Professional Documents
Culture Documents
TABLE OF CONTENTS
Page
Section Description
Ref.
1.0 Introduction .......................................................................................................................................5
1.1 Purpose....................................................................................................................................5
1.2 Scope........................................................................................................................................5
1.2.1 Definitions and Overall Document Layout for Protective Coating Specifications and Scopes of Work
for RasGas Operations (Onshore and Offshore) ..............................................................................................5
1.2.2 General Safety And Hazard Considerations............................................................................................6
1.3 Definition.................................................................................................................................7
1.4 References ...............................................................................................................................8
1.5 Roles & Responsibilities ......................................................................................................11
1.5.1 Operations Technical Manager........................................................................................................11
1.5.2 Static Equipment Engineering Manager ..........................................................................................11
1.5.3 Head of Corrosion Engineering .......................................................................................................11
1.5.4 Coating Engineer .............................................................................................................................12
1.6 Procedures ............................................................................................................................13
1.6.1 Inspection Requirements: ................................................................................................................13
1.6.1.1 General inspection requirements ...................................................................................................13
1.6.1.2 Inspection System Requirements ..................................................................................................13
1.6.1.3 Inspection of Equipment, Materials and Access Facilities............................................................15
1.6.2 Mandatory Requirements For All Painting Works ..........................................................................15
1.6.2.1 Mandatory Procedures: .................................................................................................................15
1.6.2.2 Additional Mandatory Procedures for ‘Tidal Zone’ Painting works:............................................16
1.6.2.3 Exceptions:....................................................................................................................................16
1.6.3 Pre- Blasting Operations And Post Blasting Operations .................................................................17
1.6.3.1 Pre-Blasting Operations ................................................................................................................17
1.6.3.2 Post-Blasting operations................................................................................................................17
1.6.4 Surface Preparation..........................................................................................................................17
1.6.4.1 Surface Preparation Method- Carbon Steel...................................................................................17
1.6.4.2 Surface Preparation Method- Stainless Steel, Galvanized Steel, Nickel Alloy.............................18
1.6.5 General Coating Guidelines (For All Surfaces):..............................................................................19
1.6.5.1 Application Guidelines..................................................................................................................19
2.0 Coating Systems (Scopes and Specifications)................................................................................21
2.1 Section 1- Uninsulated Carbon Steel Coating System (Non-impact areas), above the splash zone, operating
at Ambient up to +100°C....................................................................................................................................21
2.2 Section 2- Uninsulated Carbon Steel Coating System in the Splash Zone, Tidal Zone and Sea Water Intake
structures operating at Ambient upto +100°C ....................................................................................................24
2.3 Section 3- Uninsulated Stainless/Galvanized Steel, Nickel Alloy Coating System operating at ambient up to
+100°C................................................................................................................................................................26
2.4 Section 4- Uninsulated Carbon Steel Coating Specification, above splash zone, for Impact Areas like deck
plates/troughs/base plates/ lay down areas/flooring............................................................................................28
2.5 Section 5- Uninsulated Carbon Steel, Stainless Steel, Galvanised Steel, Nickel Alloy operating at +101°C
upto +150°C (flex. Upto +200°C) ......................................................................................................................30
2.6 Section 6-Uninsulated Carbon Steel, Stainless Steel, Nickel Alloy surfaces operating at +151°C upto +540°C
RasGas Company Limited
Maintenance Coating Manual
** ........................................................................................................................................................................32
2.7 Section 7- Insulated Carbon Steel, Stainless Steel, Galvanised Steel operating at ambient below +120°C .34
2.8 Section 8- Insulated Steel surfaces operating at elevated temperatures (operating at +120°C and above)...35
2.9 Section 9- Uninsulated Carbon Steel Coating System in Internal, Air -conditioned areas ...........................37
2.10 Section 10- Insulated/Un-insulated Carbon/Stainless steel subject to cyclic Temperatures of +5 °C to
+300°C................................................................................................................................................................39
2.11 Section 11- COMPOSITE WRAP REPAIR SYSTEM (Protection System # RMC-CR-11).....................41
3.0 Training and Support - ...................................................................................................................52
4.0 Verification and Measurement - ....................................................................................................52
5.0 Feedback and Continual Improvement -.......................................................................................52
6.0 Appendices .......................................................................................................................................53
Appendix A.-Tables...........................................................................................................................54
Table 12 A. Corresponding Degrees Of Paint Rusting Standards .................................................................54
Table 12 B. Corresponding Surface Preparation Standards ...........................................................................54
Table 12 C.-Typical Painting And Wrapping Quality Inspection And Test Plan Checklist ..........................55
Table 12 D (Painting- Daily Inspection Report –Template Below)...............................................................57
Appendix B: Approved Paint Vendors And Products ...................................................................58
Appendix C: Warranty Requirements............................................................................................59
Appendix D: Specific Rasgas Offshore/Onshore Painting- Finish Colour Designation (Ignore
Table No. Below) ...............................................................................................................................60
Appendix E: Specific Rasgas Painting Safety Guides....................................................................64
Appendix F: Coating System Index.................................................................................................68
Prepared
by SIGNED 16-Sep-08
Coating Engineer Date
Rehan Ahmed
Verified
by SIGNED 17-Sep-08
Head of Corrosion Engg Date
David N. Robson
Endorsed
SIGNED 22-Sep-08
by
Maintenance Manager Date
Omar A. Al Misnad
Approved SIGNED
by 23-Sep-08
Operations Technical Manager Date
Bill Chase
Revision
Authorization
Rev. Changed Changed
Date Verified Endorsed Approved
No. Section By
Rehan Dr. Ayman Omar A. Al
0 23-Sep-08 Bill Chase
Ahmed Abdulsalam Misnad
Summary of
Revisions
Rev.
Date By Description of Key Changes
No.
0 23-Sep-08 Rehan Ahmed Issued For Implementation
Introduction
The Distribution List shows current users of this procedure. Procedure users will be provided with the
data link for this document. To receive an electronic copy, contact the Head of Documents / Standards.
