You are on page 1of 9

Oil Wells Cement

SPPC, SPE
INTRODUCTION: centralisation should be obtained by control considerations may dictate the
Cementing an oil or gas well comprises running a centralisation program. use of a weighted spacer. In such cases,
the displacement of cement slurry down the use of a thin wash pumped
the drillstring, tubing or casing to a A in combination with a weighted
predefined section of the annulus of the spacer may provide good mud
well. The cement slurry itself typically removal. When a turbulent
contains water, portland cement and wash, or spacer, is used a
various additives. The actual minimum contact time of 10
composition varies from application to minutes must be achieved. This
application. Cement is made from contact time should take
calcareous and argillaceous rocks such account of the effects of U-
as limestone, clay and shale and any tubing. Any spacer designed for
other material containing a high turbulent flow must be
percentage of calcium carbonate. The sufficiently viscous to suspend
dry material is finely ground and mixed the weighting agent . If
thoroughly in the correct turbulence across the complete
proportions.The chemical composition annulus cannot be achieved,
is determined and adjusted if necessary. weighted spacers in laminar
This mix is called the kiln feed. The kiln flow can provide effective mud
feed is then heated to temperatures of displacement. However, the
around 2600-2800 F (1427-1538 C). physics of such displacements
The resulting material is called clinker. are complex and the density,
The clinker is then cooled, ground and viscosity and annular flow rate
mixed with a controlled amount of minimum standoff of 70% is a good must be carefully designed taking into
gypsum and other products to form a rule-of-thumb to allow unhindered account the properties of the mud and
new product called Portland cement. circulation beneath the casing, when the cement slurry. For laminar
Gypsum (CaSO4. 2H2O) is added to mud rheology and displacement rates displacements, the ideal volume of
control the setting and hardening have been optimized. Centralizers spacer required can not be predicted and
properties of the cement slurry and to should be fastened to allow pipe minimum quoted volumes range from
prevent the flash setting cement. reciprocation, or rotation, in strings 300-1000 ft of annular fill. It is
The viscosity of the mud should be where casing movement is to be important to use a volume of spacer
reduced to the lowest practical level employed If washouts are expected, or sufficient to ensure separation of the
before the drillpipe is removed from the are known to have occurred, then the mud and cement when intermixing of
hole. Effort should be directed at number of centralizer required should be the three fluids is taken into account.
reducing the low shear-rate rheology of calculated to take the increased hole size Displacement rates should be
the mud (i.e. gel strengths and yield into account. It has been demonstrated maximised to obtain the most effective
points). However, care must be taken that good centralisation can reduce cement placement. Limiting
not to reduce the mud rheology below casing running difficulties by helping to displacement rates to those necessary to
the minimum level required to suspend prevent differential sticking. Whenever achieve turbulence is not sufficient, due
the weighting agent such as barite. possible the casing should be to the inadequacies of estimating the
Once the casing has been run, the mud reciprocated or rotated. Numerous onset of turbulence and the variable
should be further conditioned to remove laboratory and field studies have shown casing eccentricity. A useful guideline is
gelled mud which will have formed that pipe movement increases to ensure that the annular velocity
beneath the casing in areas of poor displacement efficiency by helping to (assuming concentric casing) is above
centralisation. Two to three hole break-up gelled pockets of mud. 260 ft/min. The bottom plug is first
volumes are normally considered Movement should be attempted for all released and is followed by cement.
sufficient conditioning - however, this is stages of the cementing operation - from When the bottom plug lands on the float
highly dependent hole conditioning to displacement. collar a pressure increase on surface is
upon the viscosity of the mud in the There is still a debate as whether casing indicated. A small increase in pressure
hole and the casing centralisation. reciprocation or casing movement will rupture the bottom plug and allow
If it has not been possible to reduce the provide the best displacement aid. cement to flow through it, through float
mud viscosity to the levels However, rotation does require special collar, shoe track, casing shoe and then
recommended above and casing equipment. For liners, rotation is around the casing. The top plug is
centralisation is poor, extended recommended – due to concerns over released from surface immediately after
conditioning may be required. After setting the liner and the increased the total volume of cement is pumped.
conditioning the hole, cementing should danger of swabbing gas during the The top plug is displaced by the drilling
start without any break in circulation. upstroke of reciprocation. fluid and it, in turn, pushes the cement
Good centralization is the most Optimal mud removal will be obtained slurry into the annulus. When the top
important factor in achieving efficient by the use of a simple wash, as this type plug lands on the bottom plug a pressure
mud displacement and cement of fluid will achieve turbulence around increase is observed at surface. This is
placement. The best possible casing the complete annulus at relatively low called bumping the plug.Bumping
annular velocities. However, well indicates that the total volume of cement
or gas migration problems. Stagnant 3. squeeze cementing,
areas form due to the distorted velocity 4. plug back cementing.
profile that occurs when the casing is
eccentric. Flow will favour the wide Functions of Cement
side of the annulus possibly leading to The functions of the different cement
the situation where turbulent and jobs differ according to the various
laminar flow exist in different areas objectives. The list below gives of some
across the annulus. Laboratory and field main objectives for the different cement
experience have shown that once the jobs.
stand-off falls below about 60%
Cement Powder
no practical combination of flowrate and Primary Cement functions:
is now displaced behind the casing.
fluid viscosity will remove the stagnant 1. Isolate a hydrocarbon bearing
Usually, at this time, the casing is
mud.The minimum stand off should be formation from other formations,
pressure tested to a precalculated design
at least 70%. To ensure that the stand- 2. Protect and secure the casing in the
value to check its integrity. Pressure
off is greater than 70% at all points well,
testing casing while the cement is still
along the string, a centralizer 3. Prevent caving of the hole,
wet is recommended as this reduces the
programme should be run. The 4. Provide a firm seal and anchor for the
chances of breaking the set cement or
programme should take into account the wellhead equipment,
creating micro-channels if the test is
mechanics of the complete casing string, 5. Protect casing from corrosion by
carried out a few hours later when the
along with any buoyancy and density sulfate rich formation waters
cement sets. shows the plugs
differential effects during displacement.
arrangement prior to being drilled out.
