Total hari

NO Nama berkerja Gaji sehari Advance Balance gaji


1 Wan Driver 9 70 500 130
2 Shah Driver 20 70 500 900
3 Raju 23 60 500 880
4 Saravanan 20 60 500 700
5 Kumar 23 60 500 880
6 Mumtaz 16 60 500 460
7 Rahmat 22 60 500 820
8 Ramesh 25 60 500 1000
9 Rajen 26 60 500 1060
10 Kishor 4 60 240
11 Shagor 16 60 500 460
12 Ibrahim 4 60 240
13 Samsul 20 60 500 700

Total gaji 8470


Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
01/03/2021 8.30 Wan Driver New Street Lighting 266.8 - 266.0 (NB/SL)
Monday 8.30 Rajen General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 N4 Driver inspection & Audit Jabatan Bomba Tunnel 1(SB/FL)
8.30 Rahmat General workers inspection & Audit Jabatan Bomba Tunnel 1(SB/FL)
8.30 Samsul General workers inspection & Audit Jabatan Bomba Tunnel 1(SB/FL)
8.30 Raju General workers inspection & Audit Jabatan Bomba Tunnel 1(SB/FL)
8.30 N4 Driver inspection & Audit Jabatan Bomba Tunnel 2 (NB/FL)
8.30 Saravanan General workers inspection & Audit Jabatan Bomba Tunnel 2 (NB/FL)
8.30 Mumtaz General workers inspection & Audit Jabatan Bomba Tunnel 2 (NB/FL)
8.30 Shagor General workers inspection & Audit Jabatan Bomba Tunnel 2 (NB/FL)
8.30 Ibrahim General workers Back-up Tnp (abg din) 241.6 (SB/SL)
8.30 Kishor General workers Back-up Tnp (Abg Din) 241.6 (SB/SL)
Shah Tak hadir
Abib Tak Hadir
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
02/03/2021 8.30 N4 Driver New Street Lighting 266.8 - 266.0 (NB/SL)
Tuesday 8.30 Rajen General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Shah Driver Repair & Maintenance store store
8.30 Rahmat General workers Repair & Maintenance store store
8.30 Samsul General workers Repair & Maintenance store store
8.30 Raju General workers Repair & Maintenance store store
8.30 Shah Driver kutip Signboard site sec N5 / Store
8.30 Saravanan General workers kutip Signboard site sec N5 / Store
8.30 Mumtaz General workers kutip Signboard site sec N5 / Store
8.30 Shagor General workers kutip Signboard site sec N5 / Store
8.30 Abid General workers Back-up Tnp 242.3 (NB/SL)
8.30 Ibrahim General workers Back-up Tnp 242.3 (NB/SL)
8.30 Kishor General workers Back-up Tnp 242.3 (NB/SL)
Wan Tak hadir
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
03/03/2021 8.30 Wan Driver New Street Lighting 266.8 - 266.0 (NB/SL)
Wednesday 8.30 Rajen General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Shah Driver Repair Bridge Join 240.6 (NB/SL)
8.30 Rahmat General workers Repair Bridge Join 240.6 (NB/SL)
8.30 Samsul General workers Repair Bridge Join 240.6 (NB/SL)
8.30 Kishor General workers Repair Bridge Join 240.6 (NB/SL)
8.30 Raju General workers Buat kerja di Store dgn Bob Store
8.30 Abid General workers Back-up Tnp (Din) 244.6 - 246.6 (NB/
8.30 Ibrahim General workers Back-up Tnp (Din) 242
22.00 N4 Driver Tunnel work Tunnel 1 (SB/FL)
22.00 Mumtaz General workers Tunnel work Tunnel 1 (SB/FL)
22.00 Saravanan General workers Tunnel work Tunnel 1 (SB/FL)
22.00 Shagor General workers Tunnel work Tunnel 1 (SB/FL)
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
04/03/2021 8.30 Wan Driver New Street Lighting 266.8 - 266.0 (NB/SL)
Thursday 8.30 Rajen General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Shah Driver Repair Bridge Join 240.6 (NB/SL)
8.30 Rahmat General workers Repair Bridge Join 240.6 (NB/SL)
8.30 Samsul General workers Repair Bridge Join 240.6 (NB/SL)
8.30 Raju General workers Repair Bridge Join 240.6 (NB/SL)
8.30 Safarul (Angah) Driver Huls geosynthetich (Rock slope) 258.5 (SB/SL)
8.30 Abid General workers Huls geosynthetich (Rock slope) 258.5 (SB/SL)
8.30 Kishor General workers Huls geosynthetich (Rock slope) 258.5 (SB/SL)
8.30 Ibrahim General workers Huls geosynthetich (Rock slope) 258.5 (SB/SL)
22.00 Atan N4 Driver Tunnel work Tunnel 1 (SB/SL)
22.00 Mumtaz General workers Tunnel work Tunnel 1 (SB/SL)
22.00 Shagor General workers Tunnel work Tunnel 1 (SB/SL)
22.00 G/W N4 General workers Tunnel work Tunnel 1 (SB/SL)
22.30 Zam N4 Driver Huls geosynthetich (Rock slope) 258.5 (SB/SL/ML)
22.30 Saravanan General workers Huls geosynthetich (Rock slope) 258.5 (SB/SL/ML)
22.30 G/W N4 General workers Huls geosynthetich (Rock slope) 258.5 (SB/SL/ML)
22.30 G/W N4 General workers Huls geosynthetich (Rock slope) 258.5 (SB/SL/ML)
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
05/03/2021 8.30 (Naja N4) Driver New Street Lighting 266.8 - 266.0 (NB/SL)
Friday 8.30 Rajen General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Shah Driver Repair Bridge Join 240.6 (SB/SL)
8.30 Rahmat General workers Repair Bridge Join 240.6 (SB/SL)
8.30 Samsul General workers Repair Bridge Join 240.6 (SB/SL)
8.30 Raju General workers Repair Bridge Join 240.6 (SB/SL)
8.30 Shagor General workers Maintenance & pindah barang store Store
8.30 Mumtaz General workers Maintenance & pindah barang store Store
Wan Driver Cuti
Abid General workers Cuti
Ibrahim General workers Cuti
Kishor General workers Cuti
Saravanan General workers Cuti
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
08/03/2021 8.30 Wan Driver New Street Lighting 266.8 - 265.8 (NB/SL)
Monday 8.30 Rajen General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Shah Driver Maintenance Store
8.30 Saravanan General workers Maintenance Store
8.30 Mumtaz General workers Maintenance Store
8.30 Shagor General workers Maintenance Store
8.30 Rahmat General workers Maintenance Store

