Table of Contents
1. Introduction..............................................................................................................................2
2. Literature review......................................................................................................................2
3. Research questions...................................................................................................................6
4. Research aim and scope...........................................................................................................6
5. Research methodology.............................................................................................................6
6. Research need and impact of research.....................................................................................8
7. References................................................................................................................................9
1. Introduction
Most countries have accessibility through rivers and canals to enormous quantities of water.
Electricity may be created without damaging the environment with this renewable energy source.
Due to the growing need for power, the growth prospects of hydroelectric power is vital to
evaluate. The growth of the energy mix and the implementation of measures to manage the
electricity market development might thus be planned through the utilization of sustainable
hydroelectric projects. Hydraulic power is the method used to generate electricity through rivers,
canals, or streams using the potential energy of water(Okot, 2013). Water delivered to a turbine
via a channel, which hits the turbine blades and rotates the shaft. The spinning shaft is coupled to
a generator that turns a shaft's mechanical energy into electricity. Hydropower projects are
usually classified as small and big hydraulic power in two portions. Small hydropower outputs
are defined with the top limit ranging from 5 to 50 MW. This term differs across countries. The
big component in the company's growth is the low cost and ample availability of electricity. The
electrical power provided from the main power plants cannot be accessed by every user.
2. Literature review
Energy is nowadays one of our world's most crucial factors. However, certain resources to get
effective energy performances cannot be achieved because of costs, issues, pollution from these
resources, and so on. It is therefore vital to concentrate the study on discovering alternatives to
generate greener, cheaper and more efficient energy. A few new objectives were suggested in the
European Union in 2008 to tackle climate change and to enhance the energy efficiency and low
CO2 dependence of the European market(Mishra, Singal, & Khatod, 2011). By the end of 2021,
it has determined that 20% of the total energy consumption must come from renewables. In
addition, 20% of the emissions of greenhouse gases must be decreased by the same deadline as
in 1990. Finally, by enhancing the efficiency of the elements utilized, 20 percent of energy usage
must be lowered. Energy is directly linked with development. The increased output of fossil fuel
energy makes a considerable contribution to local and worldwide environmental challenges. The
power industry has the challenge of rising demand for electricity and regulating emissions of
found. There are few power generating choices, such as solar, wind and minor hydropower
according to these parameters. Hydroelectricity projects can help to the development of a wide
Manfrida, & Fiaschi, 2021). Flowing water energy is the pure, renewable energy source.
Hydraulic power is one of the most ancient types of energy for the human race. Smaller
hydroelectricity is nowadays one of rural electricity's most useful sources and may increase
productivity. Numerous drinking water and irrigation systems projects can benefit from the
Figure 1. Effect of conventional unit cost electricity on short-cut model parameter (Raurell Font
cost-effective source of electricity as the best natural resources conceivable. The method used for
feeding water is delivered to the city by a pressurizing conduit, generally fitted with valves
lowering pressure from the reservoir to the treatment plant for dissipating the extra
energy(Mishra, Singal, & Khatod, 2013). If the hydropower plant is built in the water supply
systems to use extra energy, a turbine can replace this energy dissipation mechanism. Water is
drawn from the river in a typical modest hydroelectric system using a weir(Chavan et al., 2020).
The Weir is a man-made system constructed on the river that keeps the feed continuously
flowing. The water travels through a desilting tank where the water is appropriately slowed down
to clear suspended particles prior to falling into the turbine. Water is delivered to the foreshore
by a canal in medium or high-head constructions. Water usually comes straight from the turbine
in low-head setups.
Figure 2. Kyoto target for European member and CO2 emissions(Raurell Font & Reales Ferreres,
2010)
The technical efficiency of hydroelectric production facilities was evaluated(Barros & Peypoch,
2007), and the influence of increased competition and regulation was investigated. The study
heterogeneous factors in cost function, this approach may integrate many inputs and outputs into
evaluating relative efficiencies. The contemporary technology and current situation of tiny
hydroelectricity was researched(Paish, 2002). Hydropower has been determined to be one of the
most efficient energy solutions on a small scale. The present situation of hydropower has been
examined, i.e. how much is accessible technically and how much is economically feasible and
how much yet to be used. Although the initial capital cost for setting up a hydro plant may be
significant, it cannot be overlooked for its long-term efficiency and reduced environmental
consequences.
