You are on page 1of 7

PAPER 2008-339

All Metal PCP Field Trial Update


A. DAMNJANOVIC, S. JAHN, G. MITSKOPOULOS, L. SEINCE
Kudu Industries, PCM

This paper has been selected for presentation and publication in the Proceedings for the World Heavy Oil Congress 2008.
All papers selected will become the property of WHOC. The right to publish is retained by the WHOC’s Publications Committee.
The authors agree to assign the right to publish the above-titled paper to WHOC, who have conveyed non-exclusive right to the
Petroleum Society to publish, if it is selected.

1
Abstract The process proved to be the most cost effective and had the
best quality control and tolerances. Figure 2 illustrates the final
With unprecedented global growth and the consumption of shape of the hydro-formed stator inside the External housing.
oil, significant emphasis is placed on heavy oil and bitumen
production in meeting this growing demand. Among the
artificial lift technologies available to produce heavy oil, the External housing Hydro-formed stator
Progressing Cavity Pump has proven to be the most accepted
method in terms of its ability to handle solids, viscosity range,
pump efficiency and operating cost.

With the addition of thermal recovery processes such as


Steam Assisted Gravity Drainage (SAGD) and Cyclic Steam
Stimulation (CSS), enhanced production of extra heavy oil is
possible. However, the standard elastomer technology has an
operating temperature limit of around 160oC, far below thermal
production requirements. A new technology called the PCM
Vulcain™ is based on a completely metallic pump and pushes
the temperature limit to 350°C. Furthermore, a high
temperature surface seal has been designed to operate at these Figure 2.
elevated temperatures. Since 2005, the PCM Vulcain™ has
been tested successfully in several field trials throughout Two prototypes were tested at TOTAL’s research facility
northern Alberta (Cold Lake and Athabasca). (CERT) in Gonfreville, France. The results of this testing were
presented in a SPE paper (SPE 97796). The results confirmed
This paper will discuss the completion configuration for the strength of the pump, hydraulic performance, differential
both downhole and surface equipment along with results and pressures, RPM and ability to handle a wide range of
benefits attained from the field trials. The intent is to launch this viscosities. As with an elastomer pump, the efficiency of the all
new technology from pilot to commercialization in early 2008. metal PCP increases with RPM.

The next step was to incorporate an environmentally


Introduction friendly high temperature seal capable of handling the high
injection and producing temperatures in CSS wells along with
The key requirement to producing thermal recover wells is a the conventional lower pressure high temperature SAGD wells.
flexible and efficient artificial lift system. Given the huge After the seal was designed it needed to be laboratory tested
success of the elastomer Progressing Cavity Pumps (PCP) in before being installed in the field. The environmentally friendly
conventional heavy oil applications it was obvious this positive high temperature seal was designed and then independently
displacement pump was a very good fit for thermal recovery. tested to 315°C. The original design called for a cooling loop
However, with temperature being a limiting factor for the with a hydraulic cooler, which was required to help dissipate
elastomer, an alternative was required. PCM started the the high temperature. After field testing the loop was removed
development of the all metal PCP in the mid 1990’s. The first as it was not required because of the heat dissipation between
pump had excellent hydraulic characteristics and the theory of the drivehead connection and the high temperature seals. The
an all metal PCP was proven as a potential solution. Several seal is called the High Temperature Oryx Seal and to date has
manufacturing techniques were tried for an efficient and cost proven to be extremely reliable.
effective means of manufacturing the all metal PCP. PCM
developed a hydro-forming process used to manufacture the
internal stator sleeve. PCM currently has two patents pertaining
to the all Metal PCP with another pending:
1. A patent for the use of an all metallic PCP in oilwells
up to 300°C.
2. A patent for the hydro-forming manufacturing
process. Figure 1.