Procedure Users
1.2 Scope
1.2.1 Definitions and Overall Document Layout for Protective Coating Specifications and
Scopes of Work for RasGas Operations (Onshore and Offshore)
All RasGas Safety Procedures, Rules and Regulations shall be adhered to at all times. Under no
circumstances shall they be compromised. In case of conflict between this document and the RasGas
safety document, the latter shall prevail. Additionally, the relevant personnel from RasGas need to
be informed as soon as the problem is detected and no longer than 24 hours (in writing) of the
conflict
*NB (Special attention to be paid to EPS-35-B-70 Section 6, Guidance note 13, EGE 35-B-1 Section
10 and relevant JSA’s pertaining to the works to be carried out – see appendix G)
1.4 References
1.6.1.1.1 All surface preparation, painting work carried out under or to the intent of this specification
shall be subject to systematic inspection at each stage of preparation, surface preparation, painting
and repair by the RasGas Engineer. In addition, the work shall be subject to random inspection as
and when the RasGas Engineer deems it necessary.
1.6.1.1.2 The basic inspection requirements and system shall be detailed in a formal Quality
Inspection and Test Plan and presented by the Contractor as part of the contract documentation for
approval by the RasGas Engineer. A typical Inspection Plan Checklist is shown as Table 12 C. Such
a Plan shall not relieve the Contractor from his responsibility to carry out all work in a safe and
timely manner using skilled personnel and good practices to achieve a high quality product meeting
all other specification requirements.
1.6.1.1.3 All defective or non-conforming work identified at each stage shall be rectified to the
required standard by the Contractor. Any preparatory, painting work carried out to this Specification
that is not systematically inspected and approved by the RasGas Engineer at each stage shall be
deemed not to meet the Specification. The coating shall be removed from all affected areas and they
shall be re-prepared and recoated to the approval of the RasGas Engineer by the Contractor.
1.6.1.1.4 The Contractor shall provide required number of authorized persons who shall be a
qualified Painting Inspector to the minimum standard specified below to coordinate the inspection
work carried out and report the results obtained. The proposed Contractor employees, who may be
Supervisor or Manager, shall also be individually acceptable to the RasGas Engineer. Additionally,
either an appointed RasGas Painting Inspector or an approved qualified Third Party Painting
Inspector shall act on behalf of the RasGas Engineer under the contract, to ensure that the required
inspection work is being carried out in a satisfactory and effective manner to consistently give a
good quality product.
1.6.1.1.5 All proposed Painting Inspectors shall be qualified to at least TWI (ex-ERS) Level 1,
FROSIO or NACE Level 2 and shall have at least five years approved experience of industrial
painting of oil and gas facilities at inspector or supervisor level. The certification and resume of each
Inspector shall be submitted to the RasGas Engineer for approval and they shall be interviewed at the
start of each contract to confirm their technical capability. The Inspectors shall consult the Paint
Manufacturer to obtain the necessary technical support to ensure compliance with product
recommendations.
1.6.1.1.6 The Contractor shall provide a comprehensive range of approved calibrated inspection
equipment at each site of any work that is in progress, to enable all inspection work that is required
under the approved Inspection and Test Plan and Work Specification to be carried out. He shall
provide sufficient “sets” of commonly used inspection equipment to avoid any delays in carrying out
the required inspection at all work sites.
1.6.1.2 Inspection System Requirements
1.6.1.2.1 The proposed inspection system for all preparatory, painting work shall operate via a series
of Hold Points in the work schedule, from which the Contractor shall not proceed until he is given
formal clearance by the RasGas Engineer. This does not mean that these are the only points at which
1.6.1.3.1 The RasGas Engineer shall have the right to inspect all tools, equipment, plant,
instruments, materials, and access scaffolding and facilities that are used or to be used in the
performance of the preparatory, coating application, and inspection work at the start of and at all
times during the contract. The Contractor shall make all parts of the worksites accessible for these
inspections.
1.6.1.3.2 RasGas reserves the right to reject any tools, equipment, plant, instruments, materials or
access facilities which are considered unsuitable, unserviceable, inadequate or unsafe for the
proposed work or not to fully meet the contract requirements. All rejected items and materials shall
be reported as such and replaced or rectified as instructed by the RasGas Engineer.
1.6.1.3.3 The Contractor shall provide recent calibration certificates for all equipment and
instrumentation used for the contract, where appropriate and as requested by the RasGas Engineer.
Equipment and instrumentation which cannot be calibrated shall be replaced by the Contractor, if
considered to be unserviceable or unsuitable by the RasGas Engineer.
1.6.1.3.4 Upon request, the Contactor shall permit the RasGas Engineer or his Appointed Painting
Inspector to use any item of inspection equipment, to assess its reliability, accuracy and suitability
for the proposed inspection activity. If any item is deemed to be inadequate to carry out an
inspection activity, an alternative item that is acceptable to the RasGas Engineer shall be provided by
the Contractor.
1.6.2 Mandatory Requirements For All Painting Works
1.6.2.1 Mandatory Procedures:
1.6.2.1.1 All paints in the coating system to come from the same manufacturer and manufacturers
application instructions to be followed.
1.6.2.2.1 All paints in the coating system to come from the same manufacturer and manufacturers
application instructions to be followed.
1.6.2.2.2 All painting shall be done after seasonal low tide levels are determined and it is confirmed
to the best assessment of the meteorological department that the sea state throughout the work period
will be favorable
1.6.2.2.3 All painting done on surface wetted by sea waves and splash shall be rejected, re-blasted
and recoated.
1.6.2.2.4 All priming operations shall be done immediately after blasting operations and
establishment of degree of pitting has been carried out, but shall under no circumstances exceed 24
Hours.
1.6.2.2.5 No painting work shall be done during inclement weather, high tide, when the sea is rough
or choppy.
1.6.2.3 Exceptions:
1.6.2.3.1 GRP Gratings, Newly installed Handrails, equipment and Piping systems (As dictated by
RasGas Engineer)
1.6.2.3.2 Equipment or Instrumentation designated to be hand or machine tool cleaned
1.6.2.3.3 All Electrical Wiring, Cables, and cable Trays
1.6.2.3.4 Safety Equipment, Sensors and Alarms
1.6.2.3.5 All piping/equipment operating above 55°C (NOTE: This refers to surface temp during
painting operations, not service temperatures)
1.6.2.3.6 Shock Cell Pads and Wear pads on boat landing
1.6.2.3.7 Fire Proofed Surfaces and Cryogenic Lines (external Surfaces)
1.6.3.1.1 All of the above to be adequately protected to avoid either direct (over blast) damage or
indirect damage by dust accumulation / contamination (equipment / instrumentation)
1.6.3.1.2 All grating panels to be removed to expose supporting structure
1.6.3.1.3 Inspect the surface to be blasted to ensure no weld spatter, slag, slivers, impact damage,
gouges or other sharp protrusions that would be detrimental to the coating are present on the surface.