Numerous studies have shown that if the Liner Cement
Efficient mud displacement is essential
displacing fluid is in turbulent flow the 1. Case off open hole below a long
in order to achieve a good cement bond
displacement will be highly effective. intermediate casing,
and zonal isolation. Incomplete mud
However, in an eccentric annulus 2. Case off open hole resulting from
removal can lead to cement channelling,
ensuring turbulence occurs at all points casing stuck at the bottom,
allowing hydrocarbon invasion and
across the annulus is difficult. More 3. Case off previous open-hole
communication between permeable
often than not, the turbulent completion in order to control water, gas
zones. The force required to initiate
displacement will result in gelled mud or sand,
movement in a mud which has been left
remaining in the narrow section of the 4. Case off zones of lost circulation or
to gel can be considerable and will
annulus. Where turbulence for the high pressure zones encountered during
increase with time. The current
spacer/wash can be achieved, the drilling,
understanding of how best to mobilize
displacement rate should be as high as
gelled mud is poor, mainly due to the
possible to achieve the best results. Squeeze Cement functions
difficulties of characterising the gelation
Where turbulent flow cannot be 1. Reduce water-oil, water-gas, or gas-
properties of muds. The standard 10-
achieved it is still possible to achieve oil ratios,
minute gel-strength test is
effective displacements by using a 2. Shut off a zone that is been depleted,
unrepresentative of the complex effect
carefully designed laminar is not economical to produce or whose
of the shear-history of the mud and the
displacement. production will
prevailing downhole conditions. Gelled
Although the physics of mud removal be delayed until the more promising
mud can only be removed by applying
through casing movement is complex to zones in the same borehole are depleted,
sufficient shear stress to overcome the
analyse, the beneficial effects of 3. Isolate a zone before perforating for
gelled strength of the mud. This shear
reciprocating and rotating casing have production or stimulation,
stress can come from pipe movement or
been shown in laboratory and field tests. 4. Supplement a faulty primary cement
from the mobile mud (or other
Both reciprocation and rotation are job,
displacing fluids). In the latter case, the
beneficial, however, reciprocation 5. Repair casing or joint leaks, spit or
required shear stress is generated by
suffers the following drawbacks: parted casing,
frictional pressure drop. Thus, the shear
(a) Induced swab and surge pressures 6. Stop lost circulation in an open hole
stresses generated can be increased by
which can lead to well control problems, while drilling.
increasing the mud flow rate, or varying
especially Plug Back Cement
the properties of the mobile fluid.
with small annular clearances. 1.Shut off bottom hole water
Ideally, the problem should be
(b) The risk of the casing becoming production,
minimised by reducing the mud's low
stuck. 2. Abandon permanently deeper zones,
shear-rate viscosity and gel-strength
Typically casing is reciprocated 3. Completing a zone uphole,
during circulation before the casing is
between 20-40 ft over 1-5 minutes. 4. Place a cement bridge plug,
run.
However, the movement downhole can 5. Set plug to provide a seat for
Once the hole has been circulated clean
be reduced due to pipe stretch and directional tools like whipstock,
of cuttings, additional circulation can be
buckling. Pipe rotation is commonly 6. Set plug in unintentionally deviated
used to condition the mud and to
undertaken for liners at rates between well when vertical trajectory is
remove the gelled and dehydrated mud
10-40 rpm. intended. After setting
that becomes far more difficult to
the plug the vertical hole is continued.
remove after a prolonged static period.
When casing is run in a deviated well,
Different cement slurry placement 7. Set plug through keyseat portion of
the resulting eccentricity will trap
techniques are: the well and redrill it.
pockets of mud against the low side of
1. primary cementing, Properties of Cement Slurry
the hole resulting in cement channelling
2. liner cementing,
and possible incomplete zonal isolation,
API has defined standard classes (Class ones of the drilling fluids discussed in Extenders are used to increase the
A to Class H) as well as standard types previous sections volume of the cement slurry gained per
of cement used Physical Properties sack cement (yield).
within oil and gas wells. The standard The physical properties of cement and This is done by allowing an adding of
types are: cement slurries include: extra water to the slurry. In turn, this
1. Ordinary, 1. Thickening time, extra water reduces
2. Moderate sulfate-resistant, 2. Fineness, the density of the cement slurry.
3. High sulfate-resistant, 3. Water content, Commonly used extenders that reduce
The standard classes are defined as: 4. Slurry density, the density of the slurry are low specific
1. Class A: Intended depth range for 5. Compressive strength, gravity solids like:
usage: surface to 6,000 [ft], when 6. Fluid loss, 1. Bentonite,
special properties are 7. Yield, 2. Diatomaceous earth,
not required, available in ordinary type 8. Bottom hole temperature 3. Solid hydrocarbons,
only. Slurry density 4. Expanded perlite,
2. Class B: Intended depth range for To minimize the danger of fracturing 5. Natural pozzolans,
usage: surface to 6,000 [ft], when the formations, lost circulation or kicks, 6. Silica,
conditions require the cement slurry density should be the 7. Chemical extenders (liquid or solid
moderate to high sulfate-resistance, same as the drilling fluid density at silicate).
