DECLARATION
The candidate herewith adjudges that the work presented in this Dissertation on “AN
(Honours) degree presented to the Department of Quantity Surveying in the Faculty of the Built
Environment at the National University of Science and Technology, is that of the candidate alone
and has not previously been submitted, in whole or part, in respect of any other academic award
and has not been published in any form by any person except where due reference is given.
Candidate
Supervisor or marker
i
DEDICATION
I would like to dedicate this research to my fiancée Mildred Yahaya for all her support and
continuous encouragement.
ii
ACKNOWLEDGEMENTS
I would like to extend my sincere gratitude and appreciation to the people who made
contributions to make this research possible.. This study could not have been completed without
My affectionate gratitude goes to my supervisor Mr R. Muvungani for his continued support and
guidance throughout the writing of this dissertation. His supervision was superb and I will
continue to cherish him for the good work. I am particularly grateful to my parents, my brothers,
sisters and all relatives among others, for their prayers, encouragement, and love.
iii
ABSTRACT
Project success can be achieved if the construction works flows efficiently within the time limits.
The inability to complete projects on time continues to be a chronic problem worldwide, and
Zimbabwe is not an exception. Most of the construction projects in Zimbabwe have had problems
with delays in completion, which has caused considerable concern. The focus on this study was to
investigate the causes, the effects and strategic measures to minimize the occurrence of
construction delays on construction projects. This study was treated in two parts. The first part
covered the review of literature on the subject matter of construction delays on construction
projects. The information and recommendations found from literature were used to develop and
establish direction for the second part of the study. The second part was an investigation of
construction delays on Zimbabwean construction projects through analysing four cases of
construction projects in Zimbabwe and questionnaire survey of nineteen contractors, eight
construction consultants (amongst which quantity surveyors, architects and civil engineers) and
four projects owners. Twenty two causes of construction delays were identified from literature
review. The field survey identified the main causes of construction delays and these include
financial difficulties of the client; variations; contractor‟s financial difficulties and late payment.
The results also showed that construction delays resulted mostly in cost overruns; badly affected
company reputation; bad contractual relationships and project suspension amongst others. Eleven
strategic measures were identified from literature and the results of the study recommended five
measures to be effective in curbing construction delays. It is recommended from this study that
clients must secure sufficient construction finances before engaging into a project, consultants and
the procurement team must choose a competent contractor and contractors must not engage into
projects which they are not capable of executing.
iv
CONTENTS
DECLARATION.............................................................................................................................................. i
DEDICATION ............................................................................................................................................... ii
ACKNOWLEDGEMENTS ..............................................................................................................................iii
ABSTRACT ...................................................................................................................................................iv
CONTENTS .................................................................................................................................................. v
LIST OF FIGURES .........................................................................................................................................ix
LIST OF TABLES ............................................................................................................................................x
CHAPTER ONE: INTRODUCTION ..................................................................................................................... 1
1.1 BACKGROUND ................................................................................................................................ 1
1.2 PROBLEM STATEMENT ................................................................................................................... 4
1.3 RESEARCH QUESTIONS ................................................................................................................... 5
1.4 AIM OF STUDY ................................................................................................................................ 5
1.5 OBJECTIVES ..................................................................................................................................... 5
1.6 JUSTIFICATION ................................................................................................................................ 5
1.7 RESEARCH OUTLINE........................................................................................................................ 6
1.7.1 Chapter One: Introduction ..................................................................................................... 6
1.7.2 Chapter Two: Literature Review............................................................................................. 6
1.7.3 Chapter Three: Methodology ................................................................................................. 6
1.7.4 Chapter Four: Data Presentation and Analysis ...................................................................... 6
1.7.5 Chapter Five: Conclusions and Recommendations ................................................................ 7
CHAPTER TWO: LITERATURE REVIEW ............................................................................................................ 8
2.1 INTRODUCTION .............................................................................................................................. 8
2.2 CONSTRUCTION DELAYS................................................................................................................. 8
2.3 TYPES OF CONSTRUCTION DELAYS ................................................................................................. 9
2.3.1 Excusable ................................................................................................................................ 9
2.3.2 Non-excusable delays ........................................................................................................... 10
2.4 THE CAUSES OF CONSTRUCTION DELAYS..................................................................................... 10
2.4.1 Contractors’ Financial Difficulties......................................................................................... 12
2.4.2 Large scale and high quality requirements .......................................................................... 12
2.4.3 International involvement .................................................................................................... 12
2.4.4 Contractual relationship ....................................................................................................... 12
2.4.5 Coordination Problems......................................................................................................... 13
2.4.6 Contractor’s incapability ...................................................................................................... 13
v
2.4.7 Financial market instability .................................................................................................. 13
2.4.8 Over commitment of construction firms ............................................................................. 14
2.4.9 Labour shortage ................................................................................................................... 14
2.4.10 General labor strikes ............................................................................................................ 14
2.4.11 Wrong time estimation ........................................................................................................ 14
2.4.12 Language barrier .................................................................................................................. 15
2.4.13 Construction Mistakes and Defective Works ....................................................................... 16
2.4.14 Change orders by clients ...................................................................................................... 16
2.4.15 Financial difficulties of the client.......................................................................................... 16
2.4.16 Late Payment ........................................................................................................................ 17
2.4.17 Bad weather conditions ....................................................................................................... 17
2.4.18 Insufficient financial resources............................................................................................. 17
2.4.19 Shortage of equipment ........................................................................................................ 18
2.4.20 Lost Productivity and Efficiency ........................................................................................... 18
2.4.21 Poor site management. ........................................................................................................ 18
2.4.22 Acts of God ........................................................................................................................... 19
2.5 THE EFFECTS OF CONSTRUCTION DELAYS.................................................................................... 19
2.5.1 Time Overrun........................................................................................................................ 19
2.5.2 Rescheduling ........................................................................................................................ 20
2.5.3 Cost Overrun ........................................................................................................................ 20
2.5.4 Disputes ................................................................................................................................ 21
2.5.5 Arbitration ............................................................................................................................ 21
2.5.6 Litigation ............................................................................................................................... 21
2.5.7 Company Reputation............................................................................................................ 21
2.5.8 Total Abandonment ............................................................................................................. 22
2.6 STRATEGIC MEASURES TO ENHANCE SUCCESSFUL PROJECT DELIVERY ...................................... 22
2.6.1 Early payment....................................................................................................................... 23
2.6.2 Acceleration of site activities ............................................................................................... 23
2.6.3 Reinforcement of liquidated damages clauses .................................................................... 23
2.6.4 Proper pre-construction planning ........................................................................................ 24
2.6.5 Developing appropriate communication system ................................................................. 24
2.6.6 Management during construction. ...................................................................................... 24
2.6.7 Contingency allowance ........................................................................................................ 25
2.6.8 Motivation of staff................................................................................................................ 25
vi
CHAPTER THREE-RESEARCH METHODOLOGY .............................................................................................. 26
3.1 INTRODUCTION ............................................................................................................................ 26
3.2 RESEARCH Design ......................................................................................................................... 26
3.3 AREA OF STUDY ............................................................................................................................ 26
3.4 TARGET POPULATION................................................................................................................... 26
3.4.1 Sampling Frame .................................................................................................................... 27
3.4.2 Sampling size ........................................................................................................................ 27
3.4.3 Sampling methods ................................................................................................................ 28
3.5 DATA COLLECTION TOOLS ............................................................................................................ 29
3.5.1 Primary Data Sources ........................................................................................................... 29
3.5.2 Interviews ............................................................................................................................. 29
3.5.3 Questionnaires ..................................................................................................................... 30
3.5.4 Case studies .......................................................................................................................... 31
3.5.5 Secondary Data Sources ....................................................................................................... 31
3.6 DATA PRESENTATION AND ANALYSIS .......................................................................................... 32
3.7 CONCLUSION ................................................................................................................................ 32
CHAPTER FOUR- DATA PRESENTATION AND ANALYSIS ............................................................................... 33
4.1 INTRODUCTION ............................................................................................................................ 33
4.2 GENERAL INFORMATION .............................................................................................................. 33
4.2.1 Questionnaire response rate................................................................................................ 33
4.2.2 Interviews response rate ...................................................................................................... 34
4.2.3 Years of experience of organisations ................................................................................... 34
4.3 CONSTRUCTION DELAYS............................................................................................................... 35
4.3.1 Responsible part to construction delays .............................................................................. 36
4.3.2 Causes of construction delays .............................................................................................. 37
4.3.3 Effects of construction delays .............................................................................................. 43
4.4 STRATEGIC MEASURES TO MINIMISE DELAYS.............................................................................. 46
4.5 SUMMARY .................................................................................................................................... 51
CHAPTER FIVE RECCOMENDATIONS AND CONCLUSSION............................................................................ 52
5.1 INTRODUCTION ............................................................................................................................ 52
5.2 CONCLUSIONS .............................................................................................................................. 52
5.2.1 Causes of construction delays .............................................................................................. 52
5.2.2 Effects of construction delays .............................................................................................. 53
5.2.3 Suggested measures to minimize construction delays ........................................................ 53
vii
5.3 RECOMMENDATIONS ................................................................................................................... 53
5.4 AREA FOR FURTHER RESEARCH .................................................................................................... 54
REFERENCES ............................................................................................................................................. 55
APPENDICES ............................................................................................................................................. 61
APPENDIX A: QUESTIONNAIRE ............................................................................................................ 62
APPENDIX B: INTERVIEW QUESTIONS .................................................................................................. 68
viii
LIST OF FIGURES
Fig 4.4 Case study: Percentage response to the causes of construction delays .............................. 42
ix
LIST OF TABLES
x
ABBREVIATIONS
xi
CHAPTER ONE: INTRODUCTION
1.1 BACKGROUND
The Zimbabwean construction industry continues to occupy an important position in the nation‟s
economy even though it contributes less than other services industries. This contribution of the
industry by means of cost-effectiveness and timelines and would certainly contribute to cost
criticism facing the Zimbabwean construction industry is the growing rate of construction delays
in project delivery.
