30 Aug 2020, Steel
30 Aug 2020, Steel
Span = 9m
Shed Length = 18 m
Building Clear height upto the eaves = 8m
Structural form
A trapezoidal truss is adopted with
Roof slope of 1 to 4
Full height at mid-span of 2.9 m
and End depth of 0 m
Truss Spacing
Truss spacing should be in the region of 1/4 to 1/5 of the span length.
For 5 m spacing,
Span/Spacing = 1.8454724 NG
Then,
Number of bays = 3.6909449 no.
Truss Configuration
0.5
2.50
1
1.00
9
6.00
8 @ 1.13 m = 9 m
25.00
Load Calculation
Value of Cpi
Assume wall openings between
Then,
Cpi = ± 0.2
Value of Cpe
Roof angle, α = 14.00 ⁰
Height of the building to eaves = 8.00 m
Lesser dimension of the building in plan, w = 9.00 m
Value of pd
Basic wind speed (Vb) = 47.00 m/s
Total height of building = 10.90 m
Design wind speed vz is given by
Vz = k1 × k2 × k3 × Vb
Here,
Risk Coefficient, k1 = 1.00
(Assuming the industrial building as general building and its
probable life about 50 years.)
Design Condition
Material Properties
Characteristic Strength of concrete, fck (adopt) = 20 MPa
Characteristic strength of rebars, fy (adopt) = 500 MPa
Allowable bearing pressure on soil = 125 kN/m2
Required depth of footing bottom below ground level = 1.5 m
Unit Weight of soil below backfill = 18 kN/m3
Design of Pedestal
A pedestal of 0.40 x 0.40 x 1.05 m shall be used.
For combo I,
Net downward load = 129.2 kN
Moment at the base of pedestal due to shear = 0 kNm
Total Moment at base of pedestal = 0 kNm
Then,
Design Compression = 129.2 kN
Design Moment = 0 kNm
Design of Footing
Direct Load from pedestal, W1 = 129.20 kN
Moment from pedestal = 0.00 kNm
𝑏/6
Eccentricity of resultant vertical force = 0.00 m < = 0.50 m
Therefore,
Base pressure distribution is triangular with no part in tension.
Width of footing in contact with soil = 3.00 m
Now,
Maximum pressure = 44.17 kN/m2 < 1.25 x 125 kN/m2 = 156.25 kN/m2 OK
Provide 12 mm dia bars @ 150 mm c/c on top and bottom both ways.
1. To transfer moment (Welded Seat angle connection on top and bottom flange)
2. To Transfer Shear (Web angle connection- bolted to beam’s web and welded to column)
Use 4.6 grade bolts of M12 size. Bolts are in double shear.
eccentricity
65 mm
check #DIV/0!