available as moderate and high sulfate- cementing operations. Accelerators
resistance types. To reduce the thickening time as well as
3. Class C: Intended depth range for Yield increase the rate of early strength and
usage: surface to 6,000 [ft], when By definition, the yield is the volume of thus reduce
condition require high early strength, cement slurry obtained when mixing the WOC time, accelerators are added to
available in ordinary, moderate and high one sack of cement the cement slurries. When cementing
sulfate-resistance types. with a specified amount of water as well shallow, low temperature section of
4. Class D: Intended depth range for as other additives. Note that one sack wells, accelerators are often essential.
usage: 6,000 to 10,000 [ft], at cement (94 [lb] Commonly applied accelerators are:
moderately high temperatures and sack) contains 1 [ft3] bulk volume and 1. Sodium chloride,
pressures conditions, available in 0.48 [ft3] absolute volume 2. Calcium chloride,
moderate and high sulfate-resistance Thickening Time 3. Hemihydrate form of gypsum,
types. The length of time the cement slurry is 4. Potassium chloride,
5. Class E: Intended depth range for pumpable is also called “thickening 5. Sodium silicate,
usage: 10,000 to 14,000 [ft], at high time”. To control the thickening time, 6. Sea water for mixing.
temperature and pressure conditions, adding of setting time retarders, a Retarders
available in moderate and high sulfate- reduction of rapidly hydrating In contrary to the accelerators, retarders
resistance types. components and an adjustment of the are added to cement slurries to prolong
6. Class F: Intended depth range for cement fineness is performed. When the the thickening time and decrease the
usage: 10,000 to 16,000 [ft], at time it takes to properly place the rate of early strength development.
extremely high temperature and cement slurry at the predetermined 1. Calcium lignosulfate at very low
pressure conditions, available in annulus interval (mixing and concentrations,
moderate and high sulfate-resistance displacement time), including a safety 2. Calcium-sodium lignosulfate used
type. factor, exceeds the thickening time, with high concentration of bentonite,
7. Class G: Intended as basic cement in parts of the cement will remain in the 3. Sodium tetraborate decahydrate
the depth range: surface to 8,000 [ft], tubular used to pump down the cement (borax) used as a catalyst for the
when used with accelerators and slurry. deflocculants,
retarders covers wide range of Compressive Strength 4. Carboxymethyl hydroxyethyl
temperatures and pressures, no other To hold the casing in place, enable cellulose.
additions than calcium sulfate, water or support capability of the surface Weighting Material
both are to be blended with the clinker, wellhead equipment and withstand Weighting material are cement additives
available in moderate and high sulfate- the differential pressures across the that are capable of increasing the
resistance types. cement-formation interface, the density of the cement slurry. Commonly
8. Class H: Intended as basic cement in compressive strength of the set and used weighting materials are high-
the depth range: surface to 8,000 [ft], hardened cement has to be high enough. specific gravity solids like:
when used with accelerators and As general practice, 500 [psi] of 1. Barite,
retarders covers wide range of compressive strength has to be 2. Ottawa sand,
temperatures and pressures, no other developed by the hardening cement 3. Hematite,
additions than calcium sulfate, water or before any other downhole operation 4. Ilmenite.
both are to be blended with the clinker, commences. The time it takes the Fluid Loss Material
available in moderate sulfate-resistance cement to reach this minimum Fluid loss material is added to the
type only. compressive strength is often referenced cement slurry to help minimize the loss
Cement properties include the chemical, as “wait on cement” (WOC). During of water from the slurry into the
physical and rheological characteristics this time, other routine surface service formations. During displacement and
of the cement. operations are usually carried out. cement setting, a differential pressure
The rheological properties of cement Extenders across permeable formations and the
slurries are generally the same as the cement does develop which causes a
reduction of water in the slurry that is
lost into the formations. Commonly spacers and preflushes, the displacement reciprocated or rotated to help displace
added fluid loss materials are: process itself and the appropriate the mud. When the top plug moves
1. Latex, cement slurry composition as well as down the casing, it wipes cement off the
2. Bentonite with a dispersant, mixing procedures have to be designed. inside walls. It also prevents the mixing
3. Various organic polymers, For example, in most drilling operations of the cement slurry with the
4. Attapulgite, laminar flow behavior displacement fluid behind it. Since the
5.Carboxymethyl hydroxyethyl is desired, for displacing the cement top plug is solid, once it lands on top of
cellulose. slurry, turbulent flow is the preferred the bottom plug, flow stops and the
Dispersants one. Having this in mind, the pressure rises. This increase of pressure
Dispersants are added to thin the cement corresponding pumping rate can be indicates that the cement is fully in
slurry. This causes a reduction of slurry computed applying the power-law flow place and the pumps are bled off. When
viscosity and is achieved without adding model. the pressure inside the casing is
of extra water. Commonly applied In conventional primary cementing the released, the valve in the float collar
thinners are: cement is displaced through the casing. closes and keeps the cement from
1. Calcium lignosulfate, In order to avoid contamination of the flowing back up the casing
2. Sodium chloride, cement with mud, a so called “spacer” is Pressure in the casing should be
3. Certain long chain polymers. placed between them. The spacer in released before the cement sets since it
front of the cement, which is also called causes the casing to bulg. When the
“preflush”, pressure is released after the cement
is starts to set, the casing pulls away from
commonly the hardening cement and looses the
water. bond.
Water is Liner Cementing
often chosen Liner cementing constitutes one of the
since it is most difficult cementing operations. To
easy to perform it successfully following
obtain, it individual processes are to be compl-
can be put in eted:
turbulent 1. Running the liner on drillpipe,
flow 2. Pumping the cement slurry through
condition at the drillpipe
relatively and the liner,
low 3. Displace the cement slurry behind the
circulation liner up to
rates and it just above the liner hanger.
does not The equipment used to perform a liner
cementing job includes: a float shoe, a
Cement Truck affect the
float collar, a landing collar, the liner,
setting time
the liner hanger, liner setting sleeve and
of the
setting tools, the swivel assembly and
Primary Cementing cement. The column of water pumped
liner wipe plug as well as a pump down
ahead of the cement causes a desired
plug.