The name for the all metal PCP is the PCM Vulcain™.
Figure 1. External envelope containing
pressurized fluid

Die

Figure 3 Oryx Seal

2
With the pump proven and an environmentally friendly temperature and pressure. The pilot was to prove operation,
sealing solution found, it was time to begin field trails. Field performance and maintenance baseline on a first cycle well
trials would enable a better understanding of the practical limits candidate.
in a producing environment and how an all metal PCP
completion needs to differ from a conventional elastomer PCP
installation. Case One
This case was the first CSS project for the all metal pump.
The environment in the CSS application is as follows:
Principles of Operation • Vertical wellhead to horizontal production zone
• Initial high pressure
PCP’s are positive displacement pumps, which consist of a • High fluid temperature / low viscosity
stator and a rotor. The elastomer PCP is described as a gear • High free gas and potential for steam flashing
pump with a single helical rotor, which rotates inside a double
internal helical elastomer lined stator. The installation used:
The all metal PCP is constructed of three hydro-formed • 8 5/8” production casing
stator tubes. These tubes then have flanges welded to them, and • 4 1/2” tubing
the flanges are connected to the outer housing. Figure 4 • 25.4 mm Corod
illustrates the internal profile of the stator with a rotor cross • 550MET750 pump
section. • VH100HP drivehead
• High Temperature Oryx Seal
• 100HP EXP electric motor
• Pump setting depth of 640 m MD
• Pump inclination 80°
• No Anchor or Antivibration Sub (AVS)

The first pump installed in November 2005 was put on steam


and allowed to flowback until January. The pump was
started in the middle of January 2006 at 200 RPM and
gradually increased to 300 RPM by the end of the month.
After 1600 hours of run time the rotor was inspected and
measured. Minor wear was observed and even though the
Figure 4 All metal Pump internals rotor still met dimensional specifications, a new rotor was
installed. The pump continued to run until the end of cycle
There are currently two versions of the pumps operational at one, with a run time of approximately 2300 hours.
the current time. Production volumetric efficiency was calculated to be around
• Version 1 (V1) and 70% during the length of the cycle.
• Version 2 (V2) has addition internal flanges used
to distribute the applied torque and deflection of Cycle two began steaming in May 2006 to November 2006.
the stator tubes. Version 2 became operational in The pump restarted and went through the second production
early September 2007 and to date there are no cycle with no down time due to the pump or drivehead.
failures. The pump ran at:
≥ 200 RPM for 99% of the time
Nomenclature for pump models. ≥ 300 RPM for 89% of the time
≥ 400 RPM 45% of the time
550MET750
550 is the flow rate at 500 RPM and 0 head The results above are worth noting as vibration testing has
MET is for all metal PCP shown the pump runs with less vibration at higher RPM.
750 meters lift of water column
The pump efficiency over cycle two dropped to as
Refer to the Appendix for the Pump Model chart. low as 50% and as high as 70%. A flow meter was installed
on this well, but was non-operational for most of the pump’s
life. Production numbers were inferred from group
Developmental Testing production and a periodic test to a rig tank was performed
when fluid conditions were appropriate. The pump never ran
PCM conducted extensive testing in France on a loop before in “cool bitumen” environment so the expected efficiency
proceeding with field trials in North America. A Joint Industry increase with higher viscosity was not realized. The stator
Project (JIP) “laboratory testing of Artificial Lift System for failed after approximately 5000 hours of run time, shortly
low Pressure SAGD” was conducted at the Centre for after the beginning of the third pumping cycle. The failure
Frontiering Engineering Research (CFER) in 2005. The results was attributed to a combination of torque and vibration near
of testing are confidential to the JIP participants. the flanges. We suspect one of the stator tubes broke near the
flanges and was allowed to spin freely for a length of time
In 2005, an operator created an initiative to trial other forms causing the tube to break apart into ¾” diameter pieces.
of artificial lift. The results of the JIP inspired our first field
trials in CSS wells at Cold Lake. The first pump was installed in This first pilot well proved the technology worked
November 2005. The criteria included that the pump would well using essentially a standard PCP configuration. The
remain downhole during steaming and flowback. The successes of this first well trial lead to a six well test
equipment also had to operate over a wide range of production, expansion. These six pumps ran in virtually the same

