You are on page 1of 6

Adaptive Remedial Action Scheme Based on

Phasor Measurement Unit


Ahmad Yusuf Salile Nanang Hariyanto Masayuki Watanabe Fathin Saifur Rahman
PT. PLN (Persero) Bandung Institute of Technology Kyushu Institute of Technology Bandung Institute of Technology
Jakarta, Indonesia Bandung, Indonesia Fukuoka, Kitakyushu, Japan Bandung, Indonesia
ays@pln.co.id nanang.hariyanto@stei.itb.ac.id watanabe@ele.kyutech.ac.jp fathinsr@stei.itb.ac.id

Abstract— Most of the blackout occurrences are caused by phasor measurement unit (PMU) data, in which the sag effect
non-credible contingency events and often, the response to these has been included.
situations is not prepared. One of such contingency event is the
violation of transmission line limits leading to the disconnection To prevent the transmission lines operates above their
of multiple highly loaded transmission lines. To prevent this loadability limits and negatively impact the system stability,
event, knowing the loadability of the transmission line is in this paper, the application of an adaptive remedial action
important. In this research, a method to obtain the loadability scheme (RAS) based on the phasor measurement unit (PMU)
of the transmission line is proposed. The data from the phasor is proposed. RAS is a scheme that enables immediate
measurement units are utilized to obtain the characteristics of corrective actions to be taken when abnormal system
the transmission lines (i.e. reactance, voltage drop pattern). conditions are detected. Based on the design methodology,
Then, the loadability of the transmission lines in terms of RAS classified as event-based and response-based [4]. In [5],
thermal, voltage drop, and stability limits are calculated. The an overload shedding (OLS) scheme based on the dynamic
adaptive remedial action scheme (RAS) is also designed to rating of transmission lines is presented. However, this
maintain power transfer within a safe limit by load shedding scheme only considers the thermal rating. In [6] the OLS is
and/or generation rejection. This scheme will update the total designed by considering both transient and overload factors.
amount of load shedding or generation rejection and select the However, only a small amount of load shedding may be
target based on the sensitivity of voltage to active power change.
applied to keep the frequency in the normal range. A
The method is applied to the Java-Bali system, in which a high
probabilistic approach based on statistical distribution factors
amount of power is transferred from eastern to the western part
through the transmission lines at the north and south corridors
that allow the computation of an overload index in real-time is
and hence, knowing the loadability limits of each corridor is proposed in [7]. However, the application of the method is
important. Using the proposed method, the separation of limited to lines that are connected to the same bus. In this
western and eastern Java could be effectively prevented. paper, an adaptive RAS that performs a load shedding (LS)
with or without generation rejection (GR) is proposed. LS
Keywords—Adaptive remedial action scheme, greedy would be applied at the load-heavy area, while GR would be
algorithm, loadability, phasor measurement unit, voltage performed at the generation-rich area. Thus, by using the
sensitivity methods proposed in this paper, the actual loadability of the
transmission line could be obtained and then, the overloading
I. INTRODUCTION of the transmission lines could be effectively prevented while
In the last two years, there were at least two significant maintaining the system frequency within the normal range.
blackouts in some areas in the Java-Bali system because of the The main contributions of this paper are: a) Determination of
fault at the 500 kV extra-high voltage transmission lines the loadability of transmission lines based on PMU data, and
(EHVTL). In September 2018, a fault occurred on Paiton– b) Designing an adaptive RAS scheme to effectively prevent
Grati EHVTL followed by a forced outage with the amount of line overloading while maintaining frequency within limits.
3846 MW of generations and 2621 MW of loads. In August
2019, the fault occurred at two circuits of Ungaran–Pemalang II. METHODOLOGY
EHVTLs (north corridor) followed by the trip two circuits of A. Research Objective
Tasik–Depok EHVTLs (south corridor) triggered by out-of-
In this paper, a study is conducted on the 500 kV
step protection. Hence, the system split into two sub-systems.
interconnection between the eastern and western regions of the
To stabilize the frequency, under-frequency protection in the
Java-Bali system. It comprises of two circuits at each of the
western region was triggered to release 2043 MW of loads.
north and south corridors as shown in Fig. 1. The PMUs have
Meanwhile, over-speed protection in the eastern region was
been installed at the studied segment. Thus, the real-time
triggered to release 2263 MW of generations.
change in system parameters at the line could be monitored.
Considering technical, operational, and economic aspects,
it is important to exploit the transmission lines within their
limits. However, without proper knowledge of their actual
loadability limits, the instability might occur in the system and
causing system blackouts. The modeling of the loadability of
the transmission line using representations of auxiliary
constants A, B, and C is proposed in [1]. In [2], the error in the
calculation of the transmission line parameter due to the sag
effect is investigated. To reduce the error, the application of a
linear estimator is proposed in [3]. In this paper, the loadability
of the transmission lines will be determined based on the Fig. 1. Simplified west-east Java interconnection