Construction delays are the most serious problems which send bad signals to foreign investors
thereby slowing national development (Niazai and Gidado, 2012). Tse and Ganesan, (1997) and
Crosthwaite, (2000) as cited by Wibowo, (2009) acknowledge that the construction industry
accounts for a sizeable proportion of Gross Domestic Product (GDP) in economies of developed
and developing countries stimulating economic growth through backward and forward linkages.
In countries like United Arab Emirates (UAE), where construction plays a major role in its
development and contributes up to 14% to the GDP, construction delays participate negatively in
declining the economy‟s GDP, (Abu Dhabi Chamber of Commerce and Industry 2009). The
construction industry of Zimbabwe has a potential of accounting for at least 20% of the country‟s
(http://www.amazingvictoriafalls.com/archives/5309).
Although the construction industry represents a substantial portion of the economy, the
performance and improvement in construction productivity in the world over the past years has
been declining (Choy, 2004). This decline has been echoed by such researchers like Hewage and
1
Ruwanpura (2007); and Sharpe (2006). Zimbabwe has not been spared from this predicament.
Since Zimbabwe as a developing country executing new construction works and refurbishment of
existing infrastructure, most of the construction projects are not achieving their goals due to
Construction delays can be defined as the time overrun either beyond the contract date or beyond
the date that the parties have agreed upon for delivery (Assaf and Al-Hejji 2006). More so, Aibinu
and Jabgoro (2002) defined construction delays as a situation where a contractor and the project
owner jointly or severally contribute to the non-completion of the project within the original or
the stipulated or agreed contract period. Therefore, one can sum up the definition of construction
Construction delays occur when progress of a contract falls behind schedule and this may have
been caused by any party to the contract and may be a direct result of one or more circumstances.
Kaliba et al, (2009) found that the major causes of construction delays on construction projects in
Zambia were: delayed payments; financial deficiencies; on the part of the client or contractor;
mistakes; poor coordination on site; changes in specification; labour disputes and strikes. In
addition monthly payment difficulties from agencies; poor contractor management; material
procurement; poor technical performances; and escalation of material prices were identified as the
main factors which cause construction delays in Ghana, (Frimpong, 2003). Kouskili and Kartan
(2004) identified the main factors affecting time overrun in Malaysia as adequate equipment,
tools and plants; unreliable sources of materials on the local market and site accidents. This shows
that the causes of construction delays vary from country to country, and there are also different
2
Chan and Kumaraswamy‟s (1997) study on construction delays in Hong Kong concluded that
construction delays for whatever reasons, most probably lead to time overrun as the project may
experience extension of time. They further argue that extension of time also may lead to time
overrun where it involves extra financial expenditure. Mohamad, (2010) researched on the effects
of construction delays on government projects in Jordan. The research indicated that, there were
five different effects of construction delays on projects and these were cost overrun; rescheduling
and rearrangement; litigation; disputes and arbitration. In addition, construction delays cause
disruption of work and loss of productivity; late completion of project; increased time related
costs and third party claims and abandonment or termination of contract, (Abedi et al, 2011). In as
much as construction delays are complex from one project to another, it is important for a further
This area has been widely studied by researchers from different countries (Bramble and
Callanham, 1992; Mansfield et al, 1994; Assaf and Mohammed, 1995; Al Kass and Mazeroll,
1996; Thorvaldsson et al, 1996; Odeyinka and Yusif, 1997; Kumaraswamy and Chan, 1998; Al
Khalil, 1999; Odeh, 2002; Aibinu and Jabgoro, 2002; Battaineh, 2002; Hussein, 2002; Crawford
and Frimpong, 2003; Koushki and Kartam, 2005; Lo et al, 2006; Abdul Rahman and Yahya,
2006; Ajibade and Henry, 2006) just to mention a few, and different conclusions have been drawn
with respect to each country. However, the Zimbabwean construction industry has its own
More so, in Zimbabwe there are limited publications, if any, which have sought to identify the
causes and extent to which construction delays are contributing to the Zimbabwean construction
3
1.2 PROBLEM STATEMENT
Construction delays occurs in most construction projects and the magnitude of these delays varies
considerably from project to project, and this problem is a worldwide phenomenon. According to
a research by Shen et al, (2001), in UAE the majority of building projects were not completed
within the stipulated contract period. Another study by Aibinu and Jabgoro, (2002), deduced that
construction projects in Nigeria were experiencing cost overruns due to construction delays.
Moreover, Mohammed & Isah, (2012) conducted a review on projects in developing countries
and found that they were experiencing construction delays and were being abandoned.
This inability to complete projects on time continues to be a chronic problem worldwide, and
Zimbabwe is not an exception. For instance most, of the construction projects in Zimbabwe have
had problems with delays in completion, which has caused considerable concern. Joina Centre, a
major commercial centre in Harare, had a time overrun of eight years (8), (Business Herald 18
March 2010), as quoted by Chigara and Mangore, (2012).This time overrun gives rise to an
increased construction budget to the client. The construction of the country‟s largest inland water
reservoir, Tokwe-Mukosi Dam, was delayed due to suspension in 1999 as a result of lack of funds
continues to be a stumbling block in the completion of the Great Limpopo Transfrontier Park,
with tourists facing difficulties in accessing Zimbabwe‟s Gonarezhou National Park, (The Herald
30 March 2006).
Even though the construction industry of Zimbabwe tried to improve the advances in crafting
Construction delays therefore are a problem which needs to be properly addressed and minimized
4
1.3 RESEARCH QUESTIONS
What are the effects the construction delays on Zimbabwean construction projects?
What strategic measures that can be taken to improve successful project delivery?
The aim of this research is to investigate the causes and effects of construction delays in the
1.5 OBJECTIVES
1.6 JUSTIFICATION
The research is carried out for the purpose to fill in the gap of construction delays on Zimbabwean
situation. Carrying out a research on the causes and effects of construction delays in Zimbabwe is
needful since many Zimbabwean projects are experiencing construction delays. The outcomes of
the research will then be a guideline to the parties that will be involved in construction projects so
as to minimise or get rid of construction delays. More so, the outcomes of the research will help
the project team to suggest on several strategies that can be adopted to minimise construction
The project team will benefit from the outcomes of this research in sense that they will have ideas
of the causes of construction delays and their effects on projects. Knowing these will alert them to
5
avoid risks of construction delays and enhance successful project delivery in terms of time. On
the other hand successful project delivery will benefit other stakeholders, such as occupancies;
residents; tenants and the community. These will access the services offered by the project team
on time.
This chapter introduces the reader to construction delays, background information on the matter;
the problem statement; aim of the research; research objectives; the justification and finally the
research outline.
This chapter will explore previous studies related to variation orders on construction projects.
The origin, causes and impact of variation orders on projects performance will be discussed.
This chapter focuses on the research methodology that will be used during the research process.
The chapter comprises of research design, target population, sample population, data collection
This chapter details all the findings obtained during the research and the findings will be analysed
in relation to the body of existing knowledge discussed in Chapter Two. Different methods of
data analysis and presentation will be used in the analysis and presentation of data.
6
1.7.5 Chapter Five: Conclusions and Recommendations
This chapter is for recommendations and conclusions of the research. The researcher‟s
recommendations and conclusion of the causes and effects of construction delays and strategic
7
CHAPTER TWO: LITERATURE REVIEW
2.1 INTRODUCTION
This chapter explores previous work done by other scholars and researchers. It looks at the
empirical and theoretical evidence of articles, journals and text books on construction delays.
According to Hart (2003), literature review is the selection of the available documents, both
published and unpublished, on the topic, which contains information, ideas, data and evidence
written from a particular stand point to fulfil certain aims on the nature of the topic and how it is
to be investigated and the effective evaluation of these documents in relation to the reason being
proposed. Furthermore, Boote & Beile, (2005) discussed literature review as an evaluative report
of studies found in the literature related to a selected area. However a literature review goes
beyond the search for information and includes the identification and articulation of relationships
Sanders and Eagles (2001) define construction delays as an event that causes extended time to
complete all or part of a project. According to Assaf and Al-Hejji (2006), construction delays
refer to the time overrun in completion or delivery of project beyond the date on which parties
agreed or project completion date specified. In addition, construction delays may also be defined
as the time overrun, either beyond the date of completion specified by the contract or beyond the
Construction delays are a global phenomenon (Sambasivan and Soon, 2007) affecting not only
the construction industry but the overall economies of countries as well (Faradi and El-Sayegh,
(2006). They involve multiple complex issues all of which are invariably of critical negative
effect to the parties to the construction contract. These issues concern entitlement to recover costs
of delay or the necessity to prolong the project with the consequential entitlement to recovery
8
costs for adjustments to the contract schedules. Questions arise as to the causes of construction
delays and the assigning of fault often evolves into disputes and litigation (Bolton, 1990).