8.30 Raju General workers pergi N4


8.30 Samsul General workers pergi N4

Abid General workers Cuti


Kishor General workers Cuti
Ibrahim General workers Cuti
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
09/03/2021 8.30 Wan Driver New Street Lighting 266.8 - 265.8 (NB/SL)
Tuesday 8.30 Rajen General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Shah Driver Maintenance Store
8.30 Saravanan General workers Maintenance Store
8.30 Mumtaz General workers Maintenance Store
8.30 Shagor General workers Maintenance Store
8.30 Rahmat General workers Maintenance Store
8.30 Raju General workers pergi N4
8.30 Samsul General workers pergi N4
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
10/03/2021 8.30 Wan Driver New Street Lighting 266.8 - 265.8 (NB/SL)
Wednesday 8.30 Rajen General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Naja N4 Driver Pavement work 265.1 - 266.1 (SB/SL)
8.30 Saravanan General workers Pavement work 265.1 - 266.1 (SB/SL)
8.30 Mumtaz General workers Pavement work 265.1 - 266.1 (SB/SL)
8.30 Shagor General workers Pavement work 265.1 - 266.1 (SB/SL)
8.30 Shah Driver Maintenance & pindah barier Store
8.30 Rahmat General workers Maintenance & pindah barier Store
8.30 Raju General workers Maintenance & pindah barier Store
8.30 Samsul General workers Maintenance & pindah barier Store

22.00 Atan N4 Driver Tunnel routine maintenance Tunnel 2 (NB/SL)


22.00 Gw N4 General workers Tunnel routine maintenance Tunnel 2 (NB/SL)
22.00 Gw N4 General workers Tunnel routine maintenance Tunnel 2 (NB/SL)
22.00 Gw N4 General workers Tunnel routine maintenance Tunnel 2 (NB/SL)
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
11/03/2021 8.30 Wan Driver New Street Lighting 266.8 - 265.8 (NB/SL)
Thursday 8.30 Rajen General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Shah Driver Pavement work 265.1 - 266.1 (SB/SL)
8.30 Rahmat General workers Pavement work 265.1 - 266.1 (SB/SL)
8.30 Samsul General workers Pavement work 265.1 - 266.1 (SB/SL)
8.30 Raju General workers Pavement work 265.1 - 266.1 (SB/SL)
22.00 Naja N4 Driver Tunnel routine maintenance Tunnel 2 (NB/SL)
22.00 Saravanan General workers Tunnel routine maintenance Tunnel 2 (NB/SL)
22.00 Mumtaz General workers Tunnel routine maintenance Tunnel 2 (NB/SL)
22.00 Shagor General workers Tunnel routine maintenance Tunnel 2 (NB/SL)
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
12/03/2021 8.30 Naja N4 Driver New Street Lighting 266.5 - 264.5 (NB/SL)
Friday 8.30 Rajen General workers New Street Lighting 266.5 - 264.5 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.5 - 264.5 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.5 - 264.5 (NB/SL)
8.30 Rahmat General workers Maintenance Stor
8.30 Saravanan General workers Maintenance Stor
8.30 Raju General workers Maintenance Stor
8.30 Mumtaz General workers Maintenance Stor
8.30 Shagor General workers Maintenance Stor