3
downhole conditions as the first trial pump. Of these six footprint, ease of installation, lower capital and operating cost
pumps, two failed prematurely. These failures are attributed accounted as additional benefits. After only 24 hours of a break
to a combination of vibration and torque near the welded- in period the pump ran at 500 RPM. The pump ran at very low
flanged connections. It is important to note that the failures torque for the first two weeks. The reservoir pressure was high
occurred away from the heat affected zone created during enough that the pump was driving the rod string. The pump
welding. The other four pumps ran well with a presumed efficiency started at 90% and dropped down to 80% and leveled
efficiency of 65% but were pulled before the next steam off when the pump was in or near a pump off condition. The
cycle, as to not risk future production. pad had a power bump 45 days into the production cycle. The
well was restarted with a quick ramp up time back to 500 RPM.
Lessons learned in this first application are: The rapid change on downhole pressure caused a sand bridge to
• The internal component in the first pump failed break and enter the pump in high concentrations. The pump
and broke into small metal pieces. It was inspected in is good structural condition with the exception of
recognized that the intake was required to work as excessive wear. During evaluation of the stator large amounts of
a “junk basket” to prevent any pieces of the pump sand were noticed, which was due a large influx of sand. The
from contaminating the wellbore after a failure. efficiency dropped and the torque increased during this time.
• Explosion Proof Electric motors can become
contaminated with moisture from the CSS Lessons learned from this application are:
application. • Differential pressure across the pump is required to
• Additional internal components. prevent 3 things;
• The temperate at the High Temperature Oryx Seal o Keep the rod string in tension.
was low enough that the cooling loop could be o Keep the pump from driving the rod
removed. string.
• An additional secondary final rope packing seal to o Keep steam from flashing in the tubing.
the polished rod was added to the High • Increase the ramp up time after a shutdown to be
Temperature Oryx Seal. more representative of a sandy well application.
• Run a slotted intake on the pump with the same
slot sizes as the liner to break up any large sand
slugs, initial design was for ten times the open
flow area for a 3 1/2” tubing joint.

Case Three
The first SAGD project for the all metal pump was at
Athabasca Oilsands area. The operator is very experienced
using PCP’s in other areas internationally. They were searching
for an artificial lift method that didn’t have the production
limitations of Beam Pump or the temperature and viscosity
restrictions of an Electric Submersible Pump (ESP). The
operator was also looking for increased production at low
operating and capital costs along with less complex well
completions.

The environment differed from the CSS applications in the


follow areas:
• Slant well
• Shallow depth
Figure 5 all metal PCP in CSS application • Low pressure
• Cooler bitumen temperature; high viscosity
Case Two • Less free gas and potential for flashing
Our second CCS installation was in the Cold Lake Oilsands
area as well. The downhole configuration was the same as the
Pilot well. The installation used:
• 7” production casing inside 11 3/4” casing
The installation used: • 4 1/2” tubing
• 9 5/8” casing • 1.90” Tenaris Hollow Rod
• 4 ½” tubing • 3 1/2” tubing and 8.5DR Continuous Rod was used
• 25.4 mm Corod when Hollow Rod was unavailable.
• 550MET750 pump • 550MET750 pump
• VH100HP drivehead • VH100HP drivehead
• High Temerpature Oryx Seal • High Temperature Oryx Seal
• 100HP Exp electric motor • 60HP Exp electric motor
• Pump setting depth of 630 m MD • High Temperature Oryx Seal
• Pump inclination 88° • Pump setting depth of 327 m MD
• No Anchor or Antivibration Sub (AVS) • Pump inclination 86°
• Kudu Cam Loc Torque Anchor
The main goal of this trail was to compare the initial
production increase versus the 1280 pump jacks and The first pump, which was a 550 MET 750 lasted for 387
incremental overall production between steam cycles. Smaller days (approximately 8700 hours). The pump efficiency started

