MPTJO - For BTS EPC grid survey 2020

QUESTION AND ANSWER


Requirement

No. Date Doc References Original Statements

1 9/26/2020 Appendix 1 ( 1.2 ) Cable Line Route

2 9/26/2020 Appendix 1 ( 1.3 ) EPC Recommecdation Letter

3 9/26/2020 Appendix 1 ( 1.4 ) VEC donation agreement letter

4 9/26/2020 Appendix 1 Not specify original Statements.

5 9/26/2020 Appendix 2 ( 2.14 ) Even for item not include herein

6 9/26/2020 Appendix 3 Estimated grid type by MPT

7 9/26/2020 Appendix 8 EPC Transformer data

8 9/26/2020 Not specify. Not specify.


ON AND ANSWERS
Bidder

Questions/statement Answers

Do we need to report by
PDF format or KMZ format?
Do we need EPC circle
seal on letter?
We need to know
VEC donation agreement letter
or VEC donation request letter?
Our SOW include or not include
for ROW pole location and ROW line route
negotiation process?

We need to know sample for this.

In this section , We need to follow up


HT or LT accroding to
estimated grid type by MPT ?
We need to know EPC transformer data only for
target site's grid type is LT ?
Do we need to survey for transformer location.
If we need to survey for transformer location,
we need to know tower lease area contract
and Detail design layout drawing of Tower area.