building. The
• Automatic tracer gas monitor with a microprocessor-
building has a poured concrete structural system. The
controlled electron capture gas chromatograph. The
mechanical system serving the library is equipped with
monitor was used to measure the concentration of sulfur
central chilled water and hot water production and central air
hexafluoride present in the space. The monitor has an
distribution. Two air handlers located in a mechanical room
onboard supply of calibration gas diluted in ultra-pure
on the ground level supply floors one through four and two
air. An onboard vacuum pump pulls the test air into the
rooftop air-handling units located on the roof serve the fifth
chromatograph. Measurements are stored on a diskette
floor. The two main constant-speed supply air fans supply
during testing for later off-line analysis. The accuracy of
78,000 cfm (36.8 m3/s) and 67,000 cfm (31.6 m3/s), respec-
the tracer gas monitor is ±3% of the reading in its linear
tively. Indoor comfort is maintained through the use of reheat
dynamic range, 0.05 to 10 ppb.
coils located in the distribution air ducts. In addition to the
supply fans, there are also two return fans with capacities of • Sealing material used to cover large areas, such as the
93,000 cfm (43.9 m3/s) and 44,000 cfm (20.8 m3/s). An exhaust and return dampers, in both the library and
exhaust fan located on the roof serves the lavatories. the office building. A six mil plastic sheeting was
used.
Site 2—Office Building • Duct tape was used to adhere the plastic sheeting to the
The office building is a 64-story, 841 ft (256 m) tall return grilles in the blower door method. Additionally,
structure located in Pittsburgh, Pennsylvania. It encloses duct tape was also used to seal doors between zones by
approximately 2.9 million ft2 (270,000 m2) of floor area, of covering the crack between the door frame and the door
which 2.4 million ft2 (220,000 m2) is leasable. The office itself.
building has an exterior structural steel frame with curtain • Injection / withdrawal manifold, designed to achieve
wall construction. All the windows in the building are uniform dispersion of the tracer gas in the ducts and
operable and are routinely opened for cleaning purposes. provide accurate average samples. The manifold had a
At the time of testing, window mullions were in the early rigid return/supply header across the duct with evenly
stages of being retrofitted to eliminate direct air passage spaced flexible tubes dropping vertically through the
through the large openings between the widow and the cross section of the duct. This arrangement permitted
window frame that was evident in most windows. Four easy transport and installation of the manifold. Pinhole
mechanical rooms are located throughout the building (on orifices were distributed along each of the flexible
floors 3, 34, 63/64, and on the general concourse level/ tubes.