978-1-7281-4701-7/20/$31.00 ©2020 IEEE

Authorized licensed use limited to: Universiti Malaysia Perlis. Downloaded on May 06,2021 at 07:30:54 UTC from IEEE Xplore. Restrictions apply.
To anticipate the overload of transmission lines under heating due to the current flow. All factors that affect the
normal conditions subject to credible or non-credible reactance value will be included as an equivalent reactance
contingencies, an adaptive remedial action scheme (RAS) is Xeq . In section III, the relation of an equivalent reactance with
proposed. This scheme will keep the power transfer within the the sine of power angle (4) is described.
transmission loadability by releasing loads and/or releasing
generators. The total disconnected load or generator should be Xeq = f(sin δ) (4)
determined in a way that guarantees the transmission line
loading returns within the allowable limits with a high voltage The relationship of other system variables with respect to
rise at the sending-end bus while maintaining the frequency the voltage drop is investigated by using the regression
within normal limits of 49.5 Hz and 50.5 Hz. To accomplish method. The variables that might be correlated with the
those objectives, the optimization method is used to determine voltage drop (Vdrop ) are active power (Ps), voltage (Vs), and
the proper amount of load shedding and/or generation
rejection based on the sensitivity of the voltage change respect power factor (PF) (5). Hence, the voltage drop is defined as
to the active power change (dv/dP), while maintaining the the function of these variables.
frequency within normal limits.
Vdrop = f (Ps, Vs, PF) (5)
B. Research Procedures
In this study, several aspects related to the transmission In this paper, the adaptive RAS will shed a certain amount
lines are calculated, including the transmission loadability and of load if the power transfer exceeds one of the three transfer
the expected voltage increase at the bus. The obtained results limits [12] as shown in (6), and the expected frequency after
will then used to design the appropriate adaptive RAS. the shedding (7) is not higher than 50.5 Hz. However, if the
expected frequency after the load shedding is higher than 50.5
Three principal factors that affect the ability to transfer Hz, it is necessary to simultaneously shed the load at the
active power are the thermal limit, voltage drop limit, and receiving region and shed the generation at the sending region
small-signal stability limit [8]. Thermal limits are set by the to maintain the frequency within its limits. In this paper, the
strength of the physical structure itself due to exposed system stiffness of 919.87 MW/Hz is used. This value is based
temperature fluctuation. For safety purposes, the ground on the regression of the frequency response of the system due
clearance between conductors with the object underneath is to the generation outage events during a year.
necessary to be maintained within its design standard. The sag
increases at high temperatures or high loading of the
Pshed = Ps − min (Pt-limit , Pv-limit , Ps-limit ) (6)
transmission line. In this study, the effect of temperature is not
directly considered. However, a specific current value limit
according to the design considering the two factors above is fexpect = factual − Pshed / SS (7)
taken into consideration. The thermal power transfer limit is
expressed with the following equation: The maximum amount of generation shedding or rejection
is half of the total power shedding and the rest of the amount
Pt-limit = √3 V It cos θ (1) is load shedding. To achieve the expected frequency of 50 Hz
after power shedding, (8) and (9) are used.
Meanwhile, the voltage drop is generally limited to 5%.
This value is acceptable to represent heavy line loading GR = 0.5Pshed + SS ( factual − 50 ) (8)
without any system problems [9]. In this study, the voltage
quality limit [10] is applied and determined based on the grid LS = Pshed − GR + SS ( factual − 50 ) (9)
code of the Java-Bali system, in which the lowest voltage at
the 500 kV bus is 0.95 p.u. or 475 kV. An optimization method is used to determine the target of
The active power transfer is the function of voltage load shedding or generation rejection based on the sensitivity
magnitude at sending Vs and receiving-end bus Vr , sine of of the voltage variation at the sending-end of the overloaded
power angle δ at sending and receiving-end bus, and the transmission lines to the active power of the target candidates.
inverse of reactance X (2). The small-signal stability is limited The constraints are ≤ and ≥ . RAS must
to 70% of the maximum power transfer, or at a power angle of be run in a short amount of time. Therefore, the optimization
44.4º [8]. We now have (3). method must be able to obtain the desired solutions with fast
processing time. Hence, the greedy algorithm and dynamic
= Vs Vr sin δ⁄X (2) programming as two efficient algorithms [13] are investigated.
The dynamic programming solves the problems by
Ps-limit = 0.7 Vs Vr ⁄X (3) breaking down the main problem into sub-problems,
combining sub-problem solutions, and obtaining solutions to
PMU provides real-time measurements of essential state the main problem. Dynamic programming has an issue of time
variables such as voltage, current magnitude, and power angle. complexity as O (n Pshed ) [14], where O is time complexity,
With these data, the reactance of the transmission line in (2) and n is the candidate number of shedding objects. Meanwhile,
could be obtained [11]. In the 500 kV transmission system, the the greedy algorithm presents the decision that seems to be the
reactance is more dominant compared to the resistance and best during the process. It offers locally optimal decisions and
thus, the resistance is negligible in most cases. In this case, we the expected outcomes lead to the globally optimal solution.
do not consider the resistance as a separate parameter. The greedy algorithm does not always produce the most
However, it is included in the reactance parameter as a optimal solution. The greedy algorithm has time complexity
variable factor that changes depends on the level of conductor stated in function as O (n log n ) [15].

