Quantity Estimation for P354 Portal Beam

Unit price
No. Description Unit Quantity Amount (BDT) Reamarks
(BDT)
1 Cross Beam: Rebar Fixing Ton. 6891.32 50.914 350864.6537515
Cross Beam: Bench / Tower support, Screw jack, beam cross
2 Set 50921.05 1 50921.0515
road Installation
Cross Beam: Bench / Tower support, Screw jack, beam cross
3 Set 62236.83 1 62236.83475
road dismantle
4 Cross Beam: Formwork Installation sqm. 1244.74 295.6768 368041.479224
5 Cross Beam: Embed Item Installation Set 11315.79 1 11315.794
6 Cross Beam: Pouring Concrete cum. 1010.50 261.78 264528.69
7 Cross Beam: Dismantle Formwork sqm. 261.39 295.6768 77285.849964
8 Cross Beam: Curing Concrete sqm. 198.03 408.1363 80821.496909725
9 Seismic buffer & Bearing Base: Rebar fixing Ton. 6891.32 1.619 11157.04667525

10 Seismic buffer & Bearing Base: Formwork Installation sqm. 1471.05 11.7712 17316.0414168

11 Seismic buffer & Bearing Base: Pouring Concrete cum. 1018.42 2.88864 2941.85669256
12 Seismic buffer & Bearing Base: Dismantle Formwork sqm. 261.39 17.1 4469.704875
13 Seismic buffer & Bearing Base: Curing Concrete sqm. 198.03 18.0482 3574.00834115
Grand Total (BDT) 1,305,474.51
Quantity Estimation for P363 Portal Beam

Unit price
No. Description Unit Quantity Amount (BDT) Reamarks
(BDT)
1 Cross Beam: Rebar Fixing Ton. 6891.32 48.7808 336164.0904608
Cross Beam: Bench / Tower support, Screw jack, beam cross
2 road Installation Set 50921.05 1 50921.0515

3 Cross Beam: Formwork Installation sqm. 1244.74 193.87662 241326.46867035


Grand Total (BDT) 628,411.61

Quantity Estimation for P364 Portal Beam

Unit price
No. Description Unit Quantity Amount (BDT) Remarks
(BDT)
1 Cross Beam: Rebar Fixing Ton. 6891.32 47.586 327930.3416235
Cross Beam: Bench / Tower support, Screw jack, beam cross
2 Set 50921.05 1 25460.52575
road Installation

3 Cross Beam: Bench / Tower support, Screw jack, beam cross Set 62236.83 1 62236.83475
road dismantle
4 Cross Beam: Formwork Installation sqm. 1244.74 307.04 382185.7372
5 Cross Beam: Embed Item Installation Set 11315.79 1 11315.794
6 Cross Beam: Pouring Concrete cum. 1010.50 279.52 282454.96
7 Cross Beam: Dismantle Formwork sqm. 261.39 307.04 80256.0342
8 Cross Beam: Curing Concrete sqm. 198.03 415.03 82186.6270225
9 Seismic buffer & Bearing Base: Rebar fixing Ton. 6891.32 0.7905 5447.588262375
Grand Total (BDT) 1,259,474.44
Quantity Estimation for P365 Portal Beam

Unit price
No. Description Unit Quantity Amount (BDT) Remarks
(BDT)
1 Cross Beam: Rebar Fixing Ton. 6891.32 55.135 379952.91441625

2 Cross Beam: Bench / Tower support, Screw jack, beam cross Set 50921.05 1 50921.0515
road Installation

3 Cross Beam: Bench / Tower support, Screw jack, beam cross Set 62236.83 1 62236.83475
road dismantle
4 Cross Beam: Formwork Installation sqm. 1244.74 272.834 339608.075245
5 Cross Beam: Embed Item Installation Set 11315.79 1 11315.794
6 Cross Beam: Pouring Concrete cum. 1010.50 234.57 237032.985
7 Cross Beam: Dismantle Formwork sqm. 261.39 272.834 71315.0561325
8 Cross Beam: Curing Concrete sqm. 198.03 357.734 70840.5436505
9 Seismic buffer & Bearing Base: Rebar fixing Ton. 6891.32 1.56 10750.45881