 
RESULTS

Floor-by-Floor Blower Door Method


Testing was conducted first at the university library site,
beginning with the floor-by-floor blower door method.
Numerous attempts were made to execute this procedure, but
adequately sealing a single floor to isolate it from its neighbors
was found to be impossible. Elevators, doors, ducts, and other
apparent leakage paths were carefully and completely sealed,
yet a large amount of additional, inaccessible floor-to-floor
leakage remained. This was evident because, with the test
floor sealed and adjacent floors pressurized by additional
blower doors, high pressures were recorded on the test floor Figure 6 Five-story library test data (9 July 1997).
when the blower door fan was off. The inability to adequately
seal the test floor is perhaps more significant in view of the fact conducted only at the library site because the outside air grille
that a crew of four workers spent nearly three hours in the of the tested zone of the tall office building was not accessible.
effort on each occasion that the procedure was tested. Extrap- It was desired to compare orifice and tracer measurements at
olating this level of effort very roughly to the larger office the library. Unfortunately, the unforeseen early start of remod-
building, one obtains an estimate on the order of 500-1,000 eling at this site resulted in the envelope undergoing consid-
person hours simply to seal interfloor leakage paths. erable change between the orifice plate and tracer gas tests.
Further efforts to find hidden leaks did not substantially Consequently, results of the two procedures could not be
reduce interzonal leakage. Numerous holes and cracks that compared directly. In addition, reliable calibration of the
could not be reached and sealed were found in return risers and orifice plate in the field proved difficult to obtain. For these
elevator shafts. Further, the return air shaft was found to be reasons, orifice plate results are not discussed in this paper.
constructed of 16 in. concrete masonry unit (CMU) blocks that Discussion of these tests may be found in the final report for
offer only a small resistance to airflow. Sealing this return this project (Bahnfleth et al. 1998).
shaft leakage was not feasible. It was concluded on the basis
Tracer Gas Flow Measurement. Results obtained using
of these discouraging experiences that the floor-by-floor
tracer gas flow measurement were consistent and repeatable.
blower door test method is impractical for general use and it
The concentration downstream of the supply air fan for two
was not tested further.
typical, 12-minute tests at the six-story library is shown in
It is possible that a floor-by-floor method could be applied Figure 6. This figure indicates both the repeatability of typical
more successfully in buildings with floor-by-floor air- tests and how rapidly steady state was achieved. The outdoor
handling systems. In such buildings, there are no riser shafts airflow rates used to compute the envelope leakage flow coef-
to serve as large interzonal leakage paths. However, elevator ficient and exponent were the average of the last three
and stair shafts must be sealed. At the library test site, elevator measured values for each test run, (minutes 8, 10, and 12),
shafts were constructed of poured concrete and were essen- which, as can be seen, are essentially steady-state values.
tially impervious to leakage once the doors were sealed with
Tables 2 and 3 summarize tracer gas test results for the
plastic sheeting. When this is the case, there is some hope of
6-story library and the 64-story office building, respectively.
reducing leakage area between floors to the extent that blower
The most striking aspect of these results is that flow expo-
doors can be used to zero the interzonal flow.
nents for the library are somewhat lower than the theoretical
At the completion of blower door testing, the three-person minimum value of 0.5 for fixed-size cracks and that the
crews were working approximately eight hours per test zone result for the office building exceeds the theoretical maxi-
at the library, or a total of 24 person-hours per floor. In larger mum of 1.0. This variation in flow exponent values may be
buildings, the time requirement for sealing could be expected caused by the change in leakage path areas under the influ-
to increase in proportion to the floor area of the building, while ence of pressure differential. This explanation would suggest
the 12 person-hours required for actual testing should remain that increased pressure differential at the library site tended
relatively constant. to open leakage paths, at least prior to the removal of the
curtain wall.
Air-Handler Method
After gaining experience with the tracer gas method at the
The air-handler method was tested at both the university library test site, the authors found the second application at the
library and office building sites. In both buildings the simpler, office building site to be relatively easy. Preparation consisted
more accurate, 100% outdoor air configuration was found to of inspection of mechanical drawings and one visit to the
be workable. The tracer gas flow measurement method was building. The complete test setup and removal, with a crew of
tested at both sites. Orifice plate flow measurements were two persons, was performed in two hours. Testing required a

 
TABLE 2
Results of Air-Handler Pressurization with 100% Outdoor Air Tracer Gas Flow Measurement (Library)

5-Story Library

C n Q50 Q50/Unit Area

Test cfm/(in. H2O)n m3/s⋅Pan dimensionless cfm m3/s cfm/ft2 (m3/s)/m3


1 43,497 1.62 0.46 20,746 9.79 0.400 0.00203
2 41,604 1.73 0.44 20,492 9.67 0.396 0.00201
3 38,994 1.81 0.42 19,835 9.36 0.383 0.00194

TABLE 3
Results of Air-Handler Pressurization with 100% Outdoor Air Tracer Gas Flow Measurement (Office Building)

