In class assessment-Primavera( Schedule)

Task Name Duration Start Finish Predecessors Resource Names

Commercial Construction 344 days 2/22/2021 8:00 6/16/2022 17:00


WBS-1 General Conditions 17 days 2/22/2021 8:00 3/16/2021 17:00
Receive notice to proceed and sign contract 3 days 2/22/2021 8:00 2/24/2021 17:00 G.C. General Management
G.C. Project Management,G.C. General
Submit bond and insurance documents 2 days 2/25/2021 8:00 2/26/2021 17:00 2
Management[0.25]
Prepare and submit project schedule 2 days 3/1/2021 8:00 3/2/2021 17:00 3 G.C. Project Management[0.25],G.C. Scheduler
G.C. General Management[0.1],G.C. Project
Prepare and submit schedule of values 2 days 3/3/2021 8:00 3/4/2021 17:00 4
Management
Obtain building permits 4 days 2/25/2021 8:00 3/2/2021 17:00 2 G.C. Project Management[0.5],G.C. Procurement[0.5]

Submit preliminary shop drawings 2 wks 3/3/2021 8:00 3/16/2021 17:00 6 G.C. Project Management[0.5],G.C. Procurement[0.5]
Submit monthly requests for payment 1 day 2/25/2021 8:00 2/25/2021 17:00 2
WBS-2 Long Lead Procurement 70 days 2/26/2021 8:00 6/3/2021 17:00
Submit shop drawings and order long lead items - steel 2 wks 2/26/2021 8:00 3/11/2021 17:00 8 Steel Erection Contractor Management
Submit shop drawings and order long lead items - roofing 2 wks 3/17/2021 8:00 3/30/2021 17:00 7 Roofing Contractor Management
Submit shop drawings and order long lead items - elevator 2 wks 3/17/2021 8:00 3/30/2021 17:00 7 Elevator Contractor Management
Submit shop drawings and order long lead items - plumbing 2 wks 3/17/2021 8:00 3/30/2021 17:00 7 Plumbing Contractor Management
Submit shop drawings and order long lead items - electric 2 wks 3/17/2021 8:00 3/30/2021 17:00 7 Electric Contractor Management
Submit shop drawings and order long lead items - HVAC 2 wks 3/17/2021 8:00 3/30/2021 17:00 7 HVAC Contractor Management
Steel Erection Contractor Management[0.5],Steel
Detail, fabricate and deliver steel 12 wks 3/12/2021 8:00 6/3/2021 17:00 10
Erection Contractor[0.5]
WBS-3 Mobilize on Site 10 days 2/25/2021 8:00 3/10/2021 17:00
Install temporary power 2 days 2/25/2021 8:00 2/26/2021 17:00 2 Electric Contractor
Install temporary water service 2 days 2/25/2021 8:00 2/26/2021 17:00 2 Plumbing Contractor
Set up site office 3 days 3/1/2021 8:00 3/3/2021 17:00 18,19 G.C. Superintendent,G.C. Labor Crew[0.1]
Set line and grade benchmarks 3 days 3/4/2021 8:00 3/8/2021 17:00 20 G.C. Survey Crew
Prepare site - lay down yard and temporary fencing 2 days 3/9/2021 8:00 3/10/2021 17:00 21 Site Grading Contractor,G.C. Labor Crew[0.1]
WBS-4 Site Grading and Utilities 35 days 3/11/2021 8:00 4/28/2021 17:00
Clear and grub site 3 days 3/11/2021 8:00 3/15/2021 17:00 20,22 Site Grading Contractor
Stone site access and temporary parking area 2 days 3/16/2021 8:00 3/17/2021 17:00 24,22 Site Grading Contractor
Rough grade site (cut and fill) 1 wk 3/18/2021 8:00 3/24/2021 17:00 25 Site Grading Contractor