If found these shall be ground flush prior to blasting operations commencing
1.6.3.2 Post-Blasting operations
1.6.3.2.1 All masking to be removed and mechanical / hand tool cleaning / painting to be carried out
on “exceptions” as required.
1.6.3.2.2 Scaffold contact points and surrounding GRP grating clamp screw points uncoated after
removal of scaffold to be painted to specification standard.
1.6.3.2.3 Verify anchor profile in accordance with ASTM D4417 by using a spring-loaded
micrometer and/or either a coarse or extra coarse replica tape, as required by the anchor profile
depth. (Random-Spot check)
1.6.4.1.1 The surface to be blasted should be washed down with a RasGas Engineer approved
biodegradable alkali based detergent / degreaser applied as per the manufacturers instructions in
such a manner to remove all surface contamination that would be detrimental to the coating.
1.6.4.1.2 The surface should then be washed with potable water (chloride content to be below
20ppm) at high pressure to remove the contaminated detergent/degreaser before it dries on the
surface.
1.6.4.1.3 Contaminant materials such as *salts (metallic or chloride) can become embedded in the
steel and cannot be removed by abrasive blasting; these contaminants are to be removed by high
pressure potable water washing or potable water blasting. Adequate supply of potable water for these
operations is essential. (*A RasGas approved diluted chloride neutralizing agent may be used)
1.6.4.1.4 The surface shall be abrasive blasted (with a mineral abrasive) to remove loose scale and
heavy corrosion products or hand tool surface prepared as deemed necessary by the RasGas
Engineer. If the loose scale is found to contain deep pitting and a composite repair system is deemed
necessary for application by the RasGas Engineer, then the surface preparation shall be carried out as
laid out in the document contained in Section 9.
1.6.4.1.5 Repeat operation 1.6.4.1.3 above.
1.6.4.1.6 The surface shall then be inspected for the presence of contaminants by means of a RasGas
approved salt contamination meter at equal intervals of 5 tests per 200 m2, any test results showing
salt contamination of 20mg./m2 or more shall require operation 1.6.4.1.3 above repeated until the salt
Acceptable surface preparation methods can be varied for this specification dependant on the size
and the access to the item being coated.
• Vessels, cabinets, large bore pipe and valves shall be “Brush –off blast cleaned” to standard
NACE No. 4/SSPC SP 7.
• Small bore piping, valves and instruments may be prepared by hand tool cleaning by “sanding”
to achieve an abraded surface profile to enable adequate coating adhesion.
1.6.4.2.1 Pre-Blasting Operations
• All adjacent coated carbon steel, GRP piping, sight glasses, gauges and instruments to be
adequately protected to avoid either direct (over blast) damage or indirect damage by dust
accumulation / contamination (equipment / instrumentation)
1.6.4.2.2 Abrasive “Brush-off” blasting method
• The surface to be blasted should be washed down with a RasGas approved biodegradable alkali
based detergent /degreaser applied as per the manufacturers instructions in such a manner to
remove all surface contamination that would be detrimental to the coating.
• Keep the surface wet during the operation (using potable water) and rinse afterwards to ensure
the sanding residue does not dry on the surface to be primed
1.6.5 General Coating Guidelines (For All Surfaces):
1.6.5.1 Application Guidelines
The following specification shall applied apply to all Primary, Secondary and Tertiary carbon steel
items within those packages Including (but not confined to)Cellar Decks, Mezzanine Deck, Drill
Deck, Production Decks, Top Decks, Heli-Deck, Crane and Pedestal and staircases above the Splash
Zone.
Exceptions
All Primary, Secondary and Tertiary non-carbon steel (or non-ferrous steel) items. All carbon steel
subject to impact and/or high temperature (above +100°C). All carbon steel items, equipment, piping
under insulation. All steel in the Splash Zone.
Specification Ref.: Paint System # RMC-PS-01 (Un-insulated Carbon Steel, above Splash
Zone, operating at ambient upto +100°C)
(For Impact Areas like deck plates/troughs/base plates/ lay down areas, see Section 2.4)
2.1.1 Zinc Rich Primer coat
The primer coat should be a polyamide cured, two component, zinc rich epoxy primer, suitable for
application on blast cleaned surfaces with ability to be applied during high humidity (upto 95%) if
required.
a. Apply the stripe coat.
b. Significant areas of corrosion pitting or metal loss that are exposed during blasting operations are
to be referred to RasGas for inspection and passed as acceptable prior to any further
coating/wrapping of these areas.
c. Apply the primer coat by airless or conventional spay method to achieve a minimum dry film
thickness of 50 μm.
d. Remove all masking materials either damaged during blasting operation or containing blasting
media which may dislodge during coating operations.
e. Wash all surfaces with potable water to ensure removal of any accumulated dust and check
surface for contamination as per operation 1.6.4.1.6 (of Surface Preparation) above.
f. Renew all masking of items not to be coated or items which may be affected by overspray during
coating application.
g. Ensure Manufacturers recommended over coating time has not been exceeded before coating
commences.
h. Note that for sweep blasted areas, primer coat needs to be touched up in places where bare metal
has been exposed before application of subsequent coats.
2.1.5 Table 1-Dry Film Coating Thickness for Paint System # RMC-PS-01
Specification Ref.: Paint System # RMC-PS-02 (Un-insulated Carbon Steel, in Splash Zone,
operating at ambient upto 100°C)
2.2.1 Corrosion Inhibiting Primer coat
The primer coat should be a polyamide cured, two component, corrosion inhibiting epoxy primer,
compatible to a well designed cathodic protection system and suitable on wet blast cleaned surfaces
(dry or damp) with ability to be applied during high humidity (upto 95%) if required.
a. Apply the primer stripe coat
b. Apply the primer coat by airless or conventional spay method to achieve a minimum dry film
thickness of 75 μm.
c. Significant areas of corrosion pitting or metal loss that are exposed during blasting operations are
to be referred to RasGas for inspection and passed as acceptable prior to any further coating of
these areas.
d. Remove all masking materials either damaged during blasting operation or containing blasting
media which may dislodge during coating operations.
e. Wash all surfaces with potable water to ensure removal of any accumulated dust and check
surface for contamination as per operation 1.6.4.1.6 (of surface preparation) above.
f. Renew all masking of items not to be coated or items which may be affected by overspray during
coating application.
g. Ensure Manufacturers recommended over coating time has not been exceeded before coating
commences.