Authorized licensed use limited to: Universiti Malaysia Perlis. Downloaded on May 06,2021 at 07:30:54 UTC from IEEE Xplore. Restrictions apply.
TABLE I. STATISTICAL DATA OF REACTANCE REGRESSION
2
Line Min Max Mean a b c R RMSE NRMSE N(sample)

North Normal 32.69 61.40 34.21 0.05 -1.32 32.67 0.992 0.212 -0.008 3345886

North N-1 64.50 66.68 65.24 0.28 -1.25 62.73 0.641 0.244 -0.139 1530000

South Normal 7.57 26.84 23.58 -1.71 -0.47 32.61 0.994 0.219 0.009 2423420

South N-1 16.60 24.70 21.47 -0.48 -0.75 27.06 0.997 0.129 0.016 841199

The plotted data coincides with the


regression line, it means and
sin have a high correlation

Fig. 3. Extrapolation of reactance for normal cases in the north corridor.

The plotted data less coincides with


the regression line, it means that
and sin have less correlation

Fig. 4. Extrapolation of reactance for N-1 cases in the north corridor.

Fig. 2. Flowchart of Adaptive RAS


The plotted data coincides with the
The outline of the procedures is illustrated in Fig. 2. For regression line, it means and
two or more corridors, if the violation occurs at the same time, sin have a high correlation
the new power shedding candidate of substation or power
plant is a complement of previously selected substations or
power plants.

LSopt-new ∆ LSopt-old (10) Fig. 5. Extrapolation of reactance for normal cases in the south corridor.