10 Seismic buffer & Bearing Base: Formwork Installation sqm. 1471.05 11.075 16291.8953625

11 Seismic buffer & Bearing Base: Pouring Concrete cum. 1018.42 2.677 2726.31770175
12 Seismic buffer & Bearing Base: Dismantle Formwork sqm. 261.39 11.075 2894.85271875
13 Seismic buffer & Bearing Base: Curing Concrete sqm. 198.03 16.43 3253.5630725
Grand Total (BDT) 1,259,140.34
Quantity Estimation for P366 Portal Beam

Unit price
No. Description Unit Quantity Amount (BDT) Remarks
(BDT)
1 Cross Beam: Rebar Fixing Ton. 6891.32 59.269 408441.63026275
Cross Beam: Bench / Tower support, Screw jack, beam cross
2 road Installation Set 50921.05 1 50921.0515

Cross Beam: Bench / Tower support, Screw jack, beam cross


3 Set 62236.83 1 62236.83475
road dismantle
4 Cross Beam: Formwork Installation sqm. 1244.74 317.04 394633.1622
5 Cross Beam: Embed Item Installation Set 11315.79 1 11315.794
6 Cross Beam: Pouring Concrete cum. 1010.50 269.34 272168.07
7 Cross Beam: Dismantle Formwork sqm. 261.39 317.04 82869.8967
8 Cross Beam: Curing Concrete sqm. 198.03 411.24 81436.10943
9 Seismic buffer & Bearing Base: Rebar fixing Ton. 6891.32 1.215 8372.95349625
Grand Total (BDT) 1,372,395.50
Quantity Estimation for P367 Portal Beam

Unit price
No. Description Unit Quantity Amount (BDT) Remarks
(BDT)
1 Cross Beam: Rebar Fixing Ton. 6891.32 52.813 363951.26995675
Cross Beam: Bench / Tower support, Screw jack, beam cross
2 Set 50921.05 1 50921.0515
road Installation
Cross Beam: Bench / Tower support, Screw jack, beam cross
3 road dismantle Set 62236.83 1 62236.83475

4 Cross Beam: Formwork Installation sqm. 1244.74 257.53 320558.536025


5 Cross Beam: Embed Item Installation Set 11315.79 1 11315.794
6 Cross Beam: Pouring Concrete cum. 1010.50 223.32 225664.86
7 Cross Beam: Dismantle Formwork sqm. 261.39 257.53 67314.8009625
8 Cross Beam: Curing Concrete sqm. 198.03 347.68 68849.59276
9 Seismic buffer & Bearing Base: Rebar fixing Ton. 6891.32 1.168 8049.061468
Grand Total (BDT) 1,178,861.80

Quantity Estimation for P368 Portal Beam

Unit price
No. Description Unit Quantity Amount (BDT) Remarks
(BDT)
1 Cross Beam: Rebar Fixing Ton. 6891.32 52.549 362131.96154275
Cross Beam: Bench / Tower support, Screw jack, beam cross
2 road Installation Set 50921.05 1 50921.0515

3 Cross Beam: Formwork Installation sqm. 1244.74 255.78 318380.23665


4 Cross Beam: Embed Item Installation Set 11315.79 1 11315.794
5 Cross Beam: Pouring Concrete cum. 1010.50 222.123 224455.2915
6 Seismic buffer & Bearing Base: Rebar fixing Ton. 6891.32 1.168 8049.061468
Grand Total (BDT) 975,253.40

Quantity Estimation for P369 Portal Beam

Unit price
No. Description Unit (BDT) Quantity Amount (BDT) Remarks

1 Cross Beam: Rebar Fixing Ton. 6891.32 8.6 59265.34985


Cross Beam: Bench / Tower support, Screw jack, beam cross
2 Set 50921.05 1 50921.0515
road Installation