4
at 55% and dropped the 35% over the run life of the pump. The Two pumps were installed in late October 2007. High
average RPM over this period was 320 RPM. Low efficiency bottom hole pressure caused the pump to turn the rod string.
was the reason for pulling this pump and was found to have no Low flowline pressure allowed for some steam flashing. Steam
mechanical failure. The longest running 400 MET 1000 lasted flashing pushed a slug of water and bitumen up the tubing
for 333 days, with efficiency ranging from 70% to roughly causing a quick RPM increase in the pumping system. The
45%. The reason for failure is currently being investigated. inline choke on the tubing was used to increase the back
This pump had approximately 7300 hours of run time. pressure on the well increasing the differential pressure on the
pump. This action eliminated the drive from the reservoir,
There are currently four V1 pumps operating with the turning of the rod string and eradicated compression in the
longest run time being approximately 6600 hours with an sucker rod string. At the time of this paper operational
efficiency of 40%. The first six V2 pumps are still currently requirements and performance were being evaluated.
operating with the longest run time of approximately 3000
hours and an efficiency of 45%. Lessons learned in this application are:
• Differential pressure requirement as in Case
These applications used Hollow rod where as our other two.
applications used Continuous Sucker Rod. The main advantage
with the hollow rod is the string can be pulled using the service Case Five
rig reducing downtime and added rig expense. An additional Our third SAGD application was in the Athasbasca Oilsands
advantage was reduced rod wrap due to the stiff nature of the area. The operator was seeking an artificial lift method that
rod string. Three of the wells with hollow rod have been didn’t have the production limitations of Gas Lift. Secondly,
inspected and have shown no significant signs if wear. they also wanted lower capital, operation and repair costs.
Therefore, the rod tubing wear characteristics are estimated to
be similar to continuous sucker rod. The SAGD application was as follows:
• Slant wellhead
• Shallow depth
• Low pressure
• Less free gas and potential for flashing

The installation used:


• 11 3/4” production casing inside
• 4 1/2” tubing
• 28.6 mm PROROD
• 1100MET500 pump
• VH100HP electric drivehead
• 100HP EXP motor
• 100 HP VFD
• Pump setting depth of 312 m MD
• Pump inclination 86°
• No Anchor or Antivibration Sub AVS

Figure 6 all metal PCP in SAGD application The pump was installed in November; however, at the time
of this paper the equipment was not running due to work at the
Case Four facilities.
Our second SAGD application was in the Cold Lake
Oilsands area. The operator has an artificial lift history deeply Summary
rooted in PCP’s. They were looking for an artificial lift method
to replace the gas lift currently installed in the field. The Efficiency
operator wanted increased production at low operating and
capital costs. The volumetric pump efficiency on start up typically is in
the 70% to 90% range. This number will change based on the
The SAGD application was as follows: water cut, bitumen temperature (viscosity), pump differential
• Vertical wellhead pressure and pump RPM. Over the life of the pump the
• Medium depth volumetric efficiency has dropped as low as 35%. Typically a
• High pressure small increase in RPM will improve the pump efficiency.
• Less free gas and potential for flashing Manufacturing and quality control improvements have been
improving the pump efficiency on new pump models. PCM has
The installation used: defined a new standard for pump efficiency and start up torque.
• 11 3/4” production casing inside
• 5 1/2” tubing
• 1.90” Tenaris Hollow Rod
• 550MET750 pump
• VH100HP hydraulic drivehead
• 5.7 GM hydraulic walk-in enclosure
• Pump setting depth of 529 m MD
• Pump inclination 72°
• No Anchor or Antivibration Sub AVS
• Additional Tail Joint