2.2.2 Abrasion Resistant Build Coat
The High build/Finish coating should be a two part, Solvent free or High solids, amine cured
Phenolic or Glassflake High Build Epoxy Coating that is capable of being applied at high thickness
per coat and is capable of fully curing in atmosphere or when underwater. The minimum volume
solids should be 85%, preferably 100 %. It should have excellent impact and abrasion resistance.
The high build coat is to be applied in 2 distinctive coats (unless written waiver is obtained by paint
manufacturer to apply in 1 coat).
a. Apply stripe coat of 1st. High build coat.
b. Apply 1st. High build coat by airless or conventional spray method (brush or roller may be used
for limited areas where access is difficult to coat by spraying).
Specification Ref.: Paint System # RMC-PS-04 (Un-insulated Carbon Steel, above Splash
Zone, subjected to impact and collection of water/salt/grease/oil/mild chemicals/mild
acids/mild alkalis/solvents)
2.4.1 Corrosion Inhibiting Primer coat
The primer coat should be a polyamide cured, two component, corrosion inhibiting epoxy primer,
with ability to be applied during high humidity (upto 95%) if required.
a. Apply the primer stripe coat.
b. Apply the primer coat by airless or conventional spay method to achieve a minimum dry film
thickness of 75 μm.
c. Significant areas of corrosion pitting or metal loss that are exposed during blasting operations are
to be referred to RasGas for inspection and passed as acceptable prior to any further
coating/wrapping of these areas.
d. Remove all masking materials either damaged during blasting operation or containing blasting
media which may dislodge during coating operations.
e. Wash all surfaces with potable water to ensure removal of any accumulated dust and check
surface for contamination as per operation 1.6.4.1.6 (of Surface Preparation) above.
f. Renew all masking of items not to be coated or items which may be affected by overspray during
coating application.
g. Ensure Manufacturers recommended over coating time has not been exceeded before coating
commences.
h. For spot repairs and hand tool/power tool cleaned surfaces, follow the same procedure as laid out
above followed by the subsequent coat(s) of paint.
2.4.2 Abrasion Resistant Build Coat
The High build/Finish coating should be a two part, Solvent free or High solids, amine cured
Phenolic or Glassflake High Build Epoxy Coating that is capable of being applied at high thickness
per coat and is capable of fully curing in atmosphere or when underwater. The minimum volume
solids should be 85%, preferably 100 %. It should have excellent impact and abrasion resistance
with the ability to resist exposure to water/salt/grease/oil/mild chemicals/mild acids/mild
alkalis/solvents. The high build coat is to be applied in 2 distinctive coats.
a. Apply stripe coat of 1st. High build coat.
Exceptions:
All Primary, Secondary and Tertiary non-carbon steel (or non-ferrous steel) items operating outside
the abovementioned temperature range. All carbon steel subjected to impact. All carbon, non-carbon
(non-ferrous) steel items, equipment, piping under insulation.
2.5.2 Table 5-Dry Film Coating Thickness for Paint System # RMC-PS-05
Exceptions:
All Primary, Secondary and Tertiary non-carbon steel (or non-ferrous steel) items operating outside
the above-mentioned temperature range. All carbon steel subjected to impact. All carbon, non-
carbon (non-ferrous) steel items, equipment, piping under insulation.
Specification Ref.: Paint System # RMC-PS-06 (Uninsulated Carbon Steel, Stainless Steel,
Nickel Alloy operating at +151°C upto +540°C **)
2.6.1 Inorganic Zinc Silicate Primer coat
The primer coat should be a 2-component Inorganic Moisture Curing Ethyl Zinc Silicate (IZS)
primer
a. Apply the primer stripe coat
b. Apply the primer coat by airless or conventional spay method to achieve a minimum dry film
thickness of 50μm. Apply by Brush/roller in hard-to-reach areas. Ensure that the relative
humidity is at least 50% during primer application, if not, then spray the touch-dried surface of
primer with clean potable water periodically to facilitate curing.
c. Remove all masking materials either damaged during blasting operation or containing blasting
media which may dislodge during coating operations.
d. Wash all surfaces with potable water to ensure removal of any accumulated dust and check
surface for contamination as per operation 1.6.4.1.6(of Surface Preparation) above.
e. Note to apply mist coat-full coat technique for subsequent coats to prevent pin holes on finished
surface.
f. Renew all masking of items not to be coated or items which may be affected by overspray during
coating application.
g. Ensure Manufacturers recommended over-coating time has not been exceeded before coating
commences.
h. In case adequate moisture is not present (>50%)in the air in order for an IZS to cure properly,
then wet with clean potable water at regular intervals to ensure curing process (refer to
manufacturer’s recommendation on forced curing)
i. For spot-blast repaired surfaces, follow the same procedure as laid out above followed by the
subsequent coat(s) of paint.
2.6.2 HT Silicone Aluminium Midcoat/Topcoat
The mid/top-coat should be a single component, heat resistant silicone aluminum that is capable of
withstanding temperatures upto +540°C and is to be applied in 2 coats
a. Apply stripe coat of 1st. HT Silicone Alum. Coat.
b. Apply 1st. HT Silicone Alum. coat by conventional spray method (brush or roller may be used
for limited areas where access is difficult to coat by spraying) to achieve a min. total dry film
2.6.3 Table 6-Dry Film Coating Thickness for Paint System # RMC-PS-06
Surface Preparation SSPC SP 5
NOTE: For Stainless Steel Surfaces and Nickel Alloy Surfaces, Aluminum pigmented Heat
Resistant Silicones are not recommended. Please use Graphite pigmented Heat Resistant
Silicone finish.
** Surfaces that operate continuously above +150°C shall be coated with paint system RMC-PS-
06 or shall have a Thermally Sprayed Aluminum Coating (TSA) as manufactured by
Metallisation Ltd. (Or equal and approved) applied and in accordance with RasGas
Specification S-EPS 35-P-83 (For Offshore), or RGX-S-00-13A0-012 (For Onshore).