Since construction delays are a global phenomenon (Sambasivan and Soon, 2007) many nations
experience construction delays in their construction projects. A study by Saleh, Abdelnaser and
Abdul (2009), shows that construction delays were also one of the biggest problems faced by
construction firms in Libya. Another study by Ogunlana and Promkuntong shows that
construction delays are a problem faced mainly in developing countries such as Thailand and
others.
The occurrence of construction delays raises the issue of which party should bear the
responsibility. In deciding this question, courts, boards of contract appeals, and arbitration panels
look both to the causes of the delay and to the express and implied obligations imposed by the
parties‟ contract (Smith 2005). Therefore determining the legal consequences that flow from a
given construction delay, and identifying the party that will bear the legal consequences of the
same, depend upon correctly identifying the type of construction delays that have occurred.
Construction delays fall into two major categories (Wortham, 2014; Smith, 2005; Bolton, 1990)
2.3.1 Excusable
Excusable delays are construction delays that are unforeseeable and beyond the control of the
contract for an extension of performance time (Smith, 2005). Excusable delays are also either
compensable, permitting the recovery of both time and money, or non-compensable, permitting
9
2.3.1.1 Non-compansable
According to Abudal et al (2002) non-compensable delays are caused by third parties or incidents
beyond the control of both the owner and the contractor. Examples typically include acts of God,
unusual weather, strikes, fires, acts of government in its sovereign capacity, etc. In this case, the
contractor is normally entitled to a time extension but no compensation for delay damages.
2.3.1.2 Compensable
Compensable delays are caused by the client or the client's agents (http://www.cohenseglias.com).
An example of this would be the late release of drawings from the client's architect. This was
schedule extension and exposes the owner to financial damages claimed by the contractor. In this
case, the contractor incurs additional indirect costs for both extended field office and home office
Non-excusable delays are delays that are foreseeable or within the contractor's control
(http://www.cohenseglias.com ). These are caused solely by the contractor or his suppliers. The
contractor is generally not entitled to relief and must either make up the lost time through
acceleration or compensate the owner (Abudal et al 2009). This compensation may come about
through either liquidated damages or actual damages, provided there is no liquidated damages
clause in the contact. Liquidated damages are generally expressed as a daily rate that is based on a
forecast of costs the owner is likely to incur in the event of late completion by the contractor.
Construction delays occur when the progress of a contract falls behind schedule, (Apolot and
Tindiwensi 2013). This may be caused by any party to the contract and may be a direct result of
one or more circumstances. Sambasivan and Soon (2007) find that poor planning, poor site
management, inadequate supervisory skills on the part of the contractor, delayed payments,
10
material shortages, labour supply shortages, equipment availability and failure, poor
communication and rework were the major causes of construction delays in the Malaysian
construction industry. According to El-Razek, Bassioni and Mobarak‟s (2008) study: delayed
payments, slow delivery of payments, coordination problems and poor communication were the
major causes of construction delays in construction projects in Egypt. Furthermore Kaliba, Muya
and Mumba (2009) deduced that the major causes of construction delays in construction projects
in Zambia were delayed payments, financial deficiencies on the part of the client or the
mistakes, poor coordination on site, changes in specifications, labour disputes and strikes.
The causes of construction delays tend to be variable with industries and nations. Ayman (2000)
investigated the causes of construction delays on 130 projects in Jordan. The results indicated that
the main causes of construction delays on construction projects were related to designers, user
changes, weather, site conditions, late deliveries, economic conditions, and increase in quantity.
Assaf and AlHejji (2006) conducted a time performance survey of different types of construction
projects in Saudi Arabia to determine the causes of construction delays according to each project
participant (client, consultant, and contractor) and they identified seventy three (73) causes during
the research.
Sambasvian and Soon (2007) identified the causes of construction delays and their impact on
project completion in the Malaysian construction industry. The results indicated that there are
many different causes of construction delays. This was supported by Ren et al., (2008), who
outlined several causes of construction delays amongst which a few has been chosen for the sake
of this research.
11
2.4.1 Contractors’ Financial Difficulties
According to Zagorsky (2007), financial difficulty is defined as getting into a situation where a
respondent's credit is adversely impacted, such as not paying bills. Choon (2008) defined
contractor‟s financial difficulties as the contractor not having sufficient funds to carry out the
construction works. This includes payment for materials, labour and equipment. Thornton (2007),
in his survey, found that slow collection, low profit margins and insufficient capital or excessive
debt are the major causes of financial difficulties among contractors. This is supported by Arshi
and Sameh (2005), Frimpong et al. (2003), who found that delay in payment from the client
would eventually cause financial difficulties to the contractor and most of the construction works
Numerous large projects, for example the Palm, Dubai International Airport extension, Dubai
Marina, Souk Al Nakheel, (Ren et al., 2008) request high quality, not only in workmanship and
construction materials but also in design for an upscale lifestyle. The design, construction and
Since the indigenous companies often do not have the qualifications to design, (Tumi et al., 2009)
construction or management these projects. Foreign companies are involved in some of the
industry sectors. They bring the state of art construction technology and management techniques,
however, many of them are involved in contractual claims and disputes with project delayed and
cost overrun.
Most of the construction projects adopt traditional procurement approach (Odeh and Battaineh,
2001). The purpose of conditions of contract which are incorporated in construction contracts is to
amplify and explain the basic obligations of parties to the contract. The conditions also provide
12
the administrative mechanisms for ensuring that the correct procedures are observed (Murdoch
and Hughes, 1992). Unfortunately, there is the perception that some parties are not very familiar
with the conditions of contract resulting in breaches in contract causing construction delays
(Fugar et al 2010).
In a construction project, there are many parties involved such as contractor, consultant, sub-
contractor and client. Often, it may be difficult for these various separate parties to coordinate
well in order to complete the project. In one study conducted by Assaf et al. (1995) it was found
that difficulty in coordination between the parties was one of the factors that contributes to
construction delays. In addition, Majid and McCaffer (1998) as quoted by Choon (2008) also
agreed that coordination problems will contribute to construction delays and this was also
supported by Ali et al. (2008) and Kadir et al. (2005) who stated that lack of coordination
between contractors and subcontractors will lead to delay, for example in the situation that newly
revised construction drawings of a project may be issued later by the contractors to the
subcontractors. This leads to construction mistakes and the work requiring to be redone.
Reconstruction work takes additional time, therefore impacting upon the completion time of the
project.
There are a large number of small construction firms (Motaleb and Kishk, 2010), who are
incapable to work on large scale or middle-sized projects. They often delay their work due to the
limited resources. It is remarkable that these companies are easily affected by the fluctuation of
the market.
According to Ahmed et al (2003) and Alaghbari (2005), the external factor of poor economic
conditions such as currency and inflation rate would significantly give impact to project ‟ s cash
13
flow, and hence affect the timely performance of the project. The underlying causes to financial
market instability, which will then lead to cash flow problems in construction project include:
increment of interest rate in repayment of loan, fluctuation of material prices, labour wages and
transportation costs and increment of foreign exchange rate for imported materials and plants.
Given the high demanding industry, most of the construction firms are over-loaded by taking
more projects than what they can handle (Choon, 2002.). The multitude of projects often beyond
Bruce and Dulipovici (2001) defined labour shortages in simple terms as the difficulty in finding
the right people to fill in the available job. Labour shortage is a problem faced by many countries
all over the world ( Choon 2008). Many companies suffer from the high turnover of skilled
technicians, engineers and labours and the impact is quite severe during the high peak of
construction period.
Strikes and labor unrest are frequent causes of construction delays on most construction projects
(Dinakar 2014). However, that not all strikes are considered as excusable construction delays.
Generally, a contract clause listing strikes as an excusable construction delay also carries a
qualification that the cause for the construction delay must have been unforeseen and beyond the
control of the contractor. Strikes that are foreseeable at the time of signing the contract are not
Wrong time estimation often reduces the productivity and delays project progress. This may be
due to the lack of personnel with estimating skills within the contractors‟ and clients‟
14
organizations (Fugar et al 2010). Thus, the work programmes from the clients or the contractors
abundant evidence to support the assertion that many contractors are reluctant to employ high
level skilled staff, (Fugar et al 2010) such as University graduates. Indeed, many contractors in
developing countries are entrepreneurs who are in the business to make more profit (Ogulana and
Olomolaiye ,1989; Wahab, 1997) and therefore, may not be willing to pay highly skilled staff.
In Saudi Arabia, (Ren et al., 2008) the contract language is always Arabic and then translated into
English. Most of the project participants prefer to speak and write in their own language without
employing qualified interpreters. This affects the communication, progress and quality of work.
