Professional Documents
Culture Documents
Level Crossing
Figure 2.1
Figure 2.2
The selection of a particular type of cross drainage work depends upon the
following factors.
The relative bed levels and discharge of the canal and drainage are the primary
factors which govern and dictate the type of cross drainage work that may prove to be most suitable
at a particular place. The relative bed levels of the canal and drainage may be changed and
manipulated by suitably changing the canal alignment, so that the point of crossing is shifted
upstream or downstream of the drainage. The canal alignment is finalized after deciding the
location of cross drainage works.
The design of aqueduct or siphon aqueduct, a super passage and a siphon is done in
the following steps.
The maximum flood discharge and high flood level is determined with the help of
empirical formulae for small drains and with the help of hydrograph analysis etc. for large drains.
The value of waterway of drain can be obtained by the use of Lacey’s equation i.e.
P= 4.75√�; where P is the wetted perimeter in meters and Q is the total discharge in cumecs. For
wide drains, the wetted perimeter is taken equal to the width of the drain and therefore, equal to
the waterway required. No extra provision is made for the space occupied by piers. Hence, if the
total waterway provided is equal to P, the effective or clear waterway will be less than P by as
much extent as is occupied by pier width. For smaller drains, a smaller figure for the waterway
than that given by Lacey’s regime perimeter is chosen. The maximum permissible reduction in
waterway from Lacey’s perimeter is 20%. After fixing the waterway width and number of bays
the height of the drain barrels is fixed. In case of an aqueduct, the canal trough is carried clear
above the drain HFL and drain bed is not to be depressed. Therefore, the height of bay openings
is automatically fixed in aqueducts, as equal to the difference between HFL and DBL of the drain.
In siphon-aqueducts, the required area of drainage waterway can be obtained by dividing the
drainage discharge by the permissible velocity through the barrels. This velocity through the
barrels is generally limited to 2 to 3 m/sec. The waterway area is then divided by the decided
waterway width of the openings, to compute the height of the openings and the extent of depressed
floor. Due to the reduction in the width of the drainage, afflux is produced near the work site. The
afflux will increase more and more, if the waterway is reduced more and more. The value of afflux
is limited, so that there is no flooding of the adjoining area.
A velocity higher than 2 to 3 m/sec can cause quick abrasion of the barrel surfaces
by rolling grit etc. and result into higher amount of afflux on the upstream side of the siphon or
siphon aqueduct, thus requiring higher and longer banks. Therefore, velocity is limited to about 2
to 3m/sec through siphon barrels. The head loss through siphon barrels and velocity through the
barrels are generally related by Unwin’s formula, as given below:
� �2 ��2
h=[1 + � +� ] - (19.1)
� � �
f1 = Coefficient of head loss at entry= 0.505 for unshaped mouth and 0.08 for bell shaped mouth
�
f2= a [1+ ], (19.2)
�
Where the values of ‘a’ and ‘b’ for different materials may be taken as given in Table_____1.
Table______1___
After fixing the velocity (v= 2 to 3 m/sec) through the barrels, head (h) required to
generate that much velocity can be found by the equation 19.1. The HFL of the drain downstream
of work remains unchanged, but the HFL of the upstream sides increases by the amount ‘h’, called
afflux or total head loss as calculated by Unwin’s equation. The top of guide banks and or other
marginal bunds etc. should be governed by this raised HFL. The extent of bed protection in the
drain to downstream of the work depends upon the value of afflux. Thus by permitting a higher
value of afflux, thereby higher velocity through the siphon barrel, the cross-sectional area of the
siphon barrel is reduced, but there is corresponding increase in the cost due to higher guide banks
etc. and greater length of protection downstream of the work. Also, in order to reduce the afflux,
the entry should be smooth, by providing bell mouth shaped piers. The inside surface of the barrel
should be made as smooth as possible.
The fluming of the canal or the contraction in the waterway of the canal will reduce
the length of barrels or the width of the aqueduct. It is likely to help economy in many cases. When
the canal section is in earthen banks, the fluming of the canal is generally not done. The fluming
is governed by the rule that velocity in the trough should remain subcritical (3m/sec), because if
supercritical velocities are generated then the transition back to the normal section on the
downstream side of the work may involve the possibility of the formation of a hydraulic jump.
The hydraulic jump where not specifically required and designed for, would lead to undue loss of
head and would induce large stresses on the work. The extent of fluming is further governed by
the economy. More the fluming more is the length of transition wings, upstream as well as
downstream. The extra cost of transition wings is balanced by the saving obtained due to the
reduction in the width of the aqueduct. Hence, an economic balance has to be worked out for any
proposed design.