Specification Ref.: Paint System # RMC-PS-08 (Insulated Steel surfaces operating at elevated
temperature, operating at +120°C and above**)
2.8.1 Inorganic Zinc Silicate Primer coat
The primer coat should be a 2-component Inorganic Moisture Curing Ethyl Zinc Silicate (IZS)
primer.
a. Apply the primer stripe coat.
b. Apply the primer coat by airless or conventional spay method to achieve a minimum dry film
thickness of 50 μm. Apply by Brush/roller in hard-to-reach areas. Ensure that the relative
humidity is at least 50% during primer application, if not, then spray the touch-dried surface of
primer with clean potable water periodically to facilitate curing.
c. Remove all masking materials either damaged during blasting operation or containing blasting
media which may dislodge during coating operations.
d. Wash all surfaces with potable water to ensure removal of any accumulated dust and check
surface for contamination as per operation 1.6.4.1.6. above.
e. Note to apply mist coat-full coat technique for subsequent coats to prevent pin holes on finished
surface.
f. Renew all masking of items not to be coated or items which may be affected by overspray during
coating application.
g. Ensure Manufacturers recommended over-coating time has not been exceeded before coating
commences.
h. In case adequate moisture is not present (>50%)in the air in order for an IZS to cure properly,
then wet with clean potable water at regular intervals to ensure curing process (refer to
manufacturer’s recommendation on forced curing)
2.8.2 Heat Resistant Silicone Aluminium Midcoat/Topcoat
The mid/top-coat should be a single component, heat resistant silicone aluminum that is capable of
withstanding temperatures upto +540°C It is to be applied in 2 coats
a. Apply stripe coat of 1st. HT Silicone Alum. Coat.
b. Apply 1st. HT Silicone Alum. coat by conventional spray method (brush or roller may be used
for limited areas where access is difficult to coat by spraying) to achieve a minimum total dry
film thickness of 25 μm dft. Apply in mist coat fashion to minimize “popping” on IZS primer,
rub down surface with fine emery paper after flash cure if “popping” occurs and apply next coat.
c. Wash all surfaces with potable water to ensure removal of any accumulated dust and check
surface for contamination as per operation 1.6.4.1.6 (of Surface Preparation) above
d. Apply stripe coat of 2nd. HT Silicone Alum. Coat
Document No: T12-X01-004 Revision No: 0 Sheet: 35 of 70
Document Part: 000 RasGas Use Only Issue Date: 23-Sep-08
RasGas Company Limited
Maintenance Coating Manual
e. Apply 2nd. HT Silicone Alum. coat by conventional spray method to achieve a minimum total
dry film thickness of 25 μm dft
2.8.3 Table 8-Dry Film Coating Thickness for Paint System # RMC-PS-08
NOTE: For Stainless Steel Surfaces and Nickel Alloy Surfaces, Aluminum pigmented Heat
Resistant Silicones are not recommended. Please use Graphite pigmented Heat Resistant
Silicone finish.
Specification Ref.: Paint System # RMC-PS-09 (Steel, Interior steel surfaces in an Air
Conditioned environment)
2.9.1 Zinc Rich Primer coat
The primer coat should be a polyamide cured, two component, zinc rich epoxy primer, suitable for
application on blast cleaned surfaces.
a. Apply the primer stripe coat.
b. Significant areas of corrosion pitting or metal loss that are exposed during blasting operations are
to be referred to RasGas for inspection and passed as acceptable prior to any further
coating/wrapping of these areas.
c. Apply the primer coat by airless or conventional spay method to achieve a min. dry film
thickness of 50 μm.
d. Remove all masking materials either damaged during blasting operation or containing blasting
media which may dislodge during coating operations.
e. Wash all surfaces with potable water to ensure removal of any accumulated dust and check
surface for contamination as per operation 1.6.4.1.6 (of Surface Preparation) above.
f. Renew all masking of items not to be coated or items affected by overspray during coat
application.
g. Ensure Manufacturers recommended over coating time has not been exceeded before coating
commences.
h. Note that for sweep blasted and hand/power tool cleaned surfaces, primer coat needs to be
touched up in places where bare metal has been exposed before application of subsequent coats.
2.9.2 High Build MIO coat
The mid-coat should be a two component, polyamide cured recoatable High Build MIO (Micaceous
Iron Oxide) pigmented Epoxy Coating that is capable of being applied at high thickness per coat.
The minimum volume solids should be 60%. It should have good impact and abrasion resistance.
a. Apply stripe coat of High build MIO coat.
b. Apply High build coat by airless or conventional spray method (brush or roller may be used for
limited areas where access is difficult to coat by spraying).
c. Wash all surfaces with potable water to ensure removal of any accumulated dust and check
surface for contamination as per operation 1.6.4.1.6 (of Surface Preparation) above.
2.9.4 Table 9-Dry Film Coating Thickness for Paint System # RMC-PS-09
NOTE: Do not apply topcoat for Insulated areas and surfaces under floor tiles/cladding
2.10.3 Table 10-Dry Film Coating Thickness for Paint System # RMC-PS-10
2.11 Section 11- COMPOSITE WRAP REPAIR SYSTEM (Protection System # RMC-CR-11)
Suppliers of repair methods should have qualified their system for use in specific applications in
complying with the requirements of the design method. Personnel involved in the installation of
composite repairs shall have had appropriate training and be qualified in the repair method to be
undertaken. This shall include the handling of composite materials, surface preparation, lay-up
techniques, quality control procedures, and health and safety procedures (as per RasGas
requirements). It is important that the training given provides sufficient technical background to
allow personnel to obtain a good understanding as to why key operations such as surface
preparation, material handling and lay-up technique are so important.
This also applies to the use of material in the pre-packaged form. Selection of these materials does
not reduce the need for ensuring personnel are suitably trained.
Ideally training should include practical demonstration through the pressure testing of demonstration
samples.
Note that training in one repair option does not necessarily qualify personnel for alternative methods.
Installation personnel should be the subject of a continuing review of competency with a log kept of
experience in the application of repairs. This is important as the levels of competence and experience
achieved by an individual applicator should also consider in the context of repair activities. For
example, working in confined spaces or applying material around complicated geometries can pose
additional difficulties that should be taken in to account.
Supervisory personnel shall also be trained in the relevant technique and should have had a period
during which they were engaged in the application of repairs. Supervisors shall also be the subject of
a continuing review of competency. Guidance on the content of a suitable training programme may
be obtained from ISO 14692 where the training requirements for the installation of composite (GRP)
pipe are given. Full details of pipe jointing approval schemes are also given in related NTS
(Norway) and CSWIP (UK) documents.
a. Surface Preparation
Surface preparation is single most important operation in the achievement of a successful repair.
The surface preparation should extend over the whole surface onto which the composite laminate is
to be applied.