Using the Arabic language in the contract documents is an important issue and most of the
15
2.4.13 Construction Mistakes and Defective Works
Gerskup (2010) claimed that poor workmanship, carelessness and shortcuts are the three key
factors that will contribute to defective works. Zanis (2010) also agrees that poor workmanship is
the main contributor to defective works. Careless mistakes such as taking incorrect measurements
from plans and specifications will lead to construction mistakes (Thomas, 1991). Additionally,
incorrect units and measures during construction will produce defective work. As a result, the
contractors need to reconstruct those construction mistakes which results in taking additional time
Thomas (1991) emphasized that contractors usually use shortcuts to complete the construction
work due to time and cost constraints. A shortcut can be defined as the path that takes lesser time
to complete compared to the usual path. Shortcuts will, however, eventually produce defective
works which need to be rectified later in the completion stage. This will subsequently delay the
project.
According to Ren et al., (2008) the clients in Dubai have absolute power on projects than in other
countries. When the client visits site, he may issue change orders which must be obeyed. On the
other hand, they do not always see the necessity for prompt action with respect to their contractual
obligations.
Financial difficulties were identified to be the most influential factors causing construction delays
in construction projects in Malaysia by Alaghbari et al. 2007 and Assaf et al. 1995. This was
supported Fugar et al (2010) who postulated that inability of clients to honour payments on time
was determined by as the major factor that causes construction delays in building construction
projects in Ghana. In the same study, it was noted that clients interviewed were admitting that
their inability to provide the needed funds on time was the most influential factor to construction
16
delays. Failure to pay contractors regularly for work done impedes progress and causes
construction delays (Abd El-Razek et al. 2008). Furthermore, failure to provide adequate funding
resources to contractors will make it impossible for contractors to meet project of objectives
According to Nichol (2008), late payment is a common problem especially during times of
economic crisis. This is supported by Still (2000) who found that late payment is a major problem
in Western countries. In the study by Odeh and Battaineh (2002), late payment was the second
highest factor contributing to delay, ranked by consultants. Late payment may occur during the
construction process and it is likely to be more severe during delay periods. The owner or client
may use postponement of the project as a reason to delay the payment to the contractor.
Bad weather conditions are natural events which cannot be controlled by the parties. In Ghana,
(Fugar et al 2010), the climate is tropical with wet and dry seasons. During the rainy season
construction works especially outdoor activities are disrupted due to high temperatures and
relatively high humidity. High temperatures and high humidity certainly affect the productivity of
construction workers as a result of dullness of their senses, poor coordination and discomfort from
A survey by Ubaid (1991) concluded that the contractor‟s financial resources are the major
measures on the contractors‟ performance. According to Kaming et al (1997), one of the most
influential factors causing construction delays on projects in Indonesia was shortage of resources.
and concluded that one of the main causes of construction delays was insufficient resources of an
organisation. Abdul-Rahman et al (2006) addressed that lack of funds may affect the project‟s
17
cash flow and lead to delays on site possession, which consequently causes construction delays in
Chang et al. (1991) highlighted that the input of tools and equipment used on a construction site
are either provided through direct investment by the contractor or acquired through hiring. Some
contractors may acquire tools and equipment using both methods. The contractor has to plan the
usage of equipment according to the construction work to be carried out during a particular period
of time because equipment obtained through hiring attracts cost during the hiring period. Shree
(2007) stated that the cost of hiring construction equipment has risen by around 30% to 40% in
only a few years. The increasing cost of equipment affects the contractor greatly as they will face
financial difficulty in hiring that equipment. Therefore, the contractor will have to suffer from
tools and equipment shortage which consequently, contributes to construction delays on the
project.
According to McDonald and Zack (2004), productivity is the measurement of labour efficiency to
complete the required work. Lost productivity and efficiency of the labourers always occur when
construction delays has happened (Bramble and Callahan, 2000). This occurs due to acceleration
of the schedule and also the pressure to complete the work. In addition, delays caused by
construction mistakes will need rework and this leads to a significant increase in the amount of
work the labourers are required to complete. This directly reduces the productivity and efficiency
Effective and efficient site management by contractors is very important to ensure projects are
completed on time (Choon 2008) and poor coordination contributes to delay from estimated
completion time. Poor site management may occur when contractors do not have enough
18
experience and suffer from a lack of knowledge in managing the project team (Kadir et al., 2005).
However poor site management from the project manager‟s side will affect the whole team and
also the progress of works, resulting in the eventual outcome of project experiencing construction
delays . This view is supported by studies conducted by Augustine and Mangvwat (2001), Arshi
and Sameh (2006), Aibinu and Odenyika (2006) and Ahmed et al. (2003) who concluded that
poor site management is one of the factors that contribute to delay in construction projects.
Dinakar (2014) defined an act of God as a natural occurrence caused directly and exclusively by
natural forces without any human intervention, which could not have been reasonably foreseen,
nor could have been prevented. The author further discussed that, earthquakes, landslides,
tornados, hurricanes, lightning, floods, etc., are all examples of acts of God. These therefore affect
Construction delays are insidious often resulting in time overrun, cost overrun, disputes,
litigation, and complete abandonment of projects (Sambasivan and Soon, 2007). Many projects
are of such a nature that the client will suffer hardships, expenses, or loss of revenue if the work is
delayed beyond the time specified in the contract (Clough, 1986). Then again, construction delays
have cost consequences for the contractor: standby costs of non-productive workers, supervisors,
and equipment, expenses caused by disrupted construction and material delivery schedules and
Murali et al., (2007) argued that both contractor related factors and client related factors such as
inadequate contractor experience and owner interference have impact on time overrun. On the
other hand, Aibinu and Jagboro (2002) studied the effects of construction delays on project
19
delivery in Nigerian construction industry and identified that time overrun was one of the major
2.5.2 Rescheduling
According to Vieira et al. (2003), rescheduling is the change of original schedule of time in order
to respond to disruption and problems which have occurred. In the construction industry,
schedules may be updated in order to monitor the time and work in construction projects (Liu and
Shih, 2009). The importances of schedule updates are as mentioned by Liu and Shih (2009) to
include:
compare the original schedule with the actual progress of the project;
Based on the schedule update, delayed activities can be identified and usually, rescheduling is
required due to the delayed work. Thus, rescheduling is one of the effects of delay in construction
projects.
Mohamad (2010) studied the causes and effects of construction delays in government
construction project and identified cost overrun as one of the effects of construction delays in
Malaysia. Regarding cost overrun, Koushki et al., (2005) identified three main causes that were
contractor related problems, material-related problems, and owners financial constraints, whereas
Wiguna and Scott (2005) identified the most critical factors included: high inflation, increased
material price; design change by client; defective design; weather conditions; delayed payment on
20
2.5.4 Disputes
Disputes may arise during the construction process amongst the project parties. Lack of
According to Murali et al., (2007) the factors such as lack of communication between the various
parties, problem with neighbours, unforeseen site conditions, delay in payments for completed
contract documents will give rise to disputes between the various parties. Furthermore, if the
disputes cannot be solved amicably or easily it can lead to arbitration or litigation (Mohamad
2010).
2.5.5 Arbitration
According to Sambasivan and Soon, (2007) construction delays which are caused by the client
relate factors and contractor related factors such as change in order, mistakes or discrepancies in
contract document and lack of communication between various parties which may rise the
disputes will be settled through arbitration process. For these circumstances, it is necessitate
having a competent third party that can settle the disputes amicably or easily without going to
court.
2.5.6 Litigation
Based on Murali et al., (2007) when construction delays are caused by client related, contract
related, labor related, external related factors and contract relationship related factors such as
delay in payment for completed works, problems with site conditions and less of labor supply
where eventually rise the disputes to be settled by the litigation process. The parties involved in
the construction projects use litigation as a last alternative to settle the disputes.
According to Djordjevic and Djukic (2008), company reputation is one of the most important
intangible assets. Ismail et al. (2006) support this statement and add that reputation is built from
21
the overall performance of the company. The reputation of a company is very important because
an adversely affected reputation can become a business threat (Murray, 2003). Strategic planning,
corporate governance and corporate codes of conduct are the top three factors that affect company
reputation according to the study conducted by Ismail et al. (2006). Thus, delay in construction
The most critical adverse effect of construction delays on construction projects is abandonment
that could be temporary or in worse conditions total abandonment. The major causes of
construction delays such as client related, consultant related, contractor related and external
related may lead to project abandonment that will lead to delays in construction projects. Aibinu
and Jagboro (2002) studied the effects of construction delays on project delivery in Nigerian
construction industry and identified total abandonment as one of the major effects of construction
delays.
According to Abedi et al, 2011 the success of construction projects is critically significant for all
project participants especially for clients as well as the country economy and in bigger picture it
project is commonly acknowledged as successful when the aim of the project is achieved in terms
of predetermined objectives that are mainly completed the project on time, within budget and
specified quality in accordance with the specifications and to stakeholders‟ satisfaction. For a
project to be successful; construction delays must be minimized or reduced (Aibinu and Jabgoro
2002). Many researches were conducted from different countries to try and address the problem
of construction delays.