Figure 3. Hydropower energy status in Australia(Bahadori, Zahedi, & Zendehboudi, 2013)
The pico hydro system was explored(A. Williams & Simpson, 2009) and is a cost efficient
solution for rural distant grid electrification. Pico hydro project, cost for generating is less than
tiny generators of petrol or diesel, wind turbines or PV systems(Arkhypova & Mandryk). It was
also addressed how to pick components from the schemes that can cut costs and boost the
effectiveness and stability of the system in order to achieve cheap installation costs per unit
power production. (Dursun & Gokcol, 2011) examined the current state of Turkish hydropower
and quality of life. A further study on the growth of the Turkey hydroelectric river basin was
carried out(Akpınar, Kömürcü, & Kankal, 2011). The author also gave a comparative of Turkey's
A computer tool for the preliminary evaluation of hydropower systems of modest size has been
created (Dursun & Gokcol, 2011). The application gives the user adequate operational and
economical information to justify more investments. It also has access to accurate non-financial
characteristics such as the environmental and economic effect at a local/national level. The
special technical economic restrictions are also taken into consideration in this Program. The
novel simulation program for hydropower plants with a riot system was created(Zafra, Vázquez,
& Garrido Jurado, 2009) and a component library design was offered for hydropower plants. The
hydroelectric plant has a broad model with a river system running. OOM (Object-Oriented
Modeling), like Ecosimpro software, was used for the hydropower plant library section. The
results from a simulator show that the designed tool and the real data are in strong
agreement(Gil-González, Montoya, & Garces, 2020). The simulator was also used to simulate
the condition of the plant in uncommon or unforeseen scenarios like a major river flood.
It is reported that the investment in small hydro-electric power plants is determined by analyses
Saad, 2019). This means analyzing that numerous specialists together act and use considerable
time and money. A model OPAH was given to resolve these challenges. For optimizing the
Remeňáková, 2018). OPAH models employ numeric simulation models with instable flow under
pressures for hydraulic circuit analysis. This is used to examine project risks and market
variability through an economical and financial simulation model(Malhan & Mittal, 2021). The
multi-stage mixed integer linear stochastic programming shown(Uddin et al., 2019). The
program is used to build a short-term output plan for an uncertainly pricing hydropower facility.
This is driven by prior obligations from the present production. This made the scheduling of
short production a question of distribution between the plant's reservoir(Singh & Singal, 2017).
Water should be distributed across reservoirs in order to balance present profit and predicted
future gains.
3. Research questions
1. What is the procedure of development of micro hydro plan project?
The purpose of this question is to study the participants and describe how a micro-hydro
The aim of this question is to assess the efficiency of the micro hydro plant in providing the
The aim of the research question is to evaluate public involvement at village level and
suppliers with low cost possibilities. Firstly, a site survey is conducted and a research is
undertaken on the turbine and equipment. This chapter is aimed at giving an idea of how much
energy may be generated and what type of equipment should be placed. Secondly, to identify the
community efficiency of the plant and, thirdly, to evaluate the role of public participation in the
effectiveness of the program. This project will not be involved in the analysis of the
5. Research methodology
Preliminary research methodology will be implemented in this research(C. Williams, 2007). Part
one should clarify an estimate of the energy production that can be achieved with a particular
turbine and generator. Towards the same processes as the theoretical, the Turbine and generator
parameters. Two characteristics, the flow rate of the stream and the water head, should be stated
in the property survey(Zhou et al., 2019). In view of the broad use of hydroelectric resources,
study aims to highlight, in accordance with the principles of environment regard and
compatibility with settings of elevated environmental values, the approach established in order to
use this resource. In compliance with all applicable regulations, the research went beyond the
criteria, since it asked how tiny plants with a decreased environmental effect might be
implemented.
The new technological and political-governmental options, which in fact show the territorial
similarity among the demand for energy source and the conversion and use, allow the use of
renewable power off-grid energy to be generated, which is by their very character broadly
available and not transporting. Indeed, the global grid is likely to never reach many hilly or
mountain areas that do have adequate hydro sources to support the local people's fundamental
needs in home and cottage industries. The technique developed consisted of two primary phases:
a complete understanding phase, marked by the conduct of context analysis and an overview
phase, characterized by carrying out a series of global suitability controls which led to the
eventual construction of the viability study(Sachdev, Akella, & Kumar, 2015). The aim of the
first stage was to analyze the region of interest and its characteristics, to select the optimal
placement in the context of the planned water power plant. The evaluation research was carried
out both to estimate electricity output and the compliance with existing limitations of the
hydropower project.
Once all the general factors were identified, an analysis of whether the plant was eligible under
urban planning rules was carried out. Then, among the many alternative solutions, the
investigation established a range of indicators: environmental, economic, technological and
esthetic(Okpanefe & Owolabi, 2001). This approach has led to the development of a degree of
"global compatibility," assessed with a score, which is the synthesis of all preliminary analyzes
and assessments. This compatibility is evaluated by a number of indications, the first being the
preliminary indication. The legal and sustainability compatibility indication is indeed more of a
priority than the others: if it is not met, it cannot execute the design solution in question. After
then, the hydraulic electricity was left aside with the introduction of a steam engine driven by
carbon fuels because compared to the same period one, other challenges were involved, such as
the necessity to locate plants away from populated areas and the road network(Jaber, 2012).
Some of the economic features of this form of energy generation have been punished.
generates power in these facilities (renewable energy). The first argument is that no fuel is
needed and then the price of the plant-generated power is not dependent on international market
pricing. The government also has to import the petroleum so it may save a lot of money. The
water in the dam may be gathered by day. When the network covers a summit hydroelectric
plants can operate. The hydroelectric power stations may operate less than nuclear and thermal
power stations so that the network generally uses nuclear and thermal power stations.