Shah Driver Cuti


Wan Driver Cuti
Samsul General workers Cuti
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
15/03/2021 8.30 Wan Driver New Street Lighting 266.4 - 264.4 (NB/SL)
Monday 8.30 Rajen General workers New Street Lighting 266.5 - 264.5 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.5 - 264.5 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.5 - 264.5 (NB/SL)
22.00-12.00 Shah Driver pavement work 265.1 - 266.1 (SB/SL)
22.00-12.00 Rahmat General workers pavement work 265.1 - 266.1 (SB/SL)
22.00-12.00 Samsul General workers pavement work 265.1 - 266.1 (SB/SL)
22.00-12.00 Raju General workers pavement work 265.1 - 266.1 (SB/SL)
22.00 Asraf N4 Driver Routine maintenance tunnel Tunnel 1(SB/SL)
22.00 Saravanan General workers Routine maintenance tunnel Tunnel 1(SB/SL)
22.00 Mumtaz General workers Routine maintenance tunnel Tunnel 1(SB/SL)
22.00 Shagor General workers Routine maintenance tunnel Tunnel 1(SB/SL)
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
16/03/2021 8.30 Wan Driver New Street Lighting 266.4 - 264.4 (NB/SL)
Tuesday 8.30 Rajen General workers New Street Lighting 266.5 - 264.5 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.5 - 264.5 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.5 - 264.5 (NB/SL)
22.00-12.00 Shah Driver pavement work 264.5 - 266.1 (SB/SL)
22.00-12.00 Saravanan General workers pavement work 264.5 - 266.1 (SB/SL)
22.00-12.00 Mumtaz General workers pavement work 264.5 - 266.1 (SB/SL)
22.00-12.00 Shagor General workers pavement work 264.5 - 266.1 (SB/SL)
22.00 Asraf N4 Driver Routine maintenance tunnel Tunnel 2 (SB/SL)
22.00 Rahmat General workers Routine maintenance tunnel Tunnel 2 (SB/SL)
22.00 Raju General workers Routine maintenance tunnel Tunnel 2 (SB/SL)
22.00 Samsul General workers Routine maintenance tunnel Tunnel 2 (SB/SL)
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
17/03/2021 8.30 Atan N4 Driver New Street Lighting 266.4 - 265.8 (NB/SL)
Wednesday 8.30 Rajen General workers New Street Lighting 266.4 - 265.8 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.4 - 265.8 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.4 - 265.8 (NB/SL)
22.00-12.00 Naja N4 Driver pavement work 264.5 - 266.1 (SB/FL)
22.00-12.00 Saravanan General workers pavement work 264.5 - 266.1 (SB/FL)
22.00-12.00 Mumtaz General workers pavement work 264.5 - 266.1 (SB/FL)
22.00-12.00 Shagor General workers pavement work 264.5 - 266.1 (SB/FL)
22.00 Asraf N4 Driver Routine maintenance tunnel Tunnel 1 (SB/FL)
22.00 Rahmat General workers Routine maintenance tunnel Tunnel 1 (SB/FL)
22.00 Raju General workers Routine maintenance tunnel Tunnel 1 (SB/FL)
22.00 Samsul General workers Routine maintenance tunnel Tunnel 1 (SB/FL)