64-Story Office

C n Q50 Q50/Unit Area

Test cfm/(in. H2O)n m3/s⋅Pan dimensionless cfm m3/s cfm/ft2 (m3/s)/m3


1 52,700 0.19 1.30 65,085 30.72 0.435 0.00221

crew of four persons to move from floor to floor and measure handling system zones. When a building has floor-by-floor
the pressure on each level. This testing lasted 4 hours (16 air-handling systems, the air-handling system method may be
person hours). This totals to approximately 24 person-hours, applicable on a floor-by-floor level.
or less than 2 person-hours per floor, including setup. This is The air-handler method with tracer gas flow measure-
far superior in labor requirement to the time spent in the ment requires a working knowledge of the relatively complex
blower door method. tracer gas testing equipment. However, equipment for this
measurement procedure is quickly set up in the mechanical
DISCUSSION room and testing can then begin with little lead time. Once the
The leakage testing procedures considered in this user has gained familiarity with the procedure, testing can be
research can be applied to a variety of tall buildings. However, completed quickly and smoothly.
because of the diversity of HVAC system types found in high-
rise construction, it is unlikely that a single test procedure Tracer Gas Leakage Measurement Uncertainty
would be applicable to every tall building. The best envelope Tracer gas flow measurement proved to be relatively easy
leakage test procedure for each application will be determined to carry out as well as very accurate. Aside from the initial
by the characteristics of the building being tested. expense of the necessary equipment, it appears to be a gener-
A major factor in the selection of the best test procedure ally superior method for measuring flow rate in tall building
is the type of space conditioning systems in a building. A leakage tests. The uncertainty associated with tracer gas leak-
building with central air-handling units serving multiple floors age measurements was evaluated by means of a root sum
typically has numerous additional interfloor leakage paths due square error analysis as described in, for example, Doebelin
to supply and return shaft penetrations. These flow paths (1975).
frequently are inaccessible by reasonable means and preclude Uncertainty in a tracer gas envelope leakage flow rate
tight sealing on a floor-by-floor level, as is required for blower measurement is a function of uncertainties in the tracer source
door testing. Even if leaks are accessible, thorough sealing is strength, concentration measurements, and interzonal leakage
a difficult, labor-intensive job. In this situation, the air- from the test zone to other interior areas of a building. The
handling system method will provide the best results, for three expression for this error in terms of root square error is
reasons. One is that the ratio of the envelope leakage area to
 ∂Q OA  2  ∂Q OA  2  ∂Q OA
0.5
the interfloor leakage area is increased when several floors are 2
 -------------------- ∆C Ret1 +  -------------------- ∆C Ret2 +  ----------------- ∆C Sup1
tested at once. The second is that the air-handling system  ∂C Ret1   ∂C Ret2   ∂C Sup 
Error RSS =
method can achieve higher building pressures, so that the ratio ∂Q 2
+  ---------------- ∆S + ( Interzone Leakage ) 2
OA
of the building pressure to the interfloor pressure difference  ∂S 
caused by imperfect balancing of the pressures on neighboring
(8)
floors is greater. The third reason is that in some buildings
there will be fewer openings through the floors between air- The partial derivatives of leakage flow rate shown in
handling system zones than through the floors within air- Equation 8 are calculated by differentiation of the appropriate

 
form of the tracer gas method expression for leakage flow TABLE 4
rate—Equation 6 when there is recirculation and Equation 7 Tracer Gas Flow Measurement
when the 100% outdoor air configuration is used. Component Uncertainty Values
Component errors used in estimating uncertainty are
summarized in Table 4. Values were obtained from manufac- Source of Error Error (%)
turers’ specifications for instrumentation. In the cases of inter- 1. SF6 concentration supply flow rate reading error (ppb⋅L/s) 3
zonal leakage, an estimated value of 5% of total flow rate was
2. SF6 supply flow loss in fittings (ppb⋅L/s) 5
assumed based on the construction of the office building and
anticipated deviation from zero pressure differential across the 3. Uneven SF6 distribution in duct (ppb⋅L/s) 10
top and bottom of the tested zone. The resulting absolute and 4. Return 1 concentration reading error (ppb) 3
relative error for six tests is shown in Table 5.
5. Return 2 concentration reading error (ppb) 3
Q50 Uncertainty 6. Supply concentration reading error (ppb) 3
The leakage rate estimate at 50 Pa, Q50, is the most 7. Interzonal leakage (L/s) 5
common standard for comparison of envelope leakage values
(Sherman and Palmiter 1995). It is calculated using the flow TABLE 5
coefficient and flow exponent, determined by regression anal- Absolute and Relative Error for Leakage Rate
ysis of test data, to estimate the leakage rate at a pressure Measured by Tracer Gas Dilution (Library)
difference of 50 Pa. The uncertainty introduced by a poor fit
to the test data must be accounted for in this procedure. Deriv- Tracer Gas with Tracer Gas with 100%
Recirculating Air Outdoor Air
ing the statistical uncertainty in the leakage flow rate estimate
requires analysis beyond the scope of this project. Therefore, Absolute Error Relative Absolute Error Relative
total error was estimated via a numerical experiment. Errors in Test cfm (m3/s) Error (%) cfm (m3/s) Error (%)
flow rate and pressure “measurement” values were produced
1 5720 (2.70) 8.8
by a random number generator using known component
uncertainties and added to “exact” values generated by an 2 5265 (2.48) 8.1
assumed power law leakage model (Bahnfleth et al. 1998). 3 4550 (2.15) 7.0
Flow rate measurement uncertainty was assumed to
4 7425 (3.50) 5.6
correspond to the tracer gas procedure, roughly 6% to 9%. To
this was added uncertainty in measurement of pressure differ- 5 7280 (3.43) 5.5
ential, which arises from pressure sensor accuracy limitations 6 7163 (3.38) 5.4
and error induced by wind pressure. The instrument error for
the pressure gauges used is one percent of the pressure read- TABLE 6
ing, as given by the pressure sensor manufacturer. The wind Relative Uncertainty in the Q50 Flow Rate Estimate
error is a function of the wind speed, number of pressure at a Wind Speed of 8.9 mph (4 m/s)
sensors, location of pressure sensors, and orientation of the
building. Wind error uncertainties derived as described previ- Number of Sensors per Wall Face Total Error in the Flow Rate
ously were used in this analysis. 1 3.28%
The estimated total uncertainty in Q50 for a wind speed
2 3.43%
of 9 mph (4 m/s) is shown in Table 6. The maximum value is
slightly less than 3.5%. For a speed of 6 m/s, the maximum 3 3.21%
uncertainty increases to more than 4.5%. Inspection of this 4 3.16%
table indicates that the number of pressure sensors across the
5 3.23%
face of the wall does not significantly decrease the overall
uncertainty in the flow measurement. This result may seem 6 2.96%
counterintuitive; however, it results from the fact that flow
measurement uncertainty is substantially larger than the address the problems arising in tall building leakage measure-
pressure measurement uncertainty at a wind speed of 9 mph ments. However, they and other published leakage measure-
(4 m/s). ment methods provide a variety of options suitable for
development into methods applicable to tall buildings.
SUMMARY AND CONCLUSIONS
Procedures for application to tall buildings require refine-
This research has reviewed methods used to measure ments and extension of generic procedures to overcome obsta-
envelope leakage rate and evaluated their applicability to tall cles to accurate measurement that are much less significant in
buildings. The two existing envelope leakage pressurization small, low-rise buildings. These include large envelope leak-
standards, ASTM Standard E779 (ASTM 1992) and the CAN/ age area, interfloor leakage, wind pressure, long vertical