22
2.6.1 Early payment
Haseeb et al 2011 conducted a research and concluded that construction delays were badly
affecting the large construction industries of different countries and it was needed to find
solutions for countering construction delays. Since they identified financial problems as the main
cause of construction delays, they suggested that financial problems should be avoided by making
the payments on time. Their argument was that clients should make timely payments to the
contractor and contractor should make the timely payments to the subcontractors, suppliers and
labor. Furthermore, Koushki et al. (2005) identified: ensuring an adequate source of project
In Nigeria, Aibinu and Jagboro (2002) identified two methods of minimizing delays amongst
which acceleration of site activities was noted out. This was further supported by Wortham (2014)
and he defined acceleration is action taken by the main contractor in order to speed up the
progress of the project to accomplish early completion or to make up for lost time. In addition
Abudul-Rahman et al. (2006) identified it as the procedures taken by the contractor as to the
A contract must be specific in terms of the time required to perform the work. Odeh and Battaineh
(2002) recommend that reinforcement of liquidated damages clauses can minimize construction
delays. According to Viscarello (2006), not all liquidated damages clauses are enforceable. For a
liquidated damages clause to be enforceable, it must satisfy the parties. Because of this,
23
2.6.4 Proper pre-construction planning
A research by Abdelnaser et al., (2005) concluded that in order to avoid delays during
construction stage, the construction parties should make proper planning. Furthermore, Koushki
et al. (2005) identified some of the methods of minimizing construction delays in Kuwait. They
were pointing out that; performance of pre-construction planning, allocation of sufficient time and
finances during the design phase, hiring of independent supervising engineers to monitor progress
of work, ensuring timely delivery of materials and selection of competent and reliable consultants
to carry out the work will minimize the occurrence of construction delays. This was also
supported by Dayang (2009) whom in his researches identified proper project planning and
Aiyetan (2011) added that at the design stage, attention should be paid to adequate briefing,
and these will help in minimizing construction delays. More so, Odeh and Battaineh (2002)
recommend that at design stage, project parties should ensure the availability of resources, hiring
a competent project manager and utilization of appropriate construction methods, incentive offer
Dayang (2009) postulated that developing appropriate communication system linked to all
Dainty et al. (2002) cited Cooke-Davis (2001) who declares that project management competence
represents only one of many criteria upon which project performance is contingent. According to
Ponpeng & Liston (2003), problems such as construction delays, large number of claims and
litigation result to a large extent from not selecting the best contractor to construct the facility.
Quality of management during construction concerns the steps taken to ensure that products are in
24
accordance with the quality standards and measure the effectiveness/competency of consultants
and contractors (Aiyetan 2011). The factors that contribute to quality of management during
construction are forecasted planning data such as analysis of construction methods; analysis of
resource movement to and within site; analysis of work sequencing to achieve and maintain
workflow; monitoring and updating of plans to appropriately reflect work status; responding to,
and recovering from problems or taking advantage of opportunities present; effective coordination
Contingency sums are allowances of project cost included in the pre-contract estimate for the
purpose of ensuring that the budget set aside is realistic and sufficient to contain the risk of
unforeseen cost increases during construction (Aibinu and Jabgoro 2002). Investigation by these
authors revealed that 5–10% contingency allowance is a common practice in Nigeria. Provision of
adequate contingency sum at the pre-contract stage could buffer the extra financial burden arising
Productivity in the construction industry has been steadily declining (Aiyetan 2011) and labour
efficiency has been cited as poor, resulting in construction delays. Several techniques can be used
to positively influence workers‟ behaviour. Two of these techniques are the behavioural and
economic approaches. The former views motivation from the workers‟ psychological
requirements and the second views it from the economic approach, placing emphasis on monetary
rewards (Andawei, 2002). Motivation variables that could impact on construction time are: pay
and allowances; job security; a sense of belonging and identification with the project team;
recognition of contribution made; opportunity to extend skills and experience through learning;
equitable rewards relative to others‟ input into the project, and the exercise of power and
25
CHAPTER THREE-RESEARCH METHODOLOGY
3.1 INTRODUCTION
This chapter aims at presenting the methods or techniques that were employed in conducting this
research. The data collection procedures and analysis techniques are also outlined, with the
justification of the tools and research methods chosen clearly spelt out.
Kish, 1995 defined a research design as a declaration of the object of the investigation and added
that it will show the strategies that will be used for collecting data, analysing the data and
reporting the findings. The research was skewed towards quantitative and qualitative assessment
qualitative research is used to „subjectively‟ evaluate the „opinion‟, „view‟, or the perception of a
respondent towards a particular subject. Qualitative research allows opinions from different
parties in the construction industry to be drawn on the subject matter. According to Thomas
by the respondents and events in which the researcher studies on. A quantitative research design
gives detailed representation of results through figures, tables, pie charts and percentages. The
In a bid to enhance feasibility of the study, the research was confined to Bulawayo and Midlands
provinces. These provinces were selected for the study because there are construction activities
being carried out in these provinces and also time and financial constraints.
The targeted population of this research were the professionals and contractors in the construction
industry of Zimbabwe.
26
3.4.1 Sampling Frame
A sample frame is defined as a complete list of all the cases in the population from which sample
is drawn from (Saunders, 1997). The researcher gathered information from clients and property
developers with on-going or recently finished projects. Contractors registered with either
Zimbabwe (CIFOZ) categories A to H were considered for participation in this research. More so,
Engineers (ZIE) and Zimbabwe Institute of Quantity Surveyors (ZIQS) were also considered for
this study.
Leedy (2003) refers to sampling as a method of coming up with the actual sample to be used to
gather data. A certain number of participants was drawn from the target population of contractors,
clients and consultants to make up a sample size. The composition of the sample size is as shown
27
Table 3.1: Composition of the sample size
Quantity Surveyors 5
Architects 5
Engineers 5
Contractors 20
Clients 5
TOTAL 40
For the purpose of this dissertation non probability sampling methods was used. According to
O‟Leary (2004) non-probability sampling methods are used when there is need to address
something about a discrete phenomenon, (people, places, objects, etc.) or when there is need to
answer the “how” and “why” questions. The researcher makes use of convenience and purposive
sampling methods.
Convenience sampling methods were used to select respondents who are convenient to the
researcher. Respondents who are conveniently accessible geographically were selected. This
enabled the researcher to easily, quickly and economically obtain data from the potential
respondents (Lewis 1997). This method was used in distributing questionnaire to the targeted
population.
population that one thinks knows most about the subject matter (Walliman 2005). This method
28
3.5 DATA COLLECTION TOOLS
There are two sources of data collection, and these are primary and secondary sources of data and
the researcher employed both sources to increase validity and reliability of the data in this
research.
Primary data sources come from first-hand knowledge of the person referenced in the data or
from a witness of the phenomenon under study (Shuttleworth, 2008). This is data that is collected
specifically for the purpose of the investigation at hand hence they are precise, current, tailored
and private. Primary data helps provide satisfactory information since secondary data does not
resolve all questions. Data was collected from selected case studies where interviews will be
done, and augmented by questionnaires that were distributed to the rest of the respondents.
3.5.2 Interviews
The researcher used interviews on the subject of construction delays to get information from
construction parties. The interview method of collecting data involves presentation of oral-verbal
stimuli and reply in terms of oral-verbal responses (Kothari, 1985). Interviews were done face to
face with contractors, clients and consultants on four selected case studies. There were cases
where the respondents with necessary information cannot be easily reached, telephone interview
were done. These interviews were taking not more than thirty (30) minutes long.
The researcher employed interviews because they produced a high response rate and reduce
incomplete answers as the respondents were able to give answers and the researcher noting them
down. The interviewer also was able to probe deeper into a response given by the interviewee,
providing a wider depth of information and the respondents were able to give personal views
towards subject matter and ask questions where they need clarity.
29
Semi-structured interviews were used whereby a set of questions were prepared but allowing a
great freedom for the respondent and the researcher for further explanation.
3.5.3 Questionnaires
Survey questionnaires were sent out and distributed to contractors registered with CIFOZ
categories A to H, clients with both on-going and recently finished projects and consultants
registered with ZIE, IAZ, and ZIQS. The questionnaires were sort for the respondents‟
contributions and opinions on the subject matter of construction delays. These were personally
delivered to projects and a few were sent via email in a bid to increase the response rate. The
researcher personally collected the questionnaires from the respondents whereas some were
returned through email. Questions were open and close ended types and standardised to reduce
bias. Spaces were provided for open ended questions whilst close ended questions consisted of
options where respondents were required to choose from the provided options. Respondents
remained anonymous and were therefore free to respond genuinely and honestly. Questionnaires
They reduce bias. The researcher‟s opinions were not influencing the respondent to
answer the question in a certain manner. In other words, there were no verbal clues to
They are less intrusive. The respondent was completing the questionnaire at own spare
time. Thus, the respondent answers the questions properly and accurately because the
They are easy to analyse. Data entry and tabulation for nearly all surveys was done easily.
30
3.5.4 Case studies
The case study method is a very popular form of qualitative analysis and involves a careful and
even the entire community (Kothari 1985). Four (4) purposively selected projects, which were
medium and large scale according to Construction Industry Federation of Zimbabwe (CIFOZ),
were included in this study. These projects were consisting of one (1) recently completed housing
project, two on-going projects building projects and another on-going housing project.
This is ready data, recorded for other purposes but related to the research topic. Evans and
Berman (1990) define secondary data as data that have been gathered for the purposes other than
the current research. Secondary data recorded involves both qualitative and quantitative data.