Wan Driver Cuti


Shah Driver Cuti
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
18/03/2021 8.30 Shah Driver New Street Lighting 266.4 - 265.8 (NB/SL)
Thursday 8.30 Rajen General workers New Street Lighting 266.4 - 265.8 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.4 - 265.8 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.4 - 265.8 (NB/SL)
22.00 Atan N4 Driver pavement work 264.5 - 266.1 (SB/FL)
22.00 Saravanan General workers pavement work 264.5 - 266.1 (SB/FL)
22.00 Mumtaz General workers pavement work 264.5 - 266.1 (SB/FL)
22.00 Shagor General workers pavement work 264.5 - 266.1 (SB/FL)
22.00 Asraf N4 Driver Routine maintenance tunnel Tunnel 1 (SB/FL)
22.00 Rahmat General workers Routine maintenance tunnel Tunnel 1 (SB/FL)
22.00 Raju General workers Routine maintenance tunnel Tunnel 1 (SB/FL)
22.00 Samsul General workers Routine maintenance tunnel Tunnel 1 (SB/FL)

Wan Driver Cuti


Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
19/03/2021 8.30 Shah Driver New Street Lighting 266.4 - 265.8 (NB/SL)
Friday 8.30 Rajen General workers New Street Lighting 266.4 - 265.8 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.4 - 265.8 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.4 - 265.8 (NB/SL)
22.00 Saravanan General workers Maintenance Store
22.00 Mumtaz General workers Maintenance Store
22.00 Shagor General workers Maintenance Store
22.00 Rahmat General workers Maintenance Store
22.00 Raju General workers Maintenance Store
22.00 Samsul General workers Maintenance Store

Wan Driver Cuti


Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
20/03/2021 8.30 Naja N4 Driver New Street Lighting 266.8 - 266.0 (NB/SL)
Saturday 8.30 Rajen General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Kumar General workers New Street Lighting 266.8 - 266.0 (NB/SL)
8.30 Atan N4 Driver Collect barrier & Holding Tunnel / Store
8.30 N4 General workers Collect barrier & Holding Tunnel / Store
8.30 N4 General workers Collect barrier & Holding Tunnel / Store
8.30 N4 General workers Collect barrier & Holding Tunnel / Store
8.30 Asraf N4 Driver Collect barrier & Holding Tunnel / Store
8.30 Saravanan General workers Collect barrier & Holding Tunnel / Store
8.30 Samsul General workers Collect barrier & Holding Tunnel / Store
8.30 Raju General workers Collect barrier & Holding Tunnel / Store
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
21/03/2021 8.30 Atan N4 Driver New Street Lighting 266.3 - 265.8 (NB/SL)
Sunday 8.30 Rajen General workers New Street Lighting 266.3 - 265.8 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.3 - 265.8 (NB/SL)
8.30 Raju General workers New Street Lighting 266.3 - 265.8 (NB/SL)
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
22/03/2021 8.30 Zam N4 Driver New Street Lighting 266.3 - 264.5 (NB/SL)
Monday 8.30 Rajen General workers New Street Lighting 266.3 - 264.5 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.3 - 264.5 (NB/SL)
8.30 Raju General workers New Street Lighting 266.3 - 264.5 (NB/SL)
8.30 Shah Driver Collect signboard & Store Store
8.30 Saravanan General workers Collect signboard & Store Store
8.30 Mumtaz General workers Collect signboard & Store Store
8.30 Shagor General workers Collect signboard & Store Store

Rahmat General workers Cuti


Samsul General workers Cuti
Kumar General workers Cuti
Wan Driver Cuti
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
23/03/2021 8.30 Zam N4 Driver New Street Lighting 266.9 - 265.8 (NB/SL)
Tuesday 8.30 Rahmat General workers New Street Lighting 266.9 - 265.8 (NB/SL)
8.30 Raju General workers New Street Lighting 266.9 - 265.8 (NB/SL)
8.30 Samsul General workers New Street Lighting 266.9 - 265.8 (NB/SL)
8.30 Shah Driver Site Demarcation 225.0 -227.0 (SB/SL)
8.30 Rajen General workers Site Demarcation 225.0 -227.0 (SB/SL)
8.30 Ramesh General workers Site Demarcation 225.0 -227.0 (SB/SL)
8.30 Kumar General workers Site Demarcation 225.0 -227.0 (SB/SL)

Saravanan General workers Cuti


Mumtaz General workers Cuti
Shagor General workers Cuti
Wan Driver Cuti
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
24/03/2021 8.30 Zam N4 Driver New Street Lighting 266.9 - 265.4 (NB/SL)
Wednesday 8.30 Rahmat General workers New Street Lighting 266.9 - 265.4 (NB/SL)
8.30 Raju General workers New Street Lighting 266.9 - 265.4 (NB/SL)
8.30 Samsul General workers New Street Lighting 266.9 - 265.4 (NB/SL)
8.30 Shah Driver Site Demarcation 229 - 231 (SB/SL)
8.30 Rajen General workers Site Demarcation 225.0 -227.0 (SB/SL)
8.30 Ramesh General workers Site Demarcation 225.0 -227.0 (SB/SL)
8.30 Kumar General workers Site Demarcation 225.0 -227.0 (SB/SL)