 
shafts, and stack effect. These factors compromise the effec- on recommendations in existing standards and from the expe-
tiveness of established methods and motivate the development rience gained in this project. The guidelines are intended to
of a method specific to tall buildings. This project has inves- limit uncertainty caused by poor regression analysis, varying
tigated two candidate procedures for measuring the envelope wind pressure, building orientation, and stack effect.
leakage of tall buildings: the floor-by-floor blower door General guidelines for conducting a pressurization test
method and the air-handler method. These methods are pres- include the following.
surization test procedures of a type widely used for smaller
To improve the precision of the regression analysis:
buildings that have been adapted for use in tall buildings. Both
were tested on two large buildings. • Minimum envelope pressure differential = 0.05 in. H2O
(12.5 Pa)
The floor-by-floor blower door method procedure is
• Maximum envelope pressure differential = 0.30 in. H2O
intended to isolate a selected floor of a building to determine
(75 Pa)
the envelope leakage rate associated with that test floor. This
method has conceptual merits, such as the ability to locate the To reduce the effects of wind pressure due to wind speed and
vertical position of large envelope leakage. Unfortunately, its building orientation:
applicability to tall buildings is rather limited because sealing • Maximum wind velocity = 9 mph (4 m/s)
leakage paths between floors and through shafts is an impos- To reduce the effects of stack effect:
sible task in many buildings. Testing of this method in a build-
• Minimum outside temperature = 41°F (5°C)
ing with a central air distribution system was not successful.
Buildings with either floor-by-floor air-handling units or • Maximum outside temperature = 95°F (35°C)
through-the-wall ventilating units, both with limited vertical The authors have shown through simulation that if the
shafts, are ideal for the blower door testing method and seem preceding set of guidelines is followed, the overall uncertainty
to compose the extent of its range of test buildings. in the estimate of the leakage flow rate at 0.20 in. H2O (50 Pa),
The air-handler method has a wider range of applicability. Q50, can be as low as 3%.
This method uses the air-handler to pressurize a portion of the As is the case with most field measurement methods, the
envelope varying in size from a single zone to the entire build- ease of use and accuracy of the leakage testing procedures
ing. The majority of tall buildings have large centralized air- considered in this project are in inverse proportion to the ambi-
handling units and are compatible with this method. tiousness of the test objectives. As a procedure for character-
izing the leakage of the whole building envelope (including
A number of flow measurement techniques can be used
normal but uncontrolled leakage through openings at the tops
in the air-handler method, including tracer gas dilution,
of elevator shafts and stairways and similar paths), the air-
orifice plate, and pitot tube traverse. Measurement tech-
handler method is very satisfactory and has been shown
niques that were tested in this research were tracer gas with
analytically and in application to be repeatable and accurate.
recirculation, tracer gas with 100% outdoor air, and orifice
It will be harder to use this method for measuring leakage
plate. Orifice plate measurements at the library were not
through a particular leakage path, such as the exterior walls of
satisfactory because of field calibration problems. The tracer
buildings. In order to make such a measurement the user must
gas test with 100% outdoor airflow resulted in Q50 of
seal all the leakage paths that are not to be included. In a large
20,400 cfm (9.61 m3/s) for the five-story library. The 64-
building this could be a difficult task.
story office building was tested with the tracer gas with
100% outdoor air method and was found to have Q50 of
REFERENCES
65,100 cfm (30.72 m3/s) for a 13-story zone. These results
can be compared on the basis of Q50 per unit of envelope ASTM. 1992. ASTM Standard E779-92, Standard test
area. Values of Q50/A for the library and the office building method for determining air leakage rate by fan pressur-
were, respectively, 0.393 cfm/ft2 (0.00199 (m3/s)/m2) and ization. Philadelphia: American Society for Testing and
0.435 cfm/ft2 (0.00221 (m3/s)/m2). Materials.
The uncertainty of tracer gas flow rate measurement and ASHRAE. 1997. 1997 ASHRAE Handbook—Fundamen-
of Q50 were investigated by means of a root sum square error tals. Atlanta: American Society of Heating, Refrigerat-
analysis. Flow measurement uncertainty for the tracer gas ing and Air-Conditioning Engineers, Inc.
method was found to be 8.8% or less with recirculation and Bahnfleth, W.P., G.K Yuill, and B.W. Lee. 1998. Protocol
5.6% or less with 100% outdoor air. These flow rate uncer- for field testing of tall buildings to determine envelope
tainties include an interzonal leakage estimate of 5%. The air leakage rate. Final Report for ASHRAE Research
overall uncertainty Q50 was estimated to be 3.0% to 4.6% for Project 935.
a wind speed range from 790 to 1180 ft/min (4 to 6 m/s) and CGSB. 1996. CAN/CGSB-149.15, Determination of the
1 to 6 pressure taps per exposure. overall envelope airtightness of buildings by the fan
Guidelines have been proposed to promote accurate test- pressurization method using the building’s air handling
ing of building envelope leakage. These guidelines are based system. Ottawa: Canadian General Standards Board.