Install storm drainage 2 wks 3/25/2021 8:00 4/7/2021 17:00 26 Site Grading Contractor
Install exterior fire line and building fire riser 2 wks 3/25/2021 8:00 4/7/2021 17:00 26 Plumbing Contractor
Perform final site grading 2 wks 4/8/2021 8:00 4/21/2021 17:00 27FF+1 day,28 Site Grading Contractor
Erect building batter boards and layout building 1 wk 4/22/2021 8:00 4/28/2021 17:00 29 G.C. Survey Crew
WBS-5 Foundations 33 days 4/29/2021 8:00 6/14/2021 17:00
Excavate foundations 2 wks 4/29/2021 8:00 5/12/2021 17:00 30 Site Grading Contractor[0.5]
Excavate elevator pit 2 days 4/29/2021 8:00 4/30/2021 17:00 30 Site Grading Contractor
Form column piers and spread foundations 4 days 5/13/2021 8:00 5/18/2021 17:00 32 G.C. Rough Carpenter Crew
Rough-in electric and plumbing in elevator 4 days 5/3/2021 8:00 5/6/2021 17:00 33 Plumbing Contractor,Electric Contractor
Form elevator pit walls 4 days 5/7/2021 8:00 5/12/2021 17:00 35 G.C. Rough Carpenter Crew
Set reinforcing and anchor bolts 4 days 5/19/2021 8:00 5/24/2021 17:00 34 G.C. Rough Carpenter Crew
Pour column piers and foundations 5 days 5/25/2021 8:00 5/31/2021 17:00 37 G.C. Concrete Crew
Pour concrete elevator walls 1 day 5/13/2021 8:00 5/13/2021 17:00 36 G.C. Concrete Crew
Cure elevator wall concrete 7 days 5/14/2021 8:00 5/24/2021 17:00 39 G.C. Labor Crew[0.1]
Cure piers and foundations 7 days 6/1/2021 8:00 6/9/2021 17:00 38 G.C. Labor Crew[0.1]
Strip wall forms 1 day 5/25/2021 8:00 5/25/2021 17:00 40 G.C. Labor Crew[0.1]
Strip column piers and foundation forms 3 days 6/10/2021 8:00 6/14/2021 17:00 41 G.C. Labor Crew
Install pneumatic tube in elevator pit 3 days 5/26/2021 8:00 5/28/2021 17:00 42 Elevator Contractor
Prepare and pour concrete floor in elevator pit 1 day 5/31/2021 8:00 5/31/2021 17:00 44 G.C. Concrete Crew
WBS-6 Steel Erection 45 days 6/15/2021 8:00 8/16/2021 17:00
Erect steel columns, beams and joist - 1st and 2nd floors 2 wks 6/15/2021 8:00 6/28/2021 17:00 43,16 Steel Erection Contractor
Erect steel columns, beams and joist - 3rd floor and roof 2 wks 6/29/2021 8:00 7/12/2021 17:00 47 Steel Erection Contractor
Install miscellaneous iron and bracing - 1st and 2nd floors 2 wks 6/29/2021 8:00 7/12/2021 17:00 47 Steel Erection Contractor[0.75]
Install miscellaneous iron and bracing - 3rd floor and roof 2 wks 7/13/2021 8:00 7/26/2021 17:00 48 Steel Erection Contractor[0.75]
Install stairs and miscellaneous iron railing 2 wks 7/27/2021 8:00 8/9/2021 17:00 50 Steel Erection Contractor[0.5]
Touch-up paint on steel 1 wk 8/10/2021 8:00 8/16/2021 17:00 51 Steel Erection Contractor[0.2]
WBS-7 Form and Pour Concrete - Floors and Roof 85 days 6/29/2021 8:00 10/25/2021 17:00
Form 2nd floor including all floor openings 5 days 8/17/2021 8:00 8/23/2021 17:00 52,13,14,15,47 G.C. Rough Carpenter Crew,G.C. Labor Crew[0.2]
Install rebar and in-floor utilities (including mechanical, electrical, G.C. Labor Crew[0.33],Plumbing
5 days 6/29/2021 8:00 7/5/2021 17:00 47
