Professional Documents
Culture Documents
0 INSTALLATION
- 27 -
3.0 INSTALLATION
SERVICE
SERVICE CLEARANCE OF CONTROL BOX
CLEARANCE
1219 [48"] SERVICE CLEARANCE
OF
OF 1524 [60]
610 [24"]
SERVICE CLEARANCE OF
1219 [48"]
- 28 -
3.0 INSTALLATION
CG
Multi Pit
CG CG
Notes:
1.) All dimensions are minimal, unless otherwise noted.
2.) Pit installations are not re-commended. Re-circulation of hot
CG
condenser air in combination with surface air turbulence cannot
be predicted. Hot air re-circulation will severely affect unit
efficiency (EER) and can cause high pressure or fan motor
temperature trips. Dunham-Bush will not be responsible for
ducting fans to a higher level to alleviate the above mentioned
conditions.
- 29 -
3.0 INSTALLATION
(For spring isolator models DHB only)
3.8 UNIT ISOLATION
4. Align mounting hole of the chiller base with the
In case of structure-borne vibration may be of concern, leveling screw bolt hole of the upper housing of the
it is recommended to install vibration isolators under spring isolators.
the base of the Packaged Chiller. 5. Pass through leveling screw bolt & turn Clock-Wise
Rubber-in-shear or spring vibration isolators are offered (CW) to load spring until desired level (FH & OH) is
as optional items. When spring isolators are used, achieved. Leave the locking nut loose for moment.
flexible connections must be installed in the water 6. After completing level adjustment of all spring
piping system and in the refrigerant lines if it is a split isolators, lock the locking nut of the spring isolators
system. tight (CW).
Note: These flexible connectors must be suitable 7. Bolt down the spring isolators to the floor.
for the fluid and pressures involved.
All piping which is external to the chiller must be (For spring isolator models YRS only)
supported by spring mounted hangers and any piping 4. Align mounting hole of the chiller base with the
which goes through the wall, ceiling or floor should be tapped hole of the upper housing of the spring
properly sheathed to prevent transmission of piping isolators.
vibration to the structure. 5. Adjust the leveling screw bolt until desired level (FH
When spring isolators are used, electrical service to the & OH) is achieved. Turn clock-wise (CW) to load
unit must also be connected by means of a 36" [914mm] spring or counter-clockwise (CCW) to unload spring.
section of flexible conduit. 6. After completing level adjustment of all spring
The installation of spring isolators shall follow the isolators, lock the tapped bolt tight (CW) to fix the
instructions as below: spring isolators to the chiller.
1. Place all the spring isolators in place on the 7. Bolt down the spring isolators to the floor.
foundation, according to the isolator models and
locations in the provided GA drawing. 3.9 NOISE CONSIDERATION
2. (For spring isolator models DHB only) Unscrew
Another consideration is the chiller must not be located
leveling screw bolt (assembled with spring isolator)
near noise sensitive spaces. The chiller must have
by turning counter-clockwise, (CCW) from the spring
adequate support to avoid vibration and noise
isolator.
transmission into the building. Chiller could be mounted
3. Lift up the chiller as per the instructions in Section 3.4 over corridors, utility areas, rest rooms or other auxiliary
Rigging, and position the chiller on top of the upper areas where sound level is not an important factor.
housing of the spring isolators. Sound and Structural consultants should be consulted
for critical installations
Refer to section 2.4.4 for unit sound pressure data.
- 30 -