You are on page 1of 1

DAILY RFI

SCHEDULE Date 20.02.2021


STERLING & WILSON
From To GLOBELEQ/WSP

Work Sub SW Construction SW Quality


No. Inspection items Location Session Client Representative Inspection Status
Nature/Type Contractor Team Team
Pier Foundation Civil Polyphase Block 5 Sec 3 -8 Tracker's , Section 8 Morning Vikram Naveen Kumar Tom Oyuga
1 - 8 Trackers
Pier Foundation Civil Polyphase Block 4 - Section 1 & Section 2 (16 Morning Vikram Naveen Kumar
2 Tom Oyuga
trackers)
Pier Foundation Civil Polyphase Block 6 Sec 3 - 10 Tracker's Morning Vikram Naveen Kumar
3 Block 6 sec 4 - 9 Tracker's Tom Oyuga

4 Tracker & Module Installation Mechanical Polyphase Block 1 - Section 1 , 2 & 3 Morning Sabeel Naveen Kumar Samwel Kariuki
5 Tracker & Module Installation Mechanical Polyphase Block 7 - Section 1 , 2 & 3 Morning Sabeel Naveen Kumar Samwel Kariuki
6 Tracker & Module Installation Mechanical Polyphase Block 5 - Section 1 , 2 Morning Sabeel Naveen Kumar Samwel Kariuki
7 CCTV cable trench sand bedding above the FO cable - North side/CCTV trench Electrical Polyphase Block-1 Morning Srikant Giri Priyaranjan Brian Nyangaresi
8 Soil bedding and warning tape laying - North side/CCTV trench Electrical Polyphase Block-1 Morning Srikant Giri Priyaranjan Brian Nyangaresi
9 Sand bedding above the FO cable - Inverter station Second inverter DC merging trench Electrical Polyphase Block-3 Morning Srikant Giri Priyaranjan Denis Ginara
10 Soil bedding and warning tape laying - Merging Trench Electrical Polyphase Block-3 Morning Srikant Giri Priyaranjan Denis Ginara
11 warning tape laying for all trench Electrical Polyphase Block-4 - T2 Morning Srikant Giri Dhanajay Denis Ginara
12 sand bedding above the DC cable Electrical Polyphase Block-4 - Main trench T3/T4 Morning Srikant Giri Dhanajay Denis Ginara
13 Second layer cable laying Electrical Polyphase Block-4 - Main trench T3/T5 Morning Srikant Giri Dhanajay Denis Ginara
14 Sand bedding above the FO cable Electrical Polyphase Block-4 - T4 Morning Srikant Giri Dhanajay Denis Ginara
15 Sand bedding and control cable laying Electrical Polyphase Block-2 Morning Srikant Giri Dhanajay Brian Nyangaresi
16 Sand bedding and Communication cable laying - Inverter station Electrical Polyphase Block-2 Morning Srikant Giri Dhanajay Brian Nyangaresi
17 First inverter 16 nos SCB RFI - Inverter -3,16 SCB Electrical Polyphase Block-2 Afternoon Srikant Giri Dhanajay Brian Nyangaresi
18 SCB MV switchgear room cable trench base. Civil IET SCB Building Morning Robinson Priyaranjan Isaac Ginara
19 sellers trench PCC Civil IET Seller Side Morning Robinson Priyaranjan Isaac Ginara
20 Guard house column RCC Civil IET Substation Morning Robinson Priyaranjan Isaac Ginara
21 Pcc for trafo 7a gradeslab in the afternoon schedule Civil SAVA Block 7 Morning Tarani Mandal Priyaranjan Isaac Ginara
Switchyard Fenching North Side
22 Civil IET Substation Morning Saajjith Priyaranjan Isaac Ginara
23 Exothermic Welding Inspection Electrical IET Substation Morning Saajjith Priyaranjan Isaac Ginara

S&W Quality: _______________________________ Date:________________ CLIENT:_________________________ Date:_____________