plumbing) Contractor[0.33],Electric Contractor[0.33]
Pour 2nd floor slab 4 days 8/24/2021 8:00 8/27/2021 17:00 55,54 G.C. Concrete Crew
Cure 2nd floor slab 7 days 8/30/2021 8:00 9/7/2021 17:00 56 G.C. Labor Crew[0.1]
Strip forms from 2nd floor slab 2 days 9/8/2021 8:00 9/9/2021 17:00 57 G.C. Labor Crew
Form 3rd floor including all floor openings 5 days 9/8/2021 8:00 9/14/2021 17:00 57 G.C. Rough Carpenter Crew[0.5],G.C. Labor Crew[0.2]
Install rebar and in-floor utilities (including mechanical, electrical, G.C. Labor Crew[0.33],Plumbing
5 days 9/8/2021 8:00 9/14/2021 17:00 57
plumbing) Contractor[0.33],Electric Contractor[0.33]
Pour 3rd floor slab 4 days 9/15/2021 8:00 9/20/2021 17:00 60,59 G.C. Concrete Crew
Cure 3rd floor slab 7 days 9/21/2021 8:00 9/29/2021 17:00 61 G.C. Labor Crew[0.1]
Strip forms from 3rd floor slab 2 days 9/30/2021 8:00 10/1/2021 17:00 62 G.C. Labor Crew
Form roof slab including all floor openings 5 days 9/30/2021 8:00 10/6/2021 17:00 62 G.C. Rough Carpenter Crew,G.C. Labor Crew[0.2]
Install rebar and in-floor utilities (including mechanical, electrical, G.C. Labor Crew[0.33],Plumbing
5 days 9/30/2021 8:00 10/6/2021 17:00 62
plumbing) Contractor[0.33],Electric Contractor[0.33]
Pour roof slab 4 days 10/7/2021 8:00 10/12/2021 17:00 65,64 G.C. Concrete Crew
Cure roof slab 7 days 10/13/2021 8:00 10/21/2021 17:00 66 G.C. Labor Crew[0.1]
Strip forms from roof slab 2 days 10/22/2021 8:00 10/25/2021 17:00 67 G.C. Labor Crew
Form 1st floor 4 days 9/10/2021 8:00 9/15/2021 17:00 58 G.C. Rough Carpenter Crew
Install electrical underground 1 wk 9/10/2021 8:00 9/16/2021 17:00 58 Electric Contractor
Install plumbing underground 1 wk 9/10/2021 8:00 9/16/2021 17:00 58 Plumbing Contractor
G.C. Labor Crew[0.33],Plumbing
Install rebar and in-floor utilities 4 days 9/10/2021 8:00 9/15/2021 17:00 58
Contractor[0.33],Electric Contractor[0.33]
Pour 1st floor slab 4 days 9/17/2021 8:00 9/22/2021 17:00 69,72,70,71 G.C. Concrete Crew
Cure 1st floor slab 7 days 9/23/2021 8:00 10/1/2021 17:00 73 G.C. Labor Crew[0.1]
Strip forms from 1st floor slab 2 days 10/4/2021 8:00 10/5/2021 17:00 74 G.C. Labor Crew
WBS-8 Carpentry Work 15 days 10/26/2021 8:00 11/15/2021 17:00
Install exterior sheathing and metal studs 3 wks 10/26/2021 8:00 11/15/2021 17:00 63,68 Drywall Contractor
WBS-9 Masonry Work 110 days 7/27/2021 8:00 12/27/2021 17:00
Rough-in plumbing at toilets and masonry walls 4 wks 10/6/2021 8:00 11/2/2021 17:00 75,13 Plumbing Contractor
Lay masonry at core, mechanical, and toilets 4 wks 7/27/2021 8:00 8/23/2021 17:00 49,50 Masonry Contractor
Install exterior masonry work 5 wks 11/16/2021 8:00 12/20/2021 17:00 77 Masonry Contractor
Install roof drains 2 days 12/21/2021 8:00 12/22/2021 17:00 81 Roofing Contractor
Install tile in toilet rooms 2 wks 11/3/2021 8:00 11/16/2021 17:00 79 Tile Contractor
Clean masonry 1 wk 12/21/2021 8:00 12/27/2021 17:00 81 Masonry Contractor[0.5]
Clean toilet room tile 1 wk 11/17/2021 8:00 11/23/2021 17:00 83 Tile Contractor[0.5]