GR opt-new ∆ GR opt-old (11)

III. RESULT AND DISCUSSION


According to the historical PMU data at monitored
transmission lines, there is no state of overloading yet. Hence,
the loadability of transmission lines is estimated by using an
The plotted data coincides with the
extrapolation approach. regression line, it means and
sin have a high correlation
A. Extrapolation
To estimate the variable outside the range of the sample
observed data, we use an acceptable regression model to
predict the value. The extrapolation parameters are the
equivalent reactance and the voltage drop. Fig. 6. Extrapolation of reactance for N-1 cases in the south corridor.

Authorized licensed use limited to: Universiti Malaysia Perlis. Downloaded on May 06,2021 at 07:30:54 UTC from IEEE Xplore. Restrictions apply.
Referring to (2), the calculated reactance value is not
constant but varies. The correlation of the obtained value with
the available variable can be found out. The result discovers
that the value of X has a firm relationship with the parameter
of sin δ. From the results, it is discovered that X has a firm
- The plotted data gathered in one spot:
relationship with sin δ. The regression model which have the sample is insufficient
best fit is non-linear power regression given by (12). - The correlation of , and is
high enough

Xeq =a( sin δ)b +c (12)

The reactance extrapolation is shown in Fig. 3 and the


summary of the statistics is shown in Table I. Almost all of the
Fig. 9. Extrapolation of voltage drop for normal cases in the south corridor
cases fit with the proposed regression models with a high
correlation reaching more than 99%, except the N-1 of south
corridor case with correlation around 64%.
The result of extrapolating points out that the value of
equivalent reactance of the north corridor is decreasing and
tends to be constant with the higher value of sin δ. On the
- The plotted data scattered only in x-
contrary, the equivalent reactance value of the southern axis: sample is insufficient
corridor is increasing and tends to be constant with the higher - The correlation of , and is
value of sin δ. We will use the predicted value of Xeq at sin δ very high
= 0.7 to calculate the power transfer stability limit.
Next, we observe the behavior and the response of the
other parameters that drive the change of voltage at the
receiving-end bus and find out the values of other elements Fig. 10. Extrapolation of voltage drop for N-1 cases in the south corridor
when the voltage at the receiving-end bus reaches a minimum
acceptable limit. As initial assumptions, parameters that related to the
voltage at the received-end are the sending power, the
TABLE II. STATISTICAL DATA OF VOLTAGE DROP REGRESSION sending-end voltage, and the power factor. Nevertheless, from
Line p00 p10 p01 p20 p11 p02 R2 RMSE N_Sample the preliminary results of the current experiment, parameters
North Normal -775.1 0.2 2.4 -1.3E-06 -3.0E-04 -1.8E-03 0.779 1.241 2423420
of the sending power and the sending-end voltage have a better
North N-1 -12160.2 -0.8 49.5 -3.2E-04 2.6E-03 -5.1E-02 0.761 1.982 1530000
bond level. A polynomial second-order regression model is
applied to this sample data with the function shown in (13).
South Normal -5824.5 1.2 22.6 1.1E-05 -2.3E-03 -2.2E-02 0.797 0.877 2423420

Vdrop =p00+p10 Vs +p01 Ps +p20 Vs 2 +p11 Vs Ps +p02 Ps2 (13)


South N-1 68382.7 0.3 -266.8 -5.6E-06 -5.8E-04 2.6E-01 0.966 0.544 841199

The voltage drops pattern and its interpolation is shown as


color gradation in Figs. 7 to 10 and the summary of the
- The plotted data scattered enough: statistics is shown in Table II. The correlation of the regression
data sample is sufficient
- The correlation of , and
model and sample data has quite good grades with R2 over
is high enough 77%. The pattern generated by the regression model and its
interpolation still needs to be improved; this is due to the
plotted data gathered at one or two spots.
B. Loadability of Transmission Line
The loadability curve of the transmission line is obtained
by taking the minimum value of the power transfer limit based
Fig. 7. Extrapolation of voltage drop for normal cases in the north corridor on thermal, voltage, and quality. The power transfer curve
considering the thermal limit is obtained by (1). The power
transfer curve considering the voltage quality limit is obtained
by derivating the regression model (13) then we have (14).