7. References
Akpınar, A., Kömürcü, M. İ., & Kankal, M. (2011). Development of hydropower energy in Turkey: the case
of Coruh river basin. Renewable and Sustainable Energy Reviews, 15(2), 1201-1209.
Arkhypova, L., & Mandryk, O. TECHNICAL COMPONENTS OF ECOLOGICALLY SAFE INSTALLATION OF
SMALL HYDRO POWER PLANTS IN THE UKRAINIAN CARPATHIANS. 6FLHQWLILF 7HFKQLFDO
&RQIHUHQFH, 2300(4100), 125.
Bahadori, A., Zahedi, G., & Zendehboudi, S. (2013). An overview of Australia's hydropower energy:
Status and future prospects. Renewable and Sustainable Energy Reviews, 20, 565-569.
Barros, C. P., & Peypoch, N. (2007). The determinants of cost efficiency of hydroelectric generating
plants: a random frontier approach. Energy Policy, 35(9), 4463-4470.
Chavan, P., Shinde, S., Patil, V., Yadav, S. J., Sayyed, N. J., Mahajan, D. V., & Kharde, R. S. (2020). Ultra
Small Water Power Generation with Help of Canal. International Journal of Research in
Engineering, Science and Management, 3(2), 88-90.
Dursun, B., & Gokcol, C. (2011). The role of hydroelectric power and contribution of small hydropower
plants for sustainable development in Turkey. Renewable Energy, 36(4), 1227-1235.
Gil-González, W., Montoya, O. D., & Garces, A. (2020). Modeling and control of a small hydro-power
plant for a DC microgrid. Electric Power Systems Research, 180, 106104.
Hatata, A., El-Saadawi, M., & Saad, S. (2019). A feasibility study of small hydro power for selected
locations in Egypt. Energy Strategy Reviews, 24, 300-313.
Jaber, J. O. (2012). Prospects and Challenges of Small Hydropower Development in Jordan. Jordan
Journal of Mechanical & Industrial Engineering, 6(2).
Malhan, P., & Mittal, M. (2021). Evaluation of different statistical techniques for developing cost
correlations of micro hydro power plants. Sustainable Energy Technologies and Assessments, 43,
100904.
Mishra, S., Singal, S., & Khatod, D. (2011). Optimal installation of small hydropower plant—A review.
Renewable and Sustainable Energy Reviews, 15(8), 3862-3869.
Mishra, S., Singal, S., & Khatod, D. (2013). Cost analysis for electromechanical equipment in small
hydropower projects. International journal of green energy, 10(8), 835-847.
Okot, D. K. (2013). Review of small hydropower technology. Renewable and Sustainable Energy Reviews,
26, 515-520.
Okpanefe, P., & Owolabi, S. (2001). Small hydropower in Nigeria. Paper presented at the 2001 TCDC
Training Workshop on SHP.
Paish, O. (2002). Small hydro power: technology and current status. Renewable and Sustainable Energy
Reviews, 6(6), 537-556.
Raurell Font, A., & Reales Ferreres, X. (2010). Installation of a new hydropower plant: in Ockelbo
Sweden. In.
Sachdev, H. S., Akella, A. K., & Kumar, N. (2015). Analysis and evaluation of small hydropower plants: A
bibliographical survey. Renewable and Sustainable Energy Reviews, 51, 1013-1022.
Shamoushaki, M., Niknam, P. H., Talluri, L., Manfrida, G., & Fiaschi, D. (2021). Development of Cost
Correlations for the Economic Assessment of Power Plant Equipment. Energies, 14(9), 2665.
Singh, V. K., & Singal, S. (2017). Operation of hydro power plants-a review. Renewable and Sustainable
Energy Reviews, 69, 610-619.
Uddin, W., Zeb, K., Haider, A., Khan, B., ul Islam, S., Ishfaq, M., . . . Kim, H. J. (2019). Current and future
prospects of small hydro power in Pakistan: A survey. Energy Strategy Reviews, 24, 166-177.
Williams, A., & Simpson, R. (2009). Pico hydro–Reducing technical risks for rural electrification.
Renewable Energy, 34(8), 1986-1991.
Williams, C. (2007). Research methods. Journal of Business & Economics Research (JBER), 5(3).
Zafra, Á., Vázquez, F., & Garrido Jurado, J. (2009). Object oriented modelling and simulation of
hydropower plants with run-of-river scheme: A new simulation tool.
Zeleňáková, M., Fijko, R., Diaconu, D. C., & Remeňáková, I. (2018). Environmental impact of small hydro
power plant—a case study. Environments, 5(1), 12.
Zhou, Y., Chang, L.-C., Uen, T.-S., Guo, S., Xu, C.-Y., & Chang, F.-J. (2019). Prospect for small-hydropower
installation settled upon optimal water allocation: An action to stimulate synergies of water-
food-energy nexus. Applied Energy, 238, 668-682.