Literature review and study of documentation available (published and unpublished) were useful
in this research. This enhanced the verification and reliability of methods of data collection,
The secondary data sources that were employed in this research were:
textbooks
magazines
news papers
31
3.6 DATA PRESENTATION AND ANALYSIS
Fink (2003) described data analysis as the process of systematic application of statistical and/or
logical techniques to describe, illustrate, condense, recap and evaluate data. Questionnaires were
checked for physical completeness. The researcher then sieves the data, discarding whatever
irrelevant to the study and consolidating important content. The idea was to allow the most
significant observations to emerge from all the data gathered in the field while reducing the
volume of the data. Presentation of the data was done using excel, pie charts, tables and graphs
where necessary and analysis was done using the Relative Importance Indices. The information
obtained from the research survey was also compared with what was obtained in the review of
3.7 CONCLUSION
The research design, data analysis plan and the data collection summary was outlined in this
chapter. Suitability, validity and appropriateness of data sources and research instruments to be
used have been exposed. The following chapter will seek to present and analyze the collected data
and information.
32
CHAPTER FOUR- DATA PRESENTATION AND ANALYSIS
4.1 INTRODUCTION
This chapter evaluates the findings of the study, the factors that limited the data as well as the
reliability and validity of the data. The general part is composed of the questionnaire response
rates, the composition of respondents and measures put in place to ensure validity and reliability
of information. The second part is the data analysis, in which data was analyzed according to each
research objective.
Generally, the reception in the industry was fair. Most of the questionnaires distributed to the
respondents were returned with all the questions fully answered giving a response rate of 79% as
Quantity Surveyors 5 2 40
Architects 5 4 80
Engineers 5 3 80
Contractors 20 19 95
Clients 5 5 100
TOTAL 40 33 79
Thirty-three (33) out of forty (40) questionnaires were positively responded to, bringing the
response rate of 79% which was significantly enough to give credibility to the findings that are
33
presented and discussed hereafter. In a similar research which was successfully done by Olusegun
and Akintunde (2012), 30 questionnaires were distributed and achieved 73% response rate,
therefore since this research earned 79%, it shows that the results are dependable, valid and
The response rate was 100% which shows willingness on the part of the interviewees to give the
necessary information. The interviewees were willing to be interviewed within the appointed
times which had been set up by the researcher and the interviewees.
Contractor 4 4 100%
Client/Property 4 4 100%
Developer
Architect 4 4 100%
Total 17 17 100%
Respondents were expected to identify their companies and firms they are currently employed at,
registration with construction boards, experience in terms of time and types of projects. The
following graph shows the information of the respondents in their respective construction boards
34
35%
25%
15% ZIE
ZIQS
10%
AIZ
5%
0%
<4 Years 4-8 Years 8⁺ Years
Number of years of experience
The results shows that most organisations are between 4 and 8 years of experience in the
construction industry implying that the industry is flooded by small scale organisations. Most of
them respondents were found to be participating in both building, housing schemes, civil
engineering construction works. The reason was shortage of construction jobs in Zimbabwe and
most small scale contractors were found participating in jobs which they are incapable of
executing.
The companies‟ experience shows that most of them have a experience in the industry of between
4 and 8 years as shown, with response rate of 51% followed with those with more than 8 years of
Initially the respondents were required to indicate whether they had ever experienced construction
delays and Fig 4.4 illustrates their responses for experiencing construction delays.
35
100%
90%
80%
Percentage Responses
70%
60%
50%
40% Experienced delays
20%
10%
0%
Quantity Architects Engineers Contactors
Surveyors
Construction Organisations
The investigation revealed that most respondents had faced construction delays from their
In order to find the causes of construction delays, the respondents were asked identify among the
four construction parties namely; client, contractor, consultant and other factors which party was
responsible. The results according to the questionnaire respondents are presented in Fig 4.3
Other factors
Consultant
3%
10%
Main
contractor
26% Client
61%
36
The results showed that the client was the most contributing party to construction delays with
61% of respondents supporting the idea. This complied with the studies by Fugar et al (2010),
which revealed that the client was the most responsible part to construction delays. Following the
client was the contractor, 26% of respondents noted the contractor as the second part in causing
construction delays. The consultant had 10% while was other factor in which the case studies
The results obtained from the responses to causes of construction delays are provided in Table
4.3. In total 22 factors were analysed, with the top ten factors contributing to more than 60% of
the causes of construction delays. From the ranking assigned to each cause of construction delays,
the researcher was able to identify the most influential factors of construction delays in
37
Table 4.3 Questionnaire results of the causes of delays
1 2 3 4 5 RII RANK
38
Based on the ranking, Relative Importance Indices (RII), the top four most important causes of
construction delays as perceived by respondents are discussed. The first ranked was financial
difficulties of the client (RII = 0.9290). The reason behind this was the economic crisis in
Zimbabwe and the world at large. Many investors are not able to secure sufficient funds for
construction project hence they end up delaying construction project because of financial
difficulties
Next to financial difficulties of the client was change order by clients or variations during
construction period (RII = 0.9097) which was ranked the second. Respondents agrees with Long
et.al (2004) who identified client‟s change orders or variations to the scope of contract as the
significant cause of construction delays. This was supported by three (3) interviewees of the four
(4) case studies that clients change orders cause construction delays. They added that variations
are inevitable in the construction due to high technological environment where clients tend to
change their needs rapidly within the project execution process. However change orders mean the
need for the extension of construction time to accommodate the variations and thus delaying the
project time.
Contractor‟s financial difficulties with RII = 0.8516, was ranked the third. This factor was
supported by Assaf and Hejji (2006) indicating that most contractors face challenges in financing
the awarded projects. However this is merely due to misappropriation of the allocated funds from
the clients and contractor‟s lower bidding strategies that expose them to financial insecurities.
Four (4) clients interviewed on case studies indicated that contractors seem to under-price as a
way of securing jobs but however as a result they fail to execute due to financial difficulties and
39
Late payment (RII = 0.8323) as indicated by most of the contractors was ranked fourth. This
factor was noted in the studies by El-Razek et al, (2008) which stated that delay in issuing of
progress payments by the client to the contractor impacts the viability of a project since most
contractors relies on such payments to finance their projects. Furthermore from the results of the
case studies it was noted that the interviewees were pointing this factor as one of the root causes
of construction delays. The assertion is worthwhile since any hiccup in payment flow to the
Wrong time estimation (RII=0.7742), was rated the fifth. This was supported by many contractors
that time estimation at design stage cannot be reliable. They pointed out that many clients
stipulate time expected for the project, whilst it may not be the real time taken on the ground. This
will then be marked as delays, since the contractors may not be able to comply with the stipulated
contract time.
Construction projects in Zimbabwe are rarely delayed by language barriers. Language barriers
was ranked the last of the twenty-two causes of construction delays with (RII=0.2387). This
shows that the construction industry of Zimbabwe is not sensitive to languages like other Asian
countries as mentioned by Ren et al., 2008, that in Saudi Arabia, construction projects were being
delayed due to language barriers. This is because Most of the project participants prefer to speak
and write in their own language without employing qualified interpreters. This affects
communication which further leads to delay in progress of the project. However, in Zimbabwe
English is used as one common language for all activities and few or no translation is needed
Acts of God was rated the second least, (RII=0.2645). This was because respondents mentioned
no case of construction delays caused by the Acts of God such as hurricanes, tornadoes,
earthquakes and other natural disasters as it happen with other countries which suffer from theses.
40
Many Zimbabwean construction activities do not incorporate the involvement of international
parties. International involvement was rated the third from last, (RII=0.3032). Unlike other
countries like UAE, the workforces employed in projects are of mixed nationalities, which bring
different traditions, rules, habits, religions. For example, the religions holidays include holy
Friday for Muslims, Sunday holiday for Christians, and regular holidays and festivals for Indians.
most of the investors are local investors because of the Indigenisation Act which was passed in
Shortage of equipment was ranked the fourteenth, (RII=0.5097). This was argued by many
contractors that construction delays are not caused by shortage of equipment, though some clients
stated shortage of equipment as a cause of construction delays in Zimbabwe. This was because
contractors mentioned that they have idle pieces of equipment due to shortage of construction
jobs in Zimbabwe, thus equipment is available for construction. Unlike Libya as studied by
Chang (2006), contractors were delaying projects due to shortage of equipment and the case is
In Zimbabwe labour shortage is not a problem to construction activities. Labour shortage was
rated the eighteenth with RII=0.3161. Contrary to the studies of Choon (2008); which postulated
that labour shortage was a problem faced by many countries all over the world, Zimbabwe has a
high unemployment rate according to the respondents. Many companies in UAE as concluded by
Atout et al (2008), suffer from the high turnover of skilled technicians, engineers and labours.
However in Zimbabwe these are available and there are no jobs for them to participate in thus
construction delays are not severely caused by labour shortage as it is the case with other
countries.
Figure 4.4 shows the perception about the causes of construction delays as noted from four case
studies.