= − + − +2 +

- The plotted data gathered in one spot:


−4 −4 −4 +4 ( −
sample is insufficient
- The correlation of , and is 475) 2 (14)
high enough
Meanwhile, the power transfer curve considering the
stability limit is obtained by substituting (12) into (3) at
sin δ = 0.7, and using (13) to obtain in (3). The resulting
Fig. 8. Extrapolation of voltage drop for N-1 cases in the north corridor equation is shown in (15). After that, the numerical method is
used to obtain the solution.

Authorized licensed use limited to: Universiti Malaysia Perlis. Downloaded on May 06,2021 at 07:30:54 UTC from IEEE Xplore. Restrictions apply.
. C. Optimization of Power Management
= − + + +
Load shedding and/or generation rejection selected based
+ + (15) on voltage sensitivity gives a higher voltage rise at the
sending-end bus. Optimization methods are utilized to obtain
The power transfer limit of each factor is achieved by the composition of load shedding and/or generation rejection
plotting the thermal limit (red line), voltage quality limit target that adequately finds the total of power shedding and
(green line), and stability limit (blue line). The power transfer increases the voltage at violating transmission bus. This
(MW) is on the vertical axis and the sending-end voltage (kV) additional voltage is expected to get a beneficial impact to
is on the horizontal axis. The continuous and dashed lines increase the power transfer and reduce further power
show normal and N-1 state, respectively. shedding. By the comparison based on the objective of
optimization that obtains the highest voltage increase,
The loadability of transmission lines on the north corridor dynamic programming is always superior to the greedy
with the assumption of the power factor is 0.85, is shown in algorithm. However, when the processing time is compared,
Fig. 11. Under normal circumstances, the power transfer is the greedy algorithm is the fastest and more stable under 0.01s.
limited by the voltage quality section when the sending-end In contrast, the processing time of dynamic programming
voltage is below 495 kV and limited by the thermal section increases as the target load increases, as shown in Table III.
when the sending-end voltage is above 495 kV. Under N-1 The greedy algorithm is applied in the adaptive RAS since it
circumstances, the loadability of transmission lines is only meets the main criteria for selecting the optimization method
limited by voltage quality. in this study (i.e. can obtain an optimal solution with the fastest
Similar to the northern corridor, the loadability of time during any circumstances).
transmission lines on the southern corridor also is limited by D. Simulation Result
the voltage drop section when the sending-end voltage below
480 kV and limited by the thermal section when the sending- Since there is no power transfer violation history based on
end voltage above 480 kV as shown in Fig. 12. Under N-1 PMU data, in this study, some hypothetical scenarios are used
contingencies, power transfer is limited by the thermal factor. to see how this proposed method works.
a) Load shedding (LS)-only scenario
This scenario occurs if the power transfer exceeds the
loadability of transmission lines and the expected frequency
after the power shedding is lower than 50.5 Hz. Hence,
generation rejection (GR) is not necessary. Fig. 13 shows that
the initial frequency is 49.89 Hz and the power transfer exceed
the limit as 273.0 MW. This excess power will be set as a
power shedding. The system stiffness is assumed to be around
919.8 MW. So, the estimated expected frequency using (7) is
fexpect-1 = 49.89 + 273.0⁄919.8 = 50.19 Hz, lower than 50.5
Hz. Therefore, only load shedding (LS) is triggered. The total
actual LS obtained from the greedy algorithm is 326.5 MW,
Fig. 11. Power transfer curve of the north corridor which targets five substations in the western region. The
expected voltage rise at the substation “A” is 0.5 kV and the
frequency is expected to increase 0.35 Hz becomes 50.25 Hz.
b) Load shedding and generation rejection scenario
This scenario occurs if the power transfer exceeds the
loadability of transmission lines and the expected frequency
after the power shedding is higher than 50.5 Hz. In this
condition, generation rejection should also be performed to
prevent over frequency in the system. Fig. 14 shows that the
initial frequency is 50.11 Hz. The power transfer at the north
corridor is 937.9 MW higher than loadability. The estimated
expected frequency after power shedding using (7) is
fexpect-1 = 50.11 + 937.9⁄919.8 = 51.13 Hz, higher than 50.5
Fig. 12. Power transfer curve of the south corridor
Hz. Hence, both load shedding (LS) and generation rejection
(GR) should be activated. The calculated GR target obtained
TABLE III. DYNAMIC PROGRAMMING VS. GREEDY using (8) is = 0.5 (937.9) + 919.8 (50.11 − 50) =
570.1 . The total actual GR obtained from greedy
Target
Dynamic Programming Greedy
algorithm is 554.0 MW, which targets four power plants in the
(MW) Shed
(MW)
deltaV
(k V)
Elapsed
(s)
Shed
(MW)
deltaV
(k V)
Elapsed
(s)
eastern region. The rest of required power shedding (i.e. in the
100 97.3 0.20 0.2458 89.0 0.17 0.0041
form of LS) is calculated using (9) as = 937.9 −
200 196.5 0.40 0.4619 177.1 0.33 0.0077
554.0 + 919.8 (50.11 − 50 ) = 487.1 . The result
500 490.9 0.95 3.5650 487.8 0.74 0.0030
of the optimization of the LS target is 487.8 MW in which the
1000 982.0 1.75 7.6271 940.1 1.35 0.0012
targets are nine substations in the western region. The
1500 1466.0 2.38 12.0190 1495.9 1.88 0.0015
expected voltage rise at bus “A” is 0.7 kV, and the final
2000 1956.9 2.91 16.1828 1982.1 2.36 0.0017
frequency after power shedding is 50.04 Hz.

