You are on page 1of 2

Decommissioning & Environmental Remediation

Decommissioning and environmental


remediation: an overview
By Irena Chatzis
Environmental remediation, on the other
hand, is concerned with reducing existing
radiation exposure from land, soil and
groundwater contamination that results from
past activities involving the use of radioactive
material for civil or military purposes (see
box, next page).

Oversight to ensure safety


The objective in both decommissioning and
environmental remediation is to lower levels
of residual radioactivity enough that the
sites may be used for any purpose, without
restriction. In some cases, however, this
may not be practical and restrictions may
be placed on future land use. Following
decommissioning, for example, some sites
may be reused for non-nuclear industrial
activities, but not for habitation. Some former
uranium mining sites may be released for
Decommissioning staff cutting
down a piece of large metal
equipment at a nuclear facility.
N uclear decommissioning and
environmental remediation share a
common objective: to reduce radiation
reuse as nature reserves or for other leisure
activities.

(Photo: Sellafield Ltd./UK) exposure to people and the environment Both decommissioning and environmental
at sites where radioactivity levels require remediation are major industrial projects in
restrictions in their use. which the safety of the workforce, the local
public and the environment must be ensured
Decommissioning is a planned activity at the from both radiological and conventional
end of life of facilities that have a regulatory hazards. Hence, an appropriate legal and
licence to conduct nuclear or nuclear- regulatory framework, as well as proper
related activities. It is concerned with all training for personnel both in implementation
the activities needed to remove them from and in regulatory oversight are among the
regulatory control and thus release the site for necessary preconditions to ensure safety.
other uses (see box).

Decommissioning
Decommissioning is a normal part of the Both the decommissioning plan and the cost
lifecycle of almost all industrial facilities. estimate will evolve during the lifetime of
When the facility no longer serves a useful the plant and will become progressively more
social or economic purpose, it needs to be detailed toward the end of the plant life.
dismantled and the site made available for
other uses. However, such plans do not exist for
several facilities constructed in the early
Requirements for decommissioning should days of the nuclear industry. In the case
be considered during design and planning of these older plants, there may also
of facilities. The decommissioning plan and be a lack of comprehensive records of
associated cost estimates need to be prepared the plant configuration and detailed
in advance, to ensure that sufficient financial accounts of the operational history. Such
resources are available. situations add additional complexity to the
decommissioning process.

4 | IAEA Bulletin, April 2016


Decommissioning & Environmental Remediation

Radioactive waste management Funding


A well-coordinated system for managing Sufficient funding is a key factor in
the wastes that arise from decommissioning decommissioning and environmental
or environmental remediation is another remediation projects, which are generally
important requirement. Decommissioning very expensive. A significant proportion
generally results in the production of large of sites requiring decommissioning
amounts of material with low levels of or remediation are state-owned and
radioactivity. Depending on the material implementation costs are paid from national
and on national regulations, a large part budgets. Often, the amount of funds allocated
of the waste may be disposed of in near to environmental cleanup activities depends Application of a combined
surface disposal facilities compliant with on the priorities of the government. scheme for covering and
international safety standards for permanent draining uranium mill tailings.
disposal. Such facilities already exist in For commercial power plants, funding (Photo: Wismut GmbH/Germany)
several countries; for others the waste decommissioning is generally the
material has to be held in temporary storage responsibility of the plant’s owner. The
until a long-term solution is identified. funding is usually either invested in a special
fund dedicated to cover decommissioning
The amount of radioactive waste involved costs or, in the case of some large utilities,
can be reduced significantly through are provided directly from the company’s
decontamination of the plant systems prior operational revenues and cash flow.
to their dismantling. Some countries also
have facilities for recycling scrap metal,
e.g. by melting. Waste with higher levels of Current status
radioactivity or long lived components will Although some countries have achieved
generally have to be placed in repositories substantial progress, many are facing
located deep underground. significant difficulties in implementing
their decommissioning and environmental
For environmental remediation, the quantities remediation programmes.
of waste material involved can be much larger
if, for example, soil needs to be removed Having plans in place for managing the entire
and subsequently disposed of as waste. lifecycle of nuclear facilities is nowadays a
Opportunities for volume reduction also exist universal requirement for commencing new
in this case, for example by separating soil projects.
components with higher contamination levels
from those with lower levels.

Environmental remediation
Environmental remediation aims to reduce There are four major elements that need to be
radiation exposure from contaminated soil, considered in environmental remediation:
waste storage facilities or other contaminated
infrastructure, groundwater or surface water. 1. The levels of radiation exposure to people that
Its purpose is to protect the people and the result from the contamination.
environment from potential harmful effects due
to exposure to ionizing radiation. This may result 2. Reducing radiation doses and risks, making
from activities such as the mining and processing best use of the available financial, technical and
of uranium or the release of radioactive substances labour resources.
to the environment after a nuclear or radiological
accident. 3. Returning a site to the conditions before the
event that caused the contamination may not
The generation of radioactive materials may also be necessary, and is often not easily achievable
be a result of non-nuclear industries, such as oil anyway.
and gas production, in which exploration and
mining activities can increase the potential for 4. In many cases, the main driver for remediation
exposure from naturally occurring radioactive is the public perception of the risks and benefits
material. of undertaking the cleanup activity. In such
situations, the overall well-being of the local
community is an important factor in determining
the planned final state of the site.

IAEA Bulletin, April 2016 | 5

You might also like