41
120
80
60
40
20
0
Financial Change Contractors Consultant's Project Slow Late
difficulties orders financial late approval complexity decision payment
of the client difficulties of making
documents
Causes of construction delays
Fig 4.4 Case study: Percentage response to the causes of construction delays
Deductively, the perception about causes of construction delays in the construction industry of
Zimbabwe is the same that they are mostly caused by financial difficulties of the client. 100%
responses from the case studies confirmed the same. They added that it was the economic crisis in
Zimbabwe and many investors are failing to secure sufficient funds for construction project hence
Most clients seem to be ignorant of the implications of too many change orders projects. Change
orders by clients was supported to be one of the main causes of construction delays by 75% of the
respondents to case studies. Having too many change orders and at the same time having financial
difficulties will add an extra financial burden upon the client which will latter lead to construction
delays. Financial difficulties of the contractor was also noted to be one of the causes of
construction delays.
Other causes of construction delays were noted which also contribute much to construction delays
42
Consultant‟s late approval of document
Project complexity
The effects of project delays were rated in relation with the severity of each effect to the project
operations. Fig 4.7 shows the effects of construction delays to construction project and their
Litigation 65.4%
Arbitration 64.6%
Disputes 66.9%
Rescheduling 77.4%
Percentage response
Cost overrun, (RII =0.967) was ranked highly by the respondents. This alone has proven that
construction delays on a project can lead to cost overrun in Zimbabwe. This is possibly because
when the budgeted cost of the project is exceeded the burden lies with the client and might end up
43
taking longer than normal trying to source extra funds for the project therefore delaying the
completion dates and latter suspends the project as is the case with many projects in Zimbabwe.
Again contractors also contribute much to cost overrun since their mismanagement of resources
will lead to wastages that have a cost impact. All the ten (10) causes of construction delays
discussed earlier in this chapter directly affect the completion time of the project and cause cost
overrun.
Results from case studies pointed out much on cost overrun as the most experienced effects of
construction delays. Table 4.5 shows how cost was affected by construction delays as given by
four cases. Change orders from clients, construction mistakes and defective work result in cost
44
Table 4.4 Case study: Effects of construction delays on cost
The results indicated that as time overrun increases, percentage cost overrun increases also. This
is because extra costs are incurred paying idle machinery and equipment, extra costs of
In extreme cases, some projects might be totally abandoned (RII = 0.967). Clients and contractors
contribute to the total abandonment of the projects as argued by the consultants, since they are the
major stakeholder for a project as well as the main wheels to project success if they exercise their
duties properly. In Zimbabwe, most public projects were temporarily suspended during the
financial crisis period. Many of these projects have now become so prohibitively expensive that
they are totally abandoned or are now being resumed at a very slow pace, for example, the
construction of a Mortuary at Mpilo Central hospital, Bulawayo, was abandoned since the
Late delivery of services was rated as one of the most severe effect of construction delays. This
was supported by mostly clients that the community suffers from late access to services as a result
of construction delays. For example late completion of the Central Library, National University of
45
Science and Technology, (NUST) students find it difficult to study in the library which is not
Most consultants argued that construction delays leads to bad contractual relationship. This effect
of construction delays (RII=0.8850) was also supported by the results of case studies. Contractors
pointed that bad contractual relationships are due to communication problems. However bad
Contractors supported this, citing that when a project is delayed the society pinpoints the
contractor as the main actor to cause construction delays, in which in some cases he may not have
been responsible.
The respondents supported the point that construction delays have negative impacts on project
costs as a result of rescheduling (RII = 0.7740). Love et al, (2000) suggested that when
construction delays have occurred, the project manager has to decide to prescribe for rescheduling
Whenever there are construction delays, there are disputes (RII = 0.6691) as to who should bear
the responsibility and the cost. All project parties are affected by disputes that arise during the
course of the project. The respondents agrees with Murali et al (2007) that if disputes are not
resolved amicably, they can lead to arbitration (RII=0.6543 or litigation (RII=0.6461). This is
probably because factors such as delay in the payments for completed work, variations,
communication problems between the various parties, and improper site management give rise to
Respondents have agreed to the prescriptions that have been suggested to reduce construction
delays on projects. The suggested measures were rated in relation to their effectiveness in
46
reducing project delays. Fig 4.8 illustrates the relative importance computation and rankings done
to the delay mitigation measures that could be instituted to curb the problem as perceived by the
respondents. Five strategic measures were rated extremely effective by respondents and for the
47
Table 4.5 Strategic measures to minimize delays
STRATEGIC MEASURE TO
EFFECTIVENESS RATING
MINIMIZE DELAYS
1 2 3 4 5 RII RANK
variations 1 1 4 25 0.9419 3
Development of appropriate
clauses 5 15 5 6 0.4774 9
The statistics presented on the Table 4.2 complied very well with the results of the case studies
shown in Fig It has been seen that most respondents agrees with the studies of Koushki et al.
(2005) which identified that ensuring an adequate source of project finance is a methods of
minimizing construction delays. Providing adequate project finances (RII=0.9806) was rated the
most effective method to minimize delays by both contractors and consultants. Their argument
was that clients should make timely payments to the contractor and contractors should make their
48
timely payments to the subcontractors, suppliers and labour. However clients put their argument
that payment in time becomes difficult when contractors keep on over claiming and especially in
Results from case studies, Fig 4.8 indicated that construction delays can be minimised effectively
by proper pre-construction planning, early payment to the contractor and by educating the client
120
100
Percentage response
80
60
40
20
0
Proper pre- Educate the Early payment to Choose a Proper project Early approval of
construction client on contractor competent management documents
planning implication of contractor
variations
Suggested Measures to minimize delays
Choosing a competent contractor (RII=0.9742) was rated the second measure which is most
effective in curbing construction delays. Some contractors agreed with the responses from
consultants that most small scale contractors bid for jobs which they are not capable of executing.
The idea tallies with the studies of Sambasivan and Soon, (2006) in Malaysia. Most small scale
49
contractors were winning jobs which they were not capable of completing and end up in
construction delays. In Zimbabwe, because of the bad economic situation small scale contractors
bid for jobs which they are not capable of completing without considering their incapability.
Some of the contractors will not have proper equipment for the jobs they bid for and end up
delaying the jobs trying to hired equipment and subcontracting the jobs.
Most respondents were identifying the clients on the issue of change orders. They rated educating
the client on the implication of variations (RII=0.9419) the third as an effective measure to
minimize construction delays. Their contribution to this idea was to minimise the number of
changes and their negative impact on project performance. Nicholas (2003) recommends a formal
system for change review and control to allow for change definition, schedule and budget impact
assessment. The purpose of the approach is to reduce the number and impact of changes to a
minimum and make sure that all related changed work is authorised and introduced in a controlled
planned manner.
Proper pre-construction planning (RII=9290) rated the fourth by respondents was found to be one
of the most effective ways of curbing construction delays. They stated that most problems faced
during construction period amongst which is construction delays, originate from pre-construction
planning which may not have been effectively done. It was noted from case studies that most
interviewees were stating that proper pre-construction planning will enable the construction
parties minimize construction delays. They were arguing that too many change orders by the
client was because of improper planning during the design stage. Therefore many changes will be
noticed during the implementation stage and these lead to construction delays. Thus proper pre-
It has been seen that some respondents have agreed with Lichtenberg (2005) that management
during construction (RII = 0.938) has a greater impact on minimizing the occurrence of
50
construction delays in the construction. Management during construction means the use of project
management technic. The technic is widely being used by construction practitioners. Project
management is believed to improve project star-ups, development of realistic plans and budgets
and team building which enhances project success. Respondents from case studies also argue that
adequate project financing is equally as important as project management because if there are
timely cash flows for the project that determine the success of a project. Therefore project
management goes hand in hand with proper funding of the project as there is need for
management of allocated fund to each project activity for a project to become viable.
4.5 SUMMARY
From the presentations and analysis of data made in this chapter it has been noted that there ten
(10) main causes of construction delays with which financial difficulties and change orders being
the most severe cause of construction delays. Respondents noted time overrun, cost overrun,
project suspension, bad contractual relationships and badly affected company reputation as the top
five (5) severe effects of construction delays. They also instigated various ways used to combat
the problem of delays. Diversity of backgrounds of the respondents assured effective results and
51
CHAPTER FIVE RECCOMENDATIONS AND CONCLUSSION
5.1 INTRODUCTION
The previous chapter presented, analysed and interpreted the data collected from the industry. In
this chapter, the highlights of the research are summarized and conclusions are made from the
findings. The main aim of this chapter is to draw conclusions and give recommendations to the
research dealing with research objectives and questions introduce in chapter one. The study
objective was to investigate the causes and effects of construction delays and strategic measures
that can be taken to minimize their occurrence on Zimbabwean construction projects. Having
collected data from the field and analysed it in the previous chapter, the researcher is now able to
5.2 CONCLUSIONS
It can be concluded that construction delays happen in the construction industry of Zimbabwe
and, the client and the contractor to the project are the main actors in causing construction delays.
The main causes of construction delays in Zimbabwe are financial difficulties of the client;
change orders from the client/variations; contractor‟s financial difficulties; late payment and
wrong time estimation. Construction delays are rarely causes or never occur in Zimbabwe because
52
5.2.2 Effects of construction delays
Construction delay is a very serious problem in the construction industry of Zimbabwe which
results into five main effects upon a project namely; time and cost overruns; badly affected
company reputation; bad contractual relationships and project suspension amongst others.
Even though construction delays re inevitable on construction projects in Zimbabwe, this study
unveils strategic measures to minimize them. It was found that the most effective measure to
contractor, .