Saravanan General workers Follow N4


Abid General workers Follow N4

Mumtaz General workers Cuti


Shagor General workers Cuti
Wan Driver Cuti
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
25/03/2021 8.30 Zam N4 Driver New Street Lighting 266.3 - 265.5 (NB/SL)
Thursday 8.30 Rahmat General workers New Street Lighting 266.3 - 265.5 (NB/SL)
8.30 Raju General workers New Street Lighting 266.3 - 265.5 (NB/SL)
8.30 Samsul General workers New Street Lighting 266.3 - 265.5 (NB/SL)
22.00 Shah Driver Site Demarcation 229 - 231 (SB/SL)
22.00 Saravanan General workers Site Demarcation 225.0 -227.0 (SB/SL)
22.00 Ramesh General workers Site Demarcation 225.0 -227.0 (SB/SL)
22.00 Rajen General workers Site Demarcation 225.0 -227.0 (SB/SL)

Kumar General workers Cuti


Mumtaz General workers Cuti
Shagor General workers Cuti
Wan Driver Cuti
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
26/03/2021 8.30 Zam N4 Driver New Street Lighting 266.8 - 265.3 (NB/SL)
Friday 8.30 Rahmat General workers New Street Lighting 266.8 - 265.3 (NB/SL)
8.30 Raju General workers New Street Lighting 266.8 - 265.3 (NB/SL)
8.30 Samsul General workers New Street Lighting 266.8 - 265.3 (NB/SL)
8.30 Shah Driver collect signboard Store
8.30 Saravanan General workers collect signboard Store
8.30 Kumar General workers collect signboard Store
8.30 Rajen General workers collect signboard Store

Ramesh General workers Cuti


Mumtaz General workers Cuti
Shagor General workers Cuti
Wan Driver Cuti
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
27/03/2021 8.30 Asraf N4 Driver New Street Lighting 265.8 - 265.0 (NB/SL)
Saturday 8.30 Kumar General workers New Street Lighting 266.8 - 265.3 (NB/SL)
8.30 Ramesh General workers New Street Lighting 266.8 - 265.3 (NB/SL)
8.30 Rajen General workers New Street Lighting 266.8 - 265.3 (NB/SL)
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
29/03/2021 8.30 Shah Driver New Street Lighting 265.4 - 264.5 (NB/SL)
Monday 8.30 Kumar General workers New Street Lighting 265.4 - 264.5 (NB/SL)
8.30 Ramesh General workers New Street Lighting 265.4 - 264.5 (NB/SL)
8.30 Rajen General workers New Street Lighting 265.4 - 264.5 (NB/SL)
8.30 Atan N4 Driver maintenance equipment Store
8.30 Rahmat General workers maintenance equipment Store
8.30 Raju General maintenance equipment Store
8.30 Samsul General workers maintenance equipment Store
8.30 Saravanan General workers Follow supervisor
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
30/03/2021 8.30 Shah Driver New Street Lighting 265.4 - 264.5 (NB/SL)
Tuesday 8.30 Ramesh General workers New Street Lighting 265.4 - 264.5 (NB/SL)
8.30 Kumar General workers New Street Lighting 265.4 - 264.5 (NB/SL)
8.30 Rajen General workers New Street Lighting 265.4 - 264.5 (NB/SL)
8.30 Atan N4 Driver maintenance equipment Store
8.30 Rahmat General workers maintenance equipment Store
8.30 Raju General maintenance equipment Store
8.30 Samsul General workers maintenance equipment Store
8.30 Saravanan General workers Follow supervisor
Tarikh Masa Nama Jawatan Lokasi Kilometer Remarks
31/03/2021 8.30 Shah Driver New Street Lighting 265.4 - 264.5 (NB/SL)
Wednesday 8.30 Ramesh General workers New Street Lighting 265.4 - 264.5 (NB/SL)
8.30 Kumar General workers New Street Lighting 265.4 - 264.5 (NB/SL)
8.30 Rajen General workers New Street Lighting 265.4 - 264.5 (NB/SL)
8.30 Atan N4 Driver maintenance equipment Store
8.30 Rahmat General workers maintenance equipment Store
8.30 Raju General workers maintenance equipment Store
8.30 Samsul General workers maintenance equipment Store