5
Test Bench Results V1 versus V2 Gas Lock

Speed Pressure Volumetric Pump Efficiency The PCP will not gas lock but free gas will take up space in
the pump cavity reducing pump efficiency. Bench testing was
RPM kPa V1 V2 conducted during the initial TOTAL testing in France. The loop
100 3000 27% 55% was taken up to 200°C and steam was injected at the pump
200 6000 60% 75% intake. A variety of differential pressures across the pump
where used to test the pump behavior during steam flashing.
300 6200 76% 85% For all practical purposes the pump did not show any vibration
400 6200 85% 90% increases, torque spikes or unusual occurrences.
500 6200 89% 93%
Capital Costs
The above test is from a 550MET750 with the same stator
and rotor before and after adding additional internal Capital costs have not been defined as the project is still in
components. The test fluid was oily water with a viscosity of pilot phase. Version One (V1) lasted one year so measurable
8cp at 20°C. 200, 300, 400, 500 RPM tests at 82% of rated field cycle life performance increase on Version Two (V2) will
head pressure. not be realized for another year. However, efficiency and torque
Note: Viscosity will affect the sealing between the rotor and improvements have already been realized.
stator. The higher the viscosity the better the seal; therefore, the
efficiency maybe higher at the low RPM depending on reservoir Installation Complexity
temperature and water cut combined viscosity.
The installation complexity of the all metal PCP is no
Temperature different than the tens of thousands if PCP’s already running in
Canada. One potential problem in the future may be the limited
The pump, while downhole was in temperatures up to bored size in the wellhead for the pump to run through. This
330°C. Start up and operation has been as high as 185°C in the limitation reduces the amount of available No Turn Tool or
CSS wells and as low as 65°C on the low pressure SAGD. Antivibration subs available for vibration dampening.
Currently the pump temperature rating is set at 350°C. The
technical limit is above our current rating of 350°C. Further Operating Complexity
practical field testing is required before increasing our set
temperature. The operating complexity of the all metal PCP is once again
not much different than the tens of thousands of PCP’s running
Operating Range RPM in Canada. Simple standard practices should be followed.
• Sufficient fluid inflow to the pump intake.
The typical operating range has been between 80 and 500 • Minimal amount of gas produced through the
RPM. A 400 RPM limit has been imposed based on the direct pump.
relationship of higher cycles = higher wear. Testing has proven • Minimal amount of sand production produced
that the pump has less vibration at higher RPM so there will be through the pump.
future testing to define this relationship.
RPM equals production leading to extremely easy well
Production Ratio control. It is able to handle viscous fluids so cold temperature
(high viscosity) low pressure start ups are possible.
The production ratio or turn down ratio is the relationship
between volumetric efficiency and RPM. The current practical Abrasion
limit is based on 100 to 400 RPM pump speed with an
efficiency range of 40% at 100 RPM and 80% at 400 RPM. To date abrasion resistance has been hard to gauge.
Therefore; the production ratio of 8:1 has been established as a Sediment testing on some fluid samples have shown only trace
rule of thumb. amounts of sand. Other sieve samples from producing wells
See note on viscosity in Test Bench Results V1 versus V2. have shown a higher percentage of sand particles, larger than
the liner slots, which is a clear indication of a liner hanger
Net Positive Suction Head (NPSH) problem or a more severe casing problem. To date only one
well has what we can characterize as an abrasion failure. At the
The Net Positive Suction Head required for PCP is very time of writing this paper a cut off for sand production has not
low. The required pressure at the pump intake is only what is been defined; however, in the future sand screens are
required to push fluid into the first empty cavity before the rotor recommended to break up large slugs of sand.
makes a rotation. If the pressure is too low the cavity will not be
full of fluid before the rotor swipes the cavity clean causing It is important to note that the Case One CSS application
pump cavitations. The benefit of low pressure start up is cooler used a bare rotor and a coated stator and the Case Three SAGD
temperature, which reduces the amount of steaming required application used a chrome rotor and coated stator. PCM’s third
before the well can be started. The quicker the producer can go generation of coatings, application, consistency and tolerances
on production the faster the steam chamber can expand in a has greatly increased over the last 18 months.
SAGD application. In the CSS applications producing longer
into a cycle will increase the oil recovery rate before the costly
steam cycle has to start again

6
Vibration Modeling
The pump has been installed in several different well bore,
The all metal pump cannot absorb and dissipate vibration bottomhole assembly and surface configurations in a wide range
and harmonics as well as an elastomer PCP. Vibration modeling of production and operating conditions. Future field pilots,
and bench testing is on going but we can make some bench, facility and laboratory testing will take the project into
conclusions. commercialization later this year.