Authorized licensed use limited to: Universiti Malaysia Perlis. Downloaded on May 06,2021 at 07:30:54 UTC from IEEE Xplore. Restrictions apply.
c) Simultaneous violation on both corridors IV. CONCLUSION
Fig. 15 shows that the power flow through the northern The loadability of the transmission lines has been obtained
corridor is 3620.5 MW and exceeds its loadability by 294.9 by processing the PMU data. Then, an adaptive remedial
MW. Meantime, the power transfer in the southern corridor is action scheme (RAS) has been proposed to maintain the power
2353.3 MW (i.e. overload by 371.7 MW). The expected transfer within the obtained limit. The greedy algorithm is
frequency after load shedding caused by overload in the north used to perform the optimization in the proposed adaptive
corridor is fexpect-1 = 50.15 – 294.9⁄919.8 = 50.47 Hz . The RAS. While its result is not as good as that of the dynamic
expected frequency after load shedding to secure the southern programming, the greedy algorithm is faster and more stable
corridor from overload is calculated by considering the value in terms of processing time. Using the proposed method, the
proper amount of load and generation shedding to prevent the
of fexpect-1 as the actual frequency. Thus, fexpect-2 = 50.47 –
instability caused by the overloading of transmission lines
371.7⁄919.8 = 50.87 Hz. To maintain the transmission lines could be effectively determined, while maintaining the system
in safe operation and the frequency within a normal range, frequency within normal limits.
simultaneous LS and GR are required since the expected
frequency after load shedding is 50.87 Hz, higher than 50.5 REFERENCES
Hz. The actual LS in the north and south corridor is 326.5 MW [1] D. Lauria, F. Mottola, and S. Quaia, “Analytical description of
and 245.2 MW, respectively. Meanwhile, the actual GR is overhead transmission lines loadability,” Energies, vol. 12, no. 16,
590.0 MW. The targets are three power plants in the eastern 2019, doi: 10.3390/en12163119.
region. The final frequency is 50.13 HZ, within a normal [2] A. Polevoy, “Impact of Data Errors on Sag Calculation Accuracy for
range, as expected. Overhead Transmission Line,” IEEE Trans. Power Deliv., vol. 29, no.
5, pp. 2040–2045, Oct. 2014, doi: 10.1109/TPWRD.2014.2325862.
[3] X. Jiao and Y. Liao, “A linear estimator for transmission line
parameters based on distributed parameter line model,” in 2017 IEEE
Power and Energy Conference at Illinois (PECI), Feb. 2017, pp. 1–8,
doi: 10.1109/PECI.2017.7935724.
V = 495.2
P = 3602.1 [4] Y. Zhang, M. E. Raoufat, and K. Tomsovic, “Remedial Action
Schemes and Defense Systems,” Smart Grid Handb., no. August, pp.
1–10, 2016, doi: 10.1002/9781118755471.sgd032.
[5] A. Z. M. Zamani, N. S. N. Yusuf, M. K. N. M. Sarmin, S. K. S.