WBS-10 Roofing 31 days 12/21/2021 8:00 2/1/2022 17:00
Install flashing at parapet walls 4 days 12/21/2021 8:00 12/24/2021 17:00 81 Roofing Contractor
Pour lightweight concrete roof fill 2 days 12/27/2021 8:00 12/28/2021 17:00 11,82,87 Roofing Contractor
Install seamless roofing material 5 days 1/5/2022 8:00 1/11/2022 17:00 88FS+5 days Roofing Contractor
Spread stone ballast on seamless roof 5 days 1/12/2022 8:00 1/18/2022 17:00 89 Roofing Contractor
Set rooftop equipment 2 wks 1/19/2022 8:00 2/1/2022 17:00 90 HVAC Contractor
WBS-11 Window wall and store front closures 60 days 12/21/2021 8:00 3/14/2022 17:00
Install window wall aluminum and glass 5 wks 12/21/2021 8:00 1/24/2022 17:00 81 Window Contractor
Install interior stud walls and drywall 5 wks 1/25/2022 8:00 2/28/2022 17:00 93 Drywall Contractor
Install interior doors and hardware 2 wks 3/1/2022 8:00 3/14/2022 17:00 94 G.C. Finish Carpenter Crew
Install store front doors and hardware 3 wks 12/21/2021 8:00 1/10/2022 17:00 81 Window Contractor
WBS-12 Building Finishes 80 days 1/25/2022 8:00 5/16/2022 17:00
Install millwork and wood trim 3 wks 3/1/2022 8:00 3/21/2022 17:00 96,94 G.C. Finish Carpenter Crew
Paint walls and woodwork 4 wks 3/22/2022 8:00 4/18/2022 17:00 98,95 Painting Contractor
Install conduit at ceiling plenum space 3 wks 1/25/2022 8:00 2/14/2022 17:00 93 Electric Contractor
Install duct in ceiling plenum space 3 wks 3/1/2022 8:00 3/21/2022 17:00 94,100 HVAC Contractor
Install ceiling grid 2 wks 3/22/2022 8:00 4/4/2022 17:00 94,101 Drywall Contractor
Install ceiling tile 2 wks 4/5/2022 8:00 4/18/2022 17:00 102 Drywall Contractor
Hang wallpaper 2 wks 4/5/2022 8:00 4/18/2022 17:00 102 Painting Contractor
Install building carpet 4 wks 4/19/2022 8:00 5/16/2022 17:00 99 Carpet Contractor
Install hardware and accessories 3 wks 4/19/2022 8:00 5/9/2022 17:00 99 G.C. Finish Carpenter Crew
Complete interior and exterior sod and plantings 2 wks 4/19/2022 8:00 5/2/2022 17:00 99 Landscape Contractor
Pave, curb, and stripe parking lot 2 wks 5/3/2022 8:00 5/16/2022 17:00 107 Paving Contractor
WBS-13 Elevators 40 days 8/24/2021 8:00 10/18/2021 17:00
Set elevator equipment in shafts 4 wks 8/24/2021 8:00 9/20/2021 17:00 80,45,12 Elevator Contractor
Set equipment in mechanical room 2 wks 9/21/2021 8:00 10/4/2021 17:00 110 Elevator Contractor
Test and align doors and equipment 2 wks 10/5/2021 8:00 10/18/2021 17:00 111 Elevator Contractor
WBS-14 Plumbing 90 days 12/28/2021 8:00 5/2/2022 17:00
Rough-in plumbing in drywall walls 4 wks 1/25/2022 8:00 2/21/2022 17:00 93 Plumbing Contractor
Tie-in fire line riser and set valves 2 wks 12/28/2021 8:00 1/10/2022 17:00 84 Plumbing Contractor
Set plumbing fixtures and trim 3 wks 2/22/2022 8:00 3/14/2022 17:00 85,114,79 Plumbing Contractor
Flush, test, and clean piping and fixtures 2 wks 4/19/2022 8:00 5/2/2022 17:00 99,115,116 Plumbing Contractor
WBS-15 Electrical 139 days 10/6/2021 8:00 4/18/2022 17:00