There are a number of surface pre-treatments, but they normally entail cleaning/degreasing and
surface abrasion. This may (or may not) be accompanied a subsequent chemical treatment stage. For
repairs to carbon steel pipe a durable bonded connection can be achieved with cleaning to remove
debris and corrosion products followed by mechanical abrasion as the sole surface preparation
activity. In these circumstances it is important that the nature of the abrasion technique is fully
specified. This shall include the grade and duration of shot blasting, the grade of any abrasive paper
or other equipment that is used. Surface roughness gauges or other measurement technique shall be
used to check that the prepared surface is as required by the specification. All paint, tape, corrosion,
dust or other loosely attached debris shall be removed.
The surface preparation issues that govern the performance of a repair material are analogous to
those that are considered to be important in the application of painting systems and other protective
coatings. These are generally listed as: the presence of rust and mill scale, the presence of surface
contaminants and the profile of the surface following preparation. Thus the surface preparation
methods mentioned in the earlier part of this document shall prevail, depending on the surface
condition, as decided by the RasGas Engineer.
The steel surface shall be blast cleaned to an SSPC SP5 (where blasting possible) using a clean
mineral abrasive as defined earlier on in this document (See 1.6.4.1-Surface Preparation Section for
details). These parameters can be changed, depending on the site limitations & as decided by the
RasGas Engineer.
The repair of other metallic pipe such as alloyed steel is likely to require a chemical treatment for a
satisfactory repair (follow wrapping manufacturer’s recommendation).
The surface preparation of GRP pipe requires mechanical abrasion only. The bonding of material
onto phenolic GRP pipe can be problematical and the pipe vendor shall be contacted in each
instance.
Any chemicals used for surface preparation shall be within the recommended shelf life, freshly
mixed (where appropriate) and applied strictly in accordance with the supplier's instructions.
Apply repair material as soon as possible after the surface has been treated since water absorption
onto a freshly prepared surface can be rapid as can the reaction of the surface with air and both of
these factors can impair the achievement of a good joint. The surface preparation of a number of
repair sites before any laminate material has been applied would not be recommended practice. The
minimum and maximum allowable time between surface preparation and bonding shall be specified
in the method statement.
It is important that prepared surfaces are protected from contamination prior to the application of the
repair laminate. Any sign of deterioration of the prepared surface through handling, the presence of
water or other influence should be cause for rejection and the surface preparation procedure
repeated.
A quality check shall be introduced into the repair schedule specifically identifying surface
preparation as a key stage and a hold point in the process. Where a chemical treatment is applied it
can be advantageous to incorporate a small amount of pigment in the solution to be applied. This
allows the operator, or the inspector supervising the work, to visibly check that it has been applied
correctly.
To check that the surface treatment has effectively promoted bonding, carry out a 'stipple' test. This
is be done by applying an amount of adhesive or resin to the prepared surface with a pallet knife and
then removing the knife with a lever action. It is recommended that the application is performed at
the 6 o'clock position. If the adhesive or resin material remains on the pipe it demonstrates that it has
properly wetted the surface.
Alternative method of demonstrating good bonding is to show that the adhesive bond is stronger
than the shear strength of the composite material. This shall be done by applying a small amount of
material to the steel surface along side the actual repair and then mechanically removing it. The test
would entail the bonding of a strip of material onto the prepared surface coincidentally with the
repair itself. A typical sample would allow a bonded area of 50 mm x 50 mm with a tab of un-
bonded material to allow the material to be pulled off. The presence of remaining composite
laminate over at least 30% of the bonded surface of the steel is evidence of a satisfactory bond. A
test area of 50 mm by 50 mm will be sufficient. The specified technique cannot be replaced by
another without explicit guidance from the supplier who will need to have qualified the alternative as
part of a revised design. The means by which the quality of a prepared surface is measured is not
straightforward. There are some potential techniques, but these are very specific to the chemistry of
the substrate and the surface preparation process. Measurement of surface tension (the wetting
behaviour of a droplet on the surface) is a recommended method.
b. Laminate Lay-up
The details of the lay-up procedure shall be fully specified by the supplier (vary according to the
repair method to be used).
Material variants include pre-packaged material supplied as a pre-pregnated roll or reinforcement
and resin supplied separately requiring cutting and metering on a bespoke basis. Both of these
alternatives should be applied using contact moulding. Another variant is for reinforcement to be
supplied pre-cut and then applied at the site of the repair using a resin infusion process. Other
proprietary systems, for example, the bonding of fully cured composite material onto a repair site
can be utilized as well, subject to prior approval from RasGas Corrosion Engg. Department.
resin, catalyst/hardener and any other ingredient or permitted filler shall be accurately measured and
thoroughly mixed. Dual volume syringes can be used as a means of achieving this for two part
systems.
For certain repair methods it is necessary to use proprietary in-fill compounds to make good local
surface imperfections, e.g. external corrosion damage. The final geometry of the surface should be
measured and shall comply with the specified tolerances. The external surface of the filler shall be
prepared according to manufacturer’s instructions.
Where separate adhesive material is required to achieve a bond between individual laminate layers
attention needs to be given ensuring the adhesive is applied uniformly and that bond line thickness is
in accordance with design.
Individual layers should be applied to the repair site in a sequential manner in the order specified viz
method statement. Particular care should be taken with directional reinforcement where the fiber
alignment needs to be controlled according to the requirements of the design. The overlaps between
individual layers will be dependent on the nature of the reinforcement and these should be defined as
part of the laminating procedure. Overlaps should be staggered around the geometry of the repair
area. Consolidation of the layers of reinforcement and resin can be accomplished through the use of
simple hand tools such as rollers. This needs to be carried out thoroughly to ensure adhesion
between individual layers and to remove air inclusions, but excessive pressure should be avoided to
prevent damage or undesired reorientation of fibers. The geometry and orientation of the pipe being
repaired can have an influence on the quality of the repair. Small diameters and regions of rapidly
changing curvature, e.g. a tee intersection, can be difficult to laminate due to the resistance in the
reinforcement to drape. The use of lighter weight fabrics or directional reinforcement to 'tie' the
laminate into difficult areas can be useful. On vertical surfaces drainage of resin prior to cure may
cause difficulties and the addition of thixotropic additives may be required.
The minimum thickness for the repair laminate shall be 5 mm. The extent of the laminate over the
surface should be specified within the design. This should normally be the larger of 100 mm or
2(D.t)0.5 in all directions beyond the damaged region, where ‘D’ and ‘t’ are the external diameter and
thickness of the pipe respectively. Care should be taken to ensure that there are no significant
discontinuities in laminate thickness at the edge of the repair. Typically thickness should be tapered
to give a minimum slope of 6:1. In the event of excessive heat generation in resin containers,
evidence of premature gelation, or a significant increase in viscosity, the material should be
discarded and a further batch of material prepared.