Abdullah, and A. A. Rahim, “Adaptive load shedding scheme for
transmission line overloading problem in TNB,” 2014 IEEE Innov.
Smart Grid Technol. - Asia, ISGT ASIA 2014, pp. 227–231, 2014, doi:
10.1109/ISGT-Asia.2014.6873794.
[6] Y. Chai and H. Zhang, “Load shedding considering transient security
and overload constraints,” Asia-Pacific Power Energy Eng. Conf.
APPEEC, vol. 2016-Decem, no. 1, pp. 1995–1999, 2016, doi:
Fig. 13. Load shedding triggered by north corridor violation 10.1109/APPEEC.2016.7779873.
[7] J. C. Cepeda, D. Ramirez, and D. G. Colome, “Real-time adaptive load
shedding based on probabilistic overload estimation,” 2014 IEEE PES
Transm. Distrib. Conf. Expo. PES T D-LA 2014 - Conf. Proc., vol.
2014-Octob, 2014, doi: 10.1109/TDC-LA.2014.6955190.
V = 498.1
[8] P. S. Kundur, “Power system dynamics and stability,” in Power System
P = 4370.6 Stability and Control, Third Edition, 2017.
[9] R. D. Dunlop, R. Gutman, and P. P. Marchenko, “Analytical
development of loadability characteristics for EHV and UHV
transmission lines,” IEEE Trans. Power Appar. Syst., vol. PAS-98, no.
2, 1979, doi: 10.1109/TPAS.1979.319410.
[10] J. Hao and W. Xu, “Extended transmission line loadability curve by
including voltage stability constrains,” 2008 IEEE Electr. Power
Energy Conf. - Energy Innov., vol. 2, no. 4, pp. 1–5, 2008, doi:
10.1109/EPC.2008.4763379.
[11] D. Shi, D. J. Tylavsky, K. M. Koellner, N. Logic, and D. E. Wheeler,
“Transmission line parameter identification using PMU
Fig. 14. Load shedding and generation rejection triggered measurements,” Eur. Trans. Electr. Power, vol. 21, no. 4, pp. 1574–
1588, 2011, doi: 10.1002/etep.522.
[12] P. W. Sauer, “Technical challenges of computing available transfer
capability (ATC) in electric power systems,” Proc. Hawaii Int. Conf.
Syst. Sci., vol. 5, no. 2, pp. 589–593, 1997, doi:
10.1109/HICSS.1997.663220.
V = 495.1
P = 3620.5 [13] T. H. Cormen, C. E. Leiserson, R. L. Rivest, and C. Stein, Introduction
to Algorithms, Third Edit. The MIT Press, 2009.
[14] O. Banias, “Dynamic programming optimization algorithm applied in
test case selection,” in 2018 International Symposium on Electronics
and Telecommunications (ISETC), Nov. 2018, pp. 1–4, doi:
10.1109/ISETC.2018.8583984.
[15] A. Khutoretskii and S. Bredikhin, “A Greedy Algorithm for Jobs
V = 495.1 Allocation in a Multiprocessor System,” in 2019 15th International
P = 2353.3
Asian School-Seminar Optimization Problems of Complex Systems
(OPCS), Aug. 2019, pp. 82–85, doi: 10.1109/OPCS.2019.8880192.

Fig. 15. Power transfer violation at both north and south corridor

Authorized licensed use limited to: Universiti Malaysia Perlis. Downloaded on May 06,2021 at 07:30:54 UTC from IEEE Xplore. Restrictions apply.

You might also like