The first step when performing a reduction of hydrostatic pressure in the
primary cementing job is to calculate annulus. To calculate the pump rate to
the volume of cement and cement slurry displace the spacer in turbulent flow, the
required to fill the annulus interval that Newtonian flow model is used.
has to be cemented. The cement volume The procedure of primary cementing is
is calculated by estimating the volume described as follows:
between the casing and the borehole To perform the primary cementing job,
wall at the selected interval. When the a device called “cement head” or “plug
borehole is ingauge this volume is container”,, is mounted on the top joint
straight forward to calculate. When of the casing which is hanging in the
washouts and other gauge variations are elevator. This cement head serves as
connection from the cement pumps to Sometimes it is necessary to extend a
present, the hole diameter has to be
the casing. Inside the cement head, a Cement Plug
checked with a caliper log and an
average borehole diameter calculated. bottom wiper plug and a top wiper plug, liner back to the surface in order to
Other parameters that have to be are placed. complete the well. This casing type is
computed before the cement job When the bottom plug reaches the float also known as “tieback liner”. When the
commences are: collar, it stops and while continuing liner is extended back but not until the
1. Determination of the quantities of pumping, the pump pressure surface, the casing is called “stub liner”.
cement and additives, increases.At a certain pressure the To repair a leaking liner top, a stub liner
2. Thickening time, diaphragm of the bottom plug ruptures is installed usually.
3. Displacement volume, and the cement slurry can flow through Squeeze Cementing
4. Differential forces, the open valve in the collar, out the Under squeeze cementing, the process
5. Annular velocities. guide shoe and into the annular space of forcing a cement slurry under
Once these parameters are known, between the casing and the borehole. pressure into a confined interval of the
displacement rates, type and amount of During this flow, the casing is often well behind a casing is understood. A
squeeze cementing job may be spacer behind the cement, is most often will have a compressive strength much
necessary during drilling, at completing carried out. When the hight of the lower than properly mixed cement. In
the well or as workover after the well is spacer inside the tubing is equal to the the majority of these cases, no bentonite
completed and/or producing. The main hight of the preflush, the cement plug is or other appropriate additive is being
influence to the success of squeeze placed balanced used, so there will be settling. Further,
cementing operations is how good the Cement requirement, water volume to the cement column weight will be lower
cement slurry is placed into the interval be pumped behind the slurry to balance than anticipated, and that can be a
that is to be squeezed off. Normally, the the plug, plug length before the pipe is problem in wells that need the fluid
interval (e.g. perforations) is treated retrieved from the slurry. In 1824, column weight to kill the well for proper
with an acid wash or matrix acidizing Joseph Aspdin, a British bricklayer, was setting.
using hydrochloric acid to clean the granted a patent for making a cement he Wells should be plugged and completed
surfaces before the job is performed. called Portland cement after stone with the highest density cement
To perform a squeeze cement job, three quarried on the Isle of Portland in practical under the particular
different methods can Dorset, England. However, this original circumstances. In the shallow wells
be applied: Portland cement, was actually an here in Kentucky, that would almost
1. Bradenhead method, artificial hydraulic lime similar to a always be 5.2 or at the most 5.5 gallons
2. Packer squeeze method, material called Roman cement, a crude of water per sack neat cement. While I
3. Hesitation squeeze method. formulation of lime and volcanic ash have no statistics, it is likely there have
To perform a squeeze cement job with used as early as 27 BCE (pozzolanic been plugging failures due to
the Bradenhead method, materials are still used in oil well improperly mixed cement. There is no
the following procedure has to be cementing to this day). It is sometimes doubt there have been completion
completed: reported that Aspdin did his original failures, but these do not show up on the
1. Running the drillpipe to just above experiments with his kitchen oven. The regulatory radar here as much as they
the perforations first true Portland cement is believed to would in say Texas due to differences in
where the cement has to be squeezed in, have been made in Germany around the rules on completions (every Texas
2. Displace cement from the drillpipe, 1867. completion must have a pressure test, a
3. Close the pipe rams and apply a bond log, and the compressive strength
precalculated pressure from the surface Dealing with water intrusion into oil of cement is specified). Notably, in
to squeeze off the perforations. wells, and the use of cement to prevent overpressured wells, the heaviest
When using the packer squeeze method, such movement, led to the birth of practical cement slurry may be crucial
either a retrievable squeeze packer or a petroleum engineering. Some primitive to even get a successful plugging job
cement retainer is applied. First the oil well cementing may have taken absent setting a bridge plug.