Where the external finish of a repair laminate is important as it is intended to carry a bearing load,
e.g. within a support, the surface can be moulded flat by applying a former prior to final cure. Any
spillage, drips or runs, which may later flake off, should be removed. The outer surface should have
a smooth contour.
For major repairs there may be a need for material to be applied in stages with cure occurring
between them. In these circumstances it may be necessary to lightly abrade the cured surface to
Document No: T12-X01-004 Revision No: 0 Sheet: 45 of 70
Document Part: 000 RasGas Use Only Issue Date: 23-Sep-08
RasGas Company Limited
Maintenance Coating Manual
ensure good secondary bonding. Repairs should be carried out above the dew point. However, it is
allowed (upon seeking permission from RasGas Engineer) to proceed in conditions of low ambient
temperatures with suitable local protection to the repair area. This may involve the use of temporary
covers or housings. The material supplier should be contacted for confirmation that resin curing will
continue to be satisfactory. Similar considerations should be taken in regions of high ambient
humidity. Where condensation is possible, e.g. repair onto a cold pipe, this should be considered at
the outset of material selection and design.
Repairs should not be applied when the temperature of the surface is less than 3 °C above the dew
point of the surrounding air or when the relative humidity of the air is greater than 85% unless local
conditions dictate otherwise. Guidance on the estimation of the probability of condensation can be
found in ISO 8502-4. Also, the pipe surface temperature, ideally, should always be more than 5 °C.
Since it isn’t possible to determine properties of the actual repair laminate, the contractor shall
prepare a sample laminate alongside repair using the same materials. This sample is to be submitted
to RasGas for measuring parameters such as fiber content and mechanical characteristics.
c. Cure
The cure of a repair laminate is strongly influenced by temperature and the correct mixing of resin
constituents prior to lamination. It is important that the prevailing temperature conditions are
considered when, for example, resin catalyst levels are being assessed. On no account, however,
should the limits set by suppliers be exceeded without recourse to further information. It should be
noted that for curing in extreme ambient conditions there may be special resin formulations that may
be more suitable.
Cure can be assisted by keeping the repair laminate covered with a plastic film during installation.
This protects the laminate from mechanical abuse and water, retains heat and excludes air that can
inhibit the cure in certain resin systems. This is especially important for thin repair laminates where
there may be insufficient material to retain heat generated due to cure.
Where elevated temperatures are required for cure it is recommended that these are achieved through
the use of heating blankets that fully cover the repair laminate. Heating blankets should extend
beyond the repaired region by at least 50 mm. A protective film should be positioned between the
blanket and the laminate to prevent material being bonded to the blanket. The temperature should be
monitored throughout the curing process.
The use of heated air guns directed to the surface of a curing laminate to accelerate the process is not
allowed due to the likely evaporation of reactants from the surface.
The time for full cure is dependent on the type of resin used in the repair and ambient conditions.
The extent of cure may be measured using Barcol or Shore hardness or DSC (Differential Scanning
Calorimetry). Acceptance values shall be obtained from the supplier for each repair method. Details
of the test methods are given in BS 2782: Part10: Method 1001, ISO 868 and ISO 11357
respectively. Typical Barcol hardness values for styrenated resins are in the region 35 to 40 (Shore
hardness approximately 60), but in any case should be at least 80% of the value obtained from cast
resin specimens.
The extent of cure achieved during installation shall be the same as that in the design.
The repaired pipe may be returned to service after full cure has been achieved, assuming the pipe
service has been reduced prior to repair application. Guidance for the repairs of live pipes are given
in Section 2.11.4.
6.0 APPENDICES
6.1 Appendix A
Appendix A- 3. Table 12C-Typical Painting and Wrapping Quality Inspection and Test
Plan Checklist
NOTES: 1. ISO 8501 Part 1 is the same as BS 7079 Part A1 and SIS 05 59 00
2. SSPC and NACE Standards are given in Steel Structures Painting Manual, Volume 2
TABLE 12 C.-Typical Painting And Wrapping Quality Inspection And Test Plan Checklist
INSPECTION
ITM. DESCRIPTION OF ITEM ACTIONS BY REMARKS
REQ’D
RG
T.P.I.
OPCO
A THROUGHOUT WORKING DAY
1 Safety/condition of equipment/machinery Visual inspection H H H
2 Correct PPE is worn by all personnel Visual inspection H H H
3 Atmospheric relative humidity/dew point Psychrometer and Tables I W R/H
4 Metal surface temperature Contact thermometer I W R/H
B BEFORE PREPARATORY CLEANING
1 Work methods/QC system/safety measures Record inspection I H H
2 Permit to work in order and authorised Record inspection H H H
3 Control/inspection instruments calibrated Visual/record inspection H H H
4 Presence of surface-breaking defects Visual inspection I R R
5 Defects found are satisfactorily removed Visual inspection I R R
6 Presence of gross surface contamination Visual inspection I R R
7 Rust grade/degree of coating breakdown Visual inspection I H H
8 Type of water/brand of degreasing agent Visual inspection I R R
9 Presence of residual oil or grease Water spray test I R R
10 Presence of residual salts* Salt test I R R
11 Type, brand and grade of abrasive used Visual inspection I R R
12 Acceptance of power/hand tool cleaning Visual inspection I W W/H
C DURING PREPARATORY CLEANING