Testing was conducted with the stator inside 9 5/8” casing NOMENCLATURE
with 2 joints of 4 1/2” tubing above the stator. Accelerometers
were attached at the pump discharge and on the drivehead. The DLS = Dog Leg Severity
pump ran at 100 to 400 RPM with 50 RPM increments across ESP = Electric Submersible Pump
differential pressures of 0, 2,500, 5,000, 6,600 kPa (6,600 kPa RPM = Revolutions Per Minute
limit was imposed by the pressure sensor, which is 88% of the MD = Measured Depth
full head rating for this pump). CSS = Cyclic Steam Stimulation
The early conclusions from the testing are: SAGD = Steam Assisted Gravity Drainage
• The pumps run smoother at 350 + RPM. PCP = Progressing Cavity Pump
• Running the stator with a No Turn Tool or NPSH = Net Positive Suction Head
Antivibration sub at the bottom of the pump VFD = Variable Speed Drive
assembly reduces the vibration.
• Running the stator without a No Turn Tool or REFERENCES
Antivbration sub was second best.
• Running the stator with a No Turn Tool or 1. J.L Beauquin, F.Ndinemenu, TOTAL E/P,
Antivibration sub at the discharge with and G.Chaler,TOTAL E/P CANADA, L. Lemay,
without a No Turn Tool or Antivibration sub had L.Seince,PCM, A Damnjanovic KUDU INDUSTRIES,
the highest pump vibration. World’s First Metal PCP SAGD Field Test Shows
Promising Artifical Lift Technology For Heavy Oil Hot
Well Profile Production: Josyln Field Case, SPE Paper 110749

• The maximum DLS above the pump setting depth 2. Development status of a Metal Progressing Cavity Pump for
was 14.2° DLS 30 m. heavy oil and hot production wells (JL.Beauquin, C.Boireau,
• The typical DLS in conventional sucker rod TOTAL; L.Lemay, L.Seince, PCM), a SPE 97796 paper presented
pumped PCP wells is below 10° DLS / 30 m. at the 2005 SPE International Thermal Operations and Heavy Oil
• The pumps have been installed primarily in the Symposium held in Calgary, Alberta, Canada, 1–3 November
deviated section with an inclination of 70° to 89°. 2005
• The average DLS in the tangent section for the
pump has been approximately 5° DLS over the
pump length. Appendix
• The recommended tangent section length is 30
meters above the pump discharge before hitting a
DLS high enough to cause bending in the tubing PCM VULCAIN Pump Models
string.
1600
3 1/2" NU - 150 MET 1500
Note: Casing and tubing size dictate the maximum DLS 1400
4" NU - 400 MET 1000
Pu m p h ead (m W C )

allowed before the pump will have bending stress. 1200


4" NU - 550 MET 750
1000 4 1/2" EUE - 1100 MET 500
800
Surface Equipment 600
400
Segmented Polished Rod – The all metal PCP is often 200
installed before the steam cycle in a CSS well. This procedure 0

requires the rotor to be lifted out of the stator, which creates 0 200 400 600 800 1000 1200

approximately 30 feet of polished rod stick up. Steam can then Pump capcity (m3/d)

be sent down the tubing and casing. The polished rod is then
secured by a structure or supported by ropes. A segmented
polished rod will allow for less obtrusive installation as a
minimal length would be sticking above the drivehead during
steaming and flowback.

Conclusion
The PCM Vulcain™ field trials have proven the all metal
PCP to be a viable artificial lift alternative with distinct
advantages. One operator has proceeded to switch all the
production completions to PCP’s. The pumps have been
installed primarily in the deviated section with an inclination of
70° to 89 °. The average DLS in the tangent section for the
pump has been approximately 5° DLS over the pump length.
The temperature range has been between 65°C and 330°C.

You might also like