 
Doebelin, E.O. 1975. Measurement systems: Application 1067, Air change rate and airtightness in buildings,
and design. New York: McGraw Hill. M.H. Sherman, ed. Philadelphia: American Society for
Davenport, A.G., and H.Y.L. Hui. 1982. External and inter- Testing and Materials.
nal wind pressures on cladding of buildings. Boundary Persily, A.K., and R.A. Grot. 1985. Accuracy in pressuriza-
Layer Wind Tunnel Laboratory, University of Western tion data analysis. ASHRAE Transactions 91 (2): 105-
Ontario, London, Ontario, Canada. BLWT-820133. 116.
Hayakawa, S., and S. Togari. 1990. Simple test method for
evaluating exterior wall airtightness of tall office build- Persily, A.K., and R.A. Grot. 1986. Pressurization testing of
ings. ASTM STP 1067, Air change rate and airtightness federal buildings. ASTM STP 904, Measured air leak-
in buildings, M.H. Sherman, ed. Philadelphia: American age of buildings, H.R. Trechsel and P.L. Lagus, eds.
Society for Testing and Materials. Philadelphia: American Society for Testing and Materi-
Hunt, C.M. 1986. Some induced-pressure measurements in a als.
high-rise office building. ASTM STP 904, Measured Air Shaw, C.Y., S. Gasparetto, and J.T. Reardon. 1990. Methods
Leakage of Buildings, H.R. Trechsel and P.L. Lagus, for measuring air leakage in high-rise apartments. ASTM
eds. Philadelphia: American Society for Testing and STP 1067, Air change rate and airtightness in buildings,
Materials. M.H. Sherman, ed. Philadelphia: American Society for
Kronvall, J. 1980. Airtightness—Measurements and mea- Testing and Materials.
surement methods. Swedish Council for Research.
Stockholm, Sweden. Shaw, C.Y., D.M. Sander, and G.T. Tamura. 1973. Air leak-
Modera, M.P. 1995. Field comparison of alternative tech- age measurements of the exterior walls of tall buildings.
niques for measuring air distribution system leakage. ASHRAE Transactions 79 (2): 40-48.
ASTM STP 1255, Airflow performance of building enve- Sherman, M., and L. Palmiter. 1995. Uncertainties in fan
lopes, components and systems, pp. 284-298. Philadel- pressurization measurements. ASTM STP 1255, Airflow
phia: American Society for Testing and Materials. performance of building envelopes, components and
Modera, M.P., and D.J. Wilson. 1990. The effects of wind on systems, pp. 266-283. Philadelphia: American Society
residential building leakage measurements. ASTM STP for Testing and Materials.

 

View publication stats

You might also like