packer is run to just above the interval place as early as 1883, but the use of It is customary practice to catch cement
that has to be squeezed off. Afterwards Portland cement to seal casing began in samples in little Styrofoam cups during
surface pressure is subjected to the 1903 in the Lompoc Field in the cement job, but many times I have
tubing or drillpipe. This provides a close California. Almond A. Perkins was the seen the cementing contractors pour off
control of the squeeze cement slurry father of the two plug method of well the separated water before handing the
during squeezing. In contrary to the cementing. In 1916, Perkins employed sample to the oil operator or to the
retrievable packer which is run on Earl P. Halliburton, and in 1919, resident regulatory inspector (it takes a
drillpipe, the retainer packer is run on Halliburton set up shop on his own as few minutes for separation to occur and
wireline. the New Method Oil Well Cementing it will not be evident at the mixing unit
At the hesitation squeeze method, the Company, changing the name to the itself). I think the problem here is a lack
cement is squeezed into the desired Halliburton Oil Well Cementing of recognition of the significance of
section with relatively low pressure Company (HOWCO) in 1920. Perkins separated water. If the mix has 5.5
while pumping intermittently. The later sued Halliburton for patent gallons per sack or less, there will be no
cement is slowly dehydrating and infringement, but the case was settled free water separation (or only a trace),
increasing in viscosity during the non- with Halliburton being granted a license and the entire mass will gel / set in the
pumping cycle. This method is used to use the Perkins sample cup (this assumes a neat cement
most often to squeeze off low permeable methodology. Halliburton eventually with no additives). The assumption
zones. even licensed inventions to Perkins, but seems to be if the stuff gels / sets at all it
Plugback Cementing in the end Halliburton wound up buying must be mixed properly. In fact much
Two different methods for plug Perkins. Halliburton perfected the use of the settling seen in wells in the field
cementing operations are encountered in of the measuring line and the jet mixer is likely attributable to settling of
practice: (a) the plugback cementing and among other well cementing slurries mixed with more than 5.5
(b) spotting a cement plug at any desired innovations. Interestingly, over the gallons of water per sack. And
depth of the well. The most common course of the first 30 years of well inspectors do not generally hang around
type, plugback cementing, is used to cementing, waiting on cement time long enough to really determine what
plug back and abandon deeper zones. gradually shrank from 28 days to a mere the ultimate settling will be, an
Spotting plug cementing is usually 72 hours. additional potential problem.
performed in open hole sections. To Cementing problems Ignorance of proper procedures is a
design the spacer and cement slurry, the It is apparent most cement mixed in large factor here, but there is a darker
same considerations and equations as Kentucky, and in perhaps a few other side to this problem. Contractors using
for primary cementing operations are jurisdictions, is being mixed with far bulk cement equipment have the
applied. For the pug cementing more than 5.5 gallons of water per opportunity to sell the same cement
operations a balanced plug techniques sack. The biggest problem with this more than once. For instance, a 5.2
that requires pumping a preflush and a practice is that the resultant set cement gallon mix will yield 1.18 cubic feet per
bag, while a 10.4 gallon mix will yield density of no less than 15.36 pounds per slurry fills the annular space. A top
1.92 cubic feet per bag. Since everyone gallon (this corresponds to the plug, which is similar to the bottom plug
uses the Halliburton cement tables in the maximum 5.5 gallons of water per sack except that it is solid, is released as the
Halliburton cementer's bible, and the ratio mentioned above). Under no last of the cement slurry enters the
tables are based on a 5.2 gallon mix, the circumstances should cement be casing. The top plug follows the
contractor has an opportunity to charge pumped with a density of less than 14.0 remaining slurry down the casing as a
for much more cement than is really pounds per gallon, but it is being done displacement fluid (usually salt water or
used, and oil operators are none the every day in Kentucky at drilling mud) is pumped in behind the
wiser. Further, contractors using present. Inspectors should also be top plug. Meanwhile, most of the
centrifugal pumps, tend to mix thin to equipped with inexpensive drilling mud cement slurry flows out of the casing
save wear and tear on equipment (and if balances to make field measurements of and into the annular space. By the time
they are using a bulk truck, they get to cement slurry density. I would hazard a the top plug seats on or "bumps" the
play the selling it twice game as well). I guess that the majority of the cement bottom plug in the float collar, which
want to make it clear that this is not an mixed for well plugging, remediation, signals the cementing pump operator to
argument against the use of centrifugal and new completions in Kentucky has shut down the pumps, the cement is
pumps for cement mixing because I been mixed with far too much water for only in the casing below the float collar
have personally mixed 15.6 pound per optimal results. Granted, light cements and in the annular space. Most of the
gallon and even a little thicker neat are sometimes used in deep wells, but casing is full of displacement fluid.
cement with my own centrifugal pump that is seldom the case in Kentucky to After the cement is run, a waiting time
cement mixing rig in years gone by. If date. The major service companies like is allotted to allow the slurry to harden.
concrete suppliers engaged in this Halliburton do not play these games, but This period of time is referred to as
practice, it would be noticed since it is the majority of the smaller independent waiting on cement or simply WOC.
well known that skimping on cement or service companies seem to, some with a After the cement hardens, tests may be
using too much water results in weak vengeance. run to ensure a good cement job, for
concrete, but oil well cement goes down After the casing string is run, the next cement is very important. Cement
a hole and is never seen again. task is cementing the casing in place. supports the casing, so the cement
This practice persists because oil An oil-well cementing service company should completely surround the casing;
operators and inspectors lack the is usually called in for this job although, this is where centralizers on the casing
equipment and/or knowledge to catch as when casing is run, the rig crew is help. If the casing is centered in the
the problem. A true neat slurry mixed available to lend assistance. hole, a cement sheath should completely
with 5.2 gallons of water per sack of Cement service companies envelop the casing. Also, cement seals
cement will have a density of 15.6 Cementing service companies stock off formations to prevent fluids from
pounds per gallon (the API preferred various types of cement and have one formation migrating up or down the
mix). But a slurry mixed with 10.4 special transport equipment to handle hole and polluting the fluids in another
gallons per sack will still weigh 13.1 this material in bulk. Bulk-cement formation. For example, cement can
pounds per gallon, and even to the storage and handling equipment is protect a freshwater formation (that
trained eye looks quite heavy and thick moved out to the rig, making it possible perhaps a nearby town is using as its
(plain water is 8.33 pounds per to mix large quantities of cement at the drinking water supply) from saltwater
gallon). The "finger test" used by some site. The cementing crew mixes the dry contamination. Further, cement protects
inspectors cannot distinguish between cement with water, using a device called the casing from the corrosive effects
these two examples with any degree of a jet-mixing hopper. The dry cement is that formation fluids (as salt water) may
reliability. Putting this example in gradually added to the hopper, and a jet have on it. comprising: a. flowing a slug
perspective, the 5.2 gallon neat mix will of water thoroughly mixes with the of preflush solution comprised of an oil
exhibit compressive strength at least cement to make a slurry (very thin water and a dispersing agent, said solution
five times greater than the 10.4 gallon cement). Special pumps pick up the having a lower viscosity and lower gel
mix, and the 10.4 gallon mix will cement slurry and send it up to a valve strength than said drilling mud and
undergo some settling. Stated bluntly, called a cementing head (also called a having a critical turbulence pump rate of
absent the use of a cement / mud plug container) mounted on the topmost no greater than three barrels per minute,
balance or a hydrometer, nobody can be joint of casing that is hanging in the into the annular space between said
certain of cement density (some of the mast or derrick a little above the rig casing and the wall of said well; b.