5.3 RECOMMENDATIONS
clients must make earlier timely payments to the contractor; however this is achievable if
the client; exercises proper pre-construction planning, ensure that funds are available or
adequate arrangements for funds are made before projects are started. The long and
be shortened for efficiency and contractors‟ payments must be honoured as and when they
the procurement team must choose a competent contractor who is capable of completing
the project on time. While selecting the contractors, the procurement team have to make
sure that the contractors are not selected based only up on the lowest bid. The selected
53
contractor must have sufficient experience, technical capability, financial capability, and
Contractors should not take up the jobs in which they do not have sufficient expertise.
Contractors should have ability to manage site activities for the smooth execution of work,
plan their work properly and provide the entire schedule to the clients, and make sure that
Since the subject of construction delays is a broad research area, a further research can be carried
can be focused on the analysis of the contractor‟s perception on the causes of construction delays.
The researcher found this interesting since construction parties blame one another on the causes of
construction delays. Again construction delays were found to be involving all construction
54
REFERENCES
1. Abd El-Razek, M.E., Bassioni, H.A.and Mobarak, A.M. (2008) „Causes of delays in
2. Abdul-Rahman H., Berawi, M.A, Berawi, A.R, Mohamed, O., Othman, M. and Yahya,
10 May 2009)
7. Aiyetan Ayodeji, Smallwood John and Shakantu, (2011), Winston A systems thinking
8. Alaghbari, W., Kadir, M.R.A., Salim, A., and Ernawati (2007) „The significant factors
55
10. Andawei, M.M. (2002), Motivation: An alternative to improve workers‟ performance
11. Apolot, R. and Tindiwensi, D. (2013). Investigation into the Causes of Delays and
12. Arshi, S.F. and Sameh, M.E. (2006) Significant factors causing delay in UAE
13. Association of Project Managers (2006) APM Body of Knowledge. fifth editition.
London: APM.
55
15. Assaf, S.A and Al-Hejji, S. (2006) Causes of delay in large construction projects.
16. Bolton, J. (1990) „Type of claims‟, Construction and disruption claims, Course
17. Chang, C.L., Ogunlana, S. and Saeed, K. (1991). Construction Project Management: A
system dynamics approach. Paper presented at the 9th International Conference of the
18. Chidambaram, R; Narayanan, S.P; and Arazi, B.I, (2012) Construction delays causing
21. Cooke-Davies, T. 2001. The „real‟ success factors on projects. International Journal of
56
22. Currie, Smith & Hancock, LLP's Common sense construction law : a practical guide
Johor and Sabah region, Faculty of Civil Engineering: Universiti Teknologi. Malaysia:
Master Thesis.
24. Dawson, Catherine (2002), Practical Research Methods, New Delhi, UBS Publisher's
Distributors
25. Dinakar Aditi, (2014), Delay Analysis in Construction Project, International Journal
26. Frimpong, Y., Oluwoye, J. and Crawford, L. (2003). Causes of delay and cost
(1/2) 103‐116
28. Gerskup, M. (2010, July 5-9). Design Errors, Construction Mistakes and Building
29. http://www.cohenseglias.com/federal-contracting-database/excusable-and-non-
excusable-delays
30. Kaming , P. , Olomolaiye , P. , Holt , G. and Harris , F. ( 1997 ) Factors infl uencing
31. Kish, L. (1995) Surveying Sampling (65th Edition). John Wiley and Sons Inc., New
York.
57
32. Kpthari, C.R. (1985) Research Methodology-Methods and Techniques, New Dehli,
33. Kottegoda, N.T; and Rosso R. (1997) Statistics, Probability, and reliability for Civil
35. Koushki.P.A, Al-Rashid.K and Kartam.N. (2005). Delays and Cost increase in the
36. Kumar, Ranjit (2005) Research Methodology-A step-by-step guide for beginners, 2nd
edition)
37. Leedy, P.D. and Ormrod, J.E. 2005. Practical Research: Planning and design 8th ed.
38. Megha, D. and Rajiv, B. (2013). A Methodology for Ranking of Causes of Delay for
39. Motaleb, O. and Kishk, M. (2010). An investigation into causes and effects of
40. Murali Sambasivan and Yau Wen Soon. (2007). Causes and effects of delays in
517-526.
41. Naoum, S.G. (2005) Dissertation research writing for construction students, 2nd
edition)
58
42. Niazai, A.G. and Gidado, K. (2012) Causes of project delay in the construction
industry in Afghanistan.
&_locator=url&_plusSign=%2B&_targetURL=http%253A%252F%252Fwww.ait.c1e
44. O'Leary, Z. (2004) The essential guide to doing research, London. Sage Publications
47. Ren, Z., Atout, M. and Jones, J. (2008). Root Causes Of Construction Project Delays
48. Shuttleworth Martyn, (2008) Descriptive Research design. Retrieved Feb 12, 2015
49. Shree, S. (2007, September 20). Equipment rentals hit construction industry. Live
hit-construc.html
50. Thomas, P.I. (1991). The Contractor’s Field Guide. New Jersey: Prentice Hall.
52. Ubaid , A . G . ( 1991 ) Factors affecting contractor performance . Master thesis, CEM
53. Walliman, N. (2005) Your research project. (2nd edition), London: sage Publications
59
54. Wibowo, M.A. 2009. The Contribution of the Construction Industry to the Economy of
24 August 2011].
55. Wortham Gene, (2014), Construction delays and best practices, Idaho Transportation
Department
56. Zagorsky, J.L. (2007). Do you have to be smart to be rich? The impact of IQ on
60
APPENDICES
Appendix A………………………………………………………………………………….. 47
Appendix B………………………………………………………………………………….. 56
61
APPENDIX A: QUESTIONNAIRE
Please fill in the blanks and tick [√] in the options as provided
1. Type of organisation
Contractor Client Consultant Other
Specify (Other)………………..……………………………………….……………………
3. If YES, in which category of the above construction board does the company fall in?
A B C Other
Housing
Schemes Other
Specify (Other)……………………………………………………………………………….…
62
SECTION B: CAUSES OF CONSTRUCTION DELAYS
1. Has the company ever experienced construction delays in any one of the past projects?
Yes No
2. If YES to Question 1
Which construction part was responsible for the delays?
Other factors
a. What were the main causes of construction delays which you experienced?
1………………………………………………………………………………………………….
2……….…………………………………………………….……………………………………..
3……………………………………………………………………………………………………..
4……………………………………………………………………………………………………
5……………………………………………………………………………………………………
3. If NO to Question 1
a) What did the project parties do so as to avoid construction delays?
1…………………………………………………………………………………………………..
2…………………………………………………………………………………………………..
3……………………………………………………………………………………………………
4……………………………………………………………………………………………………
5……………………………………………………………………………………………………
63
4. The following is a table showing some common causes of construction delays. Please rate the
severity of each of the causes of construction delays in the Zimbabwean construction industry by
putting [√ ] in the empty box on a scale of 1 to 5
1 2 3 4 5
Contractors‟ Financial Difficulties
Project complexity
International involvement
Contractual relationship
Coordination Problems
Contractors' incapability
Labour shortage
Language barrier
64
SECTION C: EFFECTS OF CONSTRUCTION DELAYS
2. If YES which of the following project parties is worst affected with the occurrence of
construction delays?
Client Contractor Consultant
All project
parties None
2……………………………………………………………………………………………………
3…………………………………………………………………………………………………..
4…………………………………………………………………………………………………..
5…………………………………………………………………………………………………..
65
4. Below are some of the effects of construction delays in the construction delays. Please
rate the severity of each of the effects of construction delays in the Zimbabwean
construction industry by putting [√ ] in the empty box on a scale of 1 to 5
(1=Not severe; 2=Slightly Severe; 3=Severe; 4=Very Severe; 5=Extremely Severe).
1 2 3 4 5
Time Overrun
Rescheduling
Cost Overrun
Bad contractual relationship
Late Payment
Disputes
Arbitration
Litigation
Affected Company Reputation
Lost Productivity and Efficiency
Project suspension
2……………………………………………………………………………………………………
3……………………………………………………………………………………………………
4……………………………………………………………………………………………………
5…………………………………………………………………………………………………….
66
2. Below are some of the strategies to minimise the occurrence of construction delays in the
construction industry. If each of these is implemented, please tick against the rating; how
effective are these strategic measures in enhancing project success in terms of time.
[1] [2] [3] [4] [5]
moderate
less effective effective effective most effective extremely effective
STRATEGIES RATING
1 2 3 4 5
Honouring project finance
Acceleration of site activities
Reinforcement of liquidated damages clauses
Proper pre-construction planning
Developing appropriate communication system
Management during construction.
Contingency allowance
Motivation of staff.
Minimize variations
SECTION E: RECCOMMENDATIONS
1. What are your recommendations so as to harness this issue of construction delays and
enhance successful project delivery in terms of time?
1……………………………………………………………………………………
2……………………………………………………………………………………
3……………………………………………………………………………………
4……………………………………………………………………………………
5…………………………………………………………………………………….
67
APPENDIX B: INTERVIEW QUESTIONS
Other effects
What strategic measures did you take in order to minimise the effects of these
delays?
68