Rough-in electrical in masonry walls 4 wks 10/6/2021 8:00 11/2/2021 17:00 75,14 Electric Contractor
Rough-in electrical in drywall walls 4 wks 1/25/2022 8:00 2/21/2022 17:00 93 Electric Contractor
Pull wire in conduit and set area transformers 3 wks 2/15/2022 8:00 3/7/2022 17:00 119,100 Electric Contractor
Install and terminate electrical devices 3 wks 3/8/2022 8:00 3/28/2022 17:00 121,120 Electric Contractor
Make electrical terminations for HVAC equipment 2 days 3/8/2022 8:00 3/9/2022 17:00 121,91 Electric Contractor
Install light fixtures - test and clean 2 wks 4/5/2022 8:00 4/18/2022 17:00 102,122 Electric Contractor
WBS-16 Heating and Ventilating - AC 180 days 8/24/2021 8:00 5/2/2022 17:00
Set equipment in mechanical room 2 wks 8/24/2021 8:00 9/6/2021 17:00 80,15 HVAC Contractor
Rough-in mechanical in masonry walls 4 wks 10/6/2021 8:00 11/2/2021 17:00 75 HVAC Contractor
Rough-in mechanical in drywall walls 2 wks 1/25/2022 8:00 2/7/2022 17:00 93 HVAC Contractor
Install duct in building chase 3 wks 1/25/2022 8:00 2/14/2022 17:00 126,127,93 HVAC Contractor
Set HVAC trim and test and balance system 4 wks 4/5/2022 8:00 5/2/2022 17:00 102,129,123 HVAC Contractor
WBS-17 Final Clean-up and Occupancy 60 days 3/1/2022 8:00 5/23/2022 17:00
Install hard tile flooring in common areas 1 wk 3/1/2022 8:00 3/7/2022 17:00 94 Tile Contractor
Clean hard tile floors 4 days 3/8/2022 8:00 3/11/2022 17:00 132 Tile Contractor[0.5]
105,104,106,107,117,
Remove debris from building and do final clean-up 4 days 5/17/2022 8:00 5/20/2022 17:00 G.C. Labor Crew
124,103,133
Substantial completion date 1 day 5/23/2022 8:00 5/23/2022 17:00 134 G.C. Superintendent
WBS-18 Complete Final Inspections 6 days 5/23/2022 8:00 5/30/2022 17:00
Complete elevator inspection and certification 3 days 5/23/2022 8:00 5/25/2022 17:00 134,112 Elevator Contractor
Perform architect's inspection 1 day 5/26/2022 8:00 5/26/2022 17:00 134,108,137 G.C. Superintendent[0.5],G.C. Project Management[0.5]

Perform local building agency inspection 1 day 5/27/2022 8:00 5/27/2022 17:00 138 G.C. Project Management[0.5],G.C. Superintendent[0.5]

Perform Fire Marshal's inspection 1 day 5/30/2022 8:00 5/30/2022 17:00 139 G.C. Superintendent[0.5],G.C. Project Management[0.5]
G.C. Superintendent[0.11],G.C. Labor
Crew[0.11],Plumbing Contractor[0.11],Electric
Complete punch list items from all inspections 2 wks 5/31/2022 8:00 6/13/2022 17:00 140 Contractor[0.11],HVAC Contractor[0.11],Drywall
Contractor[0.11],Carpet Contractor[0.11],Paving
Contractor[0.11],Painting Contractor[0.11]
Obtain certificate of occupancy 2 days 6/14/2022 8:00 6/15/2022 17:00 141 G.C. Project Management
Issue final completion documents including warranties 1 day 6/14/2022 8:00 6/14/2022 17:00 141 G.C. Project Management
G.C. Project Management[0.33],G.C.
Issue final request for payment 1 day 6/16/2022 8:00 6/16/2022 17:00 142,143
Accounting[0.33],G.C. General Management[0.33]