big cementing companies have floor. Just before the cement slurry flowing into said annular space and
continuous reading densitometers on arrives, a rubber plug (called the bottom emplacing therein a cement slurry; and
their mixing units, but this would not plug) is released from the cementing c. allowing said cement slurry to set and
likely be encountered in Kentucky). Oil head and precedes the slurry down the form an impermeable cement sheath
operators and regulators alike have been inside of the casing. The bottom plug which bonds said casing to said wall of
at the mercy of cementing contractors, stops or "seats" in the float collar, but said well.
and they do not always mix cement as continued pressure from the cement 2. The method of claim 1 wherein said
they should. pumps open a passageway through the oil is selected from the group consisting
bottom plug. Thus, the cement slurry of kerosene, diesel oil, and mixtures
Both the EPA Region IV Underground passes through the bottom plug and thereof.
Injection Control (UIC) Program with continues on down the casing. The 3. The method of claim 1 wherein the
jurisdiction over injection wells in slurry then flows out through the volume of said slug of preflush solution
Kentucky, and the Kentucky Division of opening in the guide shoe and starts up is within the range of 10 to 50 barrels.
Oil and Gas (DOG) with jurisdiction the annular space between the outside of 4. The method of claim 1 wherein said
over oil wells, need to adopt standards the casing and wall of the hole. dispersing agent is lecithin.
that require cement to have a preferred Pumping continues and the cement 5. The method of claim 4 wherein the
amount of lecithin in said preflush between the surface of the earth and the conditions.
solution is 1 to 5 pounds per barrel of bottom of the well are commonly Various procedures and apparatus,
said preflush solution. employed in drilling wells. Oil base including the Stormer viscosimeter and
6. The method of claim 1 further muds, including water-in-oil emulsion the Fann V-G Meter, have been used in
comprising, subsequent to step (a) and muds of low water content, wherein oil determining plastic viscosity, yield
prior to step (b), flowing a slug of an forms the continuous phase, are often value, and gel strengths of drilling
aqueous solution having a water wetting used in the drilling and completion of muds. In a paper entitled "Measurement
surfactant therein into said annular wells. Drilling muds serve many useful of Plastic Flow Properties" by Fred
space between said casing the the wall purposes, including removal of earth Chisholm and Sam Kohen,
of said well. cuttings from the well, control of PETROLEUM ENGINEER, vol. 26,
7. The method of claim 6 wherein said formation pressures, and cooling and No. 4, pp. B-87--B-90, April, 1954,
slug of an aqueous solution is injected in lubricating of the drill bit used in there is described a procedure
an amount within the range of 5 to 50 forming the well. However, there are employing a Model 30 Fann V-G Meter
barrels and contains therein 1/2 to 10 also certain detrimental characteristics to measure the plastic viscosity, yield
pounds per barrel of a polyoxyethylene- associated with drilling muds. For value, and gel strength of a drilling mud.
aryl ether of the structural formula: example, drilling muds tend to flow In the completion of wells, casing is
wherein: R is a hydrogen atom or an from the well into exposed permeable normally lowered into the well and a
aliphatic substituent having no more formations with the result that mud cement slurry is flowed down the well
than nine carbon atoms, and n is an solids are filtered out on the wall of the and up the annular space formed
integer within the range of 10 to 100. well, forming a filter cake thereon. between he casing and the wall of the
8. A method of cementing casing in a Thick filter cakes are particularly well. Cement slurries have been
well penetrating a subterranean harmful in that they may impede or stop emplaced in the annular space between
formation, said well having an oil base the movement of drilling tools in the the casing and the wall of the well by
drilling mud therein, comprising: a. well. Even thin filter cakes are flowing them thereinto in direct contact
flowing a slug of preflush solution detrimental in the completion of wells in with the mud, thereby displacing the
comprised of an oil, a dispersing agent, that they interfere with obtaining a good mud from the annular space. This
a viscosifier, and a weighting material, cement bond between the wall of the procedure may result in poor cement
said solution having a lower viscosity well and the casing positioned in the jobs because of contamination of the
and lower gel strength than said drilling well. cement slurry and because of failure to
mud and having a critical turbulence Drilling muds may be considered to be remove the filter cake from the wall of
pump rate of no greater than three non-Newtonian fluids and are referred the well. In order to obtain improved
barrels per minute, into the annular to as plastic-type fluids. Their fluid cement jobs, various techniques,
space between said casing and the wall movements are known as plastic flow. including the use of preflush solutions
of said well; b. flowing through said Two flow properties, plastic viscosity or washes, have been developed. For
annular space and emplacing therein a and yield value, must be known in order example, Joseph G. Savins, in U.S. Pat.