3 Cross Beam: Formwork Installation ( Pier head + Bottom ) sqm. 1244.74 122.9 152978.85325

Grand Total (BDT) 263,165.25

Total 8,242,176.86
Date : October 17, 2020
Ref: nsl/itd/mrt/invoice-Sub 6
Italian Thai Development Company Ltd.
Kind attn: Mr. Pornchai Boonmark
Dhaka MRT Development Project
Bangladesh

Subject : Bill for Sub-structure Works at CP - 03 & 04 and Two Cell Box Girders (Cast in situ) P364-P365

Dear Sir,

We are pleased to submit our invoice for Sub-Structure works at CP - 03 & 04 and Two Cell Box Girders P364-P365

Bill for Sub-structure Work:

SL No. Portal Beam Types of work executed Total Amount (BDT) Remarks

1 P 354 Cross Beam, Seismic Buffer & Bearing Base 1,305,474.51


Casting
2 P 363 Bench tower installation + Formwork 628,411.61
installation + Rebar work
3 P 364 Cross Beam, Seismic Buffer & Bearing Base 1,259,474.44
Casting
4 P 365 Cross Beam, Seismic Buffer & Bearing Base 1,259,140.34
Casting
5 P 366 Cross Beam casting, extra pier head,Seismic 1,372,395.50
Buffer & Bearing Base Rebar work
6 P 367 Cross Beam, Seismic Buffer & Bearing Base 1,178,861.80
Casting
7 P 368 Bench tower installation + Formwork 975,253.40
installation + Rebar work + Casting
8 P 369 Bench tower installation + Formwork (PH + 263,165.25
Bottom ) + Rebar work
Summary 8,242,176.86

Bill for Two Cell Box Girders:

SL No. Types of work executed Total Amount (BDT) Remarks

1 Scaffolding installation + Casting bottom slab + Formwork 2,010,498.95


of diaphragm ,web and wall + Installation of duct pipe

Grand Summary 10,252,675.81

Total Amount : BDT 10,252,675.81

Sincerely Yours,

BIMAL C. ROY
NEXTSPACES LTD
Total
Actual Total weight
Bar mark Size (mm) QTY(nos) Unit weight(kg/m) weight
length(m) (kg)
(ton)
6 40 20 10.72 9.86436498150432 2114.919852
8 40 20 3.721 9.86436498150432 734.10604192
9 40 20 6.321 9.86436498150432 1247.053021
10 40 10 4.8 9.86436498150432 473.48951911
12 20 190 6.946 2.46609124537608 3254.5992602
14 20 570 4.74 2.46609124537608 6662.8853268
18.56414
16 20 36 12 2.46609124537608 1065.351418
17 20 18 6.87 2.46609124537608 304.9568434
19 40 10 10 9.86436498150432 986.43649815
20 40 20 8.72 9.86436498150432 1720.3452528
Total weight 18564.143033
Two cell (Span P364-P365) Actual Quantity of work

Item Description Unit Unit price Quantity Amount (BDT) Remarks

Installation of Scaffolding and Support

Installation of Ring lock Scaffolding, Tower truss, Steel beam,


1 Adjust plate, Steel box, Support pipe, Lock set, Stair, Handrail
1.1 sqm. 311.18 710 220,941
and other materials follow method statement & Installation of
Square tube and Plywood for adjust Levelling H> 11.5 m.

Bottom Slab
2.1 Formwork Fabrication and Installation of Bottom Slab sqm. 876.97 934 819,093
2 2.2 Rebar Cutting, Bending & Fixing of Bottom Slab & Wall Ton. 7,434.47 50 371,724
2.3 Concrete pouring cum. 820.39 220 180,487
2.4 Curing Concrete sqm. 101.84 418 42,570
Diaphragm,Web and Wall
3 Fabrication and Installation of formwork and shoring/bracing
3.1 sqm. 905.26 325 294,211
materials for diaphragm,web and wall
4 Duct pipe/Duct profile Installation
4.1 Installation of Duct pipe m 135.79 600 81,474

Sub total of Two Cell Box Girders (Cast in situ) P364-P365 2,010,498.95