1 Batch number and date of abrasive used Visual inspection I R R
2 Presence of oil/water in compressed air Blotting paper at exhaust I R R
3 Air pressure used for blast cleaning Hypodermic needle gage. I W W
4 Blast cleaning surface cleaning standard Visual inspection v. Std. I W/H W/H
5 Profile height of blast cleaned surfaces Replica tape/comparator I W/H W/H
6 Residual dust and matter on surfaces Tape/pocket microscope I W W
7 Type/condition of power/hand tools used Visual inspection I R R
8 Standard of power/hand tool cleanliness Visual inspection I W/H W/H
9 Presence of residual millscale *(only if Copper sulphate test I R R
applicable)
10 Presence of salts* Salt Test I R R
TABLE 12 C. Typical Painting And Wrapping Quality Inspection And TestPlan Checklist
(Continued)
INSPECTION
ITM. DESCRIPTION OF ITEM ACTIONS BY REMARKS
REQ’D
RG
T.P.I. OPCO
D DURING PAINT OR COMPOSITE TAPE WRAP APPLICATION
1 Types, brands, dates, condition of paints Visual inspection I R R
2 Paint storage conditions Visual inspection I R R
3 Paint mixing procedure and control Visual inspection I W W
4 Rust present on blast cleaned surfaces Visual inspection I R R
5 Time between blast cleaning and priming Record inspection I R R
6 Paint/Wrap application technique and Visual inspection I W W
quality
7 Stripe priming of edges, corners, crevices Visual inspection I R R
8 Full primer coat thickness Wet/dry film tkns. Check I H H
9 Primer profile and appearance Visual inspection I H H
10 Time between primer and first midcoat Record inspection I R R
11 First midcoat and stripe thickness Wet/dry film tkns. Check I W W
12 First midcoat and stripe profile/appearance Visual inspection I W W
13 Time between first and second midcoat Record inspection I R R
(only if applicable)
14 Second midcoat and stripe thickness (only if Wet/dry film thickness. I W W
applicable) Check
15 Second midcoat /stripe Visual inspection I W W
profile/appearance(only if applicable)
16 Time between second midcoat and topcoat Record inspection I R R
17 Complete paint coating/wrapping thickness Wet/dry film thickness. I H H
check
18 Complete paint coating profile/appearance Visual inspection I H H
19 Final curing time for coating system Record inspection I R R
20 Presence of holidays in coating (where Low or high voltage test I H H
applicable)
21 Adhesion of coating (where applicable) Dolly pull-off test I W W
22 Identification of areas for repair Use of indelible marker I W W
23 Coating/wrapping appearance after repair Visual inspection I H H
24 Complete QIT form and associated docs. Record inspection I H H
WEATHER CONDITIONS
Time / Date
Rel. Humidity (%)
Dewpoint ( C)
Metal Temp. ( C)
GENERAL COMMENTS:
CONTRACTOR T.P.I. ( If Applicable) R.G. (OP CO)
Signature
Name
Position
Date
## CORRESPONDING DEGREES OF PAINT RUSTING STANDARDS(ISO 4628-3 / SSPC Vis. 2):
Ri 0/10- No visible rusting of coating; Ri 3/6- Marked localised rusting of 1% of surface area;
Ri 4/4- Widespread localised rusting of 10% surface area (8% for Ri.4); Ri 5/1- Extensive rusting of up to 50% of surface area
^^ Bare Metal Rust Grade standard according to Visual Standard SSPC-Vis 3
Surface
Amercoat Rustbond Hempadur Interseal 670 Jotomastic Sigmacover
Tolerant
Epoxy Primer 185 8HB 45880 HS 87 280/630
High Gloss
Amercoat Carbothane Hempathane Sigmadur
Polyurethane Interthane 990 Jotathane
Topcoat 450 S 834 55100 Gloss 7528
Corrosion
Carboguard Hempadur Penguard Sigmacover
Inhibiting Amercoat 71 Interseal 414
Primer Coat E19 15590 ZP AO 280
Hempadur
Abrasion
Amerlock Carboguard Multi- SigmaShield
Resistant Interzone 954 Jotazone
Build Coat 400 GFA 1209 strength 1200
35530
Non-Ferrous
Amercoat 71 Carboguard Hempadur Penguard Sigmacover
Surf Tolerant Intergard 269
Primer TC 893 15552 Primer 630
Inorganic Hempel's
Zinc Silicate Dimetcote 9 Carbozinc 11 Galvosil Interzinc 12 Resist GT SigmaZinc 158
Primer 15700
Hempel's
HT Silicone Amercoat Carboline Silicone Sigmatherm
Aluminium Intertherm 50 Solvalitt
878 4631 Aluminum 540
56910
Sovachem
Phenolic Amercoat 90 Phenoline Hempadur Interline 850 Sigma
Tank lining
Epoxy HS 187 15500 Intertherm 228 Phenguard
Sp8 series
Cold Spray
N/A N/A N/A Intertherm 751 N/A N/A
Aluminium
OFFSHORE:
Notes to Table 2
1. When maintenance painting is required, top coat with 89-Y-21, Lemon Yellow.
ONSHORE:
Uninsulated Carbon Steel (Non-impact areas), atmospheric exposure, operating at Ambient upto to +100 oC
Surface DFT
System
Preparation
Product µm
Comments
Primer Zinc Rich Epoxy 50
Dry Grit Blast
Intermediate Epoxy MIO 125
SSPC- SP5 / Large Area Repairs
ISO 8501-1 SA 3 Intermediate Epoxy MIO 125
Top Polyurethane 50
Primer Surface Tolerant Epoxy 75
Mechanical Prep
RMC-PS-01 Intermediate Epoxy MIO 125 Small Repairs &
SSPC-SP3 /
Intermediate Epoxy MIO 125 Touch-up
ISO 8501-1 ST 3
Top Polyurethane 50
Primer Surface Tolerant Epoxy 75
Sweep Blast Intermediate Epoxy MIO 125
Large Area Repairs
Only Intermediate Epoxy MIO 125
Top Polyurethane 50
Carbon Steel in the Splash Zone, Tidal Zone and Sea Water Intake Structures-Ambient upto to +100 oC
Surface DFT
System
Preparation
Product µm
Comments
Primer Universal Epoxy Primer 75
Dry Grit Blast
Intermediate High Build Epoxy 200
SSPC- SP5 / Large Area Repairs
Intermediate High Build Epoxy 200
ISO 8501-1 SA 3
Top-optional Polyurethane-optional (50)
Primer Universal Epoxy Primer 75
Mechanical Prep
RMC-PS-02 SSPC-SP3 /
Intermediate High Build Epoxy 200 Small Repairs &
Intermediate High Build Epoxy 200 Touch-up
ISO 8501-1 ST 3
Top-optional Polyurethane-optional (50)
Dry/Wet Blast Primer Universal Epoxy Primer 75
Tidal Zone/Sluice Gates
SSPC- SP5 / Intermediate High Build Epoxy 500
Only
ISO 8501-1 SA 3 Top High Build Epoxy 500
Carbon Steel, Areas subject to Impact, abrasion, collection of water/mild chemicals (above splash zone)
DFT
System Surface Preparation Product µm
Comments
Uninsulated Carbon/Stainless/Galvanised Steel, Nickel Alloy +101 oC upto to +150 oC (flex +200 oC)
Surface DFT
System
Preparation
Product µm
Comments