cement slurry; and c. allowing said to describe the flow behavior of a No. 3,291,211, describes a method of
cement slurry to set and form an drilling mud as compared with one flow cementing a well wherein the drilling
impermeable cement sheath which property, viscosity, required to define mud in the annular space between
bonds said casing to said wall of said the flow characteristics of a Newtonian casing and a wellbore wall is removed
well. fluid. Another property often used in by passing into a well, prior to placing a
9. The method of claim 8 wherein the characterizing a drilling mud at rest is cement slurry therein, a liquid
volume of said slug of preflush solution gel strength. comprising a solvent containing
is within the range of five to 50 barrels. dissolved therein a solute which imparts
10. The method of claim 9 wherein said Plastic viscosity is that part of flow viscoelastic properties to the liquid.
oil is selected from the group consisting resistance in a mud which represents Joseph U. Messenger, in U.S. Pat. No.
of diesel oil, kerosene, and mixtures mechanical friction (1) between solids 3,348,612, describes a technique of
thereof. in the mud, (2) between the solids and cementing casing in a well wherein a
11. The method of claim 10 wherein the liquid which surround them, and (3) slug of liquid having mutual solubility
said dispersing agent is lecithin. of the shearing of the liquid. Yield for oil and water is passed into a well
12. The method of claim 11 wherein value, the second component of and into the annular space formed
said viscosifier is an amine substituted resistance to flow in a drilling fluid, is a between the wall of the well and the
bentonite. measurement of the interparticle forces outer surface of the casing and is
Description: in the mud. These forces are the result followed by a cement slurry. A slug of
This invention relates to cementing of positive and negative electrical an organic solvent for oil and asphalt
casing in a well drilled from he surface charges located on or near particle may be passed into the annular space
of the earth into subterranean surfaces. If the mud is allowed to come ahead of the slug of liquid having
formations. to rest, the forces tend to move the solid mutual solubility for oil and water.
Wells are drilled into subterranean particles around until they reach a Another technique for cementing casing
formations for various purposes. For geometrical arrangement where the in a well is described by Joseph U.
example, they may be drilled into attraction and repulsion forces are best Messenger in U.S. Pat. No. 3,467,193.
subterranean formations for the purpose satisfied. A gel-strength measurement is A preflush comprised of formation
of producing hydrocarbons or water an indication of the magnitude of these water containing dispersants is flowed
therefrom, or for injecting fluids into the forces under conditions of rest. Yield through the annular space formed
subterranean formation. value is a measurement under flowing between casing and the wall of a well.
Rotary drilling techniques wherein a conditions of those forces in the mud Thereafter, a spearhead of cement slurry
drilling fluid or mud is circulated which cause gel strength under rest containing a turbulence inducer and
silica or diatomaceous earth particles preflush solution will go into turbulence preceding the cement slurry is sufficient
and having a density at least as great as when flowed through a 1/2-inch annulus to displace the drilling mud and filter
the drilling mud employed in drilling formed between two concentric pipes, cake from the portion of the annular
the well is flowed into the annular the smaller of which has an outside space of concern, thereby allowing a
space. This is followed by a densified diameter of 7 inches, and the larger of good cement sheath to be formed
cement slurry and the cement slurries which has an inside diameter of 8 between the casing and the wall of the
allowed to set. inches. A low critical turbulence pump well.
rate is beneficial for two reasons: (1) the
This invention is directed to a method of well wall is exposed to turbulent action An aqueous wash containing a water
cementing casing in a well penetrating a a maximum length of time for a given wetting surfactant may be flowed into
subterranean formation, which well has volume of preflush solution; and (2) a the annular space subsequent to the
therein an oil base drilling mud. A slug lower pump pressure can be used to preflush solution and prior to the cement
of a preflush solution comprised of an obtain turbulent flow than must be used slurry to remove from the casing the oil
oil and a dispersant, which solution has for solutions having higher critical film remaining from the preflush
a lower viscosity and lower gel strength turbulence pump rates. The dispersing solution, thereby providing a clean
than the drilling mud and has a critical agent employed in carrying out the surface and enhancing the bond formed
turbulence pump rate of no greater than present invention may be any suitable between the cement sheath and the
three barrels per minute, is flowed into material which functions to promote and casing. This aqueous wash, when
the annular space between the casing maintain separation of the individual, employed, should be flowed into the
and the wall of the well. Thereafter, extremely fine particles of solids which annular space in an amount of five to 50
cement slurry is emplaced in the annular are usually of colloidal size. As will be barrels, preferably 10 to 20 barrels, and
space and allowed to set and form an recognized by those skilled in he art, should contain 1/2 to 10 pounds of
impermeable cement sheath which various such dispersing agents are water wetting surfactant per barrel of
bonds the casing to the wall of the well. conventionally employed in drilling water and preferably 2 to 4 pounds per
In another embodiment, the preflush muds in order to maintain adequate barrel. A suitable water wetting
solution further includes a viscosifier, dispersion of clays added to impart surfactant may be chosen from the
and a weighting material. desired rheological properties to such classes of nonionic and anionic
muds. A particular dispersing agent surfactants. An example of a class of
DESCRIPTION OF THE which gives good results when nonionic surfactants from which a
PREFERRED EMBODIMENTS employed in the preflush and which is suitable water wetting surfactant may be
preferred in practicing the present chosen is the polyoxyethylene-aryl
This invention is directed to a method of invention is lecithin. Lecithin is a ethers of the structural formula:
cementing casing in a well that has an naturally occurring amino, and is wherein: R is a hydrogen atom or an
oil base drilling mud therein and has a available from Baroid Division, aliphatic substituent having no more
filter cake on the wall of the well. National Lead Company, under the than nine carbon atoms, and n is an
In accordance with this invention a trade name "Driltreat." integer within the range of 10 to 100.
preflush solution comprised of an oil Within the class of nonionic surfactants
and a dispersing agent is injected into a A particular preflush solution found to a preferred surfactant is the
well that has an oil base drilling mud give good results is comprised of an oil poloyoxyethylene ether of phenol
therein and into the annular space and lecithin in an amount of 1 to 5 having 30 ethylene oxide groups.
between the casing and the wall of the pounds per barrel of preflush solution. Anionic surfactants which may be
well to displace the mud and remove the Oils that are preferred are kerosene, employed in the present invention may
filter cake from at least a portion of the diesel oil, and mixtures thereof because be chosen form he class of salts of fatty
annular space. This is followed by a they are compatible with oils used in oil acids or salts of sulfonic acid
cement slurry which is emplaced in the base drilling muds. However, other oils derivatives. Two examples of anionic
annular space and allowed to set, such as light crude oils may be used. surfactants are di-ethyl sodium
thereby forming an impermeable cement succinate and sodium lauryl sulfonate.
sheath which bonds the casing to the This preflush solution goes into
wall of the well. In another turbulence at a low rate of flow, thus When cementing a well having a
embodiment, water having a water exposing the wall of the well to the weighted oil base drilling mud therein, I
wetting surfactant therein is flowed into scouring action of turbulent flow for a have found it desirable to displace the
the annular space following the preflush maximum amount of time for a given oil base drilling mud ahead of the
solution and preceding the cement slurry size slug of solution. In addition, the cement slurry with a weighted preflush
to displace the oil from the surface of dispersing agent permeates the filter solution. It is particularly important to
the casing and the wall of the well. cake and through dispersing action use a weighted preflush solution having
causes a deterioration of the filter cake. approximately the same weight as the
The preflush solution is designed for use Thus, by combination of the turbulent drilling mud when there exists in
in a well having an oil base drilling mud action and dispersing action the filter communication with the well a
therein and is formulated to have a cake is effectively removed. In addition, formation having fluids under high
lower viscosity and lower gel strength the turbulent action of the preflush pressure contained therein. The use of
than the drilling mud. Further, the solution effectively displaces the such a preflush solution ensures that the
preflush solution is formulated to have a drilling mud from the portion of the hydrostatic pressure exerted by the
critical turbulence pump rate of no annular space into which cement slurry drilling mud in the well is not lessened,
greater than three barrels per minute. By is to be emplaced. A 10- to 50 -barrel thereby allowing the fluids under high
the term "critical turbulence pump rate" slug of preflush solution injected into pressure in the formation to flow
is meant the pump rate at which the the well and into the annular space uncontrollably into the well.
spacers. Mud conditioning before
A weighted preflush solution which I cementing. Summary.
have found to be particularly suitable 2. Different types of cementing: One-
for such an application is comprised of stage cementing and two-stage
an oil, a viscosifier, a weighting cementing. Cementing with stinger.
material, and a dispersing agent Cementing a liner.
formulated to have a lower viscosity and 3. Setting cement plugs to combat lost
a lower gel strength than the drilling circulation: Thixotropic slurries, cement
mud and to have a critical turbulence gels, cement slurries without additives,
pump rate of no greater than three and their placement. Plaster Diesel Oil
barrels per minute. Oils found to be Cement (PDOC) and Diesel Oil Cement
particularly useful in this preflush (DOC), and their placement.
solution are kerosene, diesel oil and 4. Causes of failure in casing cement
mixtures thereof, though other oils may jobs and remedies: Losses during slurry
be used. A viscosifier found to be placement. Slurry overdisplacement.
particularly useful is an amine Lack of tightness of the cement sheath.
substituted bentonite used in a sufficient Flash set. Setting defect. Lack of
amount to increase the viscosity of the mechanical strength. Cement
preflush solution to a value which will deterioration. Casing disconnection.
prevent settling of the weighting The key factors necessary to ensure a
material. Normally no more than 5 successful primary oil well cement job
pounds of viscosifier per barrel of are as follows:
preflush solution are required to provide 1. Good information: Related
this viscosity. Such a viscosifier can be information such as calculated hole
prepared by treating bentonite, sodium diameter, hole volume, depth, etc from
form, with a long-chain quaternary related personnel is required in order to
ammonium salt and is available under design cementing programs.
the trade name of "Geltone." A 2. Good cementing design: There is a
weighting material suitable for use in number of cement purposes such as
this preflush solution is barite. A primary cement, cement squeeze,
sufficient amount of barite should be cement plug. To meet the purpose of
used to increase the weight of the each job, cementers must design a
preflush solution to a weight of at least cementing program in correct and good
14 pounds per gallon and preferably to way.
approximately the weight of the drilling 3. Good procedures: Clear and concise
mud in the well. A particular dispersing procedure will lead to good job because
agent found to be useful in this preflush cementer and assistants can perform the
solution is lecithin which is available cementing job correctly, fast, safely.
under the trade name of "Driltreat." A 4. Good equipment and experienced
sufficient amount of the dispersing personnel: Experienced staff with good
agent is added to ensure that the equipment can perform great jobs, no
weighted preflush solution has a critical lost time, safe and fast.
turbulence pump rate of no greater than 5. Good centralizer placement:
three barrels per minute. Normally this Centralizers help casing in the center of
requires no more than 5 pounds of hole. Casing with good centralizer
dispersing agent per barrel of preflush placement, cement can form properly
solution. The dispersing agent reduces cement sheath around casing.
the interparticle forces in the preflush
solution and thereby the yield value of
the preflush solution, thus enabling the
solution to go into turbulence at a low
rate of flow.

Cementing is a difficult operation and


the quality of the result depends on
many factors associated with: the state
of the open hole section; the equipment
and materials employed; the fluids used;
the procedures applied. This document
presents an update of the information
and recommendations on methods and
procedures to be applied at the well site.
1. Drawing up the cementing program:
Cement classes according to API
specifications. Slurries. General
information on flow regime and on

You might also like